17DCE59
17DCE59
PLANNING, SCHEDULING&ESTIMATION OF
GREEN RESIDENTIAL BUILDING
Submitted in partial fulfilment of the
requirements for the degree of
Bachelor of Engineering
By
MASTAN SHAIBAZ SAYEED (17DCE59)
SHAIKH MOHAMMED SHOAIB ATIQUERREHMAN (17DCE75)
SAYYED SHEHBAAZ SAEED AHMED (17DCE70)
KHAN MOHAMMED UMAIR ABDUL JALIL (15CE23)
Under the guidance of
Prof. G.B. Mahajan.
1
ir.aiktclibrary.org
IR@AIKTC-KRRC
PLANNING, SCHEDULING&ESTIMATION OF
GREEN RESIDENTIAL BUILDING
Submitted in partial fulfilment of the
requirements for the degree of
Bachelor of Engineering
By
MASTAN SHAIBAZ SAYEED (17DCE59)
SHAIKH MOHAMMED SHOAIB ATIQUERREHMAN (17DCE75)
SAYYED SHEHBAAZ SAEED AHMED (17DCE70)
KHAN MOHAMMED UMAIR ABDUL JALIL (15CE23)
Under the guidance of
Prof. G.B. Mahajan.
2
ir.aiktclibrary.org
IR@AIKTC-KRRC
CERTIFICATE
Prof.G.B.Mahajan
(Supervisor)
3
ir.aiktclibrary.org
IR@AIKTC-KRRC
APPROVAL SHEET
Examiners
1. …………………………
2. …………………………
Supervisors:
1. …………………………
2. …………………………
Date:
Place: Panvel
4
ir.aiktclibrary.org
IR@AIKTC-KRRC
DECLARATION
We declare that this written submission represents my ideas in our own words
and where others ideas or words have been included; we have adequately cited
and referenced the original sources. We also declare that, we have adhered to all
that any violation of the above will be cause for disciplinary action by the Institute
and can also evoke penal action from the sources which have thus not been
properly cited or from whom proper permission has not been taken when needed.
5
ir.aiktclibrary.org
IR@AIKTC-KRRC
ACKNOWLEDGEMENT
We would like to take this opportunity to express our thanks to or guide Prof.
G.B. Mahajan for his constant guidance and encouragement during the time
of completion of our dissertation work. We would never have been able to
finish our project work without his excellent and valuable suggestions during
the dissertation work. These have helped us to gain immense knowledge about
the PLANNING, SCHEDULING&ESTIMATION OF GREEN
RESIDENTIAL BUILDING.
We would like to thank my colleagues and friends for their valuable and
timely assistance and their guidance.
6
ir.aiktclibrary.org
IR@AIKTC-KRRC
ABSTARCT
This project work deals with the planning, scheduling and estimation of
starts with planning of the building using AutoCAD. Further scheduling will
prepared in Excel.
systems will get designed & installed in building. During construction also,
7
ir.aiktclibrary.org
IR@AIKTC-KRRC
Index
Table of Contents
CHAPTER 1 ....................................................................................................... 10
1.1 Genral. ........................................................................................................ 11
1.2 Aim & Objectives of Project. .................................................................... 15
1.3 Scope of Project work. ............................................................................... 15
1.4 Problem Statement ..................................................................................... 16
1.5 Probable solution ....................................................................................... 16
1.6 Expected Outcome ..................................................................................... 17
CHAPTER 2 ....................................................................................................... 18
2.1 General ....................................................................................................... 19
2.2AutoCAD .................................................................................................... 19
2.3Primavera .................................................................................................... 20
2.4Green building ............................................................................................ 20
CHAPTER 3 ....................................................................................................... 22
3.1 General ....................................................................................................... 23
3.2 Planning ..................................................................................................... 23
3.3 Cost Estimation .......................................................................................... 29
3.4 Scheduling.................................................................................................. 49
3.5. Green Building. ......................................................................................... 57
3.5.1 Rain Water Harvesting. ....................................................................... 57
3.5.1.1Designing of underground and overhead water tank for rain water
harvesting and daily municipal water supply. .............................................. 62
3.5.2.GREYWATER. ................................................................................... 65
3.5.2.1 DESIGN OF SLOW SAND FILTER............................................... 68
3.5.3 SOLAR ENERGY ............................................................................... 70
3.5.3.1Green Materials: ................................................................................ 75
ir.aiktclibrary.org
IR@AIKTC-KRRC
List of figures.
Figure 1 Detail drawing ........................................................................................................... 24
Figure 2 Foundation Plan ........................................................................................................ 27
Figure 3First Floor Plan ........................................................................................................... 28
Figure 4 OBS ........................................................................................................................... 49
Figure 5 EPR ............................................................................................................................ 49
Figure 6 WBS .......................................................................................................................... 49
Figure 7 Greywater System(a) ................................................................................................. 66
Figure 8 Greywater System(b) ................................................................................................. 66
Figure 9 Solar System .............................................................................................................. 70
Figure 10 Photovoltaic Cells .................................................................................................... 73
Figure 11 Solar Power System ................................................................................................ 74
List of tables.
Table 1Minimum Size and Width of Different Components of Residential Premises ............ 25
Table 2 Measurement Sheet ..................................................................................................... 29
Table 3 Abstract sheet .............................................................................................................. 46
Table 4 Schedule ...................................................................................................................... 50
Table 5 Gant Chart ................................................................................................................... 54
Table 6 Average rate of rainfall in mm/h................................................................................. 60
Table 7 Distribution of total domestic water consumption ...................................................... 67
Table 8 Comparison of Green VS Conventional paints........................................................... 76
Table 9 Fly ash brick VS Conventional Bricks ....................................................................... 77
ir.aiktclibrary.org
IR@AIKTC-KRRC
CHAPTER 1
Introduction
ir.aiktclibrary.org
IR@AIKTC-KRRC
CHAPTER 1
INTRODUCTION
1.1 General.
10
ir.aiktclibrary.org
IR@AIKTC-KRRC
11
ir.aiktclibrary.org
IR@AIKTC-KRRC
12
ir.aiktclibrary.org
IR@AIKTC-KRRC
1983 by Joel Koppel man and Dick Faris. It traded as a private company based in
Pennsylvania (USA), developing software for the Project Portfolio Management
market. To help expand its product capabilities, Primavera acquired Eagle Ray
Software Systems in 1999, Evolve Technologies (a professional services
automation vendor) in 2003, Pro Sight (an IT portfolio management software
vendor) in 2006, and, in the same year, Pert master (a project risk management
software vendor).
The traditional approach for scheduling and progress monitoring techniques likes
Bar Charts, CPM; PERT etc. are still being used by the project managers for
planning. These are a serious disadvantage in the decision making purpose, as
they fail to provide the necessary spatial aspects and data of the construction
project. Thus there is a gradual increase in the pressure on the project managers
to shorten the delivery time and decrease the costs involved in the process,
without a decrease in the quality of the product. The current day demand of
construction industry requires a highly accurate planning, scheduling and
management of the process of the project which can enable the overall
optimization of the cost, time and resources (Dr Gopal M. N. et. al. 2011). These
increases in the pressure on the project managers and the current day demand of
construction industry have resulted in an increase in
thenumberofcommerciallyavailablecomputerizedplanningandschedulingtools.
