The Recovery Plan Project Case - Risk Quantification Methods
The Recovery Plan Project Case - Risk Quantification Methods
Sujeeva S. Ranasinghe
Overview
Eskom’s dedicated Risk Management Committee (RMC) has analyzed the risks of power
interruptions due to a shortfall of supply and increasing electricity demand and have created a Recovery
As part of their risk analysis, the RMC employed Financial Risk Analysis, Quantitative and Qualitative
methods. In all methods, the RMC considered internal, external, organizational, and technical risks in
their analysis.
Per the PMBOK, Qualitative Risk Analysis is the process of assessing and ranking risks based on the
likelihood of occurrence, impact, and other qualitative attributes. Common qualitative scales might use
Low risks have a low probability of occurrence and low impact, often requiring minimal attention.
Medium risks have a moderate probability of occurrence and impact and can be addressed with
proactive monitoring and mitigation. High risks have both high probability of occurrence and a high
impact on the program; and once identified at any stage of the project, it must be monitored
Quantitative Risk is accomplished by using quantitative data and statistical analysis estimating the
probability of occurrence to assign numerical values to each risk factor and quantifying the impact. This
is accomplished by using quantitative data such as rainfall, predicted load forecasts, and peak load, and
estimating the probability of occurrence to evaluate each risk and quantify the impact.
3
Qualitative Analysis
Qualitative analysis was used to assign probability of occurrence and associated impacts to events
that will add risk meeting the power supply requirements of the Western Cape. The RMC utilized
lessons learned from previous, albeit less serious events as well as the proficiency and experience of the
Recovery Plan team. The qualitative analysis also took into consideration if Eskom, the City of Cape
First, the RMC created an assessment matrix and assigned the probability of these events
happening, rating them from one (1) representing that an adverse event will not occur to ten (10)
representing that an adverse event will definitely occur. Then, the RMC assigned the impact of each
adverse event. On one end of the spectrum, an impact of one (1) meant that the event is negligible and
on the other, an impact of ten (10) meant that the event would be catastrophic.
Priority was given to all risks that could impact the main project objectives, those being restoration
of the power supply or the reduction of electrical demand. Among the risks with both the highest
probability and impact was the dependency of standby plant and equipment. Therefore, Eskom can
concentrate their efforts to ensure that these plants and equipment be maintained at the highest level.
Eleven (11) of the twenty-three (23) risks identified were High impact having moderate or low
probability of occurrence; two (2) risks designated as Very High had a low probability of occurrence.
It is interesting that staff shortages and burn-out were qualified as High Probability but Moderate
Impact. Based on past experiences, Eskom may have assumed they can use less staff to maintain the
power supply. Another risk, the Potential commissioning delays in the recovery of Unit 1 was Low
Probability and High Impact, even though the case study indicated that based on past records, delays in
unit start-up following an outage are quite common. A such it could be argued that some risks that
should be both High Probability and High Impact have not been properly assessed.
4
The Risk Assessment process extensively reviewed past events to determine the risks of supplying
the Western Cape the required 4250 Mega Watts of daily power supply during the winter season.
Twenty-three (23) risks were identified and ranked qualitatively based on probability and impact as
Quantitative Risk analysis was performed in tandem and took in to account the load forecast, power
supply output and predicted rainfall. Based on this analysis, the ESKOM Recovery Team was able to
compile various risk scenarios. These scenarios were then used to determine the expected amount of
load shedding or controlled blackouts. Finally, the Financial Risk analysis revealed that the economic
impact of the power outages was more than 500 million Rand (approximately $68 Million at the time of
the analysis).
The risk analysis identified some key lessons learnt including acknowledging that the Western Cape
is vulnerable to power supply issues and that the mitigation plan should always be in place. Further, it
was recognized that streamlining the communication process with the public and government was
critical.
The risk analysis identified certain shortcomings, primarily a weak relationship between Eskom and
the City of Cape Town. Also identified was the lack of an integrated Recovery Plan between the different
stakeholders as well as risks not being categorized per Eskom standards which lead to an ad hoc
mitigation plan. Additional shortcomings from the quantification methods use were identified. For
example, the analysis was only as good as the data that was used.
5
References
Jordan, A. (2013). Risk Management for Project Driven Organizations: A Strategic Guide to Portfolio,
Riaan van Wyk, Paul Bowen, Akintola Akintoye, 2008. Project risk management practice: The case of a
South African utility company. International Journal of Project Management, Volume 26, Issue 2
Wilson, R. (2015). Mastering Risk and Procurement in Project Management: A Guide to Planning,