REPLY
REPLY
400:
As per Schedule - B Annex-I (page no. 153 of CA), Width of Deck of the elevated road
portion of the main carriageway going from Moradabad to Bareilly at Chainage 8+400 km
interchange is 5.50 m only. As it is main carriageway of the highway from Moradabad to
Bareilly, it must be designs as per IRC-SP: 84:2019; Manual of Specification and Standards
for Four Laning of highways. Thus, the Contractor seeking COS for increasing of width of
deck slab from 5.5 m (as mentioned CA) to width of 11m (as per IRC). Please furnish your
comment.
As per Schedule - B (Page No.191 of CA), two (02) Minor Bridge at Km 8+880 (1x12m) &
Km 8+450 (2x12) were proposed at Interchange Km 8.400. EPC Contractor has proposed
three Minor Bridge, for proper drainage, discharge runoff and Nalah water, according to
topography and land profile, thus it is necessary to provide minor bridges at three locations
as against that of only two in Schedule B of the Contract agreement. Please furnish your
comment
During the meeting, in the presence of the Project Director, Authority Engineer, and Contractor, it was
agreed upon that the TCS would be enclosed in Schedule B. We are currently unaware of why this point is
being revisited. The authorities need to address this matter, as providing unnecessary benefits to the
contractor may be perceived as unwarranted. It should be noted that the TCS is a part of the Tender
Document.
Besides the two structures outlined in our report titled "GAD Drawing PIU Muradabad /FFR/Elevated -1,"
the covered drain, as dictated by the site condition, is indicated in the drawing with lengths of (230 m &
180 m). This is also depicted in the drawing with its typical cross-section labeled as "Section GG" with a
width of 12m.
It was also discussed during the meeting with the Regional Officer (RO) that if the contractor doesnot
cover the drain, they are obligated to provide full protection arrangements to ensure the safety of road
users, including crash barriers. The quantity of crash barriers allocated for this purpose may be utilized to
cover the Nala as per site requirements.
And at km 3+422 the TCS 3 is applicable as per Schedule B,There is already existing slip (km 3.8 to km
5.4)road along the alignment and for this stretch the contractor have adopt the TCS 3,3A,4 with full
height RE wall for widening the road on left side as per schedule B TCS Enclosed and per per site
condition there is good enough space to retain the existing slip road by providing the overlay thickness
over it.