With the advances in the field of information technologies, construction industry
has started taking advantages of some of the developed tools.
14
ir.aiktclibrary.org
IR@AIKTC-KRRC
Based on the aim and objective mentioned in the preceding section, the scope of
the present investigation is outlined asunder:
By doing this project, we will gain knowledge about the application of civil
engineering softwares such as AutoCAD, and Primavera.
A Green Building is one, which in the process of constructing a building, uses
renewable materials, and saves money on light bills, gas bills and water bills. This
method can include using all natural materials but for the most part, it pertains to
saving environment and costs. It is a reflection of the growing concern for
environment and energy, and the awareness that huge consumption also leads to
huge depletion of resources.
14
ir.aiktclibrary.org
IR@AIKTC-KRRC
When we look at these statistics, it becomes clear that adopting sustainable design
strategies is an essential way to move forward to minimise environmental damage
and reduce energy consumption.
Sustainable architecture seeks to construct or renovate buildings using innovative
design, renewable materials and energy-efficient technology and in doing so
reduce our dependence on traditional energy sources. Sustainable design
therefore minimises both the initial environmental cost of building (through
reducing material waste and using sustainable products) and the long-term
environmental impact of the building (by constructing efficient buildings that use
only a fraction of the energy required to power and heat traditional buildings).
16
ir.aiktclibrary.org
IR@AIKTC-KRRC
16
ir.aiktclibrary.org
IR@AIKTC-KRRC
CHAPTER 2
Literature review
16
ir.aiktclibrary.org
IR@AIKTC-KRRC
Chapter 2
LITERATURE REVIEW
2.1 General
During the literature review for this work, we have referred quite a few technical and
research papers from various national and international journals. This part focuses on
the literature for understanding the concepts of green building, software information
and applications.
2.2AutoCAD
Azidah Abu Zidenet. al. (2012), studied the effectiveness of AutoCAD software in
learning of Engineering Drawing to enhance students understanding. It concludes that
AutoCAD increases the performance of high and medium level students group and
gave a positive impact to study. Effective use of the software proved to be useful based
on the data obtained.
Asmaa G. Salih et. al. (2014) presented the significant revolution with computers
usage in civil engineering business and construction process has been presented.
AutoCAD software is an extremely powerful tool and can be adapted to specific needs
in order to serve the intended purpose of any project. Civil engineering professionals
use this software for variety of infrastructure projects like: land development,
transportation, water projects and road design.
Amol A. Metkariet. al. (2015), proposed Ladies Hostel building for Rajarambapu
Institute of Technology College, Rajarambapu. In that case study, building project,
included real life example of BIM and AutoCAD uses and benefits. Also in the case
study, a prototype building project, examined the 2D, 3D, 4D and 5D model by using
AutoCAD and BIM tools.
19
IR@AIKTC-KRRC
2.3Primavera
P.Thangam [2016] investigated about the construction project which was carried out
with lack of planning, scheduling and resource allocation. After using primavera
software in work, it gives improvement. In quality of construction with stipulated cost
and time. The objectives of their study include Preparing of detailed activity plan and
scheduling based on construction project.
To make the schedule and find the critical path using P6 planner software.
Mohammed Zaki Haider[2016] Worked as an intern in NCC (National Construction
Company).In this paper author has highlighted that the main motivation of any project
is to complete project in planned schedule with proper utilization of resources. It also
helps in study of material, manpower and therefore it helps in improvement of
construction management techniques.
Ranjith Kumar et al. [2017] stated that planning and scheduling with Primavera
software provide detailed information about cost control, time management, working
hour management, update and monitoring and delay of activities which enhance
effectiveness in delivering services.
Sangeetha HM [Vol-3 issue 4 2017] dealt with the planning, scheduling and tracking
using earned value analysis and also ensures a comparison between the baseline
duration of project using project management software tool Primevera P6.
2.4Green building
Chandra Shekhar Singh [2018] stated that green practices from building design to
landscaping choices also adopting green building material is an excellent approach to
meet target. Resource efficient materials can maximize function while optimising the
use of natural resources.
ir.aiktclibrary.org
20
IR@AIKTC-KRRC
achna Dhingra [2017] mentioned that construction industry is growing over rapid
pace gaining environmental causes. India will replace Japan as third largest global
market by 2030.But this construction industry is one of the least sustainable industries
in the world as it uses massive non-renewable resource, to resolve this issues one needs
to go in for “sustainable construction” or “green building”.
ir.aiktclibrary.org
21
IR@AIKTC-KRRC
CHAPTER 3
Mythology
ir.aiktclibrary.org
22
IR@AIKTC-KRRC
CHAPTER 3
METHODOLOGY
3.1 General
1. Planning
2. Cost estimation
3. Scheduling
4. Green units
3.2 Planning
Planning of a Green building has been done by our batch as per building Bye-
Laws and IS Code requirement, keeping in mind the accommodation requirement
for 200 people for this purpose, AutoCAD software was used.
ir.aiktclibrary.org
23
IR@AIKTC-KRRC
ir.aiktclibrary.org
24
IR@AIKTC-KRRC
Minimum Size and Width of Different Components of Residential
Premises
Kitchen
Every room to be used as a kitchen shall have
ir.aiktclibrary.org
25
IR@AIKTC-KRRC
Bathroom and W. C
a) Be so situated that at least one of its walls shall open to external air and shall
have a minimum opening in the form of window or ventilation to the extent
of 0.37 sq m.
b) Not be directly over any room other than another latrine, washing place, bath
or terrace unless it has a watertight floor.
c) Have the platform or seat made of watertight non-absorbent material.
d) Be enclosed by walls or partitions and the surface of every such wall partition
shall be finished with a smooth impervious material to a height of not less
than 1.0 m. above the floor of such a room.
e) Be provided with an impervious floor covering, sloping towards the drain
with a suitable grade and not towards verandah or any other room.
f) No room containing water closets shall be used for any purpose except as a
lavatory.
g) Every water closet and/or a set of urinals shall have flushing cistern of
adequate capacity attached to it.
h) A toilet on terrace having a maximum of 2.2 mt. height shall be permitted
subject to condition that the area of toilet is counted in FAR.
ir.aiktclibrary.org
26
IR@AIKTC-KRRC
i) All the sewage outlets shall be connected to the Municipal Sewerage system.
Where no such system exists, a septic tank shall be provided within the plot
conforming to the requirements
Centre line and foundation plan is the basic plan which is used for positioning of
columns. Centre line is a line passing through the centre of column. Grid of similar for
a number of columns from centre line plan. Centre line plans help you to understand
the exact positioning of columns on site. Centreline grids for columns are plotted on
land before being excavated.
ir.aiktclibrary.org
27
IR@AIKTC-KRRC
• The first floor comprises of 4, 2BHK flats and 3, 1BHK flat in total of 7 flats.
• Provisions of openings are made to take better advantage from nature (sun,
wind).
