NPPA - GET - Part 8-1 Safety Systems Overview Protective
NPPA - GET - Part 8-1 Safety Systems Overview Protective
Personnel
1. Training Objectives
2. Definitions.
2
Training Objectives
3
Definitions
✓ NORMAL OPERATION SYSTEMS (ELEMENTS) - systems (elements) designed to assure
normal operation.
✓ Anticipated operational occurrences, or transients (AOO) – Conditions of normal operation that are expected
to occur one or more times during the life of the plant.
✓ Postulated accidents (PA) – Events which are postulated, but are not expected to occur.
✓ Design Basis Category 1 Conditions (DBC 1) - Normal Operation Conditions which are
expected frequently in the course of power operation, refuelling, maintenance or
manoeuvring of the plant. As such, Design Basis Category 1 Conditions are
accommodated with margin between any plant parameter and the value of that parameter
which would require either automatic or manual protective action.
4
Definitions
✓ Design Basis Category 2 Conditions (DBC 2) -Incident Conditions Conditions which may
occur once or more in the life of the plant (f>10-2). These conditions, at worst, result in
a reactor trip with the plant being capable of returning to operation. These conditions do
not propagate to cause a more serious fault, i.e. Design Basis Category 3 or 4 Conditions
✓ Design Basis Category 3 Conditions (DBC3) - Accident Conditions Conditions which may
occur very infrequently (10-2>f>10-4). These conditions may result in the failure of only
a small fraction of the fuel rods. A Design Basis Category 3 Condition* does not, by itself,
generate a Design Basis Category 4 Condition* or result in a consequential loss of
function of the Reactor Coolant System* or Containment System*.
✓ Design Basis Category 4 Conditions (DBC4) - Accident Conditions which are not expected
to take place (10-4 > f > 10-6) but are postulated because their consequences would
include the potential release of significant amounts of radioactive material. They are the
most extreme Design Basis Conditions* which must be designed against and represent
limiting cases.
5
Definitions
✓ Design Extension Conditions (DEC) - A specific set of accident sequences that goes beyond
DBC, to be selected on deterministic and probabilistic basis and including:
• Complex Sequences,
• Severe Accidents.
Appropriate design rules and criteria are set for DEC, in general different from those for DBC.
✓ Complex Sequences - Certain unlikely sequences which go beyond those in the
deterministic design basis in terms of failure of equipment or operator errors and have the
potential to lead to significant releases but do not involve core melt, are identified as
Complex Sequences. An example is simultaneous failure of redundant functions.
✓ Severe Accidents - certain unlikely event sequences beyond Accident Conditions
involving significant Core Damage which have the potential to lead to significant releases.
7
Protective safety systems- General provisions
Intention and basic principles of the systems design
✓ According to definition in Russian safety standard NP-001-15 General
provision for safety assurance of nuclear power plants Protective safety
systems are systems, intended for prevention or limitation of damage of
nuclear fuel, fuel component cladding, equipment and pipelines, containing
radioactive products
✓ The following basic principles are used in the protective safety systems
design:
• Resistance against single failure
• Multi-channeling
• Physical separation of channels
• Passivity
• Diversity
8
Protective safety systems- Requirements to structure and functions of systems
10
TOPIC QUESTIONS
CONTROL QUESTIONS
11
High pressure safety injection system (JND)
The system purpose
✓ High pressure safety injection system (JND) is designed for injection of boric
acid solution from containment sumps (two tanks of total volume 2300 m3 of
boron water with concentration 16 g Н3ВО3/kg Н2О) to reactor coolant system at
accidents with loss of coolant (LOCA)
The system functions
✓ The system is intended for performance of the following functions:
• The primary circuit coolant inventory maintenance
• Reactor plant (RP) cooldown to the cold state, and
• Residual heat removal from the core
During Unit operation at power the system does not operate and is in standby mode
In DBA the system performs its functions. When the primary circuit parameters for
connecting the low-pressure injection system JNG reached, the operation of the JND can
be stopped by Operator.
