Module 4 Contract Management
Module 4 Contract Management
Tender
The tender is an offer in writing to execute some specified work or to supply the
materials at certain rates within a fixed time under the certain conditions of
agreements between the contractor and department or owner of any party.
Tenderer: A person or a firm who tenders bid in response to invitation for tenders.
Tendering: The process of inviting bids and accepting them is known as tendering.
1. lower bids that may be obtained due to competition among the contractors.
2. selection of contractors can be made based upon their experience in their line.
Classification of Tender
1. Open tender
1. Open tender :
Tender usually published in the newspaper and internet chosen on the basis
of price and quality.
No favoritism occurred
maximum competition
The wrong contractor may be chosen because they are from unknown
background
Time consuming
3. Negotiated tender
Under this method, only one contractor is approached normally because the
skills of the contractor are such that the architect and other members of the
design team needed from the contractor’s specialist knowledge use for
design stage.
Following the completion of the design, the contractor will price the bill of
quantities and then enter into a negotiation with the quantity surveyor.
Pre-qualification
Administrative approval:
Technical Sanction:
Tender document:
The following tender documents are made available along with the tender forms to
enable contractors to bid for the job.
1. Notice inviting tenders (NIT) in a standard approved form of a department.
5. Bill of quantities
6. Schedule of tools and plant and other facilities to be made available by the
owner, indicating the conditions, hire changes and the place of delivery.
7. Schedule of stores to be issued by the owner indicating the rates and their place
and issue.
work.
5. Acceptance of tender
1. Tender notice
Whenever works are to be let out on contract, tenders are to be invited from the
registered contractors or both registered and unregistered contractors depending on
the magnitude and nature of the work by issuing notice in newspapers. The notice
that includes various particulars of work is named as Tender Notice. It is essential
that tenders be given adequate publicity so that a sufficient number of contractors
may bid and the most attractive offer may be obtained. At the same time it is also
necessary that bids be obtained from contractors who have the capability and
capacity to undertake the work.
Tenders are publicized by the issue of a notice inviting tenders, which indicates (1)
name and description of the work (2) estimated cost (3) completion time (4)
earnest money payable indicating the manner in which payment is to be made (5)
security deposit (6)time and place where tender documents may be inspected or
obtained (7) last date and place of obtaining tender papers and submission thereof
(8) time and place of opening the tenders (9) authority competent to accept tenders.
The tender notice may be advertised in newspapers and issued to registered
contractors by post. Copies of the tender notice are
Time limits for tender notice
Following time limits between date of call for tenders and the date of opening of
the tenders are followed by central public works department.
Up to 1 lakh 10 days
According to the directions contained in the notice inviting tenders, the contractor
are required to submit their tender on or before the date and hour fixed for the
same duly filled in, signed and witnessed. Before that he has to deposit the earnest
money deposit usually 2 to 2.5% of the estimated cost put to tender.
The sealed tenders are received are to be opened in the presence of the contractors
or their representatives tendering for the wok at the time and place already notified.
The divisional accountants should also be requested to be present on such occasion
wherever possible. The officer opening the tenders has to read out the rates offered
in case of item rate and percentage ate tenders and the amount in case of the lump
sum tenders for the information of all those present.
Comparative statement of percentage rate and lump sum tenders are made out by
the officer opening the tender. It contains the information regarding the name of
the contractor, date of receipt of tenders, percentage above or below the rates
entered in the tender document, amount in case of lump sum tenders. The
recommendations or orders regarding acceptance or rejection of the tender are
recorded on it.
5. Acceptance of tender
After investigation the comparative statement the lowest tender shall be accepted
as a rule by the competent authority. If for any reason, economical or otherwise,
the lowest tender is not accepted, reasons should be recorded confidentially and
reference shall be made to the tender committee or next higher authority for order
as to which of the contractors the work should be given. No tender can be accepted
or the circumstances under which lowest tender may be rejected.
Followings are the conditions under which the lowest tender may be rejected:
1. When the tender is informal (i.e. not submitted in the form as prescribed by the
department or within due date),
2. If it is not technically sanctioned or exceeds the sanctioned amount for the work.
After the acceptance of the tender the preparation of contract document, it the
contractor is required to pay a the security deposit before the contract agreement is
signed. The contract agreement should be executed in the prescribed form and
signed by the contractor or is authorised representatives and the authority on the
behalf of Government.
Work order:
This type of agreement is used for petty works. In this case No formal agreement is
drawn up with the contractor as in the case of piece work, when the work is
awarded by the work order. It can be used in situations where it is not possible to
call tender for petty works. The money limit is different in different states.