• Parking lot is provided on the ground floor to accommodate all types of vehicles
used by occupants of the building.
• Passage way of 1.5m width is provided for easy movement.
• First Floor is the Master Floor for 2nd, 3rd & 4th floor, planned following the
first-floor plan as “typical floor” plan.
• Two doglegged staircases are provided and elevator is also provided.
ir.aiktclibrary.org
28
IR@AIKTC-KRRC
Width/ Height/
Sr. Length
Item Description No. Breadth Depth Quantity
No. (m)
(m) (m)
Earthwork in Excavation in
1
Foundation:
Footing (1.2m x 1.2m) 40 1.60 1.60 1.80 184.32
Footing (1m x 1m) 12 1.35 1.35 1.70 37.18
COMBINED FOOTING
4 2.84 1.6 1.20 21.81
1
2 2 2.45 1.6 1.20 9.41
Shear wall 1 6.45 4 1.2 30.96
STORAGE
1 4.9 2.6 1.46 18.60
TANK4.6X2.3X1.2
Total 302.28 cu m
2 P.P.C. in Foundation
Footing (1.2m x 1.2m) 40 1.6 1.6 0.2 20.48
Footing (1m x 1m) 12 1.35 1.35 0.20 4.37
Combined Footing
4 2.84 1.60 0.20 3.64
1
2 2 2.45 1.60 0.20 1.57
Shear Wall 1 6.45 4.00 0.20 5.16
STORAGE
1 4.9 2.6 0.2 2.55
TANK4.6X2.3X1.2
Total 37.77 cu m
ir.aiktclibrary.org
29
IR@AIKTC-KRRC
3
Column
size (0.3x0.3) 65 0.30 0.30 15.00 87.75 cu m
4 CONCRETE
Footing (1.2m x 1.2m) 40 1.19 47.60
Footing (1m x 1m) 13 0.54 6.97
COMBINED
4 5.45 21.80
1
2 2 4.30 8.60
TOTAL 84.97 cu m
Shear wall 3 3.30 0.20 15.00 29.70
1 4.05 0.20 15.00 12.15
TOTAL 41.85 cu m
WATER TANK
UNDER GROUND 2 5.20 1.20 0.30 3.74
4.6X2.3X1.2 2 2.08 1.20 0.30 1.50
SLAB 1 5.20 2.60 0.13 1.76
OVERHEAD 2 5.60 1.00 0.15 1.68
(5X3X1) 2 3.00 1.00 0.15 0.90
SLAB 2 5.30 3.30 0.13 4.55
TOTAL 14.13 cu m
Plinth Beam
5
(230x230mm)
PB 1 2 4.90 0.23 0.60 1.35
PB 2 2 3.03 0.23 0.60 0.84
PB 3 2 1.48 0.23 0.60 0.41
PB 4 1 3.93 0.23 0.60 0.54
PB 5 6 1.93 0.23 0.60 1.60
PB 6 2 2.28 0.23 0.60 0.63
PB 7 2 2.64 0.23 0.60 0.73
PB 8 5 2.39 0.23 0.60 1.65
PB 9 4 1.43 0.23 0.60 0.79
PB 10 2 2.40 0.23 0.60 0.66
PB 11 2 3.74 0.23 0.60 1.03
PB 12 2 4.26 0.23 0.60 1.18
PB 13 4 2.94 0.23 0.60 1.62
PB 14 1 5.09 0.23 0.60 0.70
PB 15 2 4.26 0.23 0.60 1.18
PB 16 4 4.47 0.23 0.60 2.47
PB 17 1 5.31 0.23 0.60 0.73
PB 18 1 1.13 0.23 0.60 0.16
PB 19 2 3.73 0.23 0.60 1.03
PB 20 1 5.50 0.23 0.60 0.76
PB 21 1 6.25 0.23 0.60 0.86
PB 22 1 2.70 0.23 0.60 0.37
PB 23 1 1.98 0.23 0.60 0.27
PB 24 1 4.50 0.23 0.60 0.62
PB 25 1 3.95 0.23 0.60 0.55
ir.aiktclibrary.org
30
IR@AIKTC-KRRC
PB 27 2 1.21 0.23 0.60 0.33
PB 28 2 1.33 0.23 0.60 0.37
PB 29 3 2.22 0.23 0.60 0.92
PB 30 3 2.60 0.23 0.60 1.08
PB 31 2 2.83 0.23 0.60 0.78
PB 32 2 5.66 0.23 0.60 1.56
PB 33 2 4.17 0.23 0.60 1.15
PB 34 2 4.32 0.23 0.60 1.19
PB 35 2 4.24 0.23 0.60 1.17
PB 36 2 1.55 0.23 0.60 0.43
PB 37 2 3.39 0.23 0.60 0.94
PB 38 2 3.35 0.23 0.60 0.92
PB 39 4 3.80 0.23 0.60 2.10
PB 40 3 2.28 0.23 0.60 0.94
PB 41 3 4.20 0.23 0.60 1.74
PB 42 2 1.20 0.23 0.60 0.33
PB 43 3 4.32 0.23 0.60 1.79
PB44 1 5.01 0.23 0.60 0.69
PB45 2 2.40 0.23 0.60 0.66
PB46 1 5.17 0.23 0.60 0.71
Total 43.30
Floor Beam
6
(230x300mm)
FB1 5 4.90 0.23 0.43 2.42
FB2 10 3.03 0.23 0.43 3.00
FB3 10 1.48 0.23 0.43 1.46
FB4 1 3.93 0.23 0.43 0.39
FB5 30 1.93 0.23 0.43 5.73
FB6 10 2.28 0.23 0.43 2.25
FB7 10 2.64 0.23 0.43 2.61
FB8 25 2.39 0.23 0.43 5.91
FB9 20 1.43 0.23 0.43 2.83
FB10 10 2.40 0.23 0.43 2.37
FB11 10 3.74 0.23 0.43 3.70
FB12 10 4.26 0.23 0.43 4.21
FB13 20 2.94 0.23 0.43 5.82
FB14 5 5.09 0.23 0.43 2.52
FB15 10 4.26 0.23 0.43 4.21
FB16 20 4.47 0.23 0.43 8.84
FB17 5 5.31 0.23 0.43 2.63
FB18 5 1.13 0.23 0.43 0.56
FB19 10 3.73 0.23 0.43 3.69
FB20 5 5.50 0.23 0.43 2.72
FB21 5 6.25 0.23 0.43 3.09
FB22 5 2.70 0.23 0.43 1.34
FB23 10 1.98 0.23 0.43 1.96
ir.aiktclibrary.org
31
IR@AIKTC-KRRC
ir.aiktclibrary.org
32
IR@AIKTC-KRRC
ir.aiktclibrary.org
33
IR@AIKTC-KRRC
ir.aiktclibrary.org
34
IR@AIKTC-KRRC
ir.aiktclibrary.org
35
IR@AIKTC-KRRC
DEDUCTION
