Impact - of - Distributed - Generation - On - VoltVar - Contro
Impact - of - Distributed - Generation - On - VoltVar - Contro
net/publication/4078049
CITATIONS READS
139 1,401
3 authors, including:
All content following this page was uploaded by Taher Niknam on 02 June 2014.
D
ISTRIBUTED Generation (DG) is defined as the
generation which is dispersed throughout a utility’s II. OBJECTIVE FUNCTION
service territory and either connected to the utility’s
distribution system or small and Grid Isolated. DG From a mathematical standpoint the Volt/Var control
technologies include Photovoltaic, Wind Turbines, Fuel Cells, optimization problem is a minimization problem with
Micro Turbines and so on. inequality constraints. The objective function is summation of
During, the last decade many electrical power systems around losses in distribution system for load variation. The value of
the world have been deregulated and DG is predicted to play the objective function is determined through power flow
an increasing role in the electric power system of the near solution.
future. A study by the Electric Power Research Institute The objective function is given by equation (1).
(EPRI) indicates that by 2010, 25% of the new generation will
be distributed, and also, a study by Natural Gas Foundation F ( x ) = min Ploss dt (1)
matrices are used to obtain the power flow solution. They are
the Bus Injection to Branch Current (BIBC) and the Branch [∆V ] = [∆Va1, ∆Vb1, ∆Vc1,..., ∆VaN , ∆VbN , ∆VcN ]T
Current to Bus Voltage (BCBV) matrices [7]. = VSet − VCalc
Where:
IV. DISTRIBUTED GENERATION MODEL [Z]3N*3N: Sensitivity Matrix which is calculated based on
Depending on the contract and control status of a generator, it three phase impedance matrix of lines.
may be operated in one of the following modes: [∆V]: voltage magnitude mismatch vector for PV nodes.
1. In “parallel operation” with the feeder, i.e., the [IInjec]: injected reactive current vector in PV nodes.
generator is located near and designed to supply a large |Vset| : Scheduled voltage magnitude vector for PV nodes.
load with fixed real and reactive power output. The net |VCalc|: Calculated voltage magnitude vector for PV nodes.
effect is the reduced load at a particular location.
2. To output power at a specific power factor. Since in power system there is nonlinear relation between
3. To output power at a specific terminal voltage. voltage and current, we have used an iterative method for
The generation nodes in the first two cases can be well voltage mismatch correction as follows:
represented as PQ nodes. The generation nodes in the third Step1: solve the power flow equation with initial condition
case must be modeled as a PV node. In this paper, generators (Qgi=0).
are modeled as PV nodes.
PV nodes are modeled in similar manner as presented in [7]. Setp2: calculate mismatched voltage for each PV nodes. If
these values are less than thresholds go to next step, otherwise 2(a). In this case correspondent matrix should be refactorized.
stop. Another way to simulate the tap positions change is to modify
model Fig.l(b) by adding virtual injected currents as it is
Step3: calculate injection reactive current amplitudes. shown in Fig. 2(b).
Figure 5 shows the load curve profile in all load point in the
Calculate Power Losses
network.
Error < e
Yes
No Fig.5. Variation of load.
Stop Now for using the GA to determine the state variable of the
system i.e. tap of LTC, size of capacitors, tap of Voltage
regulators and voltage amplitude of generators, the following
Mating and Reproduction assumption is made:
Initial population: 2000
Mutation Number of good population: 300
Number of load level: 3
Limit of voltage magnitude: 0.95-1.05
Solve 3-Phase Radial Power Flow with RTVR1< RTVR2 <RTCap1 <RTCap2
Considering Modeling of Local Controllers and PV Limit of power factor in substation: 0.95-1
nodes
Limit of tap position: .97-1.05
Size of tap: 0.0001
Limit of substation capacitor: 0-1000 kVar
Calculate Power Losses Limit of local capacitors:
C1:0-450 kVar
Fig3. Flow chart of algorithm C2:0-300 kVar
In this approach, local controllers are coordinated based on Mutation: µ = 0.04 e − Counter
theirs response times. In the other word, at first local ε=0.000001
controllers in which have the shortest response time, will Ngood
response to power flow alterations. Slower controller response Error = ∑n =1
Cost n − Cost Ngood +1
will be based on output of faster local controllers. It is
assumed response time of Voltage Regulators is less than Where:
capacitors. Counter and Costi are number of iteration and value of
objective function for the ith population respectively. RTi is
VIII. SIMULATION response time for each local controller.
In the following section the application of the method for
In this section, Volt/Var control algorithm is tested on the 34 various load conditions are presented.
Bus IEEE test feeder, whose one line diagram is given in
Fig.4. The feeder line and load data is taken from [9]. A) PEAK LOAD
In this case it is assumed that in all load nodes, the load is in
its maximum level. Table II represents result of simulation for
this case.
XI. BIOGRAPHIES
Taher Niknam was born in Shiraz in Iran. He received his
B.S and M.S degree from Shiraz University and Sharif
University of Technology respectively. He is Ph.D student at
Sharif University of Technology and a faculty at the Power
System Department of South Tehran Branch of Azad
University. His interests include power system restructuring,
impact of DGs on power system and power electronics. He is
working in Niroo Research Institute and Iran Electricity
Generation and Transmission Company (TAVANIR) in
Tehran.