12
High pressure safety injection system (JND)
14
Low pressure safety injection system (JNG10)
The system purpose
✓ The system is designed to supply the solution of boric acid in the reactor coolant system during a loss of coolant
accident, when the pressure in the coolant system drops below the operating parameters of the system JNG10
The system functions
✓ The JNG system performs the following functions:
• Reactor plant cooldown during normal shutdown of the plant, in anticipated operational occurrences and in
design basis accidents on the condition of maintenance of the primary circuit integrity (jointly with the JNA
system)
• Residual heat removal from the core and keeping the temperature in primary circuit during reactor core
refueling and in repair cooldown mode.
System operation
✓ The capacity of each train is 100 %, so system capacity is 4x100%.
✓ Each train includes a pump, two heat-exchangers, valves and instrumentation
✓ The suction pipelines of each train are connected to the containment sump tanks for the storage of borated
water of low concentration 16 g Н3ВО3/kg Н2О
✓ The pressure pipelines of the two JNG trains are connected to the two loops of the primary circuit coolant
system so that half of the flow is directed to the cold leg and the other half to the hot leg. The other two trains
are connected to the pipelines from Emergency core cooling system, passive part hydro accumulators to the
reactor (see slide above)
15
Low pressure safety injection system (JNG10)
Anticipated operational occurrences - DBC 2
✓ In anticipated operational occurrences, requiring RP cooldown to cold state, the system provides
residual heat removal and RP cooldown in the temperature range from 130 °C to 60 °C at a rate of
30 °C/h together with the JNA system.In case of LOOP, the system is operable since it is energized
from the emergency power supply system.
Design basis accidents - DBC 3&4
✓ In design basis accidents the system provides reactor plant cooldown on the condition of
maintenance of the primary circuit integrity (jointly with the JNA system) and residual heat
removal from the core
✓ The emergency process signals start the JNG10 system pumps. When the JNG10 pumps start by
emergency signals and the primary circuit pressure exceeds 2.5 MPa the pumps operate in the
recirculation line. When the pressure in the primary circuit is reduced below 2.45 MPa, and the
required flow rate in the discharge line is achieved the recirculation line valves are closed and the
pumps begin feeding the boric solution from the sump tank to the reactor
System functioning under external impacts
✓ The system is able to perform all its functions under all design external impacts. The system is
protected from impact of external natural and man-made events: earthquakes, hurricanes,
extreme temperatures, shock waves and aircraft crash. 16
TOPIC QUESTIONS
17
Emergency boron injection system (JDH)
The system purpose and functions
✓ The emergency boron injection system is intended for performance of the following functions:
• Injection of boric acid solution to the pressurizer steam volume at primary-to-secondary leak accident
(PRISE)
• Supply of boric acid high-concentrated solution (40 g Н3ВО3/kg Н2О) into the primary circuit for quick
transfer of the reactor plant into subcritical condition under anticipated operational occurrences in
case of reactor trip failure.
21
Emergency gas removal system (KTP)
The system purpose
Emergency gas removal system (EGRS - KTP) is intended for steam-gas mix
removal from RP primary circuit (reactor and SG collectors) and primary pressure
decrease during the operation of safety systems, to reduce consequences of
design basic accidents (DBA) and beyond design basis accidents (BDBA)
✓ During the design basis accident:
• The system shall provide for mitigation of consequences of beyond design
basis accidents by means of removal of steam-gas mixture from RP primary
circuit (reactor and SG collectors)
• Under DBA and BDBA without the core melting conditions the system shall
provide, if necessary, for removal of team-gas mixture from RP primary
circuit (reactor and SG collectors) into containment or relief tank for creation
of the closed circuit of coolant circulation in Reactor Coolant System (RCS)
22
Emergency gas removal system (KTP)
✓ During unit operation at power the system operation is not necessary. In RP
planned cooldown mode, the EGRS (KTP) is used by operator (when
appropriate) for cooldown of reactor upper unit and SG headers, by opening of
respective paths to relief tank. In case main coolant pumps are switched off,
Reactor pressure vessel head cooling is controlled by system operation.