COLUMN 65 0.30 0.30 5.85
DUCT 1 4.85 3.55 17.22
2 3.95 3.30 26.07
2 1.70 1.65 5.61
1 1.05 1.25 1.31
2 1.65 1.00 3.30
2 1.65 1.25 4.13
STAIR 2 5.30 3.30 34.98
G TOTAL 508.54 Sq m
SIDE WALL
2 4.85 3.00 29.10
2 3.95 3.00 23.70
1 1.70 3.00 5.10
2 1.05 3.00 6.30
2 1.65 3.00 9.90
2 1.65 3.00 9.90
2 5.30 3.00 31.80
2 3.55 3.00 21.30
2 3.30 3.00 19.80
2 1.65 3.00 9.90
2 1.25 3.00 7.50
2 1.00 3.00 6.00
2 1.25 3.00 7.50
2 3.30 3.00 19.80
H TOTAL 207.60 Sq m
A+B+C-
NET 6742.90 Sq m
D+E+F+G+H
EXTERNAL PLASTER
TOTAL AREA 1 151.84 12.00 1822.08
DEDUCTION
W 4 1.50 2.15 12.90
W1 32 1.20 2.15 82.56
FD 40 1.50 2.30 138.00
STAIR WINDOW W3 10 1.80 1.20 21.60
TOTAL 1567.02 Sq m
ir.aiktclibrary.org
36
IR@AIKTC-KRRC
FLOORING
BEDROOM
16 3.05 3.75 183.00
(3.05X3.75m)
BEDROOM
16 3.05 3.60 175.68
(3.05X3.60m)
LIVING (3.95X4.15m) 8 3.95 4.15 131.14
LIVING (3.95X3.75m) 8 3.95 3.75 118.50
KITCHEN (2.60X2.45m) 8 2.60 2.45 50.96
KITCHEN (2.60X2.20m) 8 2.60 2.20 45.76
ENTRANCE (1.2X2.2m) 8 1.20 2.20 21.12
ENTRANCE (1.2X1.35m) 8 1.20 1.35 12.96
BEDROOM
4 2.75 3.65 40.15
(2.75X3.65m)
BEDROOM
8 2.75 3.05 67.10
(2.75X3.05m)
LIVING (3.05X3.80m) 8 3.05 3.80 92.72
LIVING (3.0X3.9m) 4 3.00 3.90 46.80
KITCHEN (2.60X2.30m) 8 2.60 2.30 47.84
KITCHEN (2.45X2.45m) 4 2.45 2.45 24.01
ENTRANCE (1.2X1.9m) 4 1.20 1.90 9.12
ENTRANCE (1.2X1.5m) 8 1.20 1.50 14.40
PASSAGE 1 8 1.35 1.65 17.82
2 8 1.35 1.45 15.66
3 4 1.20 1.60 7.68
4 8 1.20 1.60 15.36
5 CORIDOOR 1 32.62 32.62
WC 1.2X2.05 16 1.20 3.00 57.60
16 2.05 3.00 98.40
WC 1.2X2.0 16 1.20 3.00 57.60
16 2.00 3.00 96.00
WC 1.35X1.80 32 1.35 3.00 129.60
32 1.80 3.00 172.80
WC 1.2X1.90 8 1.20 3.00 28.80
8 1.90 3.00 45.60
WC 1.2X2.15 8 2.15 3.00 51.60
8 2.15 3.00 51.60
WC 1.35X2.4 16 1.35 3.00 64.80
16 2.40 3.00 115.20
ADDITION
DOORS (D) 1X2.3 72 1.00 0.15 10.80
DOORS (D1) 0.9X2.3 44 0.90 0.15 5.94
DOORS (D2) 0.75X2.3 56 0.75 0.15 6.30
DOORS (FD) 40 1.50 0.15 9.00
ir.aiktclibrary.org
37
IR@AIKTC-KRRC
TOTAL 2172.04 Sq m
DEDUCTION
V 0.6X0.9 56 0.60 0.90 30.24
NET TOTAL 2141.80 Sq m
PAINTING (INTERNAL)
SLAB
BEDROOM
2BHK 16 3.05 3.75 183.00
(3.05X3.75m)
BEDROOM
16 3.05 3.60 175.68
(3.05X3.60m)
LIVING (3.95X4.15m) 8 3.95 4.15 131.14
LIVING (3.95X3.75m) 8 3.95 3.75 118.50
KITCHEN (2.60X2.45m) 8 2.60 2.45 50.96
KITCHEN (2.60X2.20m) 8 2.60 2.20 45.76
ENTRANCE (1.2X2.2m) 8 1.20 2.20 21.12
ENTRANCE (1.2X1.35m) 8 1.20 1.35 12.96
BEDROOM
1BHK 4 2.75 3.65 40.15
(2.75X3.65m)
BEDROOM
8 2.75 3.05 67.10
(2.75X3.05m)
LIVING (3.05X3.80m) 8 3.05 3.80 92.72
LIVING (3.0X3.9m) 4 3.00 3.90 46.80
KITCHEN (2.60X2.30m) 8 2.60 2.30 47.84
KITCHEN (2.45X2.45m) 4 2.45 2.45 24.01
ENTRANCE (1.2X1.9m) 4 1.20 1.90 9.12
ENTRANCE (1.2X1.5m) 8 1.20 1.50 14.40
2BHK PASSAGE 1 8 1.35 1.65 17.82
2 8 1.35 1.45 15.66
1BHK 3 4 1.20 1.60 7.68
4 8 1.20 1.60 15.36
5 CORIDOOR 1 32.62 32.62
A TOTAL 1170.40 Sq m
SIDE WALL
BEDROOM
2BHK 32 3.05 3.00 292.80
(3.05X3.75m)
BEDROOM
32 3.05 3.00 292.80
(3.05X3.60m)
LIVING (3.95X4.15m) 16 3.95 3.00 189.60
LIVING (3.95X3.75m) 16 3.95 3.00 189.60
KITCHEN (2.60X2.45m) 16 2.60 3.00 124.80
KITCHEN (2.60X2.20m) 16 2.60 3.00 124.80
ENTRANCE (1.2X2.2m) 16 1.20 3.00 57.60
ENTRANCE (1.2X1.35m) 16 1.20 3.00 57.60
ir.aiktclibrary.org
38
IR@AIKTC-KRRC
BEDROOM
1BHK 8 2.75 3.00 66.00
(2.75X3.65m)
BEDROOM
16 2.75 3.00 132.00
(2.75X3.05m)
LIVING (3.05X3.80m) 16 3.05 3.00 146.40
LIVING (3.0X3.9m) 8 3.00 3.00 72.00
KITCHEN (2.60X2.30m) 8 2.60 3.00 62.40
KITCHEN (2.45X2.45m) 4 2.45 3.00 29.40
ENTRANCE (1.2X1.9m) 8 1.20 3.00 28.80
ENTRANCE (1.2X1.5m) 16 1.20 3.00 57.60
2BHK PASSAGE 1 8 1.35 3.00 32.40
2 8 1.35 3.00 32.40
1BHK 3 4 1.20 3.00 14.40
4 8 1.20 3.00 28.80
5 CORIDOOR 1 59.53 3.00 178.59
B TOTAL 2210.79 Sq m
SIDE WALL
BEDROOM
2BHK 32 3.75 3.00 360.00
(3.05X3.75m)
BEDROOM
32 3.60 3.00 345.60
