Qoutation of Fire Protection
Qoutation of Fire Protection
SCOPE OF WORKS
QUOTATION OF FIRE PROTECTION SYSTEM
MATERIAL COST LABOR COST 50%
ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT PRICE AMOUNT UNIT PRICE AMOUNT
ELECTROMACHANICAL WORKS
C VALVES
Zone Valves
1 OS&Y Zone Control Valve 4"Ø Flanged Type 6 no. 21,410.00 128,460.00 10,705.00 64,230.00 192,690.00
2 Butterfly Isolation Valve 4"Ø Flanged Type 2 no. 25,278.00 50,556.00 12,639.00 25,278.00 75,834.00
3 Alarm Check Valve 4"Ø 1 no. 38,500.00 38,500.00 1,200.00 1,200.00 39,700.00
4 OS&Y Test Valve 3"Ø Flanged Type 1 no. 18,564.00 18,564.00 1,200.00 1,200.00 19,764.00
5 Ball Type Foot Valve 4"Ø 1 no. 12,850.00 12,850.00 1,200.00 1,200.00 14,050.00
6 Foot Valve Perforated screen strainer 1 1/2"Ø 1 no. 5,750.00 5,750.00 1,200.00 1,200.00 6,950.00
7 Brass Gate Valve 1/2"Ø 6 no. 760.00 4,560.00 1,200.00 7,200.00 11,760.00
8 Brass Gate Valve 1 1/2"Ø 2 no. 1,093.00 2,186.00 1,200.00 2,400.00 4,586.00
9 Brass Gate Valve 1"Ø 7 no. 975.00 6,825.00 1,200.00 8,400.00 15,225.00
10 Fire Hose Valve 1 1/2" 5 no. 4,700.00 23,500.00 1,200.00 6,000.00 29,500.00
11 Fire Department Connection 100mmx65mmx65mm 1 no. 14,685.00 14,685.00 1,200.00 1,200.00 15,885.00
Sub-Total 834,349.00 383,464.50 1,217,813.50
3-Jan-25
Ref No. FPS-0015
Project: FIRE PROTECTION SYSTEM
Location: LEGAZPI CITY
SCOPE OF WORKS
QUOTATION OF FIRE PROTECTION SYSTEM
MATERIAL COST LABOR COST 50%
ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Fire Hose Cabinet Recessed Type w/100ft Double Jacket 5 set 20,900.00 104,500.00 10,450.00 52,250.00 156,750.00
E ASSORTED ACCESSORIES
1 Sprinkler Head
Pendent Sprinkler Head 125 no. 521.50 65,187.50 260.75 32,593.75 97,781.25
Alarm Bell
1 Gong Alarm Bell 1 no. 1,180.00 1,180.00 590.00 590.00 1,770.00
Fire Extinguisher
1 Portable Fire Extinguisher 9.46L 5 no. 8,812.00 44,060.00 4,406.00 22,030.00 66,090.00
G FIRE PUMP
Fire pump set consist of end suction centrifugal pump
driven by electric motor and vertical jockey pump. Pumps
are assembled with discharge line accessories as well as
control panel.
Fire pump:
power electric; 22kw, 30Hp (Q: 250gpm, H:100psi) 3phase,
1 lot 398,000.00 398,000.00 199,000.00 199,000.00 597,000.00
3500rpm, inlet/outlet 65x50mm, voltage 220v60Hz,
Jockey pump
power: 3.0Hp, flow 20gpm, HMT: 160psi, Inlit/outlet
25x25mm, speed 2900rpm
H CONVENTIONAL SYSTEM (FDAS)
1 Manual Pull Station 5 no. 685.00 3,425.00 342.50 1,712.50 5,137.50
2 Conventional Smoke Detector 2 wire 20 no. 325.00 6,500.00 162.50 3,250.00 9,750.00
3 THHN Electrical Wire 2.0 3 box 3,400.00 10,200.00 1,700.00 5,100.00 15,300.00
4 Conventional Heat Detector 6 no. 425.00 2,550.00 212.50 1,275.00 3,825.00
5 Conventional Fire Alarm Control Panel (CFACP) 1 no. 11,365.00 11,365.00 5,682.50 5,682.50 17,047.50
SCOPE OF WORKS
QUOTATION OF FIRE PROTECTION SYSTEM
MATERIAL COST LABOR COST 50%
ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT PRICE AMOUNT UNIT PRICE AMOUNT
Dear Madam/sir,
As per your request, we are pleased to submit our proposal for the above
mentioned subject as per attached materials list including labor cost.
MODE OF PAYMENT
1 30% down payment upon signed the approved quotation and contract.
2 30% upon completed installations of the riser pipe, mainline, and sub-mainline
3 20% upon completed installation the sprinklers heads and ready to install the fire pump sytem
4 10% upon completed the scope of works.
5 10% upon completed the duration piriod of retension
LEAD TIME OF ACCOMPLISHMENT
1 Mobilization upon received the down payment or go signal from the owner
2 scope of works will be completed with in ninety (90) working days except when the site
are workable and ready .
WARRANTY
1 The fire pump system are guaranteed for twelve (12) months
except damaged was due to force major events or done by any third party.
2 The plumbing/piping system are guaranteed for a period of twelve (12) months
except damaged was due to force major events or done by any third party.
3 The (FDAS) system are guaranteed for a period of twelve(12) months
upon fully operational except damaged was due to force major events or done by any third party.
Note…
a.. Our Quotation / price are valid only within 30 days from the date of submission
b.. The owner should provide temporary electric power & water supply on the site
c. Those not mentioned on the scope of work and contract will be automatically additional cost.
Thank you for giving us an opportunity to quote and hope it will meet your requirements.