DCdesign
DCdesign
presented in Build the Best Data Center Facility for Your Business, by Douglas Alger.
The template is written for a company project manager who needs to present Data Center
design guidelines to a contracted architectural firm. It is assumed that the architectural
firm will, in turn, create construction documents to be reviewed by the appropriate
municipal planning department and ultimately followed by the project’s contractors—
electricians, mechanical contractors, cabling vendors, and so on.
Notes to the designer introduce each section of the document. Notes are also placed at
key paragraphs to clarify requirements or explain what information must be entered.
Variables in this document—data points you must enter—are highlighted in teal. Cable
counts and other quantities have been suggested where appropriate. In other instances,
variables are represented by a description (for example., Your Company) or symbol (for
example, #).
Remove all italicized notes and color-coding after you fill out the template.
Company Logo
Name
Project Manager
Your Company
(Address Information)
(Address Information)
(Phone number)
(E-mail)
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
TABLE OF CONTENTS
1.1 Introduction
1.2 Standards
1.3 Client Approval
1.4 Acronyms and Abbreviations
1.5 Cleanup Requirements
1.6 Submittal Requirements
1.7 Monitoring
1.8 Demonstration and Personnel Instruction
4.1 Overview
4.2 Monitoring Lights
4.3 Testing
2
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: The sample drawings listed here are available in PDF format on the Cisco Press website.
To best understand this template, download and review those drawings at the same time
as this text document.
SUPPLEMENTAL DRAWINGS
3
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 1 summarizes the scope of the Data Center project and outlines basic
expectations of the project’s contractors. These requirements include the need for
contractors to clean up after their work and provide certain documentation at the start
and end of the project.
1.1 Introduction
1.11 Your Company is building a new Data Center at Address. It will be # square feet (#
square meters) in size and will be a robust, modular, flexible, and productive environment
that hosts Your Company’s most critical applications and intellectual property.
1.12 The drawings and written instructions in this Design Guidelines document are intended to
assist in the creation of Data Center construction documents by contracted architectural
firm.
1.13 All Data Center-related installations—including but not limited to room infrastructure,
in-room electrical, standby power, cooling, data cabling, monitoring lights, and fire
suppression systems—must be completed at least (2) weeks prior to cutover of the site.
This includes all testing and provision of documentation by the respective vendors for
each section of this project.
Designer: The time period listed in 1.13, suggested at 2 weeks, is to allow for supplemental work to
be performed in the Data Center after principal construction is complete and before the
server environment is brought online. Such work can include reviewing structured
cabling test results, stocking the Data Center with supplies, and installing networking
devices. Two weeks is usually appropriate. Increase this time period if the Data Center is
large—i.e., more than 10,000 square feet or 1000 square meters—or if you want to put
more time in the construction schedule to allow for missed deadlines.
1.14 Changes to these Design Guidelines must be approved in writing by the original issuer to
be valid.
1.2 Standards
1.21 Only new equipment and materials are to be used in this Data Center project. All items
will be from reputable and qualified companies and meet prevailing industry standards.
All equipment and individual connections will be verified by the Project Manager before
completion.
1.22 Additional standards for individual components are specified within the corresponding
sections of this document. (i.e., Section 3—In-Room Electrical System; Section 7—Data
Cabling System).
1.23 Where a discrepancy between this document and local building codes or building control
standards occurs, the more stringent will apply.
4
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
1.31 Your Company reserves the right to inspect and unilaterally reject installations that do
not conform to its standards of workmanship, neatness, and cleanliness. Materials used in
this project that do not conform to this Design Guidelines document or receive written
approval for substitution will not be compensated for.
1.41 The following acronyms and abbreviations are used in this document:
1.51 Debris generated during installation and testing of the room’s infrastructure systems—
power, cooling, data cabling, emergency lights, and fire suppression—must be removed
by the corresponding contractor upon conclusion of its work.
1.52 At the conclusion of all construction, the Data Center’s raised floor surface and subfloor
plenum will be professionally cleaned so that all constructed-related dust and debris are
removed.
1.61 Prior to work beginning in the Data Center, the following are to be submitted to the
Project Manager:
Designer: The Corning and Panduit certifications called for in the prior list are excellent training
programs that cover the proper handling, termination, and testing of fiber and copper
cabling, respectively. Requiring these certifications helps ensure that cabling contractor
employees possess adequate skills and knowledge to install your structured cabling.
The value of the submittals requested in Section 1.62 is explained in Chapter 14,
“Mapping, Monitoring, and Metrics.”
5
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
1.62 At the conclusion of the project the following are to be submitted to the Project Manager:
1.7 Monitoring
1.71 Electrical, standby power, cooling, and fire suppression systems will be connected to a
building automation system. This system will be compatible with the monitoring system
using in Your Company’s Operations Command Center at Address.