(3.05X3.60m)
LIVING (3.95X4.15m) 16 4.15 3.00 199.20
LIVING (3.95X3.75m) 16 3.75 3.00 180.00
KITCHEN (2.60X2.45m) 16 2.45 3.00 117.60
KITCHEN (2.60X2.20m) 16 2.20 3.00 105.60
ENTRANCE (1.2X2.2m) 16 2.20 3.00 105.60
ENTRANCE
16 1.35 3.00 64.80
(1.2X1.35m)
BEDROOM
1BHK 8 3.65 3.00 87.60
(2.75X3.65m)
BEDROOM
16 3.05 3.00 146.40
(2.75X3.05m)
LIVING (3.05X3.80m) 16 3.80 3.00 182.40
LIVING (3.0X3.9m) 8 3.90 3.00 93.60
KITCHEN (2.60X2.30m) 16 2.30 3.00 110.40
KITCHEN (2.45X2.45m) 8 2.45 3.00 58.80
ENTRANCE (1.2X1.9m) 8 1.90 3.00 45.60
ENTRANCE (1.2X1.5m) 16 1.50 3.00 72.00
2BHK PASSAGE 1 8 1.65 3.00 39.60
2 8 1.45 3.00 34.80
1BHK 3 4 1.60 3.00 19.20
4 8 1.60 3.00 38.40
5 CORIDOOR 1 59.53 3.00 178.59
C TOTAL 2585.79 Sq m
ir.aiktclibrary.org
39
IR@AIKTC-KRRC
deduction
DOORS (D) 1X2.3 72 1.00 2.30 165.60
DOORS (D1) 0.9X2.3 44 0.90 2.30 91.08
DOORS (D2) 0.75X2.3 56 0.75 2.30 96.60
DOORS (FD) 40 1.50 2.30 138.00
OPENING OP 1X2.3 76 1.00 2.30 174.80
WINDOW W 4 1.50 2.15 12.90
WINDOW W1 1.5X2.5 32 1.20 2.15 82.56
WINDOW W2 32 0.90 2.15 61.92
WINDOW W3 24 0.45 1.20 12.96
D TOTAL 836.42 Sq m
STAIRCASE
LONG WALL 4 5.00 18.00 360.00
DEDUCTION
STEPS AND LANDING 20 0.55 11.00
E TOTAL 349.00 Sq m
SHORT WALL 2 3.00 18.00 108.00
DEDUCTION
WINDOW 10 1.80 1.20 21.60
F TOTAL 86.40 Sq m
GROUND
FLOOR/PARKING
TOTAL AREA SLAB 607.01 607.01
DEDUCTION
COLUMN 65 0.30 0.30 5.85
DUCT 1 4.85 3.55 17.22
2 3.95 3.30 26.07
2 1.70 1.65 5.61
1 1.05 1.25 1.31
2 1.65 1.00 3.30
2 1.65 1.25 4.13
G TOTAL 508.54 Sq m
SIDE WALL
2 4.85 3.00 29.10
2 3.95 3.00 23.70
1 1.70 3.00 5.10
2 1.05 3.00 6.30
2 1.65 3.00 9.90
ir.aiktclibrary.org
40
IR@AIKTC-KRRC
ir.aiktclibrary.org
41
IR@AIKTC-KRRC
ir.aiktclibrary.org
42
IR@AIKTC-KRRC
WC 1.35X1.8
SHORT WALL 64 1.35 2.87 0.15 37.20
WC 1.35X2.25
SHORT WALL 16 1.35 2.87 0.15 9.30
WC 1.35X2.4
SHORT WALL 16 1.35 2.87 0.15 9.30
WC 1.2X1.9
SHORT WALL 8 1.20 2.87 0.15 4.13
WC 1.2X2.15
SHORT WALL 4 1.20 2.87 0.15 2.07
BALCONY 0.00
4 2.90 2.57 0.15 4.47
3 2.90 2.87 0.15 3.75
2 2.25 2.57 0.15 1.73
1 2.25 2.87 0.15 0.97
2 1.30 2.57 0.15 1.00
2 1.30 2.87 0.15 1.12
1 1.40 2.57 0.15 0.54
STAIR 2 5.00 15.85 0.15 23.78
2 3.30 15.85 0.15 15.69
DUCT 1 4.55 3.55 0.15 2.42
2 3.65 3.30 0.15 3.61
2 1.40 1.65 0.15 0.69
1 0.85 1.25 0.15 0.16
2 1.35 1.00 0.15 0.41
2 1.35 1.25 0.15 0.51
TOTAL 653.47 cu m
ir.aiktclibrary.org
43
IR@AIKTC-KRRC
DEDUCTION
WINDOW STAIR 10 1.80 1.20 0.15 2.70
DOORS (D) 1X2.3 72 1.00 2.30 0.15 10.80
DOORS (D1) 0.9X2.3 44 0.90 2.30 0.15 5.94
DOORS (D2) 0.75X2.3 56 0.75 2.30 0.15 6.30
DOORS (FD) 40 1.50 2.30 0.15 9.00
OPENING OP 1X2.3 76 1.20 2.30 0.15 13.68
WINDOW W 4 1.50 2.15 0.15 0.90
WINDOW W1 1.5X2.5 32 1.20 2.15 0.15 5.76
WINDOW W2 32 0.90 2.15 0.15 4.32
WINDOW W3 24 0.45 1.20 0.15 1.62
V 0.6X0.9 56 0.60 0.90 0.15 5.04
COLUMN size
65 0.15 0.15 15.00 146.25
(0.3X0.3)
TOTAL 212.31 cu m
NET 441.16 cu m
RAIN WATER
HARVESTING
EXCAVATION
STORAGE TANK
1 6.81 3.56 2.96 71.76 cu m
6.51X3.26X2.7
PCC
STORAGE TANK
1 6.81 3.56 0.2 4.85 cu m
6.51X3.26X2.7
RCC
UNDER GROUND 2 7.11 2.70 0.15 5.76
6.51X3.26X2.7 2 3.26 1.50 0.15 1.47
SLAB 1 6.54 3.53 0.13 3.00
10.23 cu m
GREY WATER
RCC OVERHEAD TANK 2 5.60 1.85 0.15 3.11
(5X3X0.5) 2 3.00 1.85 0.15 1.67
SLAB 2 5.30 3.30 0.13 4.55
9.32 cu m
ir.aiktclibrary.org
44
IR@AIKTC-KRRC
ir.aiktclibrary.org
45
IR@AIKTC-KRRC
ABSTARCT SHEET
Abstract sheet:
It is a sheet including the number of required quantity of items for the work with unit
price and thereby total amount.
The abstract estimate is the third and the final stage of detailed estimate. The amount
and the rate of everything from work touch base in the initial two stages are entered
in an abstract form.
3 PLINTH FILLING
MORUM 106.68 CU M 239.8 #REF!
BOULDER 106.68 CU M 1029 #REF!
