0% found this document useful (0 votes)
27 views2 pages

Format-II Earthing.

Typical Punch list earthing system

Uploaded by

Kalpesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views2 pages

Format-II Earthing.

Typical Punch list earthing system

Uploaded by

Kalpesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Annexure-I

PUNCH LIST-ELECTRICAL
OWNER CONTRACTOR :

CONSULTANT DATE: 18/12/2022

NAME OF WORK

JOB NO.

SYSTEM NO.

Completion Acceptance
Punch Prepared
Priority Description of Punch items AREA Action By
Item No. By
123.00 XYZ/ABC

1 A Incomplete ITP needs to be completed / Balance points in ITP and punch list in ITP needs to close out. Unit Area. XYZ/ABC

2 Unit Area
3 A Earthing riser strips to be supported with Clamp/Saddle. All Bolts inside earthing strip to be removed Unit Area. XYZ/ABC
for entire unit area wherever required.
4 A Earth strips on trays to be provided with cold zinc touch up paint Unit Area. XYZ/ABC
5 A Tray earthing not done. It is to be completed. Unit Area. XYZ/ABC
6 A ROLRM earthing to be done as per drawing and specification. Unit Area. XYZ/ABC
7 A Deluge Valve earthing to be complete as per drawing and specification. Unit Area. XYZ/ABC
8 A Push Button earthing is not completed, which is to be complete for entire unit area. Unit Area. XYZ/ABC
9 A HV Spray system and allied Control panel earthing pending. Unit Area. XYZ/ABC
10 B Main grid connection need to show during equipment earthing testing. Unit Area. XYZ/ABC
11 A LCS /Push Button earthing to be finish which are not completed for entire unit area. Unit Area. XYZ/ABC
Equipment earthing to be tested as per standerd mentioned in tender and drawing also as per ITP
12 A Unit Area. XYZ/ABC
agreed if any.
13 A Instrument earthing cable to laid inside SRR as per skecth provided. Unit Area. XYZ/ABC
14 A Earthing jumper to be completed for unit area. Unit Area. XYZ/ABC

15 A MOV earthing to be completed for entire unit area. Unit Area. XYZ/ABC
Copper lugs should be used in case where cables are used for earthing to any equipment, few casses
16 A Unit Area. XYZ/ABC
it is not there, which is to be corrected.
17 A In case of Control or Tried cable sheild to earthed properly in terminal block. Unit Area. XYZ/ABC
Earthing testing not done. Earthing testing to be completed and report to be furnished for every
18 A Unit Area. XYZ/ABC
equipment as per specification and vendor instruction if any.
Motor inside Cable armoured must be connected (Earthed) with earthing barbed wire in specified
19 A Unit Area. XYZ/ABC
earthing point. As it is not done so many MV Motors.
20 B Touch up GI painting to be done wherever earth strips are corroded Unit Area. XYZ/ABC
421-RB-1001/1002
21 A Earthing not completed. One Lugs need to fix in Reactor as per standerd Unit Area. XYZ/ABC
MOV earthing to be completed. While connecting MOV's lugs should be used in earthing cable.
22 A Unit Area. XYZ/ABC
Which is not found in few areas.
23 A Welding recepticles earthing not completed. Unit Area. XYZ/ABC
Compressor House
24 Welding recepticles earthing not completed. Unit Area. XYZ/ABC
25 A LCS earthing to be finish. Unit Area. XYZ/ABC
26 A EOT Crane Panel need to do earthing Unit Area. XYZ/ABC
121-KA-1002 B Earthplate & pipe both are found superimposing each other. Earth plate neeed to
27 A Unit Area. XYZ/ABC
shift.
421-EE-1008
28 A Only one side earthing is complete. Other side need to complete. Unit Area. XYZ/ABC
Air Fin Cooler
30 A All concrete Debris to be removed from Earth Plate and it is to be clean. Unit Area. XYZ/ABC
31 A All rusted bolts to be removed associated to Earthing. Unit Area. XYZ/ABC
32 A Earthing Cable shall be neatly dressed. Unit Area. XYZ/ABC
33 A 121-EM-2001-IB : LCS single earthing. Unit Area. XYZ/ABC
34 A 121-EM-2001-FB : LCS don’t have earthing. Unit Area. XYZ/ABC
35 A 121-EM-2001-GA : LCS don’t have earthing. Unit Area. XYZ/ABC
36 A All Hydrojet JB found not earthed. Unit Area. XYZ/ABC

Priority :- A- Needed before Pre-commissioning B- Needed for Commissioning.