A New Approach To Advanced Analytics in Utility Asset Management
A New Approach To Advanced Analytics in Utility Asset Management
A new approach to
advanced analytics in
utility asset management
Studying how one North American transmission and distribution
utility’s implementation of advanced analytics in asset management
can help other organizations embark on similar journeys.
This article is a collaborative effort by Anjan Asthana, Pranjal Dubey, Alfonso Encinas, Anand Mohanrangan,
Aditya Pande, Luis Fernando Rios Siliceo, Jesús Rodríguez González, and Willem van Schalkwyk,
representing views from McKinsey’s Electric Power & Natural Gas Practice.
© Ed Freeman/Getty Images
September 2022
Asset management can account for a significant UtilityCo: An overview
percentage of a transmission and distribution UtilityCo faced a number of key challenges that
(T&D) company’s operating expenses and capital are common in the industry. For example, the
expenditures, with optimized operations and utility didn’t take a risk-based approach when
investments key to generating savings. New making asset replacement decisions or prioritizing
technologies can enable companies to capture preventive-maintenance activities, and it had
these efficiencies. In fact, a recent McKinsey decentralized asset management operations, with
article explained how T&D utilities can leverage each operating company taking a distinct approach
advanced analytics in their asset management and methodology. In addition, although UtilityCo
strategies to unlock 10 to 20 percent in savings was able to collect valuable data, the data were
while improving overall reliability and performance underused and stored in multiple systems. Finally,
of their networks.1 UtilityCo relied on rules that oversimplified asset
management decisions—for example, the “three
This article builds on that thinking and takes a close strikes” rule, which called for replacing cables after
look at a North American T&D utility, which we they experienced three outages.
refer to as UtilityCo. In 2021, UtilityCo leveraged
advanced analytics in asset management to unlock
savings of 20 to 25 percent in operating expenses The results from advanced analytics
and 40 to 60 percent in capital expenditures, UtilityCo was able to effectively use advanced
which could then flow as savings into the profit- analytics in asset management in four ways. First, it
and-loss (P&L) statement or be reinvested to optimized capital expenditures either by maintaining
deliver significant reliability improvement. These current risk and spending less—and letting the
savings and increased investment capacity are excess capital expenditures flow into the P&L or
particularly relevant given today’s increasing be reinvested to deliver more reliability—or by
constraints, including pressure from customers spending the same amount and achieving higher
on affordability, inflation growth, supply chain reliability through replacing the riskiest assets.
bottlenecks, and the growing need for investments Second, it lowered preventive-maintenance (PM)
in the energy transition, such as renewable-energy operating expenses by optimizing PM activities.
solutions, electric-vehicle charging infrastructure, When successful, this optimization can deliver
and cybersecurity. Based on the success of the similar or better reliability at lower cost. Third, it
initial model, UtilityCo developed a road map lowered corrective-maintenance (CM) operating
that scales the asset management risk–based expenses by lowering spending on CM after those
approach to two-thirds of the capital portfolio over riskiest assets had been replaced. And fourth, it
two years. replaced the riskiest assets to help achieve higher
reliability (measured as lower SAIDI and SAIFI2
The following case study highlights the results performance) due to fewer failures.
of implementing advanced analytics at UtilityCo,
including the approach taken, the lessons Regarding capital expenditures for UtilityCo’s
learned, and the best practices to adopt for others transmission transformers, the company underwent
embarking on a similar journey. Although this a paradigm shift, collecting data about each dollar’s
article is presented as a stand-alone example, our impact on interrupted customer minutes. With this
experience shows that the results from applying new perspective, UtilityCo determined it could
advanced analytics to asset management are reduce risk approximately two to three times over
accelerated when deployed as part of a broader while spending the same amount, maintaining the
organizational transformation. same capital expenditures, and reducing customer
1
Rui de Sousa, David González Fernández, Jesús Rodríguez González, and Humayun Tai, “Harnessing the power of advanced analytics in
transmission and distribution asset management,” McKinsey, April 9, 2018.
2
System average interruption duration index and system average interruption frequency index.
Web <2022>
<EPNG UtilityX>
Exhibit
Exhibit <1>1 of <7>
The
The savings
savings potential
potential for UtilityCo’s
UtilityCo’s transmission
transmission transformers
transformers improved
by
by 40
40 to 60 percent
to 60 percent for
for capital
capitalexpenditures
expendituresand
andbyby 20
20to
to25
25percent
percentfor
for
operating expenses.
operating expenses.
