Chapter Seven
Chapter Seven
7.2.Separable components
7.3.Undiscounted methods
First, there is no one best technique for estimating project worth; each
has its own strength & weakness.
Second, these financial and economic measures of investment worth are
only tools of decision-making, i.e.,
They are necessary conditions & are not sufficient condition for
final decision.
There are many other non- quantitative and non-economic criteria
for making final decision of whether to accept or reject a project.
The payback period is the length of time from the beginning of the
project until the sum of net incremental benefits of the project equal
to total capital investment.
First, it fails to consider the time & amount of net benefits after
the payback period.
Second, it does not adequately take into account the time value
of money even in the payable periods.
Payback period = Initial payment / Annual cash inflow
But what if the project has more uneven cash inflows? Then
we need to work out the payback period on the cumulative cash
flow over the duration of the project as a whole.
Consider the following alternative projects
Alternative Year Investment cost Net incremental Commutation net
projects benefits incremental
benefits
I 0 20000 -
1 2000
2 8000
3 12000
4 6200 28200
II 0 20000 -
1 2000
2 12000
3 8000
4 12000 32000
III 0 20000 -
1 1000
2 5000
3 6000
4 8000
5 10000
6 5000
7 2000 37000
Project I & II have a payback period of 3 years. But project III has
a payback period of 4 years.
Thus, based on this criterion, project I & II have equal higher rank
than project III.
Therefore, the method fails to consider the time & amount of net
incremental benefit after the payback period- project III.
In addition, the method results equal rank for both project I and II.
Yet we know by inspection that we would choose project II over
project I because more of the returns to project II are realized
earlier.
This method is a measure of cash recovery, not profitability.
3. Rate of return on investment
The rate of return, also referred to as the average rate of return, has
many alternatives due to differences in how it is computed.
All the alternatives, however, have two features in common;
(i) use of accounting concepts in calculating benefits and
(ii) no adjustment for time value of money.
A. Proceeds per unit of outlay
Investments are ranked by the proceeds (cumulative of net incremental
benefits) per unit of outlay (investment cost).
It is the total net value of incremental net benefits divided by the total
amount of investment.
In the previous example, project I, II & III have a proceeds per outlay of
1.55, 1.7 and 1.85, respectively.
Hence, according to this criterion, project III will be ranked first.
B. Average annual proceeds per unit of outlay
This is the ratio of average income to the book value of the assets (i.e.
the value after subtracting depreciation) stated in percentage terms.
This measure, as the previous one, does not take into consideration the
timing of the benefit stream.
At = P(1 + r) t
At = total amount after t years , r = interest rate , t = time
A5 = 1567.05 (1 + 0.05)5 = 2000 Birr
I - investment cost
What positive NPV means is that the Return from the investment is
more than the risk inherent in the investment or
Accept investment: with the highest NPV and such NPV is positive
otherwise reject the investment
Cont.
Cont.
NPV= 25,000/(1+0.08) + 25,000/(1+0.08) 2 + 25,000/(1+0.08) 3+
25,000/(1+0.08) 4 + 25,000/(1+0.08) 5 - 1 million
3. Internal Rate of Return (IRR)
The internal rate of return is defined as the rate of discount,
which brings about equality between the present value of future
net benefits & initial investment.
It is the value of r in the following equation.
n
At
I 1 r
t 1
t
I – investment cost
At – Net benefit for year t
r - IRR
n - Life of the project
4. Benefit Cost Ratio
This is the ratio obtained when the present worth of the benefit
stream is divided by the present worth of the cost stream.
r - Discount rate
29
The End
Thank You