1.81 The corresponding vendors will provide the Project Manager with a videotaped
demonstration showing the correct operation of the Data Center’s standby electrical,
emergency power off, cooling, and fire suppression systems. Included on the video(s)
will be a complete review of the posted sequence of operation for each control system.
6
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 2 specifies many of the physical features of the Data Center— its walls, physical
access controls, and flooring. The Data Center is assumed to possess a raised floor—
remove these instructions if your room will not. Directions for bolting networking
cabinets or racks to the subfloor are included in this section, too, as are specifications for
the room’s telephones.
Note that a table lamp icon and a list of figures appear at the top of Section 2. The figure
numbers refer to the drawings at the end of this Design Guidelines package that are
relevant to this section.
2.11 The Data Center will have no building exterior doors or exterior windows. If external
windows must be present, they will be insulated, furred out, enclosed with drywall board,
and then covered with whatever external decorations adorn other building windows, such
as vertical blinds.
2.12 All Data Center perimeter walls need to be full height, hard wall construction. The room
is to have no windows or transparent walls to an interior corridor.
2.13 All entrances and exits into the Data Center will be covered by digitally recorded closed-
circuit television color cameras, monitored by Security.
2.14 Employee entrances will be controlled by a card access control system and equipped with
local door alarms that will sound if the door is propped open for an extended period of
time. Emergency exit doors are to be alarmed and of solid metal.
2.15 There should be no access through the Data Center to another room not related to the
Data Center, such as offices or an electrical room.
Designer: The clearances in Section 2.2 call for an 18-inch (46-centimeter) raised floor and are
assumed to accommodate the height of your Data Center server cabinets and width of a
pallet of supplies. Adjust these numbers as needed to reflect the items used in your server
environment.
2.21 An unobstructed pathway must exist connecting the Data Center, build room, storage
room, and the building exterior. All entrances, corridors, doorways, elevators, and other
openings along this path must provide a minimum clearance of 8 feet (2.4 meters) high
and 4 feet (1.2 meters) wide.
7
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
2.22 There must be at least 10.5 feet (3.2 meters) from the subfloor to the bottom of the false
ceiling. This space allows for a raised floor of 18 inches (46 centimeters), 7.5 feet (2.3
meters) tall server cabinets, and an additional 18 inches (46 centimeters) of clearance
from the top of those cabinets to the false ceiling.
Designer: The following section on telephones assumes that VoIP (Voice over Internet Protocol)
technology is deployed in the Data Center. If not, remove paragraph 2.32.
2.3 Telephones
2.31 Copper: 4 pair UL certified 350 MHz, Cat. 6 cables will be pulled from the
telecommunications room to (#) wall phone locations within the Data Center. Cabling
will terminate into wall plates mounted 44 inches (112 centimeters) above the surface of
the floor. Phones will be installed with cords 25 feet (8 meters) in length.
2.32 (#) of the phones will be connected to the Voice over Internet Protocol (VoIP) phone
system. (1) phone must be an analog line independent of the Data Center network
enabling it to function in the event of a network outage. The analog line will be near the
Data Center entrance, close enough to the Emergency Power Off and fire suppression
system buttons so that a person can manipulate these controls and use the phone
simultaneously.
Designer: Tables are provided in this template wherever specific infrastructure components are
called for in the text. Default descriptions are filled in and additional columns are
provided to list part numbers and quantities.
What country your Data Center is constructed in will determine whether you use plenum-
rated or low smoke zero halogen structured cabling.
2.41 The cabling contractor will order and install all networking cabinets (and their power
strips) in the Data Center. Server cabinets will be provided after the Data Center comes
on line by Your Company’s Data Center support staff.
2.42 Networking cabinets will be installed in two sequences—(#) cabinets in the Data Center’s
main Network Row and (1) cabinet as a Network Substation at the end of each Server
Row. Each of these networking cabinets will be aligned onto the edges of the floor tiles
directly below it and secured to the cement subfloor by (4) bolts, one at each corner.
2.43 A wire management system will be mounted on the front of all Network Row and
Network Substation cabinets. Horizontal wire management will be 2 rack units high—3.5
inches (8.9 centimeters). Vertical wire management will be 8 inches (20 centimeters) or
12 inches (30 centimeters) wide in the Network Row and 6 inches (15 centimeters) or 8
inches (20 centimeters) wide in the Network Substations. Cable troughs will also be
installed above the Network Row as needed to route cables.