Baseline and optimized capital expenditure Baseline and optimized operating expenditure
spend, $ millions preventative maintenance (PM) spend,
$ millions
Capital expenditure scenarios Operating High and medium health or criticality
expenditure Low health or criticality
scenarios
15 15 –40–60% –20–25%
1.0
1.2
1.0
7
0.5
0.3 0.2
1
Risk is a calculation of health score times criticality.
Source: McKinsey UtilityX analysis
Web <2022>
<EPNG UtilityX>
Exhibit 2of <7>
Exhibit <2>
A visualization
visualizationplatform
platformallowed
allowedUtilityCo
UtilityCototovisualize,
visualize,prioritize,
prioritize,and
and
implement new maintenance activities.
implement new maintenance activities.
Clickable dashboards
provide high
usability and
responsiveness
Maintenance-
actions dashboard
Risk map allows provides an
users to review overview of fleet
the risk level for maintenance and
each region and repair activities
identify geographic
patterns
UtilityCo implemented the asset manageable. Second, cross-functional needed to fill new technical roles, such as
management advanced-analytics teams were already working on various data scientists and engineers, and upgrade
solution as part of a broader business initiatives—for example, the IT and its IT infrastructure via cloud migration and
transformation. While the broader transmission and distribution (T&D) teams machine-learning platforms, among other
transformation wasn’t essential to were focused on workforce management— options. This was easier to do as part of
implement the advanced-analytics solution, and were thus able to build on these the transformation because UtilityCo was
it accelerated the adoption process. First, relationships to drive the advanced- already in the process of building a digital
UtilityCo had already adopted a change analytics initiative. Finally, to successfully center of excellence, which was able to
mindset, so the implementation of a new scale asset management to other assets manage these new functions.
asset management strategy was more and operating companies, UtilityCo
Web <2022>
<EPNG UtilityX>
Exhibit 3of <7>
Exhibit <3>
UtilityCo’s
UtilityCo’s approach
approach for leveraging advanced analytics was based on the
based on the
probability and cost of failure as well as on building an optimization engine.
probability and cost of failure as well as on building an optimization engine.
Description Outputs
Compute based on the following: asset in the Least critical/ Most critical/
probability of • historic outage data following year most healthy least healthy
failure (health) • structural data (eg, age
and manufacturer)
• environmental data
(eg, soil temperature and
water volume)
Criticality
2 Calculated the cost of
failure for each asset based
Cost of failure
for each
of asset Proposed
shift in
Define impact on the following: asset for the spending
of failure • repair following year
(criticality) • service
• safety
• environmental impact Health of asset
Risk/reliability
4 Generated multiple
scenarios to optimize the
Optimized list
of assets to be
Optimize schedule for the inspection replaced over the Long-term decision support
replacements or replacement of assets next year and
and inspection based on certain constraints; prioritized project-
eg, geography and age management
activities
UtilityCo’s
UtilityCo’s sequence for distribution
sequence for distribution assets wasbased
assets was basedon
onimpact
impactand
andfeasibility.
feasibility.
HIGH
Pole-top
equipment (eg,
poles, cross arms,
line transformers
Feasibility
Switches and
fuses (eg, overhead
and underground
switches, cutouts
and fuses)
Multi-assets
(eg, reclosers,
cross-asset
optimization)
LOW
LOW Impact HIGH
data (such as weather data, which stretched back number. Next, the data were divided into a training
a few years). A holdout data set3 was used to test set, which was used to train the machine-learning
the model performance. For example, when looking model, and a test set, which was used to help test
at the transmission transformers asset class, the the performance of the model after training (for
model was able to predict approximately 45 percent example, testing how often the model correctly
of failures in approximately 20 percent of the data predicted asset failure). Because UtilityCo was
(Exhibit 5). interested in going beyond a standard machine-
learning algorithm, it also incorporated a failure-
To build the health model, UtilityCo aggregated data mode analysis into the transmission-transformer
from several different systems, such as geographic models to support detailed assessments of
information and outage-management systems. probability of failure by component and to help with
The utility then cleaned and unified the data in the prioritization of condition-based maintenance.
preparation for the machine-learning model and
identified prediction targets. In some cases, the Finally, UtilityCo combined the outcomes from
process was straightforward, such as labeling a a previous engineering health model with the
transformer that had suffered an outage. In other machine-learning model to calculate the probability
cases, it was more difficult, such as when labeling of failure and improve performance.
a failed cable that was missing a serial or part
3
Holdout data, or test data, are historical, labeled data used for validating machine-learning models.