Sometimes in work order time limit with in which the work is to be completed can
be specified. Contractors are usually selected by taking quotations. payment is
made on the measurement of work and 10 percentage of total amount is deducted
from the running account bill as security deposit and which will be refund date in
the final payment on the satisfactory completion of work.
The contractor shall within 10 days of the received of the return order to take up
work, He has to supply one site order book to the sub divisional officer/ Assistant
Executive Engineer concerned. The site order book shall have machine number
pages in triplicate and will be initialed by the Assistant Engineer Incharge. This
site order book shall be kept at the site of work under the custody of the Assistant
Engineer or is authorised representative. important points related to site order book
are:
2. The contractor or his authorised representative shall regularly note the entries in
the site order book and may take any of the duplicate page of the site order book
for his own record.
3.In case of supplementary( extra climes) five terms of claim shall not be
entertained unless supported by entries in this site order book or any written order.
4. The site order book shall be enclosed along with the Final bill to verify the
Supplementary climes.
It is the amount, which the contractor has to deposit with the department at the
time of submitting a tender. This accompanies the tender form and this is usually
2% of the total estimated cost of the project. This serves as a check to prevent the
contractor from refusing to accept the work when the tender has been accepted.
The other objects of collecting earnest money are:
3.To act as compensation: When the lowest contractor refuses to take up the work,
the work can be allotted to the second lowest contractor. The earnest money
forfeited from the first lowest contractor compensates to loss of the department.
The contractor has to deposit about 10% of the tendered amount with the
department as soon as his tender is accepted. This is inclusive of the earnest money
already deposited by the contractor. This money is kept as a check so that the
contractor fulfils all the terms and conditions of the contract and carries out the
work satisfactorily in accordance with the specification and maintains satisfactory
progress for completion of the work. In case he fails to fulfill the terms of the
contract, the whole of the security money or part of it is forfeited by the
department. When the contractor completes the work as per drawings,
specifications and directions of the department within the specified time, the
security money is refunded to the contractor. Normally the security deposit is
refunded after the maintenance period, which may be 6 to 12 months after the
completion of work, and it’s handing over to the department.
Retention Money
A contract is the agreement entered into voluntarily by two or more parties who
promise to exchange money, goods, or services according to a specified schedule
and are legally enforceable.
The Contracts or agreements between various parties are framed and validated by
the Indian Contract Act. Contract Act is one of the most central laws that regulates
and oversees all the business wherever a deal or an agreement is to be reached at.
The following section will tell us what a contract is.
Contract Formulation:
2. Award of contract
Notice to a bidder of the acceptance of the submitted bid.
Written confirmation of an award of a contract by client to a successful
bidder.
Stating the amount of the award, the award date, and when the contract will
be signed.
3. letter of acceptance
Written communication by a successful bidder to client.
Formal acceptance of the bided project.
Confirms the details of the client's offer including the project cost,
perquisites, conditions and project duration.
4. Notice to proceed.
Letter from the client/ owner) to a contractor stating the date that the
contractor can begin work subject to the conditions of the contract.
The performance time of the contract starts from the NTP date.
Types of Contract:
4. Labour contract
In this type of contract, the contractor undertakes the construction work or the
execution of the specified work and completes it in all respects for a fixed amount
of money. detailed specifications of all items of works, detailed drawings, plans
etc., are supplied by the department to the contractor. The contractor on the basis
of given details, works out the total cost of the construction and quotes it in lump
sum. The design, shape and materials are as per the choice of contractor, but they
have to be got approved before the start of the work.
Advantages:
The final price is known, by the owner, before the work commences.
The contractor has more incentive to reduce his cost to increase the profit.
The contractor hopes to complete the job as quickly as possible, to minimize
overhead, to maximize profit and to move to the next Job.
When level of risks is low and quantifiable, and When the client does not
wish to be involved in the management of his project.That can be accurately
and completely described at the time of bidding such as residential and
building construction.
When limited variation is needed.
The materials used on the temporary works during construction are relieved
earlier resulting in their effective use in other works also.
Disadvantages:
The owner tries to get the maximum work out of money he spends, whereas
the tries to get the maximum profit, this causes conflicting interests.
It becomes very difficult to adjust the additions and alterations in the plan
and the specifications at a later stage.
If the plans and specifications are not clear, the contractors will quote higher
rates, resulting in high cost of the work.
