Hydrograph
Hydrograph
Unit Hydrograph
o Collins' Method
o De-convolution of Direct Runoff Hydrograph
References
Contributors
Top of page
MODULE OBJECTIVES
Top of page
UNIT HYDROGRAPH
The Unit Hydrograph (UH) is the simplest but at the same time a very powerful tool for
hydrological analysis in general and flood forecasting in particular.
The unit hydrograph may be defined as the direct runoff (outflow) hydrograph resulting from
one unit of effective rainfall, which is uniformly distributed over the basin at a uniform rate
during a specified period of time known as unit time or unit duration. The following
paragraphs make this statement still clearer.
Effective rainfall should be uniformly distributed over the basin, i.e. if there are five rain
gauges in the basin, which represent the areal distribution of rainfall over the basin, all the
five rain gauges should record for almost same amount of rainfall during specified time. A
watershed shown on the right here fully marks this stipulation, while converse is true in
respect of left one.
In addition, effective rainfall should be at a uniform rate during the unit duration. If the
average rainfall over a particular basin during 6 hour is 126mm, a unit hydrograph of 6
hours duration can be derived only if the intensity of rainfall is more or less 21 mm/hour
over 6 hours. If the same amount of rainfall is distributed with varied intensity, the unit
hydrograph cannot be precisely estimated by simple method.
The unit quantity of effective rainfall is normally taken as 1mm or 1cm; and the outflow
hydrograph is expressed by discharge in cumec. The unit duration may be of 1-hour duration
or more, depending upon the size of the catchment, storm characteristics and operational
facilities. However, the unit duration cannot be more than the time of concentration or basin lag or
period of rise. The concept of time of concentration has been covered in detail later in the
chapter.
Top of page
The following are the basic assumption in the unit hydrograph theory:
The unit hydrograph theory assumes the principle of time invariance. This implies that the
direct runoff hydrograph from a given drainage basin due to a given pattern of effective
rainfall will be always same irrespective of the time, i.e. even if the basin characteristics
change with season etc., the unit hydrograph remains the same.
Unit Hydrograph theory assumes the principle of linearity, superimposition or
proportionality. It means that:
If the ordinates of a unit hydrograph of say 1 hour duration are 0,1,6,4,3,2,1,0 units
respectively, the effective rainfall of 2 units falling in 1 hour will produce a direct
runoff hydrographs having ordinates of 0,2,12,8,6,4,2,0 units.
Secondly, if the effective rainfall of two units occurs in 2 hours, i.e. 1 unit per hour,
the direct runoff hydrograph ordinates will be obtained by summing up the
corresponding ordinates of the two unit hydrographs as shown here.
Top of page
The steps involved in derivation of UH from the analysis of the flood hydrograph with a single
peak are as follows;
Inspect discharge records at watershed outlet and corresponding rainfall events to identify
events exhibiting isolated, well defined and single peak with considerable run-off volume. Pick
up as many sets of such records as available. A plot displaying rainfall and corresponding rise
in flood hydrograph, such as here, can help selection of records.
Note - A no-break/continuous discharge series, as shown in the plot, is developed by
transforming hourly river stage (also water level) into discharge with the help of rating
equation. Rating equation used for this purpose must be developed for the period to which
flood event belongs to.
A rating equation/curve is an equation that relates discharge with water level observed at a site, and is
mathematically expressed as
Q = c * (G - Go)n
This method suggests the extension of the base flow line along its general trend before the rise
of the hydrograph up to a point B directly below the runoff hydrograph peak. From B, a straight
line BD is drawn to meet the hydrograph at point D, which is N days away from B in the time
scale. 'N' is determined by an empirical relation by Linsley as:
This method requires identification of two additional points on the recession limb of
hydrograph - one is inflection point; while the other is point E. At inflection point, curve
changes its concavity. This point also indicates end of surface flow to river. This point beyond,
discharge is a combination of interflow (also called as sub-surface flow) and base flow. After a
while, interflow also ceases; and only base flow remains in the river. The 'E' suggests this stage.