PCC M20 106.68 CU M 5575 #REF!
₹ 730097
4 RCC
1-FOOTING M30 84.97 CU M 6165 #REF!
2-SHEAR WALL M30 41.85 CU M 6165 #REF!
3-PLINTH BEAM M25 43.3 CU M 6218 #REF!
4-FLOOR BEAM M25 152.16 CU M 6218 #REF!
5-CHAJJA/LINTEL M25 38.11 CU M 6218 #REF!
6-SLAB M25 281.12 CU M 7301 #REF!
7-COLUMN M25 87.75 CU M 7598 #REF!
8-STAIR CASE M25 26.38 CU M 7301 #REF!
9-WATER TANK M25 14.13 CU M 6983 #REF!
₹ 5244636
5 BRICK WORK
FLY ASH BRICK 230X150X100 130000 NOS 5 ₹ 650000
7 PLASTERING
INTERNAL 6742.9 SQ M 240 #REF!
EXTERNAL 1567.02 SQ M 280 #REF!
Table 3 Abstract sheet
ir.aiktclibrary.org
46
IR@AIKTC-KRRC
8 PAINTING
INTERNAL 6742.9 SQ M 35 #REF!
EXTERNAL 1567.02 SQ M 40 #REF!
₹ 2355744
9 DOORS
T.W FRAME COMMERCIAL PLY FLASH DOOR 1X2.3 72 NOS 5000 #REF!
T.W FRAME COMMERCIAL PLY FLASH DOOR 0.9X2.3 44 NOS 5000 #REF!
T.W FRAME MARINE PLY FLASH DOOR 0.75X2.3 56 NOS 5000 #REF!
ALUMINIUM SLIDING DOOR (FD) 1.5X2.3 40 NOS 8200 #REF!
₹ 1188000
10 WINDOW
ir.aiktclibrary.org
47
IR@AIKTC-KRRC
ir.aiktclibrary.org
48
IR@AIKTC-KRRC
3.4 Scheduling
With the use of Primavera software, the scheduling and modelling of the project will
be done. First of all activities to be performed will get arranged. Then on the basis of
experience, appropriate durations to be assigned to all activities in order to know total
time to be required for the completion of Project. The following are the important
elements of project management.
• OBS (Organization Breakdown
Structure) CEO
Is a structure of people of an organization.
OBS is used to manage and organize
people of an organization for better Director 1 Director 2
communication and administrative
purpose. It is also used to control access of project project project
people to project. manager 1 manager 2 manager 3
This is an example of an OBS. Figure 4 OBS
M&M
• EPS (enterprise project structure)
Is a structure of a project in enterprise or an
mumbai delhi organization, EPS is used to organize projects
of an organization. It is also used to control
access to projects. EPS can be made with any
construction
project
IT project road projet reference like location, nature and budget of
project. This is an example of EPS.
Figure 5 EPR
Figure 6 WBS
ir.aiktclibrary.org
49
IR@AIKTC-KRRC
.
Activities: are task to be performed to complete a particular work. There are 6 different
types of activities:
Duration estimation: In the software work is divided and breaks down in different
work elements as WBS (works break down structure) then different activities are
performed as the respective elements. The durations of these activities are provided as
calculated by quantity and time estimation there by total time required to complete
particular activity.
Schedule
Table 4 Schedule
ir.aiktclibrary.org
50
IR@AIKTC-KRRC
ir.aiktclibrary.org
51
IR@AIKTC-KRRC
ir.aiktclibrary.org
52
IR@AIKTC-KRRC
ir.aiktclibrary.org
53
IR@AIKTC-KRRC
GANT CHART
ir.aiktclibrary.org
54
IR@AIKTC-KRRC
ir.aiktclibrary.org
55
IR@AIKTC-KRRC
ir.aiktclibrary.org
56
IR@AIKTC-KRRC
GREEN RESOURCES:
Rainwater harvesting techniques have been already been devised and used since
ancient time. These were implemented at the community level in areas where rainfall
is the only major source of freshwater, mostly in Rajasthan, Madhya Pradesh. In
Southern India rainwater harvesting systems are integrated into their architecture in
the form of small ponds/tanks for each house, and temple tanks.
The basic rainwater harvesting system is more of a plumbing job than a technical job,
as all the outlets form the buildings’ terrace are connected through pipes to an
underground tank which stores water or a dug well, which serves the purpose of
recharging wells and bore wells.
ir.aiktclibrary.org
57
IR@AIKTC-KRRC
Rainwater harvesting is one of the simplest and oldest methods of self-supply of water
for households usually financed by the user.
Rainwater harvesting provides an independent water supply during water restrictions.
In areas where clean water is costly, or difficult to come by, rainwater harvesting is a
critical source of clean water. In developed countries, rainwater is often harvested to
be used as a supplemental source of water rather than the main source, but the
harvesting of rainwater can also decrease a household's water costs or overall usage
levels.
Indian scenario
• Tamil Nadu was the first state to make rainwater harvesting compulsory for
every building to avoid groundwater depletion. The scheme was launched in
2001 and has been implemented in all rural areas of Tamil Nadu.
• In Rajasthan, rainwater harvesting has traditionally been practiced by the
people of the Thar Desert. Many ancient water harvesting systems in
Rajasthan have now been revived. Water harvesting systems are widely used
in other areas of Rajasthan, as well, for example, the chauka system from the
Jaipur district.
• Maharashtra: At present, in Pune, rainwater harvesting is compulsory for any
new housing society to be registered.
• In Mumbai, Maharashtra, rainwater harvesting is not mandatory. The
Municipal Corporation of Greater Mumbai is planning to make rainwater
harvesting mandatory for large societies.
ir.aiktclibrary.org
58
IR@AIKTC-KRRC
3. Pipes / Conduits
These transport the rainwater collected from the catchment to the harvesting system, using
gravity. PVC pipes are commonly used as they are economical and durable. The pipes
provided are of 90-120mm diameter, however for major RWH systems the National
Building Code 2005 (SP-7) has specified the ideal diameter of the pipe to be used in the
following table –
ir.aiktclibrary.org
59
IR@AIKTC-KRRC
4. First Flush
First flush is a mechanism which discards the water received in first shower. The first
shower of rains contains impurities and contaminants, such as dust, very low quantities of
pollutants, organic matter, etc. The first rain separator should be attached at outlet of each
drainpipe.
ir.aiktclibrary.org
60
IR@AIKTC-KRRC
6. Storage facility
There are various options available for the construction of these tanks with respect to the
shape, size and the material of construction.
• Shape: Cylindrical, rectangular and square.
• Material of construction: Reinforced cement concrete, (RCC), ferrocement,
masonry, plastic (polyethylene) or metal (galvanised iron) sheets are commonly used.