✓ In case of DBA (DBC 3&4), the EGRS can be used by operator from upper
points of primary circuit (Reactor, SG headers)
✓ In case of BDBA (DEC), related to core melting, the system, in pursuance of
BDBA management instruction (SAMG), is used for primary pressure decrease
to 1 MPa jointly with PRZ relief valves and/or Emergency Pressure Reduction
System by medium discharge into the containment in order to avoid rupture
of the reactor vessel at high pressure.
23
TOPIC QUESTIONS
24
System of residual heat removal (JNA)
• System of residual heat removal (JNA) is designed for the removal of
residual heat and reactor plant cooldown during normal shut down of the
plant, during anticipated operational occurrences and during design basis
accidents on the condition of preserving the integrity of the primary circuit
jointly with Low Pressure Safety Injection System JNG10
• Residual heat removal system JNA is also designed for primary circuit
protection against overpressure in cooldown and residual heat removal
modes at low temperatures of the primary circuit
• The residual heat removal system has the structure 4x50% of the trains
• Two safety valves are designed for overpressure protection of the reactor
at low temperature (below 130 °C ) under brittle strength conditions
• The pumps and heat exchangers of low-pressure safety injection system
JNG10 are used for organizing coolant circulation in the JNA system and for
heat removal from the reactor core
25
System of residual heat removal (JNA)
Normal operation – DBC 1
• When the reactor is in power operation, functioning of the JNA system is not required. The system is
disconnected from the primary circuit.
✓ Scheduled cooldown
• The system provide the reactor plant cool down at the primary circuit temperature from 130 °C to 60 °at
the of 30 °C/h С (in the initial period of cooldown) ) with operating Main Coolant Pumps (MCP) and 15
°C/h under natural circulation. The difference of coolant temperature and temperature of water feed to the
primary circuit shall be maximum 50 °C
• The work for connection of the residual heat removal system, jointly with the low pressure injection system
begin at the primary circuit temperature about 150°С for primary circuit cooldown function
• After the temperature in the primary circuit reaches 60 °C , MCPs are switched off and cooldown controller
task is changed. It is set for constant temperature maintenance mode at outlet from the reactor core
✓ Reactor plant repair cooldown (condition with decreased coolant level in the reactor pressure vessel)
• The system is used also for removal of heat from the cooled down reactor during repairs of the reactor plant
main equipment. In this case, the level in the reactor vessel needs to be reduced below the level of the hot
legs of primary circuit loops. The coolant flow opposite to the normal direction - it is taken from the lower
chamber of reactor and returned to the upper mixing chamber of the reactor.
• In case of a design basis accident not associated with a primary circuit leak, system JNA together with
system JNG10 ensure switching of the Unit into cold state
26
System of residual heat removal (JNA)
27
TOPIC QUESTIONS
28
Secondary circuit overpressure protection system
29
Secondary circuit overpressure protection system
✓ The secondary circuit overpressure protection system components are included into
the main steam valve units installed one per each steam line. Each main steam valve
unit includes two pulse safety devices for steam generators (SG PORV), one steam
dump valve to atmosphere (BRUA) and one shut-off valve upstream the BRU-A
✓ SG PORVs consist of a main valve operating from its own environment and two pulse
valves which can operate as an electromagnetic in accordance with the signals from
the protection system and as a direct-action valve when there is no power supply
✓ The BRU-A is an electrically-driven control valve. Normally is in an intermediate
position. The control is provided by two and control electrically-driven valves
mounted on the main valve body. Shut-off valve installed upstream is a piston
operated valve operating from its own environment. Normally closed
✓ The design stipulates automatic activation of the system, without intervention of the
operator. The automatic system activation takes place when the pressure in the
secondary circuit increases up to the valves actuation set point
30
Secondary circuit overpressure protection system
34
Emergency Feedwater System (LAR/LAS)
The emergency feedwater system is designed to provide feedwater supply to SGs
when the feedwater supply from the main and auxiliary feedwater systems is
impossible.