Once, these two points are located on the graph, a line from 'E' is drawn backward to meet a
vertical line from inflection point. A line A-B-C-E divides the DRH and base flow.
Nevertheless, for flood studies, the base flow component is rather insignificant and hence does
not influence the magnitude of peak runoff substantially. Therefore, inaccuracies involved in
separation of base flow are not crucial in overall flood studies.
3. Computation of direct runoff hydrograph ordinates by deducting base flow ordinates from
that of the corresponding observed flood hydrograph.
4. Scanning and analysis of the rainfall data of all rain gauge stations in and around the basin
with a view to;
Obtaining areal rainfall over the catchment by appropriate methods, such as Thiessen
Polygon or Isohyetal technique, and
Estimating phi-index. Volume of DRH equals the product of catchment area and rainfall
excess over the basin. This simple analogy helps us estimate depth of rainfall excess.
A gap between effective rainfall and averaged rainfall points to losses. Here, in the plot, ? -
index (also known as loss rate) is drawn in a manner that partitions hyetograph into two
parts- lower indicates losses, while upper rainfall excess.
5. As DRH is a consequence of given rainfall excess, say 'x' unit. Estimation of the ordinates of
the UH is obtained by dividing the ordinates of direct runoff hydrograph by 'x' rainfall excess.
A plot shown here exhibits duration of rainfall as 5-unit, of which only during 3-unit duration
rainfall exceeds 'loss rate'. Thus, for this case, UH duration is a 3-unit.
6. This process is repeated for all records picked up for this purpose.
7. It is highly probable that UHs derived for more than one record may differ in duration of
excess rainfall. They need to be converted to an identical duration before attempting step 8. A
discussion on conversion of UH duration has been added toward the end of this module.
8. All such UHs are eventually averaged. For this, first peaks, Qp, of all UH are averaged to
give Qp, followed by time to peak, tp and time base, Tb of UHs. All other ordinates are adjusted
in such a way that total run-off volume of UH equals the product of 1cm/mm and catchment
area.
More discussions on conversion of UH duration and averaging of UH have been added toward the end of
this chapter.
Top of page
Flood hydrographs with a single and sharp peak resulting from an intense and uniform rainfall
are very uncommon. Often times, observed hydrographs contain multiple peaks of various
magnitudes resulting from several spells of rainfall. UH, in such cases, are derived by
- Collins' Method
- Matrix method
- Instantaneous Unit Hydrograph
Top of page
This method uses trial and error approximations to compute UH from complex hydrograph.
The basic steps involved in this method can be best gathered by an illustrative example. This
example is available in excel file of this week schedule, which can be downloaded by
participants.
Example
The direct runoff hydrograph at site-S and the effective hydrograph due to a particular storm
over the catchment of river-R are tabulated below. We will use the given DRH and ERH to
derive unit hydrograph because of 1mm effective rainfall. Catchment area is 8570 km2.
Note- The effective rainfall hyetograph blocks are for 3 hour intervals. Therefore, the unit
duration of the unit hydrograph thus derived will be of 3-hour unit duration.