8
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: The size and amount of your wire management is driven by how many patch cords must
be accommodated, particularly copper cabling. (Fiber patch cords are thinner than
copper and therefore have less effect on wire management.) If your Data Center will
have only 12 ports of copper cabling to each cabinet location, 6- and 8-inch (15- and 20-
centimeter) vertical wire managers are probably fine. If your Data Center has 48 ports to
each cabinet location, consider 8- and 12-inch (20- and 30-centimeter) vertical wire
management.
The size of the horizontal wire managers can generally be matched to whatever copper
patch panels you use. For example, if the patch panels in your network cabinets house 48
copper ports in 3.5 inches (8.9 centimeters) of space, use 3.5-inch (8.9-centimeter) wire
managers to route cables so they can plug in to those jacks.
2.51 The Data Center will have a raised floor with a minimum raised height of 18 inches (46
centimeters), consisting of 2 × 2 feet (61 × 61 centimeters) floor tiles. Vertical stanchions
holding the floor up will be anchored to the subfloor with glue and metal anchors.
2.52 There will be (1) entrance ramp, with a 1-in-12 incline—a 1-inch increase in height for
every 12 inches in length—or conforming to local regulations. Using the 1-in-12 incline
dimensions, the ramp should be 18 feet (549 centimeters) long and feature landings that
are 6 feet (183 centimeters) long at both the top and bottom. [6 feet bottom landing + 18
feet ramp + 6 feet top landing = 30 feet/183 centimeters bottom landing + 549
centimeters ramp + 183 centimeters top landing = 915 centimeters]. The ramp and
landings should be 6 feet (183 centimeters) wide.
2.53 A handrail will be installed along the ramp per local code. The ramp will be constructed
of the same material as the raised floor. It will be covered with slip-resistant treads to
enable safe access as well as easy transport of equipment premounted in server cabinets.
The ramp must meet the same weight-loading specifications of the raised floor.
9
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
General Purpose Slip-Resistant Tread
4-inch (10-centimeter) strips
2.54 The Data Center’s raised floor, including ramps, and its subfloor must be sufficient to
support fully loaded server cabinets weighing at least 2000 pounds (907.2 kilograms).
2.55 The raised floor will consist of floor tiles that are 2 × 2 feet. (60 × 60 centimeters). The
types and number required for this project are:
Cut/Notched
Behind server
Cutout dimensions: cabinets and below (#)
8 × 8 inches network cabinets
(20 × 20 centimeters)
In front of all
Perforated (#)
cabinet locations
10
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
All other
Blank (#)
floor locations
2.56 Perforated tiles will have manual volume dampers. Openings will be lined with molded
inserts.
2.57 (#) tile pullers will be provided by the floor tile contractor. Placards for holding tile
pullers will be wall mounted by the contractor within the Data Center. Placards will be
placed about 5 feet (1.5 meters) above the raised floor, near the inside of each entrance.
2.58 Replaceable tacky mats will be installed atop the raised floor, immediately inside each
Data Center entrance.
2.61 The subfloor cement pad will be coated with a static dissipative and nonconductive
porous surface sealant designed for high-technology environments.
11
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 3 covers electrical infrastructure within the Data Center. (Standby electrical
infrastructure is outlined in Section 4.) As written, the section calls for power to run by
way of individual electrical conduits from Power Distribution Units to remote circuit
panel boards and then to individual cabinet locations. Adjust this language as needed for
the electrical infrastructure you want installed in your Data Center.
3.11 Power will be provided from Power Distribution Units (PDUs) and carried to electrical
panels installed at one end of each row. (2) panels will be located adjacent to each
Network Substation and at one end of the Network Row, positioned back-to-back. Each
panel will be fed by a different PDU.
3.12 Power will be distributed from panels by flexible electrical conduits. Provide (2) such
whips to each cabinet location, one from each electrical panel. Each whip will be the
required distance plus 2 feet (61 centimeters).
Designer: The configuration in paragraphs 3.11 and 3.12 provides power from two separate
sources to each Data Center cabinet location, for a degree of redundancy.
3.13 Individual whips will be secured by the electrical contractor to specified support posts in
the raised floor framework using hook and loop plenum cable ties.
Designer: Conduits may alternately be routed through a cable tray system. If you wish to use cable
tray, alter the language in 3.13 accordingly and include an illustrative drawing among
the figures.
3.14 Breakers in the PDUs and electrical panels are to be bolt-in type. Snap-in breakers are not
allowed.
3.21 The electrical contractor will provide all necessary tools and materials not specified (tie
wraps, screws, consumables, hardware, and so on) and equipment (ladders, lifts, storage
containers, and so on) necessary to provide a complete and operating system.
3.22 There will be (#) circuits run to each cabinet location via (#) flexible whips.
12
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Sample power configurations are listed below. Choose the correct type and number of
receptacles for this project. Common U.S. receptacles are listed first, followed by
common European receptacles.