• Position of tank: Depending on space availability these tanks could be constructed
above ground, partly underground or fully underground. Some maintenance
measures like cleaning and disinfection are required to ensure the quality of water
stored in the container.
ir.aiktclibrary.org
61
IR@AIKTC-KRRC
Rain water potential = Roof top area x avg. Annual rainfall x Run-off
Coefficient
= 305.09 m3
Assume Water Demand for RWH tank for Gardening, Car washing= 15 lpcd
Duration in Days
= 116 x 15 x 30
= 20.88 m2
ir.aiktclibrary.org
62
IR@AIKTC-KRRC
Assume L= 2B
20.88 = B × 2B
20.88 = 3B2
B = 3.256
B = 3.26 m
B = 2×3.26 = 6.51
= 135 x 116
= 15660 liter/day
= 15.66 m3
Storing 2/3 of water under ground and 1/3 of water overhead at same time
= 24 m3
Assume Depth H= 1m
10.44 = L × B × H
L = 2B
B = 2.28 = 2.3 m
L = 4.6 m
= 5.22m3≈ 6m3
L=5m
B=3m
6=L×B×H
H = 0.4 m ≈ 0.5m
ir.aiktclibrary.org
64
IR@AIKTC-KRRC
3.5.2. GREYWATER.
Grey water is described as gently used waste water that comes from sources such as
the bathroom, kitchen and laundry. It is relatively clean and cannot be compared with
the water from toilets (backwater). Generally, any water that is drained from the house
other than toilet water can be described as grey water. It may also contain traced of
food, grease, hair, dirt or particular household cleaning products.
As much as it may look dirty, grey water can be reused for other purposes and does
not necessarily have to be disposed of into the sewage system as other types of waste
water do. This means that it is not really waste water but could be repurposed for safe
and beneficial uses.
It therefore serves to substitute fresh water for some purposes thus allowing for water
conservation as well as reducing the amount of water that is sent into the sewage
system for treatment.
Indian scenario
➢ Water is becoming a rare resource in the world. In India, it has been projected
by International water management institute that by 2025, one third of the
population will live in complete water scarcity.
➢ In India, as per IS: 1172- 1957, the total domestic water consumption is about
135 litters/capita/day under normal conditions of which 70 – 90 litre is generated
as gray water
➢ In India, people use water carelessly in washing clothes, bathing etc due to
which per capita per day consumption has increased to more than 250 litres
which is comparatively very high in comparison to per capita per day
consumption in countries like Australia (85 litres) and this major difference is
generally because of careless use by people.
➢ Due to rapid industrialization and development, there is an increased
opportunity for grey water reuse in developing countries such as India. Although
India occupies only 3.29 million km2 geographical area, which forms 2.4% of
the world's land area, it supports over 15% of world's population.
ir.aiktclibrary.org
65
IR@AIKTC-KRRC
METHOD ADOPTED BY
GREYWATER
Conventional Grey water System
▪ Collection of raw grey water:
lateral pipes are installed to collect
grey water from bath, shower, and
washbasin to central vertical pipes.
▪ Conveyance and treatment of grey
water: collected raw grey water is
conveyed through these separate
vertical pipes to the basement for
treatment. Treated grey water is
then pumped to the top of building
to the storage tank.
▪ Distribution of treated grey water:
treated grey water is then
gravitationally conveyed from the
storage tank to each family unit in
each flat
ir.aiktclibrary.org
66
IR@AIKTC-KRRC
designed for the water to soak into the ground and not be available for people
or animals to drink.
4. Infiltrate grey water into the ground, don’t allow it to pool up or run off
(knowing how well water drains into your soil (or the soil percolation rate of
your soil) will help with proper design. Pooling grey water can provide
mosquito breeding grounds, as well as a place for human contact with grey water
5. .
6. Keep your system as simple as possible, avoid pumps, and avoid filters that need
upkeep. Simple systems last longer, require less maintenance, require less
energy and cost less money.
7. Install a 3-way valve for easy switching between the grey water system and the
sewer/septic.
8. Match the amount of grey water your plants will receive with their irrigation
needs.
ir.aiktclibrary.org
67
IR@AIKTC-KRRC
No of persons =116
Design:
V= 3480 lit
Rate of filtrations × 24
= 6264
100 × 24
= 2.61 m2
Assume L = 1.3 B
Area = L× B
2.61 = 1.3 B × B
B = 1.41 = 1.45 m
L= 1.88 = 1.9 m
Assume H = 2.7 m
ir.aiktclibrary.org
68
IR@AIKTC-KRRC
= 30 x 116
= 3480 liter/day
= 3.480m3
L=5m
B=3m
3.428= 5 × 3 × H
ir.aiktclibrary.org
69
IR@AIKTC-KRRC
Solar energy is radiant light and heat from the Sun that is harnessed using a range of
ever-evolving technologies such as solar heating, photovoltaics’, solar thermal
energy, solar architecture, molten salt power plants and artificial photosynthesis.
It is an essential source of renewable energy, and its technologies are broadly
characterized as either passive solar or active solar depending on how they capture
and distribute solar energy or convert it into solar power. Active solar techniques
include the use of photovoltaic systems,
concentrated solar power, and solar water
heating to harness the energy. Passive solar
techniques include orienting a building to the
Sun, selecting materials with favourable
thermal mass or light-dispersing properties,
and designing spaces that naturally circulate
air.
Figure 9 Solar System
In 2011, the International Energy Agency said
that "the development of affordable, inexhaustible and clean solar energy
technologies will have huge longer-term benefits. It will increase countries' energy
security through reliance on an indigenous, inexhaustible, and mostly import-
independent resource, enhance sustainability, reduce pollution, lower the costs of
mitigating global warming, and keep fossil fuel prices lower than otherwise. These
advantages are global. Hence the additional costs of the incentives for early
deployment should be considered learning investments; they must be wisely spent
and need to be widely shared".
Indian Scenario
• "For India to achieve its 100 GW solar energy target in just two years, by 2022,
and to emerge as a leader in climate action, it needs to prioritise solar rooftop
photovoltaic (PV) among two key users - residential buildings and the industrial
sector," the WRI India said in a statement.
• Solar power in India is a fast developing industry. The country's solar installed
capacity reached 37.627 GW as of 31 March 2020.
• India has the lowest capital cost per MW globally to install solar power plants.
• The Indian government is promoting solar energy. It announced an allocation of
₹1,000 crore (US$140 million) for the National Solar Mission and a clean-
energy fund for the 2010-11 fiscal year, an increase of ₹380 crore (US$53
ir.aiktclibrary.org
70
IR@AIKTC-KRRC
million) from the previous budget. The budget encouraged private solar
companies by reducing the import duty on solar panels by five percent. This is
expected to reduce the cost of a rooftop solar-panel installation by 15 to 20
percent.
• The 2018 manufacturing capacity of solar cells and solar modules in India was
1,590 MW and 5,620 MW, respectively.
• Indian manufacturers are gradually enhancing the production capacity of mono
crystalline silicon PERC cells to supply better performing and enduring solar
cells to local market.
COMPONENTS OF SOLAR
1. Solar Panels
Solar panels are the most noticeable component of a residential solar electric
system. The solar panels are installed outside the home, typically on the roof and
convert sunlight into electricity.
The photovoltaic effect is the process of converting sunlight into electricity. This
process gives solar panels their alternate name, PV panels.