i) From the observed flood hydrograph and observed rainfall hyetograph DRH and ERH are
separated as explained earlier;
ii) The ordinates of the DRH at different time are written under Column 2 of the Table 3;
iii) Trial & error of determining UH ordinates begins with selection of first set of trial values
representing ordinates of UH. This we can do by dividing the ordinates of DRH with 11mm
effective rainfall, and recording them under column 3 of the Table 3;
iv) The ordinates of the assumed unit hydrograph are summed up as 785.4 cumec. But the sum
of ordinates of the unit hydrograph at 3 hour interval, U for a catchment area of 8570
km2 should be:
Hence,
where A = area of catchment in km2, =8570 km2, & t = time interval in hour = 3 hours
v) In order to satisfy condition stated above, all the assumed ordinates are multiplied by a factor
1.01 (793/785.4) and the adjusted values are entered in col.4 of the table;
vi) The ordinates on adjusted UH (col.4) are multiplied by 2.4, first burst of rainfall, and are
written under col.5. Similarly, the ordinates of adjusted unit hydrograph (col.4) are multiplied
by 3.0 mm, third burst of rainfall, and are reflected in col.7 after shifting it by 6 hours. Why this
shift is warranted here? - It is so because 3.0 mm rainfall begins after 6hrs from the start of the
storm.;
vii) The ordinates in col.5 and 7 are now added together and written under column 8. This gives
the DRH resulting from rainfall excess (2.4mm + 3.0mm) excepting the largest one, i.e. 5.6mm;
viii) The DRH ordinates obtained in col.8 are deducted from the ordinates of DRH in col.2, and
are noted down in col.6. This is a DRH as a result of 5.6mm of rainfall. First ordinate due to 5.6
mm rainfall is made zero as this represents the beginning of contribution of 5.6mm rainfall;
ix) The values in col.6 are divided by 5.6mm to give the unit hydrograph, and are fed in col.9.
Since, this is a UH, it is necessary to re-validate its volume against condition stipulated under
Para (iv) above. The sum of ordinates of this UH as written in col. 9 is now 777. These ordinates
are, therefore, multiplied by 1.02 (793/777) to readjust its values as reflected in col.10.
x) The weighted average of the two unit hydrographs (the assumed one as in column 4 and
calculated one as in col.10) is reached in the following manner:
xi) The weighted average ordinates are written under column 11 of the Table-3. The ordinates of
the unit hydrograph in column 11 and column 4 are now compared for differences. If significant
differences are noticed between the two, 2nd iteration begins with unit hydrograph ordinates of
column 11; and this will occupy column 4. Thus, the process is iterative and will go on till the
differences in the assumed and calculated unit hydrographs reduce to insignificant level.
The ordinates of the derived unit hydrograph are tabulated below. At times, it is possible that
the lower part of the unit hydrograph may not be uniform. In such cases, it is smoothened and
redrawn smoothly with least variations in a manner that its volume should fulfil condition of
Para (iv).
Top of page
The discrete convolution equation allows the computation of direct runoff, Qn given excess
rainfall, Pm and the unit hydrograph, Un-m+1.
The reverse process, called de-convolution, can be utilised to derive a unit hydrograph given
data on Pm and Qn. Suppose that there are 'M' pulses or burst of rainfall excess and 'n' pulse of
direct runoff in the storm considered; then N equation can be written for Q n, n = 1,2,….,n, in
terms of (n - m + 1) unknown values of the unit hydrograph.
If Qn and Pm are given and Un-m+1 is required, the set equations is over determined, because
there are more equations (N) than unknowns (n - m + 1). The term n M in the equation
restrains the total nos. of P*U terms for Qn. In first case, when n is M, m = 1, 2, n; while in
case n is M, m = 1,2, ….M.
(For more details, reader may refer to Applied Hydrology by Ven Te Chow)
Let us derive term for Q1, assuming total number of rainfall pulse, M = 3
An observed hydrograph with rainfall excess is given as under. The time interval is 3 hours
between readings. Catchment area is 7092 km2.
There are 3 pulses of rainfall so M = 3. There are 13 pulses of observed direct runoff so n = 13.
The number of unit hydrograph ordinates is therefore, n - m +1 = 13 - 3 + 1 = 11 ordinates.
Applying this piece of information, set-up of matrices for Q, P and U appear as below
Where, [Q] is 13 by 1 matrix with discharge ordinates; [P] is a 13 by 11 matrix having three
rainfall impulse of given duration; and [U] is unknown matrix of 11 by 1 size whose ordinates
are to be determined. In matrix form, information of tabular chart reduces to
To solve this problem for [U] matrix, we choose only 11 equations to obtain 11 unknown UH
ordinates using following equation.
