Points For Bidding
Points For Bidding
If necessary, we need to take bore log to identify strata, as client has given
soil report
Transportation, government fess, royalties are in SRI scope
Water for murum compaction & drinking is in SRI scope
Filling will be in 300 mm in layers and compaction to be done accordingly and
test to be done
If required, murum to be considered brought from outside
+-50 mm deviation in final level will be allowed
Proctor density test @ 500 sqm and for each layer – 98% compaction
Need to do survey first & give coordinates to client then only we can start
development works
Control blasting also included in development work, & necessary legal
license for blasting
Pneumatic breaking also included in development work
Trees removal is in scope, 15cm girth, 1.2 m ht from GL
Tress other than small shouldn’t be cut and shall be brought to notice of
owner/consultant
Water & Electricity is in SRI scope
2m high barricading to proposed construction site
Trees to be cut/replanted at own cost with all government approvals & its
cost
Temple below tress to be built at own cost
14. DOCUMENTS TO BE SUBMITTED WITH TENDER
The contractor shall submit the following documents along with the
Commercial O er –
o 14.1 Organization chart for the project.
o 14.2 Technical sta profiles for this project
o 14.3 Equipment’s / Machineries list to be used for this project.
o 14.4 Methodology for all items to be executed
o 14.5 Quality assurance plan (QAP) and Safety statement for this
project.
o 14.6 Time Schedule/ bar chart for this project.
Duration 60 days
All HR Compliances
Payment will be done by Owner after 15 days once bill submitted
NO ADVANCE
5% Retention & 1 yr DLP
QUERIES FOR PRE-BID
Item No. 2.01 – M10 PCC- Is fly ash permitted?? & Min. cement
content ?
Item No. 2.02 – M25 RCC – Is fly ash permitted?? & min cement
content ?
Item No. 4.01 – VDF floor – Fly ash content % for concrete mix
design ? & Min. cement content?
Item No. 5.04 – M.S. Openable gate….wt in Kg/sqm ? or any
Schematic dwg ?
Item No. 5.05 – Wicket gate….wt in Kg/sqm ?
Item No. 5.07 – Telescopic entrance gate ….need schematic dwg if
any…or weight in kg/sqm ? or any Schematic dwg ?
Item No. 5.12-Sizes for RCC perforated cover
Item No. 5.13 – precast U drain sizes
BOQ Item No. 5.19 - Tensile Structure with Covered Sheets…
Need dwg if any
C) PAD_PHASE-2
Min. cement content of all grade concrete if any
If fly ash permitted, then max. % of PFA content
Item 4.04 – Bolts will be provided by PEB vendor separately, pls
confirm if supply rate to be considered in this item or only fixing to
be considered
D) SHED_PHASE-1
Min. cement content of all grade concrete if any
If fly ash permitted, then max. % of PFA content
Item 4.04 – Bolts will be provided by PEB vendor separately, pls
confirm if supply rate to be considered in this item or only fixing to
be considered
Item No. 10.02 – EWC make & catalogue code no. ? or basic rate ?
Item No.-10.29 – Sintex tank – Which layer ?
ADDITIONAL POINTS FOR BIDDING