To Organize and Classify The Tasks Weakly Nov 2024
To Organize and Classify The Tasks Weakly Nov 2024
broken down and assigned to each specific week, from November 11, 2024, to December 9,
2024. Below is an example of how you could structure the tasks for each week, following the
provided format.
Week No.: 1
Weekdays Activities
Monday Demolishing work of existing hollow concrete blocks (HCB)
Tuesday Removing existing ceramic tiles from the surface
Wednesday Dismantling hand rails and clearing the debris
Thursday Removing existing granite flooring
Friday Initial inspection and preparation for HCB replacement
Week No.: 2
Weekdays Activities
Monday Setting up for HCB wall work (Hollow Concrete Block Works)
Tuesday HCB wall construction and layout
Wednesday Plastering for the HCB walls (first coat)
Thursday Continuing plastering work and preparation for gypsum work
Friday Starting gypsum installation for walls and ceilings
Strength and Opportunities obtained (Half a Page):
Progress on the construction of HCB walls was steady this week, providing a strong base for the
upcoming plastering and gypsum work. The plastering of HCB walls also improved the
aesthetics and durability of the structure. The early initiation of gypsum work gives us an
advantage to complete finishing faster as we approach the later stages of construction.
Week No.: 3
Weekdays Activities
Monday Gypsum work on walls and ceilings
Tuesday Completing the second coat of plastering
Wednesday Roofing work preparation with RHS (Rectangular Hollow Section) material
Thursday Installing galvanized EGA (Electro Galvanized Aluminum) sheets for roofing
Friday Final inspection of roofing setup and gypsum work completion
Week No.: 4
Weekdays Activities
Monday Final electrical setup, including wiring and junction boxes
Tuesday Finalizing sanitary works, including piping and fixture placement
Wednesday Testing electrical and plumbing systems
Weekdays Activities
Thursday Addressing any electrical or sanitary issues
Friday Inspection and handover of completed electrical and sanitary installations
In November and December, significant progress was made on the project with a focus on
demolition, construction, and installation tasks. The demolition phase (HCB removal, ceramic
tiles, and granite) cleared the site for future works, laying a solid foundation for the next steps.
The HCB walls were completed along with plastering and the installation of gypsum, setting the
stage for interior finishing.
The roofing work, using RHS material and galvanized sheets, was successfully executed,
providing structural integrity and weather protection for the ongoing work inside the building.
Electrical and sanitary works were completed without major setbacks, with all systems tested and
ready for final checks.
The project is on track with a good pace of work, and while weather-related delays have
occasionally slowed the roofing and outdoor tasks, internal activities like plastering and
electrical works are progressing as scheduled. Future work will focus on finishing and detailed
inspections.
By following this template for each week, you'll have a clear record of the tasks and milestones
achieved during the month. You can easily compile these into a monthly report and address the
challenges, achievements, and overall progress of the project.