Result obtained using MS excel shown next has generated a few negative terms in the falling
limb of UH; and this has to be adjusted by the reader in such a way as to total volume of UH
must be equal to the volume of runoff emerging form the catchment as a result of 1mm uniform
& effective rainfall over it. This example, thus, underlines the likelihood of a few negative and
abnormal terms in the calculation and need subsequent readjustment.
Adjusted unit hydrograph is shown below.
At this stage, reader is advised to refer to the excel sheet for familiarizing themselves with
calculation part of this example.
Top of page
The Clark model uses two parameters, time of concentration, 'Tc', and storage constant, 'K', and
a time-area histogram concept. Before, we set out for UH by Clark model, let us first familiarize
ourselves with these new terminologies.
Top of page
The first parameter, time of concentration is the time taken by a water particle from the
hydraulically farthest point to the basin outlet. An estimate of this travel time is the time from
the end of runoff producing rainfall over the basin to the inflection point on the recession limb
of the direct Runoff Hydrograph (DRH). Because of complexities involved in rainfall-runoff
process, all such incidences never produce reproducible 'Tc' nor can we ever know true Tc. And
therefore, an averaged value of 'Tc' from observed data should be considered for analysis.
Alternatively, any empirical equation, most valid for area under study is recommended for use.
Some of the empirical equations normally used for estimation of this parameter are as under:
(For more discussion on 'Tc', reader may please refer to Hydrologic Analysis and Design by
Richard H. McCuen and Technical Reference Manual of HEC-HMS software).
Top of page
This coefficient represents the temporary storage of precipitation excess in the watershed as it
drains to the outlet point. K is expressed in terms of time. If observed short interval flood
discharges at site are available, then hydraulically, K is estimated by using the formula:
Where;
correspond to the discharge, after separating base flow, at the point of inflection on
Q1:
the recession limb of flood hydrograph.
correspond to the discharge, after separating base flow, after time t on the recession
Q2:
limb of flood hydrograph.
Adopting a suitable base flow, the value of K can be computed for different hydrographs and an
average value can be worked out.
Top of page
TIME-AREA CONCEPT
The time-area diagram represents the areas that will contribute to the flow at the outlet over
successive periods of time. Once the time of concentration is known, lines of equal time interval
called isochrones can be drawn with assumption that time of travel is directly proportional to
distance from the outlet to isochrones. In the picture shown here, dashed lines in yellow mark
isochrones.
The US Army Corps of Engineers recommends following formula to develop time area
table/diagram for estimation of inflow from areas bounded between successive isochrones. An
example at the end of this discussion explains the use of this equation.
The time-area diagram is considered as the inflow to a hypothetical reservoir (S = KO; this
implies that there is absence of wedge storage) and routed through the reservoir to obtain the
outflow hydrograph which is the required instantaneous UH for the basin. Before routing,
inflow from incremental areas between isochrones is converted into discharge units by
following equation;
Where 'ai' is the area in km2 and 't' is the routing period in hours.
Here, we will take a pause to understand as to how this model produces an outflow with time-
area concept; and inflow is generated by each time-area zone due to instantaneous 1mm
effective rainfall. Let us consider the uppermost part of the catchment. Being uppermost part of
the watershed, it does not receive any outflow (O0=0). Instead, it produces I1 runoff which takes
1 hr (if tc for the catchment is 6hrs; and isochrones are separated by 1hr each) to reach at the tip
of area just below it with a magnitude of Oi routed by following equation.
Oi = CIi + (1-C)Oi -1
Where C = (t/(K+0.5t)), here, t is routing interval in hr, k is basin storage coefficient; and Ii and
Oi are the inflow and outflow at the end of period ti.
O1 = CI1 + (1-C)* 0
Now, let us consider the area downstream of first one. Like above, this part generates inflow,
I2 and receives O1 as outflow from upper area. Using routing equation, this area will produce
O2 as
O2 = CI2 + (1-C)* O1
This process is continued till we reach terminal point of the catchment/study area.
