Abstract of Cost
Birsa Bridge
Amount
Sr. No. Description ( Rs. in ) of Bisra Bridge
1.0 Site Clearance 757876.00
2.0 Earth Work 5427069.00
3.0 CT Sub Base and Base Course 21699093.00
4.0 Bituminous Course 20550007.00
5.0 Miscellaneous 7287965.00
6.0 Protection work 951527.00
7.0 Junctions 2973561.00
8.0 Overhead Sign Board (2 Nos.) 3006426.95
9.0 Construction of Box Culverts (Total-1 Nos.) 2959516.36
10.0 RCC Retaining Wall (Total Length-100m, Ht-3m) 4212916.25
Sub-total of Road Part 69825957.56
11.0 Cost of Construction of Major
(i)Major Bridge at ch.39+510 Km. (14x28.6m) 405832748.27
Sub-total 475658705.83
A Civil Cost 475658705.83
(i) Add 18% for GST On A 85618567.00
(ii) Construction Cost (A + GST.) 561277272.83
(iii) L.C @ 1% on construction cost (A+ GST). 5612773.00
B Civil Cost 566890045.83
(i) Contingencies @ 1.0 % on 'A +L.C.' 4812715.00
(ii) Agency Charges 3% on 'A +L.C.' 14438144.00
(iii) Supervision Charges 3% on 'A +L.C.' 14438144.00
(iv) Maintenance @ 5% on ' B ' for 10 Years. 28344502.29
(V) Price Adjustment @ 5% on ' B ' for 2 Years. 28344502.29
(Vi) Cost of land acquisition 42021124.24
(Vii) Cost of Resettlement and Rehabilitation. 3000000.00
C Total Cost of Birsa Bridge 702289177.65
Say 702289177.00