Key Components of EVM

Uploaded by

Dineshkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views3 pages

Key Components of EVM

Uploaded by

Dineshkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Key Components of Earned Value Management (EVM)

1. Planned Value (PV)

Definition: PV is the budgeted cost for the work scheduled to be completed by a specific date. It

represents the value of the work planned to be done by that time.

Example: If a project has a total budget of $100,000 and is planned to be 30% complete after 3

months:

PV = $100,000 * 30% = $30,000

This means by the end of 3 months, the project was planned to deliver $30,000 worth of work.

2. Earned Value (EV)

Definition: EV is the value of the work actually completed by a specific date. It represents the

budgeted amount for the work that has been done so far.

Example: If the project is actually 25% complete after 3 months:

EV = $100,000 * 25% = $25,000

This means by the end of 3 months, $25,000 worth of work has been completed according to the

project plan.

3. Actual Cost (AC)

Definition: AC is the actual cost incurred for the work completed by a specific date. It represents how

much has actually been spent on the work done so far.

Example: If the project has spent $27,000 to achieve 25% of the work:

AC = $27,000

This means by the end of 3 months, the actual cost of completing 25% of the work is $27,000.
4. Cost Variance (CV)

Definition: CV is the difference between the earned value and the actual cost. It shows whether the

project is under or over budget.

Formula: CV = EV - AC

Example: CV = $25,000 (EV) - $27,000 (AC) = -$2,000

This indicates that the project is over budget by $2,000.

5. Schedule Variance (SV)

Definition: SV is the difference between the earned value and the planned value. It shows whether

the project is ahead or behind schedule.

Formula: SV = EV - PV

Example: SV = $25,000 (EV) - $30,000 (PV) = -$5,000

This indicates that the project is behind schedule by $5,000.

6. Cost Performance Index (CPI)

Definition: CPI is the ratio of earned value to actual cost. It measures the cost efficiency of the work

completed.

Formula: CPI = EV / AC

Example: CPI = $25,000 (EV) / $27,000 (AC) = 0.93

A CPI of 0.93 means that for every dollar spent, the project is earning only $0.93 worth of work.

7. Schedule Performance Index (SPI)

Definition: SPI is the ratio of earned value to planned value. It measures the efficiency of time

utilization in the project.


Formula: SPI = EV / PV

Example: SPI = $25,000 (EV) / $30,000 (PV) = 0.83

An SPI of 0.83 means that the project is progressing at 83% of the planned rate.

8. Estimate at Completion (EAC)

Definition: EAC is the expected total cost of completing all work on the project. It is calculated based

on performance to date.

Formula: EAC = BAC / CPI

Example: If the total budget (BAC) is $100,000 and the CPI is 0.93:

EAC = $100,000 / 0.93 = $107,527

This suggests that the project will likely cost $107,527 to complete, exceeding the original budget.

9. Estimate to Complete (ETC)

Definition: ETC is the expected cost to finish all remaining project work.

Formula: ETC = EAC - AC

Example: If EAC is $107,527 and AC is $27,000:

ETC = $107,527 - $27,000 = $80,527

This means that an additional $80,527 will be needed to complete the project.

10. Variance at Completion (VAC)

Definition: VAC is the difference between the budget at completion and the estimate at completion.

It indicates how much over or under budget the project will be.

Formula: VAC = BAC - EAC

Example: VAC = $100,000 (BAC) - $107,527 (EAC) = -$7,527

This indicates that the project is expected to exceed the budget by $7,527.