3.3 Grounding
3.31 A signal reference grid will be installed according to IEEE 1100-1999—Grid of Copper
Wire. The high frequency signal reference structure will consist of a 2 × 2 feet (60 × 60
centimeters) bare copper, round wire grid.
3.32 The raised floor will be connected to the grounding grid at each pedestal as well as all
other under-floor substructures and each PDU and air handler. Each network cabinet will
be grounded to the grid with (2) grounding straps or bonding conductor.
3.33 All Network Row and Network Substation cabinets will be grounded to the building
ground. Electrical contractor will install ground bar and ground to the building ground.
3.41 Emergency Power Off (EPO) controls will be located inside any room entrance. The EPO
system will shut down all PDUs, air handlers, and convenience outlets at the electrical
source that is outside the Data Center.
3.42 EPO controls will be a switch-knob. The controls will be covered with a transparent
plastic shell to inhibit accidental activation, and equipped with an audible alarm that will
sound, once the shell is removed.
3.51 Circuits within each electrical panel will be numbered and labeled to match the installed
electrical outlets. Panel schedules will include outlet type and cabinet location.
3.52 Receptacles will be labeled with circuit information indicating its location in the source
panel.
3.53 EPO buttons will be labeled “Emergency Power Off.” Signage explaining basic EPO
function will be installed immediately above the button. A map indicating the EPO’s
zone of effect will be posted above the button at eye level.
3.6 Testing
3.61 The following will be performed upon the Data Center electrical system:
13
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
1) Load Bank test—A field load bank will be conducted on the Uninterruptible
Power Source (UPS) batteries and standby generator.
5) A test of the Emergency Power Off system, confirming that all PDUs, air
handlers, and convenience units shut down correctly.
3.71 (#) power outlets will be placed on each Data Center wall, 18 inches (46 centimeters)
above the floor’s top surface. These outlets will not be connected to the room’s backup
power system, but will be connected to the EPO system.
3.81 All room lights are to be connected to the standby power system. Some of these lights
will be equipped with battery packs so they can continue functioning until the standby
system engages, or in the event that the standby system does not function. These battery-
equipped lights should be plentiful enough to enable safe departure of the room or
shutdown of servers.
3.82 Life safety components, (exit lights per code, security, and so on) are also to have battery
packs installed per codes.
14
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 4 addresses the standby electrical infrastructure for your Data Center—typically
a battery system UPS and a generator. The section also provides direction for the
installation of beacon lights within the Data Center to monitor the status of this standby
infrastructure.
4.1 Overview
4.11 The Data Center standby power system will be designed with an Uninterruptible Power
Source (UPS), placed in a dedicated location within the site’s building, and a standby
generator, located outside of the building.
4.12 The system will be configured such that, if utility power to the room fails, the load will
be supported by the UPS and transferred to the standby generator.
4.13 The UPS and generator will be sized for N/N + # coverage of the Data Center. The UPS
and standby generator will each have a capacity no less than ten percent greater than the
maximum possible electrical load in the Data Center.
4.14 When the Data Center is at full load, the UPS must run for a minimum of twenty minutes
and the generator must run for a minimum of eight hours without refueling.
4.21 (#) beacon lights will be installed in key locations inside and outside of the Data Center
to monitor the room’s standby power system. The lights will be wired in to the standby
power system such that they will operate when commercial power to the building is
interrupted.
4.22 Lights will be mounted so their domes are 12 inches (30 centimeters) below the Data
Center ceiling. A red-domed light will indicate when the UPS is supplying the room with
power. A blue-domed light will indicate when the generator is running and supporting the
room with power.
4.3 Testing
15
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
4.31 Performance of the monitoring lights will be verified during the full system test
conducted upon the Data Center In-Room Electrical System. See Section 3.6.
4.32 Monitoring lights must activate immediately upon each start of the UPS or generator. The
red light must activate when UPS begins actively supporting the room’s power load; the
blue light must activate when the generator is running. The red light must shut off when
the UPS is no longer supporting the load. The blue light must shut off when the generator
is no longer providing power.
16
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 5 provides instruction for Data Center cooling infrastructure. The wording is
intended to accommodate a server environment with or without hot and cold aisles.
(Information about hot and cold aisles is provided in Chapter 8, “Keeping It Cool.”)
Be aware that the Data Center depicted in this template’s sample figures does not have
hot and cold aisles. Server rows would need to alternate directions. The infrastructure
feeding those rows would additionally need to be routed so as to always be on the back
side of each server row.
5.11 The Data Center will be designed with N/N+# cooling coverage, including (#) redundant
external chillers as well as (#) spare air handlers within the room. The cooling
infrastructure must be capable of providing # watts per square foot (# watts per square
meter) of cooling.
