Method Statement For Backfilling 0001

Method statement backfilling
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views8 pages

Method Statement For Backfilling 0001

Method statement backfilling
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Client: Consultant: Contractor:

METHOD STATEMENT
Project

METHOD STATEMENT NO: 0 REV: 00

Method Statement for Backfilling

REVIEWER /
REV DATE STATUS REVISION DETAILS APPROVER

00 FA First submission for approval.

Prepared by Reviewed by Approved by


Project Manager
QA/QC Engineer QA/QC Manager

Method Statement for Backfilling Page 1


Client: Consultant: Contractor:

Table of Contents

1. INTRODUCTION
2. SCOPE
3. REFERENCES
4. RESPONSIBILITIES / SUPERVISION
5. RESOUCES
5.1 TOOLS AND EQUIPMENTS
5.2 PERSONNEL
6. QUALITY ASSURANCE/CONTROL
7. PROCEDURE
8. HEALTH AND SAFETY
9. DISTRIBUTION
10. INSPECTION TEST & PLAN (I.T.P)

Method Statement for Backfilling Page 2


Client: Consultant: Contractor:

1. INTRODUCTION

This method statement outlines the procedures and methodologies to be


employed by for the backfilling works at XYZ project XYX. It provides a
comprehensive overview of the activities, equipment, materials, quality control
measures, safety precautions, and environmental considerations associated
with the backfilling process.

This section included procedural requirement for the methodology of


backfilling work.

2. SCOPE:

This method statement provides the controlled sequence of the methodology


that will be used for backfilling Works to achieve the required grades and
compaction levels as specified in the project drawings and specifications. This
is to ensure that all activities are in fully compliance health and safety
standards.

3. REFERENCES:

 Project Specifications
 Project Quality Plan

4. RESPONSIBILITIES / SUPERVISION:

 The Construction Manager is responsible for overseeing the overall


implementation of this method statement and ensures that his team of
Engineers, Foreman and subcontractors are aware of this method
statement and the all resources – human, material and equipment’s are
available to carry out the work as planned and without any delay.

 The Site Engineer is responsible for Coordinating the backfilling


activities to carry out the work as per the approved shop drawings, and
in accordance with this method statement. He is also responsible to
ensure compliance with project requirements.

 The QA/QC Engineer is responsible to conduct regular inspection during


the backfilling process to ensure compliance with the project
specification.
Verify thickness of each layer and the compaction density using
appropriate testing methods (Nuclear density gauge or sand
replacement method).

 The Safety Engineer is responsible to ensure all personnel involved in

Method Statement for Backfilling Page 3


Client: Consultant: Contractor:

the backfilling works are trained and certified in equipment operation and
safety procedures as per the project safety plan, and all the personal on
site are using the required Personal Protective Equipment’s like –
Helmet, Gloves, Shoes.

 The Site Surveyor is responsible to establish reference points and


benchmarks to guide the backfilling process. Marking the boundaries and
conducting periodic surveys during the backfilling process and
conducting survey upon completion of the backfilling works to record the
final dimensions and alignment of the backfilled area.

 The Operators are responsible for operating the necessary equipment


(excavators, dump trucks, compactors and rollers) safely and efficiently.

5. RESOURCES:

5.1 Tools & Equipment

 Excavators with appropriate bucket sizes.


 Dump trucks and other transportation equipment’s.
 Loaders.
 Vibratory rollers.
 Water tanker.
 Surveying equipment’s.
 Safety helmets, vests, etc.

5.2 Personnel

 Construction Manager
 Site Engineers
 Surveyor
 QA/QC Engineers
 Safety Officer
 Site Foreman
 Operators
 Laborer’s

6. QUALITY ASSURANCE/CONTROL:

Method Statement for Backfilling Page 4


Client: Consultant: Contractor:

QA/QC Engineer should verify the work has been carried out as per approved
shop drawings and Inspection Request to be raised for the Backfilling and the
required tests.
However, the following points shall be ensured, in particular;

 Monitor the backfilling process closely to ensure compliance with project


specifications and quality standards.
 Conduct regular inspections and tests after layers as required to verify the
quality of the backfilled material and achieved compaction.
 Ensure that backfill material is sourced from approved location and
doesn’t contain contaminants that could harm the environment and
compaction.
 Implement erosion control measures to prevent soil erosion during and
after the backfilling process.
 Skilled operators and laborers are assigned for the job.