Solar panels are given output ratings in watts. This rating is the maximum produced
by the panel under ideal conditions.
2. Array DC Disconnect
The Array DC disconnect is used to disconnect the solar arrays from the home for
maintenance. It is called a DC disconnect because the solar arrays produce DC
(direct current) power.
3. Inverter
Solar panels and batteries produce DC (direct current) power. Standard home
appliances use AC (alternating current). An inverter converts the DC power
produced by the solar panels and batteries to the AC power required by appliances.
4. Battery Pack
Solar power systems produce electricity during the daytime, when the sun is
shining. Your home demands electricity at night and on cloudy days – when the sun
isn’t shining. To offset this mismatch, batteries can be added to the system.
5. Power Meter, Utility Meter, Kilowatt Meter
For systems that maintain a tie to the utility grid, the power meter measures the
amount of power used from the grid. In systems designed to sell power the utility,
ir.aiktclibrary.org
71
IR@AIKTC-KRRC
the power meter also measures the amount of power the solar system sends to the
grid.
6. Backup Generator
For systems that are not tied to the utility grid, a backup generator is used to provide
power during periods of low system output due to poor weather or high household
demand. Homeowners concerned with the environmental impact of generators can
install a generator that runs on alternative fuel such as biodiesel, rather than
gasoline.
7. Breaker Panel, AC Panel, Circuit Breaker Panel
The breaker panel is where the power source is joined to the electrical circuits in
your home. A circuit is a continuous route of connected wire that joins together
outlets and lights in the electric system.
For each circuit there is a circuit breaker. Circuit breakers prevent the appliances
on a circuit from drawing too much electricity and causing a fire hazard. When the
appliances on a circuit demand too much electricity, the circuit breaker will switch
off or trip, interrupting the flow of electricity.
ir.aiktclibrary.org
72
IR@AIKTC-KRRC
PHOTOVOLTAIC CELL
A photovoltaic (PV) cell is an
energy harvesting technology that
converts solar energy into useful
electricity through a process called
the photovoltaic effect. There are
several different types of PV cells
which all use semiconductors to
interact with incoming photons
from the Sun in order to generate
an electric current.
Solar PV cells generate electricity
by absorbing sunlight and using
Figure 10 Photovoltaic Cells
that light energy to create an
electrical current. There are many
photovoltaic cells within a single solar panel, and the current created by all of the cells
together adds up to enough electricity to help power your home. A standard panel used
in a rooftop residential system will have 60 cells linked together. Commercial solar
installations often use larger panels with 72 or more photovoltaic cells.
ir.aiktclibrary.org
73
IR@AIKTC-KRRC
ir.aiktclibrary.org
74
IR@AIKTC-KRRC
3.5.3.1Green Materials:
Green building is about making the best use of resources during all stages of
construction. By combining a system of components and materials that work in
harmony with one another, the goal is to create an energy-efficient, water-saving
structure with a low carbon footprint.
The use of green building materials and products represents one important strategy in
the design of a building. Using green building materials and products promotes
conservation of non-renewable resources and helps in reducing the environmental
impacts associated with the installation, reuse, recycling, and disposal etc of the
building materials.
Green building materials are composed of renewable, rather than non-renewable
resources. These materials are environment-friendly and offer specific benefits
including reduced maintenance/replacement costs over the life of the building, energy
conservation, improved occupant health and productivity, lower costs associated with
changing space configurations, greater design flexibility, and so on.
iv. VOC react with sunlight and nitrogen oxides in the atmosphere to form
ground-level ozone, a chemical that has a detrimental effect on human
health, agricultural crops, forest and ecosystems. These problems can be
eliminated using low VOC paints.
v. Selecting materials that are low in VOC helps reduce sources of pollutants
during the construction process and in the finished building. Also low
VOC paints have little odour.
vi. Use of high-VOC content materials can cause illness and may decrease
occupant productivity. These problems result in increased expenses and
liability for building owners, operators and insurance companies.
i. Now a day’s world is developing at a very fast rate so to cope with the increasing
needs of brick we were to find an alternative for clay bricks and we got the fly
ash bricks.
ii. Fly ash brick consists of fly ash which is a residue (left over material) from the
thermal power station as its main component.
iii. It has better properties from every point of view compared to the clay bricks.
iv.
v. Also the construction of fly ash brick is easier than the clay brick. This brick
needs less or no firing.
vi. The strength obtained from this brick is also far way better than the normal
bricks.
vii. The disposal of fly ash was the main issue before it was used as main component
of bricks.
viii. In fact in today's fast growing world where people needs better and sustainable
products fly ash brick has more use and its construction is increasing day-by-
day.
ir.aiktclibrary.org
76
IR@AIKTC-KRRC
❖ PVC PIPING
i. PVC piping is one of the world’s most sustainable products, making it ideal for
long-term term use in underground infrastructure. It requires less energy and
fewer resources to manufacture than old-technology materials, and its
production creates virtually no waste.
ii. PVC pipe manufacturing is extremely efficient, with virtually 100 percent of the
PVC compound being used. It takes four times less energy to make than concrete
pipe, and half that used for iron pipe.
iii. There are no smoke stacks at PVC pipe facilities and the product is completely
recyclable, making its environmental footprint far smaller than competing
piping materials. Contrast this with the cement industry – the third-largest
emitter of greenhouse gases in the world.
iv. PVC pipe’s ultra-smooth surface reduces pumping costs and its leak-free joints
eliminate water loss – which can be up to 40 percent in some old-technology
and corrosion-prone piping networks.
ir.aiktclibrary.org
77
IR@AIKTC-KRRC
For those situations where plastic is preferred over non-plastic components for the
identified green building technologies, the primary advantages cited generally
included:
Material flexibility and lighter weight, enabling greater design flexibility, ease of
installation and lower installation time and cost;
Durability and strength combined with chemical, weather and corrosion resistance and
biological inertness, leading to effective performance and long service life in the field;
Ease of colour coding and marking to identify safe acceptable uses and applications;
Cost-effectiveness in terms of manufacturing, transportation and ease of installation;
Recyclability and recycled content improves end-of-life impacts;
Extensive testing and compliance with nationally accepted consensus standards, third-
party certification, and approval in building codes and regulations.
ir.aiktclibrary.org
78
IR@AIKTC-KRRC
CONCLUSION
Water Management:
• 11% of the Total water demand has been reduced by using the Rain water
harvesting technique.
• 22.2% of water is saved from the water which comes through the Municipal
Water supply, this saving is achieved at alternate days throughout the year. With
the help of Grey Water Treatment (Conventional).
• Low-flow plumbing fixtures are used to save the water to certain extent.
• PVC pipes were used which is economical and has a life span of 50+ years.
Renewable energy:
• 11.5 kW capacity of Solar panels are used at outdoor lightning which includes
(Boundry lights, Corridor Lights, Staircase Lights, and Parking Lights) & also
for Lift in the building.
ir.aiktclibrary.org
79
IR@AIKTC-KRRC
CHAPTER 4
REFERENCES
ir.aiktclibrary.org
80
IR@AIKTC-KRRC
THANKYOU
81
ir.aiktclibrary.org