5.12 The Data Center will be maintained at 68 to 72 degrees Fahrenheit (20 to 23 degrees
Celsius) 24 hours a day, 7 days a week. The room will have a constant humidity level of
50 percent, plus or minus 10 percent (40 percent to 60 percent).
5.13 The area below the Data Center’s raised floor will serve as the room’s plenum.
5.14 Ducting will be installed in the ceiling immediately behind each server row to help draw
heated air back to the room’s air handlers. This configuration, in conjunction with placing
perforated floor tiles in front of each server row, helps to effectively circulate cool air
through and around Data Center servers and networking devices.
5.15 Air handlers will be positioned to provide the most effective cooling to the server rows.
Install the units close to Data Center walls so as to conserve floor space. Also, provide
sufficient buffer areas around each air handler to enable future maintenance access.
5.16 Place only blank floor tiles immediately in front each air handler, so as to avoid short-
cycling.
17
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 6 provides specifications for the Data Center’s smoke detection and fire
suppression infrastructure. Various types of suppressant are discussed in Chapter 8,
“Keeping It Cool.”
6.11 The Data Center will be equipped with a continuous air-sampling system that will
provide early warning of a fire. System settings must be adjustable to different levels of
sensitivity.
6.21 The fire suppression system will provide for total flooding of the Data Center with a
gaseous fire suppression agent that is clean, dry, noncorrosive, nondamaging, and
nondeteriorating. The choice of substance, traditionally Heptafluorpropane—FM-200 or
HFC-227—or Inergen, will be determined and installed in accordance with local
regulations.
6.22 The fire suppression system will also provide for particle and air sampling to initiate
stages of alarms in preparation for release of the agent.
6.23 Fire suppression system cylinders will preferably be located outside the Data Center in a
controlled room. If cylinders are placed in the Data Center, the Project Manager must be
contacted prior to installation to discuss their location.
6.24 A sprinkler system will be installed in the Data Center, per local building codes/building
control standards and fire codes. This will be a dry-pipe system.
6.31 Signage explaining fire suppression system functions will be installed adjacent to system
controls and alarm components. The following two images are examples of appropriate
signage.
18
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
6.41 Fire extinguishers will be installed within the Data Center, wall-mounted in multiple
locations around the room. These handheld extinguishers will be of the appropriate type
for a room containing electronic equipment and must meet local building codes/building
control standards and fire codes.
19
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 7 details the Data Center’s structured cabling system. This template assumes the
use of a distributed cabling design, with a Network Substation at one end of each server
row. The principles behind this design are explained in Chapter 7, “Designing a Scalable
Network Infrastructure.”
LC fiber connectors are specified throughout this section, although others may be used
without any detriment to the design.
7.11 This Data Center will consist of (#) rows—(1) Network Row and (#) Server Rows.
7.12 Network connections will be provided via copper and fiber structured cabling. This
cabling will run in bundles from the Network Row (NR) to a Network Substation (NS) at
one end of each Server Row and then from each Network Substation to all server cabinet
locations (SC) in that row. Structured cabling will also extend from the Network Row to
an external Network Room.
7.13 Cabling between the Network Row and Network Room will be run over the ceiling in
cable trays, using waterfall supports when entering or exiting cabinets. All other Data
Center cabling will be run below the raised floor.
Designer: Specify the type of cabling you want installed in your Data Center.
7.14 All structured cabling for this project will be plenum/low smoke zero halogen rated.
Designer: The two line drawings that follow illustrate a Data Center with a distributed cabling
design—one with a Storage Area Network (SAN) and the other without. Choose
whichever is appropriate for your Data Center and fill in desired quantities. (Each
drawing has been inserted within a document table. Delete the table row to remove the
image. To modify the line drawing, use the drawing toolbar.)
20
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
NS SC SC SC
Network
Room NR
NS SC SC SC
NS SC SC SC
NR
NS SC SC SC
(#) 50µ MM
Designer: Dotted lines in the second line drawing highlight SAN connections. This is merely for
clarity—there is no physical difference between the structured cabling run for SAN and
standard network connections.
7.15 The scope of work for this project includes all Data Center-related:
21
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: For the convenience of your cabling contractor, you may want to provide the specific
cabinet locations where structured cabling should terminate. These variable are
represented by XXYY. More specific details, down to what ports terminate in which
panels, are shown in accompanying Figures 10-16.
If you want to color code your Data Center, specify colors for all ports and housings that
are installed. The template’s default language calls for black jacks for connections to
network cabinets, white jacks for connections to server cabinet locations, and violet jacks
for connections that exit the Data Center. No colors are specified for the housings.