The contractor carries much of the risks. The tendered price may include
high risk contingency.
Competent contractors may decide not to bid to avoid a high-risk lump sum
contract.
2. Item Rate Contract (unit price)
In this type of contract, the contractor undertakes the work on the item rate
basis. The payment is done on the basis of quantities of items done and
payments are made on the basis of their respective rates. The quantities of
various items are worked out by detailed measurements. This type of contract is
also known as unit price contract. The approximate quantities of all possible
items of work are worked out and are shown in the tender form. Every
contractor quotes his rates against each item are arrives at the final total amount
of the work. This is the most common type of contract system, which is widely
adopted.
Advantages:
The additions and alterations in the plan and specifications can be easily
made at any stage.
As the contractor gets the payment against the actual quantities of items
done by him, the method is economical. No possibility for excess
payment.
As the rates are item-wise the contractor is not worried regarding the
uncertainties in the plan and specifications.
The work can be started after accepting the tenders without waiting for
all the detailed drawings and specifications.
Disadvantages:
The total cost of the work can only be computed after completion of
entire project.
In such case the owner may face financial difficulties if final cost
increases abnormally.
Before preparing the bills for payment of money to the contractor, all
measurements of various items of work have to be carefully taken and
suitably entered in the measurement book.
Great care shall be taken by the department officers to strictly enforce the
specifications during execution of work to avoid the using of substandard
materials by the contractor.
Contractor raises prices on certain items if he apprehends the quantity of
those items is likely to increase during execution and make
corresponding reductions of prices on other items, whose quantity likely
to reduce during execution. This increases total cost of the project.
In this type of contract the contractor agrees to take the work of construction for
fixed percentage over the actual cost of construction. This type of contract is
given when no contractor is agreeing to do work on other types due to
uncertainties and fluctuations in the market rates of materials and labour. The
department keeps the actual up to date records of the expenditure incurred on
the work and pays the fixed percentage as agreed over it to the contractor. The
contractor arranges for the labour, materials required for completion of the
work, and maintains proper account of the construction costs.
The contractor gets actual cost of construction plus an amount of fee (in
percentage of construction cost) which is inversely variable according to
increase or decrease of estimated cost agreed first by both the parties.
In this type of contract the contractor is reimbursed at cost with an agreed upon
fee up to the GMP (Guaranteed Maximum Price) which is essentially a cap.
Beyond this point the contractor is responsible for covering any additional cost
within the original project scope. Additionally an incentive clause is there,
which specifies that the contractor will receive additional profits as reward to
the contractors who minimizes the cost.
Contractor is paid the actual cost of the work and a variable percentage in
addition to allow for profit. Variable percentage allows the contractor to get
better profit for completing the work at minimum cost.
Advantages:
2. The contractor can take the this independently and the work can be
completed quickly.
1. The final cost cannot be determined before the completion of the work.
4. Labour contract
In this type of contract, all materials for the construction are arranged and
supplied at the site of work by the department or owner. The labour contractor
engages the labour and gets the work done according to specifications. The
contract is on item rate basis for labour portion only. The contractor is paid for
the quantities of work done on measurement of the different items of work at
the stipulated rate as in agreement. Contractor uses his own tools for working.
Plants and machineries are arranged by the department or owner. This system of
contract is not generally adopted in government works but preferable for private
sectors.
Advantages:
Disadvantages:
3. Theft from store, shortage of materials, accounting all the materials are
constant worries for a department.
In this form of contract, the contractors have to offer their rates for supply of
the required quantity of materials, inclusive of all local taxes, carriage and
delivery charges of materials to the specified site within the time fixed in the
tenders.
Contract Documents
4. Tender form: Contractor’s rates and time of completion, penalty clause, etc.
5. Bill of quantities: Giving quantities and rates of each item of work and the
total cost of the whole work.
9. Drawings: Complete set of drawings like plans, elevations, etc. and site plan,
of fully dimensioned
Conditions of Contract
Both parties of a construction team should be fully acquainted with their rights
and duties. So while preparing the contract agreement, certain clauses related to
the work are laid down and these will be binding on both parties. The main
purpose of the conditions of contract is to avoid dispute and keep the parties as
far as possible out of the court of law. Therefore it is imperative that all the
clauses of conditions of contract must be precise and definite and there should
not be any room for ambiguity or misconstruction therein.
The conditions of contract mainly depend upon the nature of the work. For most
of the civil engineering construction projects following clauses are mostly
provided in the contract documents:
4. Progress to be maintained
6. Mode of payment