SPM Labfile
SPM Labfile
• A statement of work,
• A resource list,
• Work breakdown structure,
• A project schedule and,
• A risk plan.
The project plan identifies the roles and responsibilities of stakeholders. The project
manager gets clarity and agreement on what will be done, by whom, as well as which
decisions each stakeholder will make. The scope of work statement is one of the most
important documents in the project plan. The scope includes the business need and
business problem, the project objectives, deliverables, and key milestones.
Q 2: How to create a new project plan and set its start date?
Procedure: Once you have downloaded and installed ProjectLibre Tool, you should see
a window like this one below:-
After clicking on ‘Create Project’ you must enter some basic project details as seen in
the screen below:-
You will need to enter the following information about your project:
Project Name: Product
Manager: Fazeela
Start Date: September 11th, 2020.
After that, click on OK.
Now, your new project plan is created with the setting of the project start date.
For changing the calendar settings, select a specific date with a single click or multiple
days using Ctrl or Shift keys in combination with left click. Then for the specific days, you
may use the standard hours (8-12, 13-17) or define your own. You may also select week
days (use Ctrl or String key for multiple week days selection).
Calendar tool normally sets to “Use default”, but you can change the settings of
calendar tool according to you in the following ways:
• For making days non-working, select "Non-Working time"
• For making days working, select “Non-default working time”.
Q 4:How to enter tasks, task duration and milestone?
Task: A task is a single unit of work - an action to accomplish in a project, a single step
in a multi-step project. A task is accomplished by a set deadline, and must contribute
toward work-related objectives. Just as project management is the coordination of
individual tasks, a task can be broken down further into subtasks, which should also have
clear start and end dates for completion.
Task Duration: Task duration would be the actual time it takes to complete a
task. This time comes from the difference between the planned completion date and the
planned start date.
Procedure: Click the task row that you want to indent or outdent, and then, on the
Task tab, click on Indent or Outdent whatever you want to do.
The four main types of activity dependencies include Finish-to-Start (FS), Start-to-Start
(SS), Start-to-Finish (SF), and Finish-to-Finish (FF). The following briefly describes these
relationship types:
• Finish-to-Start (FS): The successor activity cannot start unless the predecessor
activity finishes.
• Start-to-Start (SS): The successor activity cannot start unless the predecessor
activity starts.
• Start-to-Finish (SF): The successor activity cannot finish unless the predecessor
activity starts.
• Finish-to-Finish (FF): The successor activity cannot finish unless the
predecessor activity finishes.
Q 7:How to assign resources to task?
To view tasks click on ‘Task’ at the top menu and ‘Gantt’ button on the left.
To view resources click on ‘Resources’ at the top menu and then the ‘Resources’
button on the left.
• Project Manager, Functional Manager and Operational Manager plays their own
role in managing the software project.
• Coordinator co-ordinates the project and supervisor supervise the whole project
with their experience of work plan.
• Analyst has to visit the client in order to discuss requirements by plan.
• Tester is going to test if the project works completed.
• Database Administer has to check all the information which is saved in database.
• Developer are going to develop the project.
• Finally Developer are going to fix the project’s bugs.
Now, go at the tasks list, double-click on the first task and then click on the ‘Resources’
tab. Then, click on the blue button with the two people.
2
3
As you can see, you have the list of your project’s resources available. You can
Control+click to select multiple resources for a task. Control+click at ‘Project Manager’
and ‘Co-ordinator’ and then click on ‘Assign’.
Now two resources are allocated for the first task. We do same process for different tasks
to allocate different resources.
Work Resources are people and machines, and they need time (hours, days, weeks,
etc.) to perform the Tasks of a particular project.
▪ Project Manager
▪ Functional Manager
▪ Operational Manager
▪ Co-ordinator
▪ Superviser
▪ Analyst
▪ Tester
▪ Database Administrator
▪ Developer
Material resources:
Material Resources are consumables like electricity, fuel, concrete etc., which are used
during the project development and they are time independent.
▪ Electricity
▪ Paint
▪ Money
▪ Fuel
▪ Tools
When we click on the ‘Type’ row of any resource then two options will open (Work and
Material) as shown in the above figure, then we select one type of resource according
to our need of project.
When the project is complete, the Schedule Variance becomes zero because all Planned
Value has been earned.
When we want to calculate SV, then firstly we can save baseline to the entire project using
ProjectLibre Tool.
Without baseline our project’s Gantt chart looks like below: -
When we save baseline to the entire project then our project’s Gantt chart looks like:
After saving baseline, we insert columns of Actual Start, Actual Work, Actual Cost,
Baseline Cost, BCWP, BCWS, SV, CV, BAC as follows: -
After inserting all these columns, go to the number of task to select whole row of task
and then click on task and go to update as shown below: -
1
Update tasks open like below: -
Now Give how much percentage of task is completed. For example, suppose that for
this task we give 65% as follows: -
After that click on close, then our BCWP, BCWS and SV will be calculated
automatically according to the given completed percentage of a particular task.
Follow the above steps for calculating the Schedule Variance(SV) of all the tasks and
we get the result as follows: -
1. Project Details: - For Project Details select ‘View’ and then click on ‘Report’ as
shown below: -
Project Details
The project details report, displays the following information:
• Dates: Start, Finish, Baseline Start, Baseline Finish, Actual Start and Actual Finish.
• Duration: Scheduled, Remaining, Baseline, Actual and Percent Complete.
• Work: Scheduled, Remaining, Baseline and Actual.
• Costs: Scheduled, Remaining, Baseline, Actual and Variance.
Resource Information
Earned Value
Earned Value
3. Task Information: - Now select Task information which is just below the option of
resource information:
Constraint Dates
❖ Task Information – Cost:
The Task Information – Cost report can have a quick glance at every Task cost, Actual
cost, Remaining cost, Fixed cost and Baseline cost.
Cost
Earned Value
❖ Task Information – Tracking: Very useful report, displaying all the tasks, along
with the Actual Start, Actual Finish and Percent Complete. You can also filter the
tasks to view Completed tasks, Cost over budget tasks, Critical tasks, In-progress
tasks, Incomplete tasks, Late/over budget tasks and Normal tasks as shown in the
below figure by the arrow:
Filter Options
Tracking