• Emergency feedwater supply to the steam generators in case of LOOP
• Can be used for residual heat removal from the reactor plant trough SGs by
discharging steam into the atmosphere through the BRU-A (open loop) or in
a close loop through BRU-K
• The system consists of four identical trains fully independent from each other
with a capacity of 100% each. Each train provides for one emergency feed
pump, valves and pipelines
• Provides for water supply from each train of the system to one steam
generator
• Four make-up water system (LCU) tanks with a capacity of 700 m3 each are
used for demineralized water storage
• The total capacity of tanks enough for unit maintaining in "hot" standby
mode for at least 24 hour
35
Emergency Feedwater System (LAR/LAS)
37
TOPIC QUESTIONS
38
Reactor trip system (control and protection system actuator set)
39
Reactor trip system (control and protection system actuator set)
System design
✓ Control and Protection System (CPS) actuator set consists
of 121 Rod Cluster Control Assemblies (RCCA) engaged
with extension shafts of Control Rod Drive Mechanisms
(CRDM).
✓ RCCA consists of 18 individual neutron absorbing rods
connected (by springs and nuts) at one end to a common
hub (head) and positioned within fuel assembly guide
thimbles by a dedicated drive mechanism.
✓ The absorbing rod is a cladding sealed with the end pieces
by welding from both ends: from the bottom - by a cone,
from the top - by a tip. The cladding internal space is filled
with the absorbing material B4C. 40
Reactor trip system (control and protection system actuator set)
System design
The RCCAs drives mechanisms are located on
the reactor top head. All RCCAs are divided into
12 groups, each comprising from six to 12
RCCAs.
Groups with numbers 12, 11, 10 and 9,
containing six, seven, nine and twelve RCCAs,
respectively, are referred to the control groups.
Group No 12 is the CPS CR working group.
41
Reactor trip system (control and protection system actuator set)
✓ In normal operation conditions all RCCAs are above the core except for control grope No. 12.
Anticipated operational occurrences - DBC 2
✓ To fulfill the reactor preventive protection (PP) function the system according to the
preventive protection initiation criteria together with the drives and CR shall ensure a
decrease in the power or prohibition of increasing the power to prevent the reactor scram
and/or violations of the limits and conditions of safe operation. To fulfill this function it is
provided for:
• Preventive protection PP-2 when the monitored parameters reach respective setpoints,
• The accelerated preventive protection (APP) comes in action when malfunctions in
operation of main equipment of the power unit occur (for example switching off main
coolant pumps. APP is realized by either dropping certain CPS CRs group or from the MCR
operator’s switch.
System functioning in case of design basis accidents - DBC 3 and 4
✓ To fulfill the reactor emergency protection function the system according to the initiation
criteria shall quickly shutdown the reactor bringing it to the subcritical state.
42
Reactor trip system (control and protection system actuator set)
System functioning in case of design basis accidents - DBC 3 and 4
✓ In accident conditions in response to a signal of emergency protection all
electromagnets are deenergized, the latches are open and the extension shafts with the
RCCAs drop downwards by gravity for less than 4s.
System functioning in case of design extension conditions (DEC)
✓ Complex sequences (without fuel melting) / The system fulfill the same function as in
the modes of DBC 3 and 4 except for ATWS accidents (Anticipated transients without
scram).
✓ Severe accidents / Control rods are melted.
System functioning under external impacts
✓ The reactor trip system is able to perform all its functions with external impacts
accepted for this design.
✓ The system is protected against external impacts, natural disasters: earthquakes,
hurricanes, extreme temperatures.
