CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 1: PRELI
Item No. Payment Description Unit Quantity
SABS 1200 SECTION 1: PRELIMINARY AND GENERAL
AA

8.3 Fixed charges & Value-Related items for duration of


1.1
contract

1.1.1 8.3.1 Contractual Requirements Sum 1

8.3.2 Provision of Facilities on Site

1.1.3 (b) Facilities required by Contractor Sum 1

1.1.4 8.3.3 General Responsibilities and Other Fixed-charge Obligations


Sum 1

1.1.5 8.3.4 Removal of Site Establishment Sum 1

1.2 8.4 Time-related charges (for duration of contract, unless


otherwise stated)

1.2.1 8.4.1 Contractual Requirements Sum 1

8.4.2 Operation and Maintenance of of Facilities on Site

1.2.3 (b) Facilities for Contractor Sum 1

1.2.4 8.4.3 General Responsibilities and Other Time-related Obligations


Sum 1

1.3 EHS and other Obligations

1.3.1 Environmental Health & Safety Obligations Sum 1

1.3.1 Establishment Sum 1

1.3.2 De-establishment Sum 1

TOTAL CARRIED FORWARD TO SUMMARY

SANBI 1
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 2: SITE CLEAR


Item No. Payment Description Unit Quantity
SECTION 2: SITE CLEARANCE & EARTHWORKS

2.1 SABS Site Clearance


1200 C

8.2.1 Clearing and grubbing. Digging up and removing rubbish,


debris, vegetation, hedges, shrubs and trees, bricks and
2.1.1 kerbs not exceeding 200mm girth, bush, etc. and cutting
those branches and shrubs overhanging into the road
m² 180

Stripping average 150mm thick layer of top soil and


2.1.2 depositing material in prescribed stock piles on site Sum 180

2.1.3 Removal of tree roots during stripping of topsoil and box


cutting Sum 1

2.1.5 Tree exceeding 200mm and not exceeding 500mm girth No. 6

2.1.6 Tree exceeding 500mm and not exceeding 1000mm girth No. 4

2.1.7 Tree exceeding 1000mm and not exceeding 1500mm girth No. 2

2.1.8 Tree exceeding 1500mm and not exceeding 2000mm girth No. 2

2.2 SABS Earthworks (Small Works)


1200 DA

8.3.1 Excavation

8.3.1(a) Remove topsoil to nominal depth 150 mm, and cart away to
2.2.1 the approved dump site irresective of distance
m² 180

2.2.3 Cart away material from box cutting to the approved dumpp
site irrespective of distance m³ 180

8.3.1(c) Extra over items 2.2.2 for:

2.2.4 Intermediate excavation m³ 10

2.2.5 Hard rock excavation m³ 10

Import G5 base layer material, place and compact to 98%


2.2.6
MOD AASHTO m³ 27

TOTAL CARRIED FORWARD

SANBI 2
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 2: SITE CLEAR


Item No. Payment Description Unit Quantity
BROUGHT FORWARD

2.2.7 Import G7 subbase layer material, place and compact to 95%


MOD AASHTO m³ 27

2.2.12 Keeping excavations free of all water Sum 0

2.2.13 Density testing of all layers as shown in the drawings Sum 1

TOTAL CARRIED TO SUMMARY

SANBI 3
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 3: REINFORCED CONCRET


Item No. Payment Description Unit Quantity

2.3 SABS Concrete Structural


1200 G

8.2 Formwork

2.3.1 8.2.2 Smooth to outside of visible area of support structure m² 20

8.3 Reinforcement

2.3.2 8.3.1 Mild steel bars up to 12mm diam. To be used as dowel bars
t 1

2.3.3 Type 193 mesh reinforcement to concrete m² 285

8.4 Concrete

8.4.3 Strength concrete Grade 30/13 MPa to existing concrete


2.3.4 walkway with a non-slippery finish at the top
m³ 42.75

2.3.5 8.4.4 Unformed surface finish top of walkway slab - wood floated
m² 285

2.3.6 Strength concrete Grade 15/19 MPa to support kerbs


m³ 21.8

2.3.7 Curing of concrete using standard curing method(s) Sum 1.0

Kerbs

2.3.8 Supply and install Fig 10 kerbs, 1m long including cutting


m 610

Supply and install Concrete interlocking pavers including


edging and cutting

Concrete rectangular paver colour grey, size approximately


200 x 150 x 60mm thick (SANS 1058:2012) laid in
herringbone pattern, in accordance with SANS 1200 MJ and
CMA Concrete Block Paving Manuals, with a minimum
longitudinal fall of 1% on a transverse fall of at least 2% on
and including 20mm compacted sand bed with fine jointing
2.3.9
sand and cement mix swept and vibrated into joints, all laid
on sub-grade conforming to SANS 1200 D Degree of
Accuracy 1 (layerworks elsewhere measured).

m² 180

TOTAL CARRIED FORWARD

SECTION 3: REINFORCED CONCRET


Item No. Payment Description Unit Quantity
BROUGHT FORWARD

TOTAL CARRIED FORWARD TO SUMMARY

SANBI 4
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION
Item No. Payment Description Unit Quantity

4.5 Sub-surface drainage provisions PS 1

4.6 Profit and attendance on provisional sum % R25,000.00

TOTAL CARRIED FORWARD TO SUMMARY

SANBI 5
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SUMMARY

SECTION 1: PRELIMINARY AND GENERAL

SECTION 2: SITE CLEARANCE & EARTHWORKS

SECTION 3: REINFORCED CONCRETE , PAVING AND KERBS

SECTION 4: PROVISIONAL SUMS

SUB-TOTAL

5% CONTINGENCIES

SUB-TOTAL

15% VAT

TOTAL CONSTRUCTION COSTS

SANBI 6
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 1: PRELIMINARY AND GENERAL


Rate Amount

SANBI 7
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 2: SITE CLEARANCE & EARTHWORKS


Rate Amount

SANBI 8
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 2: SITE CLEARANCE & EARTHWORKS


Rate Amount

SANBI 9
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 3: REINFORCED CONCRETE , PAVING AND KERBS


Rate Amount

SECTION 3: REINFORCED CONCRETE , PAVING AND KERBS


Rate Amount

SANBI 10
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

SECTION 4: PROVISIONAL SUMS


Rate Amount

R25,000.00 R25,000.00

10.00% R2,500.00

R27,500.00

SANBI 11
CONSTRUCTION OF A ROAD AND WALKWAYS AT KZNNBG PROJECTNEERS CONSULTING

BS

R27,500.00

SANBI 12