Lecture 14-M5 Network Analysis For Project Planning (Contd.)
Lecture 14-M5 Network Analysis For Project Planning (Contd.)
(MN 6035)
a: optimistic time of completion of an activity, when all the conditions are favourable for
early completion than the expected. This is the shortest possible time in which an activity can
be completed in ideal conditions.
b: pessimistic time of completion when all the conditions are against the normal working
condition. This is the maximum possible time in which everything goes wrong and
abnormal situations prevailed.
m: most likely time of completion of an activity, when all the conditions are normal as
expected.
Once the mean and variance of the duration of the project is completed, the probability of
completion of a project in the pre-specified time, T, can be determined as
𝑡𝑒 − 𝐸 𝑡𝑒 𝑇 − 𝐸 𝑡𝑒 𝑇 − 𝐸 𝑡𝑒 𝑇 − 𝐸 𝑡𝑒
𝑃 𝑡𝑒 ≤ 𝑇 = 𝑃 ≤ =𝑃 𝑧≤ =𝑃 𝑧≤
𝑣𝑎𝑟 𝑡𝑒 𝑣𝑎𝑟 𝑡𝑒 𝑣𝑎𝑟 𝑡𝑒 𝜎
In the above equation, z represents standard normal random variable whose mean and
standard deviations are 0 and 1 respectively. The reason for consideration of normal
distribution is that the project completion duration, te, is the sum of random independent
variables.
Example 1: A mining project has 5 tasks
(A, B, C, D, and E). The sequence and the
time required to finish the individual task
in days are shown in the network diagram
as given below. Determine the expected
time of completion of the project. Given
the uncertainties in accurately estimating
activity durations, what is the probability of
completing the project by the deadline of
35 days?
Computation of expected duration and standard deviation of individual task
Activity Optimistic Most likely Pessimistic te = (a + 4m + b)/6 σ = (b - a)/6
time (a) time (m) time (b)
A 7 10 16 10.5 1.5
B 6 10 15 10.2 1.5
C 4 6 10 6.3 1.0
D 6 8 12 8.3 1.0
E 8 10 14 10.3 1.5
The network showing the expected
duration of each activity is shown here.
The computation of expected duration of
completion of the project will be done
using the similar approach as that of
CPM.
Computation of Project Completion Time
Activity te ES EF LS LF Slack
A* 10.5 0 10.5 0 10.5 0
B 10.2 0 10.2 0.3 10.5 0.3
C 6.3 10.5 16.8 12.5 18.8 2
D* 8.3 10.5 18.8 10.5 18.8 0
E* 10.3 18.8 29.1 18.8 29.1 0
Note: *Critical activity/task
Thus, the critical tasks involves in the project are A, D and E and the expected duration of
the project is 29.1 days.
The critical path is A-D-E.
Therefore, the variance of the project completion time (VT) = Sum of the variance of the
critical activities = σA2 + σD2 + σE2 = 1.52+ 12 + 1.52 = 5.5 (days)2
𝑡 − 𝐸 𝑡𝑒
𝑃 𝑡𝑒 ≤ 𝑡 = 𝑃 𝑧 ≤
𝜎
𝑡 − 𝑡𝑒 35 – 𝑡𝑒
𝑃 𝑡 ≤ 35 = 𝑃 𝑡 − 𝑡𝑒 ≤ 35 – 𝑡𝑒 = 𝑃 ≤
𝜎 𝜎
35 – 29.1
=𝑃 𝑧≤ = 𝑃 𝑧 ≤ 2.515 = 0.994
2.345
[Note: Refer the normal distribution table. The value is corresponding to 2.5 in column and
0.01 in row]
Probability distribution function: The probability distribution for a discrete random
variable is represented by spikes of probability values correspond to the random
variable.
The cdf, F(x), represents the probability that x is less than or equal to k, for a discrete
random variable is given by
𝑃 𝑥 ≤ 𝑘 = 𝐹 𝑥 = σ𝑘𝑥=0 𝑃(𝑥)
𝑏 3250 3250
1 1 1 3250
𝑃 (𝑘 ≤ 𝑥 ≤ 𝑏 ) = 𝑓(𝑥)𝑑𝑥 = 𝑑𝑥 = 𝑑𝑥 = 𝑥 3000
𝑘 3000 700 700 3000 700
= 0.355
Normal Distribution: Although many types of distribution functions are developed
and applied for different purposes, but the normal distribution or the Gauss
distribution is widely used. The probability density function of the normal distribution
is given by
1 (𝑥−𝜇 )2
−
𝑓 (𝑥 ) = 𝑒 2𝜎 2
2𝜋𝜎
where,
µ = mean of the distribution
σ2 = variance of the distribution
𝒙𝝐(−∞, ∞)
An arbitrary normal distribution can be converted to a standardized normal density by
changing variables to𝑧 = (𝑥 − 𝜇) 𝜎 , so dz=dx/σ, yielding
1 −𝑍 2
𝑓 (𝑧 ) = 𝑒 2
2𝜋
In the normalized PDF, μ=0 and σ=1. The CDF of a standardized normal density
function is given by:
𝑍 𝑍 𝑍2
1 − 1 𝑧
𝐹 (𝑧 ) = 𝑓(𝑧)𝑑𝑧 = 𝑒 2𝑑𝑧 = 𝑒𝑟𝑓
0 2𝜋 0 2 2
where erf is an error function. Neither F(z) nor erf can be quantified with finite
additions, subtractions, multiplications, and root extractions, and therefore the
functions need to be computed numerically or otherwise approximated.
𝑃 𝑧<𝑎 =𝜙 𝑎 𝑓𝑜𝑟 𝑎 > 0
𝑃 𝑧>𝑎 +𝑃 𝑧<𝑎 =1
𝑃 𝑧 > 𝑎 = 1 − 𝑃 𝑧 < 𝑎 = 1 − ɸ(𝑎)
Therefore, ɸ −𝑎 = 1 − ɸ(𝑎)
𝑃 𝑧 < −𝑎 = 1 − ɸ(𝑎)