43
TOPIC QUESTIONS
44
Borated water storage system (JNK)
The system purpose and functions
✓ JNK system is intended for storage of low concentration (16-20 g H3BO3 / kg
Н2O) and high concentration (39,5-44,5 g H3BO3/dm3 Н2O) borated water for
NPP operation in all operation modes for:
▪ emergency core cooling during Loss of Coolant Accidents(LOCA) or into the
containment during Break of The Steam Line inside the containment
▪ supply of borated water for the initial filling of the Core Catcher heat-exchanger at a
Severe Accident (SA)
▪ primary circuit boron concentration control under Normal Operation Conditions
(NOC) and Anticipated Operational Occurrences(AOO) – modes of DBC 2;
▪ borated water injection into the pressurizer at Primary-to-Secondary Circuit
Leakage - mode of DBC 3&4;
▪ borated water injection into the reactor during ATWS - modes of Complex
sequences at DEC.
45
Borated water storage system (JNK)
47
Borated water storage system (JNK)
48
Borated water storage system (JNK)
Design Extension Conditions
Complex sequences
✓ borated water injection into
the reactor during
Anticipated Transients
Without Scram (ATWS)
from high concentration
borated water sump tanks
Severe accident
✓ supply of borated water for
the initial filling of the Core
Catcher heat-exchanger
from low concentration
borated water tanks
49
TOPIC QUESTIONS
50
Emergency Core Cooling System (ECCS) Passive part
The system purpose and functions
✓ ECCS Passive part is intended for quick boric acid solution supply into the Reactor Vessel (RV) for
core cooling and its flooding in case of Loss of coolant accident (LOCA)
✓ At LOCA the system providing supply of borated water to reactor core when the primary pressure
below 5,9 MPa without operator action passive way.
✓ The system shall provide pressure of 5.9MPa inside the tanks of hydro accumulators by nitrogen
(N2) blanket and 50 m3 of borated water in each tank.
✓ On the connecting pipes from the hydro accumulators are placed two quick acting cut-off valves
which are intended to close automatically when the level inside a hydro accumulators becomes
critically low. The objective of these cut-off valves is to prevent entry of nitrogen in primary circuit.
✓ The means are provided for monitoring and control of system during normal operation, accidents
and post accident period.
✓ The system equipment is powered from normal and emergency electric supply systems
(batteries).
51
Emergency Core Cooling System (ECCS-JNG), Passive part
53
Emergency Core Cooling System (ECCS-JNG), Passive part
✓ At decrease in the accumulators level down to 1250 mm quick-acting isolation gate valves are
closing automatically to prevent entry of nitrogen into the reactor.
✓ No operator’s intervention in control of the system is required during 30 min after the beginning
of the accident.
Design extension condition - DEC
✓ The water storage in the system could be used if primary circuit of the nuclear unit to remains
intact. Such option are usually considered as alternative operator actions in EOP or strategy in
SAMG for prevention of severe accident.
* EOP – Emergency operator procedures, SAMG – Severe accident management guidelines
55
CONTROL QUESTIONS to ECCS-JNG), Passive part
How many independent channels are included into
system design?
1. What medium are provided pressure into the
hydro accumulators?
2. In what Design condition the operator may
activate the system?
56
Primary Circuit Overpressure Protection System
60
REFERENCES
Editorial note
This presentation may contain information from public open sources and external Internet web sites referred hereto.
The author does not guarantee that the content of such sources will remain actual, accurate or appropriate.
62
Disclaimer
This presentation has been prepared
by a representative of Worley.
To the extent permitted by law, Worley and its officers, employees, related
bodies and agents disclaim all liability—direct, indirect or consequential
(and whether or not arising out of the negligence, default or lack of care
of Worley and/or any of its agents)—for any loss or damage suffered by a
recipient or other persons arising out of, or in connection with, any use or
reliance on this presentation or information.