7.21 Copper: (#) 4-pair, UL certified, 350 MHz Cat. 6 cables will be pulled from Network
Row cabinet XXYY to Network Room cabinet XXYY. Cat. 6 cable will be terminated at
both ends in black patch panels containing violet Cat. 6 jacks.
7.22 Fiber: (#) 8.3µ SM strands and (#) 50µ MM strands will be run from Network Row
cabinet XXYY to Network Room cabinet XXYY, terminating in LC connectors on both
ends.
22
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.31 Copper: (#) 4-pair, UL certified, 350 MHz, Cat. 6-rated cables will be pulled from
Network Row cabinet XXYY to each Network Substation—cabinets XXYY, XXYY,
XXYY, XXYY, XXYY, and XXYY.
7.32 Cat. 6 cable will be terminated at both ends in RJ45 patch panels with black Cat. 6 jacks.
7.33 Fiber: (#) 8.3µ SM strands will be pulled from Network Row cabinet XXYY to each
Network Substation—cabinets XXYY, XXYY, XXYY, XXYY, XXYY, and XXYY.
Cabling will terminate in fiber housings with LC connectors.
7.34 Fiber: (#) 50µ ΜΜ strands will be pulled from Network Row cabinet XXYY to each
Network Substation—cabinets XXYY, XXYY, XXYY, XXYY, XXYY, and XXYY.
Cabling will terminate in fiber housings with LC connectors.
23
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: Section 7.4 calls for structured cabling to terminate in multimedia boxes below server
cabinet locations. If you prefer to terminate into patch panels directly into server
cabinets, adjust the text and alter the component in the list of materials.
7.41 Structured cabling will terminate in patching fields within the Network Substations and in
multimedia boxes directly below each server cabinet location. Cables will be routed in
separate bundles and carefully secured to specific support posts in the raised floor
framework, using hook and loop cable ties. Bundles will each measure distance plus 36
inches/1 m. and will not contain more than (12) Cat. 6 cables.
7.42 Copper: (#) 4-pair UL certified 350 MHz, Cat. 6 plenum-rated cables will be pulled from
each Network Substation to the copper-designated multimedia box below each server
cabinet Location. White Cat. 6 jacks are to be used.
7.43 Fiber: (#) strands of 50µ MM fiber cables will be pulled from each Network Substation to
the fiber-designated multimedia box below each server cabinet location.
24
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: If your Data Center uses a Storage Area Network (SAN), you may or may not need
additional fiber structured cabling run to SAN disk frames. The cabling is generally
needed when disk frames are placed in a server cabinet location, but unnecessary when
the frames are placed in the Network Row and patch cords are used. This subsection is
provided in the event that the additional cabling is required.
7.51 (#) 50µ MM strands will be run from Network Row cabinet XXYY to SAN disk frames
at server cabinet locations XXYY and XXYY, terminating in LC connectors on both
ends.
25
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.6 Standards
26
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
• TIA/EIA-606-A, Administration Standard for Commercial Telecommunications
Infrastructure (May 2002)
• J-STD-607-A, Commercial Building Grounding (Earthing) and Bonding Requirements
for Telecommunications (October 2002)
• National, State and Local building and fire (NFPA) codes
• OSHA Standards
7.62 All backbone fiber cable—from the Network Room to Network Row, Network Row to
Network Substations, and Network Substations to server cabinet locations—will have a
“flip” in the fiber positioning for each connector.
7.71 Station Data Cable and Backbone Data Cable: (4) unshielded twisted pairs of 24 AWG
solid copper conductors. Individually insulated conductors under a common sheath.
Cable must be plenum/low smoke zero halogen.
7.81 Fiber-optic cable used within the Data Center must conform to the following.
Specifications apply to both MM and SM fiber unless specified otherwise.
1) Manufacturer’s name
27
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
2) Fiber size (50µ MM)—50/125
3) Fiber size (SM)—8.3/125
4) Sequential length markings
50µ MM
Max. attenuation: 3.5 dB/km @ 850 nm and 1.5 dB/km @ 1300 nm
Typical attenuation: 3.0 dB/km @ 850 nm and 1.0 dB/km @ 1300 nm
Min. bandwidth: 500 MHz-km @ 850 nm and 500 MHz-km @ 1300 nm
SM
Max. attenuation: 1.0 dB/km @ 1310 nm and .75 dB/km @ 1550 nm
Typical attenuation: .5 dB/km @ 1310 nm and .4 dB/km @ 1550 nm
7.91 The cabling vendor will install all cabling and devices as shown on appended drawings.
Work will be done by qualified personnel in a neat, high quality manner and conform to
the most stringent of applicable local, state, and national building codes/building control
standards.