Gas tests
49.6
(eg, DGA1) Bottom decile
(predicted 26.1
worst health)
Structural data
(eg, age,
manufacturer) Corrective 18.8
maintenance 30.8
10.1
Preventative 8.7
maintenance 7.0
External data
(eg, weather)
18×
7.2
High-side voltage
1.4
8.7
Manufacturer 2.9
> 1.0
2.9
Network
configuration Top decile
0.1 (predicted 1.4
best health)
Web <2022>
<EPNG UtilityX>
Exhibit <6> of <7>
Exhibit 6
Key
Key dimensions are used
dimensions are used in
in calculating
calculating the
the cost
cost of
offailure
failure for
for aa typical
typical asset.
asset.
Type of impact Key indicators
Customer-service costs
Population density
Installation location
Safety
Length of cable
Number of phases
Repairs
optimize PM, a detailed failure-mode analysis incomplete or duplicated. For example, data from
was incorporated into the optimization engine to one asset class were missing installation dates. As
enable estimates of how much risk was removed a workaround, the manufacturing date was used
by each PM activity. In addition, the optimization instead. Developing data architecture and putting
engine factored in the cost required to perform processes in place to capture and perform quality
each of these activities and prioritized activities that control checks on the right types of data were key to
reduced the most risk at given costs. addressing this issue going forward.
First, the team faced internal resistance when During the advanced-analytics implementation,
getting started, including concerns about not having UtilityCo asset managers were asked to make
enough data, or the right data, to address regulatory changes to their management processes (see
considerations. The first key step to addressing this sidebar “Driving additional value from cross-asset
resistance was to implement a proof of concept, optimization”). The key to addressing this issue was
identifying assets that had good enough data to get to engage the asset managers early on and bring
started and developing a solution that was better them along as the solution was being developed.
than the current state. Success with the proof of
concept gave UtilityCo the confidence to proceed Finally, incorporating advanced analytics into the
with rolling out the solution across multiple assets processes for selecting assets for replacement
and operating companies. and updating maintenance processes and
policies based on model recommendation was
Another lesson involved data that were either siloed, an implementation and governance challenge.
scattered across several different systems, or Engaging subject matter experts (SMEs) early and
One of the key advantages of asset Because risk measurement is the same more on one asset over another based on
analytics is cross-asset optimization. across all assets, the risk-based approach estimated system average interruption
Once UtilityCo implemented advanced makes it easier to decide where to duration index (SAIDI) improvement
analytics for multiple assets, it was able to invest the next million dollars of capital per million dollars spent, resulting in
take a risk-based approach that allowed expenditures to achieve company- approximately 94 percent improvement to
replacement capital expenditures to wide objectives. For example, with the reliability (exhibit).
be invested in the assets that reduced objective of improving reliability, UtilityCo
risk and increased reliability the most. determined it was better off spending
Web <2022>
<EPNG UtilityX>
Exhibit
Exhibit <Sidebar> of <7>
Everything
Everythingbeing
beingequal,
equal,investing
investingreplacement
replacement capital expenditures in asset
asset 11 instead of asset 1 will lead to an improvement
11 instead of asset 1 will lead to an improvement in reliability
in reliability of
of approximately
approximately
94 percent. 94 percent.
7.5
6.2
4.6
–94%
2.9
2.1
1.8 1.7 1.6 1.6
0.9
0.5
Asset Asset Asset Asset Asset Asset Asset Asset Asset Asset Asset
1 2 3 4 5 6 7 8 9 10 11
Anjan Asthana is a senior partner in McKinsey’s Miami office; Pranjal Dubey is an engagement manager in the Bay Area
office, where Anand Mohanrangan and Aditya Pande are partners and Willem van Schalkwyk is an associate partner;
Alfonso Encinas is a partner in the Washington, DC, office; Luis Fernando Rios Siliceo is a consultant in the Monterrey office;
and Jesús Rodríguez González is a senior partner in the Madrid office.