The IUH can be converted to a unit hydrograph of same unit duration as routing interval simply
averaging two instantaneous hydrographs lagged by the selected duration that is,
Qi = 0.5(Oi + Oi-1)
To obtain unit hydrograph for durations other than routing interval (provided that it is exact
multiple of routing interval t. The following equation is used.
Example
Derive UH for a project site using Clark model with physiographic characteristics of the basin
given in Table 1. No observed flood hydrograph is available at the project site.
Solution
Since, no observed flood hydrograph is available at project dam site, Tc, time of concentration is
determined using the Kirpich, the Kerby and the California formulae as shown in Table 2. The
average value as 6.0 hour based on 3 formulae is adopted for project catchment up to project
site.
Since the time of concentration adopted is 6 hr, the catchment area has been divided into six
isochrones representing 1 hr equal travel time. The equation developed by U.S. Army Corps of
Engineers is used to estimate the time-area relationship of the watersheds. Table 3 presents the
resulting Time-Area relationship for river upto dam site.
Note- For HEC-HMS software savvy readers, calculation reflected in table 3 is not essential.
HEC-HMS software needs two key parameters, i.e. Tc and K to be input appropriately in its
environment, and rest of calculation and UH output are handled by software in no time.
From the Table 3, the value of catchment area can be used developing inflow for each
computational time interval using excel sheet.
Since the site specific observed short interval discharge data is not available for dam site,
therefore basin storage coefficient is estimated based on regional values of K available for
concerned river.
For estimating the value of storage coefficient 'K', observed complex flood hydrographs from
3rd to 7th September 2001, 22nd to 25th Jul-2002, September 2004 flood hydrographs at one
G&D site on the same river have been used. The detail is given below:
Therefore from Table 4, the Storage coefficient K can be taken as 9.0.
Assuming a base flow of 450 m³/s, the value of K has been computed for different hydrographs
at another site on the same river as shown in Table 5. The average value of 8.0 hr has been
adopted for observed hydrographs at this G&D site, an average value of attenuation constant K
equal to 8.0 hr has been worked out based on 4 flood events.
The K is estimated based on the fact that for a given regional value of this parameter at a
Having determined catchment area, time of concentration, Tc and storage coefficient, K, a model
depicting basin is developed in HEC-HMS and basin is subjected to 10mm=1cm effective
rainfall for 1-hr duration. Resulting hydrograph, i.e. 1-hr duration UH and its ordinates are
available below:
Top of page
Derivation of IUH
There are various methods for the determination of an IUH from the given effective rainfall
hyetograph and direct runoff hydrograph. But the most common is the model suggested by
Nash in 1957. Nash proposed a conceptual model by considering a drainage basin as 'n'
identical linear reservoirs in series. By routing a unit inflow through the reservoirs a
mathematical equation for IUH can be derived.
Where,
The values of K and n in Nash model can be evaluated by the method of moments by using
the following relations:
Where,
MDRH1= First moment arm of Direct Runoff Hydrograph (DRH)
MERH1= First moment arm of Effective Rainfall Hyetograph (ERH)
MDRH2= Second moment arm of DRH
MERH2= Second moment arm of ERH
The unit of the ordinates of IUH is per sec (sec-1). When the ordinates are multiplied by the
total volume of runoff (in cubic meters) resulting from 1mm of rainfall over the catchment
area, the unit will be cumecs.
Derivation of Unit Hydrograph from IUH
For finding the unit hydrograph from IUH, the area under the IUH is plotted with respect to
time at the point. The entire area from the start of IUH at different time interval gives points
of S Curve. If a unit hydrograph of T hour duration is required, the S Curve so arrived at is
shifted by T hour and the difference in the ordinates of the two S Curves is computed and
divided by T. The resulting curve forms the unit hydrograph of T hour duration. To illustrate
derivation of UH by Nash method, an example is presented ahead.