7. PROCEDURE:

A. Site Preparation

 Identify the areas requiring backfilling as per the project drawings and
specifications.

 Clear the area of any debris, construction materials, or


obstructions.
Ensure that the excavation is completed and any necessary inspections are
carried out before backfilling commences.

B. Backfill Material Selection

 Verify the type and quality of backfill material specified in the project
documents.

 Ensure that the backfill material is free from organic matter, debris or
contaminants.

 If using engineered backfill material, ensure compliance with


specification regarding gradation, compaction and other properties.

C. Backfilling process

 Begin backfilling from the bottom of the excavation, layer by layer,


ensuring even distribution and compaction.
 Place the backfill material in maximum allowable lifts, typically not
exceeding 300mm thickness for cohesive soils and 200mm for
granular soils.

Method Statement for Backfilling Page 5


Client: Consultant: Contractor:

 Compact each lift using suitable compaction equipment to achieve the


specified compaction density.
 Maintain uniform moisture content in the backfill material to facilitate
compaction.
 Pay special attention to the corners and edges of the excavation to
ensure proper compaction and support.
 Use hand tools or small equipment for backfilling near sensitive areas
or utilities to avoid damage.
 Perform periodic checks using surveying equipment to ensure proper
levels and alignments are maintained.

8. Health and Safety:

A. Personal Training and P.P.E

 All personnel involved in the backfilling process must undergo


comprehensive training in safety procedures and the operation of
relevant equipment.
 Personal Protective Equipment (PPE) such as hard hats, gloves,
safety boots, high-visibility vests, and eye protection must be worn at
all times during the activity.

B. Traffic Management

 Implement a traffic management plan to ensure the safety of workers


and other site personnel.
 Clearly mark out designated pedestrian walkways and vehicle routes.
 Ensure that heavy equipment operators are trained in traffic management
procedures and communicate effectively with ground personnel.

C. Equipment Operation

 Follow proper procedures for the operation of heavy equipment such as


excavators, dump trucks, and compaction machinery.
 Ensure that equipment operators are competent and certified to operate the
machinery safely.
 Conduct regular inspections and maintenance of equipment to prevent
malfunctions and accidents.

9. DISTRIBUTION:

Copies of this method statement will also be issued to the following for
information/ action/comments: -

Method Statement for Backfilling Page 6


Client: Consultant: Contractor:

 Project Manager
 Construction Manager
 Site Engineer
 HSE Manager
 QA/QC Manager

10. INSPECTION AND TEST PLAN

Method Statement for Backfilling Page 7


Client: Consultant: Contractor:

INSPECTION AND TEST PLAN

WORK SCOPE Backfilling

PART 1- APPROVALS REQUIRED PRIOR TO COMMENCEMENT OF THE WORKS


Item Description of Operation/Inspection, Test Frequency of Inspection Records Hold, or Witness Point
No. and Approval & Test Plan Generated Subcon
Approved
1 Shop Drawings Once Sub R R&A
Drawings
2 Method Statement, Once MST Sub R R&A
3 Inspection & Test Plan Once ITP Sub R R&A
Note*- All deviation from the approved drawings/documents to be recorded and discussed with the Main Consultant prior
to proceeding.
PART 2- INSPECTION AND TEST DURING CONSTRUCTION WORKS
Frequency of Hold, or Witness Point
Item Description of Operation/Inspection, Test and Records
Inspection & Test
No. Approval Generated Subcon
Plan
Each layer of backfilling By
1 IR H H I&A
(with FDT test report) Area/Stages/Layout
Final inspection after backfilling completion By
4 IR H H I&A
(with FDT, Plate load test report) Area/Stages/Layout
Abbreviations: Sub- SUBMIT, H- HOLD, R&A- REVIEW & APPROVE, RC- RANDOM CHECK, I&A- INSPECT &
APPROVE, S- SURVEILANCE, CL= CHECKLIST, IR- INSPECTION REQUEST, I- INSPECT

Method Statement for Backfilling Page 8