7.92 Cables will be placed with sufficient bending radius so as not to kink, shear, or damage
jackets, binders, or cables, including where cables are coiled for future use or slack.
Bending will not exceed manufacturers’ specified bend radii. Hook and loop tie wraps
will not be pulled so tight as to kink or crimp cable jackets. When left unattended during
installation, cabling will be secured and protected so as to avoid damage.
7.93 Contractors will ensure that floor and wall penetrations are returned to their original fire
stop rating as required by applicable codes. Sleeves and conduits will be fire stopped to a
one-hour fire rating.
7.94 The cabling vendor will individually and properly ground cabinets and other contractor-
supplied hardware to Cisco-supplied building grounds. Daisy chaining of equipment
ground is not permitted. Grounding will conform to EIA/TIA 607 and NEC articles 250
and 800. NEC Article 800-40 requires minimum #6 AWG or better wire be used for
grounding to main building ground.
7.95 Cables will contact only dedicated and properly protected cable accesses and support
mechanisms. Cables will maintain proper distances from power and lighting branch
circuit conduits and electromagnetic energy sources, including a 5 inches/13 centimeters
separation from fluorescent fixtures (per recommended good practices within ANSI-TIA-
EIA 569 Section 10).
7.96 Ceiling grid support wires will not be used for cable hangers. Installers will observe
applicable requirements and recommended good practices contained within ANSI-TIA-
EIA 568A—Telecommunications Standards and Installation Practices For Unshielded
Twisted Pair Cabling.
28
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.97 Cabling will be organized and identified so as to facilitate locating and handling
individual sheaths for maintenance.
7.98 Each cable bundle will be neatly tied without overcinching or overstressing, using hook
and loop tie wraps. Copper bundles are not to exceed (12) Cat. 6 cables per bundle.
7.10 Labeling
7.101 Cable runs will be labeled <from>/<to> where <from> is the origination cabinet and <to>
is the destination cabinet ID (i.e., Row 1 cabinet A = 1A). For example, cabling that runs
from the Network Substation at the end of row one to an adjacent cabinet will be labeled
1A/1B.
7.102 Labels will be placed upon the copper patch panels and fiber housings within the
Network Row and Network Substations.
7.103 Multimedia boxes will be labeled on their top surface, with the corresponding server
cabinet location and what cables are terminating within them.
7.104 Copper ports within the multimedia boxes will be labeled sequentially, 1-12. Each pair of
fiber strands terminating within multimedia boxes will also be labeled 1-12.
7.111 Test results must be permanently recorded and presented in both hard copy and
computer-readable format to the Project Manager for review. Any installation failing to
meet the above standards will be removed and replaced at no cost to Cisco with an
installation that proves through testing to meet the standards. The installation will not be
accepted until all terminations meet the appropriate standards.
7.112 For all installed Cat. 6 links, the following parameters will be tested as defined by
Section 11.2.4 of TIA/EIA-568-B.1.
1) Wire Map
2) Length
3) Insertion Loss (Attenuation)
4) Pair-to-pair Near-end Cross talk (NEXT)
5) Power Sum Near-end Cross talk (PSNEXT)
6) Pair-to-pair Equal-level Far-end Cross talk (ELFEXT)
7) Power Sum Equal-level Far-End Cross talk (PSELFEXT)
8) Return Loss
9) Propagation Delay
10) Delay Skew
7.113 All testing will be performed on the completely installed system. Any disturbance of a
termination after testing will invalidate the certification of that link and require retesting.
7.114 Copper test equipment will be capable of performing permanent link testing, whereby the
test leads are not part of the measured system. The type of test performed will be
permanent link testing, not basic link testing or channel testing.
29
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.115 When testing, the nominal velocity of propagation (NVP) must be set for the type of
cable being tested per the manufacturer’s instructions.
7.121 For each of the parameters listed in items 1 and 2 above, the values measured for each
permanent link will be within the limits defined in Section 11.2.4 of TIA/EIA-568-B.1.
For items 3 through 10, the TIA/EIA values listed for Cat. 6 will apply.
7.131 Test results must be permanently recorded and presented in both hard copy and
computer-readable format to the Project Manager for review. Any installation failing to
meet the above standards will be removed and replaced at no cost to Your Company with
an installation that proves through testing to meet the standards. The installation will not
be accepted until all pairs meet the appropriate standards.
1) Using an optical power meter, measure end-to-end attenuation for all installed
cables, including all splices, the terminated fiber itself, all connectors, and patch
panels. Total loss will be measured and reported for each cable at the appropriate
operating wavelengths. MM—850 and 1300 nm; SM—1310 and 1550 nm.