Example
A storm of mild intensity was experienced in the catchment of river Baitarani during the
period from 26.9.75 to 28.9.75. The rainfall was rather non-uniform. The average hourly
rainfall over the catchment and the resulting observed discharge at Anandpur site are
furnished in Table 1 & 2. The area of catchment of River Baitarani up to Anandpur is 8570
sqkm.
With this set of data pertaining to this storm, an IUH followed by the unit hydrograph of one-
hour unit duration have been computed below:
The various steps involved in the procedure are as follows:
The anticipated recession curve of the smaller peak just before this flood was
continued till the time of the peak, i.e. point B.
A suitable point was chosen on the falling limb at a distance of about 2t to 2.5t where 't'
is the time from the rise of flood hydrograph to the peak.
These points B & C were joined by a straight line. The curve thus separates the base
flow from total flood.
The base flow thus separated is deducted from the corresponding ordinates of the
flood hydrograph to get the direct runoff hydrograph (DRH).
2. Separation of Rainfall Excess from Total Rainfall
The total hourly rainfall (average over the basin) is shown in the table above. Since the storm
under consideration is in the month of September and there was a heavy storm in August
and yet another storm of smaller intensity in early September, the loss may be considered to
take place at a uniform rate.
Where, 4344 is total sum of DRH ordinates and 3hrs is time interval between two adjacent
DRH ordinates.
For the purpose of analysis, the hourly ordinate will involve a lot of computational work, and
therefore, only the three hourly rainfall ordinates have been considered. The hourly rainfalls
are assumed to be uniform during three hours and accordingly, the ordinates of DRH and
ERH are shown in Table A.1 below
3. Calculation of n and K
Hence, for analysis the values of K and n may be taken as 4 hr and 4 respectively (In case of
very sandy soil characteristics of the catchment 'n' may be taken as 5 if its value works out to be 4.47,
whereas for hilly or semi-hilly regions of catchment, n should be 4).
Once n and K are found out, the ordinates of the IUH can be found very easily by using the
relation
This will give ordinates in units of Sec-1. To find the ordinates in cumec, it is multiplied by
catchment area contribution due to 1mm effective rainfall. Thus for first time unit U(1),
Area = 8570 * 106 m2, K = 4 * 60 * 60 sec, (n-1)! = (4-1)! = 6, t = 1 hr. Pl note that in term (t/K), K
would be 4hr as we are considering t in hr. This step is repeated for rest of time units to generate
IUH. The ordinates of IUH are given in Table below:
It will be seen that the last ordinate is never zero. This is because of the fact that the recession of IUH is
generally defined by an exponential function which has zero value only at infinity. Hence, the recession
is terminated at a suitable point and volume adjusted
The tth hour ordinates of the 1-hour duration unit hydrograph can be very easily found by
simply taking the average of tth hour and (t-1)th hour ordinates of the IUH. Column 2 of the
Table above gives the ordinates of the IUH (rounded off figures) the column 5 gives the
ordinates of the 1-hour duration unit hydrograph.
Top of page
More often than not, project sites suffer from inadequate length of hydro-meteorological data or
even no data to deduce any reliable hydrological inputs or to develop reliable transfer function
in the form of a UH. In several cases, constraint of this kind is not uncommon in India, which
compels an engineer to resort to develop a synthetic unit hydrograph. A Synthetic Unit
Hydrograph (SUH) takes its shape and size according to the physical characteristics of the basin
under study. There are few methods of developing SUH. Some of the common methods for
derivation of synthetic unit hydrograph for a basin are as follows:
Snyder method
Among several known methods for development of synthetic unit hydrograph, the one
suggested by F. F. Snyder (1938) is most commonly used. Snyder analyzed a large
number of hydrographs from drainage basins in the Appalachian Mountain region in the
United States, ranging in area from 25 sq. km. to 25,000 sq. km.
