Points For Bidding

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views3 pages

Points For Bidding

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

POINTS FOR TENDER FILLING

A) LAND DEVELOPMENT WORK

 If necessary, we need to take bore log to identify strata, as client has given
soil report
 Transportation, government fess, royalties are in SRI scope
 Water for murum compaction & drinking is in SRI scope
 Filling will be in 300 mm in layers and compaction to be done accordingly and
test to be done
 If required, murum to be considered brought from outside
 +-50 mm deviation in final level will be allowed
 Proctor density test @ 500 sqm and for each layer – 98% compaction
 Need to do survey first & give coordinates to client then only we can start
development works
 Control blasting also included in development work, & necessary legal
license for blasting
 Pneumatic breaking also included in development work
 Trees removal is in scope, 15cm girth, 1.2 m ht from GL
 Tress other than small shouldn’t be cut and shall be brought to notice of
owner/consultant
 Water & Electricity is in SRI scope
 2m high barricading to proposed construction site
 Trees to be cut/replanted at own cost with all government approvals & its
cost
 Temple below tress to be built at own cost
 14. DOCUMENTS TO BE SUBMITTED WITH TENDER
The contractor shall submit the following documents along with the
Commercial O er –
o 14.1 Organization chart for the project.
o 14.2 Technical sta profiles for this project
o 14.3 Equipment’s / Machineries list to be used for this project.
o 14.4 Methodology for all items to be executed
o 14.5 Quality assurance plan (QAP) and Safety statement for this
project.
o 14.6 Time Schedule/ bar chart for this project.
 Duration 60 days
 All HR Compliances
 Payment will be done by Owner after 15 days once bill submitted
 NO ADVANCE
 5% Retention & 1 yr DLP
QUERIES FOR PRE-BID

B) ROAD, PARKING & ENTRY

 Item No. 2.01 – M10 PCC- Is fly ash permitted?? & Min. cement
content ?
 Item No. 2.02 – M25 RCC – Is fly ash permitted?? & min cement
content ?
 Item No. 4.01 – VDF floor – Fly ash content % for concrete mix
design ? & Min. cement content?
 Item No. 5.04 – M.S. Openable gate….wt in Kg/sqm ? or any
Schematic dwg ?
 Item No. 5.05 – Wicket gate….wt in Kg/sqm ?
 Item No. 5.07 – Telescopic entrance gate ….need schematic dwg if
any…or weight in kg/sqm ? or any Schematic dwg ?
 Item No. 5.12-Sizes for RCC perforated cover
 Item No. 5.13 – precast U drain sizes
 BOQ Item No. 5.19 - Tensile Structure with Covered Sheets…
Need dwg if any

C) PAD_PHASE-2
 Min. cement content of all grade concrete if any
 If fly ash permitted, then max. % of PFA content
 Item 4.04 – Bolts will be provided by PEB vendor separately, pls
confirm if supply rate to be considered in this item or only fixing to
be considered

D) SHED_PHASE-1
 Min. cement content of all grade concrete if any
 If fly ash permitted, then max. % of PFA content
 Item 4.04 – Bolts will be provided by PEB vendor separately, pls
confirm if supply rate to be considered in this item or only fixing to
be considered
 Item No. 10.02 – EWC make & catalogue code no. ? or basic rate ?
 Item No.-10.29 – Sintex tank – Which layer ?
 ADDITIONAL POINTS FOR BIDDING

Safet Manual required


SPECIAL CONDITIONS OF CONTRACT – (SCC)
o No material advance
o No mobilisation advance
o 1 RA bill in 1 month of min. 75 lacs
o RA bill will be paid after 3 weeks from the certification of
PMC
o 5% Retention will be there
o 2.5% of retention money will be released with final bill &
2.5% remaining will be after DLP
o Water & Electricity in SRI scope
o Space for labour hutment will be given by client in plot
premises
o Basic rates – Not applicable unless specified…means no
basic rates for Cement, Reinf. Bars, str. Steel
o Site to be commenced within 10 days on receipt of LOI
o Time Schedule
 Landscape & Compound wall – 60 days
 Civil Package – 6 Months
 PEB – Erection to be completed within 40 days
Supply of PEB material as per PMC/Client