30
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
pair are not to exceed .75 dB. Losses through any fusion splice, if required, will
not exceed .05 dB.
3) Per above, each fiber link will have a maximum allowable loss budget, which can
be determined through completion of a loss budget table. The contractor is
required to fill out a table, as below, and submit prior to testing.
7.133 Losses for all fiber runs may not exceed 2.00 dB. All testing will be performed on the
completely installed system. Any disturbance of a termination after testing will invalidate
certification of that link and require retesting.
7.134 Fiber test equipment must meet or exceed TIA/EIA-526-14A Section 3 requirements. For
test jumpers, only factory produced cable assemblies manufactured by Corning Cable
Systems will be used.
1) If a single light source and a single power meter are used and if the equipment
has only one fiber transceiver (i.e., ST or SC), the contractor will follow the
procedure in the latest revision (at this writing, Revision 3, dated September
2000) of Corning Cable Systems Applications Engineering Note (AEN) 62.
2) If multiple light sources and multiple power meters are used but each has only
one fiber transceiver (i.e., ST or SC), the contractor will follow the procedure in
the latest revision (at this writing, Revision 3, dated September 2000) of Corning
Cable Systems AEN 63.
31
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.136 The reference must be reestablished whenever any of the following conditions apply:
7.137 Record all optical power measurements to the nearest tenth of a unit of measure (to one
significant digit in the decimal place, i.e., -14.3 dB) and report results in this format:
Panel A Panel B
PORT # Fiber # 850nm 1300nm 850nm 1300nm
1
1
2
3
2
4
5
3
6
Panel A Panel B
PORT # Fiber # 1310nm 1500nm 1310nm 1500nm
1
1
2
3
2
4
5
3
6
7.138 The contractor is required to provide documentation of their copper and fiber testing
procedures, including referencing procedures for fiber optic testing, prior to testing. This
document must list equipment to be used (manufacturer and model number) and the date
when it was last calibrated.
7.139 All test equipment used will have been factory calibrated (or by an approved calibration
service provider) within the past two years.
32
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
7.14 Certification Requirements
7.141 The contractor’s technicians installing the data cabling are required to have completed
certification classes to install and test the copper and fiber systems specified in this
document. Contractors are required to provide certificates of the technicians working on
the project, showing completion of Corning’s EWP training and Panduit’s Integrity
Authorized Installer training.
33
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Designer: The drawings that follow are sample details useful for illustrating a Data Center design.
Figure 1—Cabinet Location Plan—This depicts a Data Center’s overall layout. The drawing is useful for
showing spacing and orientation of server rows and major infrastructure.
Figure 2—Floor Tile Location Plan—The raised floor grid, including floor tile cutout dimensions and
the placement of perforated tiles.
Figure 3—Electrical Location Plan—The types and locations of all electrical infrastructure within the
Data Center. Five examples of electrical receptacles are listed in the symbol key.
Figure 4—Data Routing Diagram—Paths for structured cabling. This illustration not only conveys the
distributed cabling hierarchy concept, but can also guide vendors so that cabling doesn’t criss-cross and
risk tangling.
Figure 5—Under-Floor Power and Cable Detail—This detail shows the placement of infrastructure
under each server row, including routing data cabling and electrical conduits along separate but parallel
paths.
Figure 6—Power and Data Cable Detail—Similar to FIG. 5, with a top-down viewpoint.
Figure 7—Under-Floor Labeling Details—Labeling examples for electrical receptacles and multimedia
boxes where structured cabling terminates under the raised floor. This illustration helps ensure that the
cabling vendor labels this infrastructure correctly and consistently.
Figure 9—Network Row Elevation—This shows where various cabling media, network devices, and wire
management are to be placed in the Data Center Network Row.
Figure 10—DC Network Row to Outside Network Room Connection Detail—Explanation of labeling
and representations of specific components.
Figure 11—Network Row Fiber Detail—Sample labeling and illustration of specific components within
the Network Row’s fiber housings.
Figure 12—Network Row Copper Detail—Sample labeling and illustration of specific components within
the Network Row’s copper patch fields.
Figure 13—Network Substations Detail—A front-view of a network substation, showing the relative
locations of infrastructure, wire management, and networking devices.
Figure 14—Network Substation Fiber Detail—This detail shows specifically where to terminate fiber
components within a network substation. Part numbers and sample labeling are shown.
Figure 15—Network Substation To Network Row Detail—An illustration of the connections between the
key networking locations in the Data Center.
34
Company Logo Data Center Design Guidelines City, State, Country
_______________________________________________________________________________________________________
Figure 16—Network Substation Copper Detail—This detail shows specifically where to terminate copper
components within a network substation. Part numbers and sample labeling are shown.
35