To sketch a unit hydrograph, it is necessary to know the time of the peak, the peak flow
and the time base. The elements must be determined for every particular or regional
location of the drainage basin. Snyder proposed the following empirical formula for the
lag time (Hr.) from mid-point of effective rainfall duration tr to peak of a unit
hydrograph:
tp = Ct (L. Lc ) 0.3
in which tp = the basin lag in hours, from midpoint of effective rainfall duration t r to peak
of a unit graph:
L= the length of the main stream from the outlet to the divide in kms;
Lc =the distance from the outlet to a point on the stream nearest to the centroid of the
basin; and Ct = a coefficient
The location of the center of area may be determined by cutting the basin outline from
cardboard and marking the point of intersection of plumb lines drawn with the map
suspended from different corners. The coefficient Ct varies from 1.0 to 2.2 with lower
values associated with basins of steeper slopes.
For the standard duration of effective rainfall tr , Snyder proposed:
For the rains of this duration, he found that synthetic unit hydrograph peak Qp in
cumecs may be obtained from the equation:
For the time base T (in days) of the synthetic unit hydrograph U.S. Army Corps of
Engineer adopted the following expression
These equations are sufficient to construct a synthetic unit hydrograph for a storm
of duration tr
o If unit hydrographs are available for several areas adjacent to a basin for which a
unit hydrograph is required but for which necessary data are lacking, then
transposition of available unit hydrograph will ordinarily give better results than
resorting to a synthetic procedure. Sherman originally proposed that the ordinates
and abscissas of unit hydrograph for similar basins might be assumed to be
proportional to the square roots respective drainage areas. Further details are
available in any textbook on applied hydrology.
1. Location of catchment area to be identified from Survey of India topo-sheet and measure
the catchment area (A)
2. Measure the length of the longest stream in Km. (L)
3. Length of the longest stream from a point opposite to C.G. of catchment to the point of
study in Km. (Lc)
4. Compute Equivalent Slope in m/Km. (Seq)
To determine equivalent slope, reader may look at following plot which displays longitudinal
profile and formula used for the purpose. We will use this formula a little later to calculate Seq.
With advances in information technology in recent years and also with the availability
of Digital Elevation Model (DEM), distillation of physiographic parameters is relatively faster and
accurate. Illustrated example in later part of this chapter demonstrates the application of GIS technique to
deduce these parameters. The DEM data are available for free at sites
http://srtm.csi.cgiar.org/SELECTION/inputCoord.asp
http://www.gdem.aster.ersdac.or.jp/search.jsp
http://glcf.umd.edu/data/landsat/
http://glcfapp.glcf.umd.edu:8080/esdi/index.jsp
Step-2 To construct 1-hour SUH
ILLUSTRATIVE EXAMPLE
Important Note
1. This example is based on hypothetical equations and is used to demonstrate the steps
required to design a synthetic UH. For real case studies, users are requested to refer to
Flood Estimation Report relevant to the area under study. Such reports are available
with CWC and concerned State Govt. departments.)
2. Readers ignorant of application of GIS software and Geo-HMS add-on package will
find it difficult to follow initial steps of this example.
The Survey of India released topo-sheets marked with contours is primary requisites to extract
basin physical parameters. Unquestionably, this process is tedious and fraught with possible
errors. Alternatively, Windows based GIS presentation Fig.1 software, such as Arc View 3.X or
similar packages can be used to extract these parameters through analysis of DEM. To showcase
strength of GIS based analysis of basin, two SRTM grids 55_7 and 55_8 are first merged followed
by extraction of a part from whole DEM, which is likely to cover outlet point and its contributing
area.
This relatively small sized patch of DEM was imported in Geo-HMS window (an extension
package that works on Arc View GIS 3.2a) for terrain and hydrological analysis. A series of
options on Geo-HMS supported menus lead users to successfully obtain a network of streams
and corresponding catchment areas. This process is termed as terrain processing.
Having reached a stage as shown in Fig.2, it is possible in the system to locate project by defining
outlet at pre-determined latitude and longitude. In Fig.2, hypothetical project location is
displayed by a point in red. A hydrologist is concerned about area shedding water at this outlet;
and therefore, only this area is abstracted at this stage for hydrological analysis subsequently.
Fig.3 displays the output of hydrological processing containing delineated watershed for project
location; the location of centre of gravity (CG) of the basin; longest flow path. These features of
this basin can be exported to HEC-HMS software for developing design flood hydrograph or any
other hydrological analysis. A set of information extracted for estimating SUH equations are as
below:
SUH parameters as given below are computed by using equations given in step 2 are as
following:
An SUH based on the estimated parameters in step -2 is shown below. The discharge ordinates
of this graph at 1 hr interval are multiplied by 1 hr and are summed up to ascertain whether it
agrees with principle of UH. Raw UH so arrived overestimates the runoff; and therefore its
falling limb ordinates are readjusted in a manner to represent basin's true UH.
Top of page
CHANGING UNIT HYDROGRAPH DURATIONS
The unit duration of the UH derived from various records may not be alike. In order to compare
and average them, it is necessary to convert all of them to the same unit duration.
Top of page
Three distinct unit hydrographs for Anandpur site on river Baitarani, as tabulated below,
have been developed by employing different techniques of UH derivation as highlighted in
preceding paragraphs. The figures in bold and italic mark the peak value of respective
columns. A cursory look at ordinates recorded under three methods reveals that the peaks,
time base, and time of occurrence of three unit hydrographs differs from one another. As a
matter of fact, if various storms are considered for development of unit graph for the same
catchment, a marked variation will be observed especially in the peak as well as the time of
occurrence of the peak. Therefore, it had better derive an average unit hydrograph for
practical use. If several unit hydrographs are averaged by averaging concurrent ordinates, it
is highly probable that the resulting average unit graph has a broader, and a quite possibly a
lower peak than any of the individual graphs.
The correct average unit hydrograph should be obtained by locating the average peak and
the average time of occurrence of the peak and sketching a menu unit hydrograph having an
area equal to 1mm of runoff and resembling the individual graph as much as possible.
However, the averaging of the unit hydrograph can't be resorted to all cases. It has been
observed that for practical purposes the shape of the unit hydrograph is hugely governed by
factors, such as amount of effective rainfall, rainfall distribution pattern, and the storm
movement etc
This aspect of UH is briefly demonstrated here with the help of a few diagrams. For more on
this subject, readers are encouraged to refer to any good book on hydrology. Adjacent figure
illustrates how the storm movement influences the shape of unit hydrograph. Yet another
picture exhibits how the concentration of localized rainfall activity over the basin can
significantly alter limbs and peak of UH. The third picture demonstrates the distinction
between impact of a concentrated and heavy effective rainfall and uniform rainfall of same
amount over the catchment.
In brief, it is not necessary that similar features will be reflected in all the storms. As a matter
of fact, the formation and distribution of the runoff is quite complex process in which large
numbers of factors are involved.
Hence for the operational use, the scheme of the unit hydrograph is to be laid down after
taking into account the primary influencing factors. It is not enough, and certainly not, to use
one un-changeable unit hydrograph for formulation of flood forecast. Different unit
hydrographs should be identified for the various conditions which have various influences
on formation and time distribution of the runoff. These unit hydrographs may then be
judiciously applied under different conditions.
Top of page
REFERENCES
1. Patra, K C, (2001), Hydrology & Water Resources Engineering, Narosa Publishing House
2. Ven Te Chow, David R Maidment, Larry W Mays, (International Edition 1988), Applied
Hydrology, McGraw-Hill Book Company
3. Raghunath, H M, (2006), Hydrology - Principles, Analysis, Design, New Age
International (P) Limited
4. Richard H McCuen, (1989), Hydrologic Analysis and Design, Prentice Hall, New Jersey
5. A multitude of e-learning materials available at https://www.meted.ucar.edu/
Top of page
CONTRIBUTORS
Anup K Srivastava,
Director, National Water Academy