From: NCR.ZN/NCR/IR/IN
To: JHS.DV/JHS/NCR/IR/IN@icms, ALD.DV/ALD/NCR/IR/IN@icms,
AGRA.DV/AGRA/NCR/IR/IN@icms
Cc: PAMCELL.RB/IR/IN@icms, ZonalUsers, NR.ZN/NR/IR/IN@icms,
NWR.ZN/NWR/IR/IN@icms, WCR.ZN/WCR/IR/IN@icms

Date: Thursday, December 19, 2024 03:23PM


Subject: TTCN 414/24- Cut & Connection work on UP line between SLV-ARI stations in
connection with 3rd line work in GWL-VGLJ section over Jhansi division.

North Central Railway


No. Optg/Block-NI/JHS/NCR/2024 Headquarters Office
Date –19.12.2024 Subedarganj, Prayagraj
DRMs
Sr.DOM, Sr.DCM, Sr.DEE(OP), Sr.DME, Sr.DEN, Sr.DSTE, Sr.DEE/TRD
JHS, PRYJ & AGRA
Sub: Cut & Connection work on UP line between SLV-ARI stations in connection
with 3rd line work in GWL-VGLJ section over Jhansi division.
Ref:- RB message no. DTP/2024/12/64 dated 19.12.2024.
**********
It is being notified for the information of all concerned that Cut & Connection work on UP line at KM 1209/27-
1208/31 & 1203/17-11 between SLV-ARI stations and dismantling of cross over point no. 101 in SLV yard in connection
with 3rd line work in GWL-VGLJ section over Jhansi division will be undertaken as per following details-

1. Block and speed restriction –


UP direction DN direction
Days Date Block Speed Block Speed
restriction restriction
D-2 18.12.24 2.30 Hrs. 20 Kmph 2 Hrs. 20 Kmph
D-1 19.12.24 2.30 Hrs. 20 Kmph 2 Hrs. 20 Kmph
D –day 20.12.24 6 Hrs. 20 Kmph 3 Hrs. 20 Kmph
(Friday) (10.00 to 16.00) (10.00 to 13.00)
D+1 21.12.24 2 Hrs. 20 Kmph 2 Hrs. 20 Kmph
D+2 to D+4 22.12.24 to 24.12.24 2 Hrs. 30 Kmph 2 Hrs. 30 Kmph
D+5 to D+8 25.12.24 to 28.12.24 2 Hrs. 45 Kmph 2 Hrs. 45 Kmph

2. Coaching Repercussion-
a. Cancellation of trains –

S.N. Train No. From - To Freq. JCO Trips


1 11807 VGLJ-AGC MEMU Daily 20.12.24 to 24.12.24 05
2 11808 AGC-VGLJ MEMU Daily 20.12.24 to 24.12.24 05
3 11901 VGLJ – AGC Daily 20.12.24 to 23.12.24 04
4 11902 AGC-VGLJ Daily 20.12.24 to 22.12.24 03
5 11903* VGLJ-ETW Daily 20.12.24 to 22.12.24 03
6 11904 ETW-VGLJ Daily 20.12.24 to 23.12.24 04
*Rake of train no. 11903 (JCO- 19.12.24) will be return to AGC as empty
coaching rake after arriving at ETW.

b. Diversion of trains-

https://icms.indianrail.gov.in/icmsmail/mail/jhsdv.nsf/(%24Inbox)/D7AD645BFF4229BC65258BF80036500A/?OpenDocument&Form=h_PrintUI&P… 1/3
19/12/2024, 15:59 icms.indianrail.gov.in/icmsmail/mail/jhsdv.nsf/(%24Inbox)/D7AD645BFF4229BC65258BF80036500A/?OpenDocument&Form…

SN Train From - To Freq. Existing route Diversion via JCO Trips


No.
MTJ-GWL- MTJ-BXN-SGAC- 20.12.24
1 12644 NZM-TVC Fri 1
VGLJ-BINA RTA-BINA
MTJ-GWL- MTJ-BXN-SGAC- 20.12.24 to
2 12780 NZM-VSG Daily 21.12.24 2
VGLJ-BINA RTA-BINA
NDLS- MTJ-GWL- MTJ-BXN-SGAC- 20.12.24 to
3 12626 Daily 21.12.24 2
TVC VGLJ-BINA RTA-BINA
NZM - W, F, MTJ-GWL- MTJ-BXN-SGAC- 20.12.24
4 12708 1
TPTY Su VGLJ-BINA RTA-BINA
NDLS- MTJ-GWL- MTJ-BXN-SGAC- 20.12.24 to
5 12628 Daily 2
SBC VGLJ-BINA RTA-BINA 21.12.24
NZM- Exc.- MTJ-GWL- MTJ-BXN-SGAC- 20.12.24
6 12808 1
VSKP W, Su VGLJ-BINA RTA-BINA
FZR- MTJ-GWL- 19.12.24
7 12138 Daily GWL-GUNA-BINA 1
CSMT VGLJ-BINA
MTJ-GWL- GWL-GUNA-RTA- 20.12.24 to
8 12618 NZM-ERS Daily 3
VGLJ-BPL MKC-BPL 22.12.24
ASR – MTJ-GWL- 19.12.24
9 18238 Daily GWL-GUNA-BINA 1
KRBA VGLJ-BINA
MTJ-GWL- 20.12.24 to
10 12191 NZM-JBP Daily GWL-GUNA-BINA 3
VGLJ-BINA 22.12.24
GWL-VGLJ- 20.12.24 to
11 11123 GWL-BJU Daily GWL-BIX-ETW-CNB 3
CNB 22.12.24
GWL-BJU GWL-VGLJ- 22.12.24
12 04137 W, Su GWL-BIX-ETW-CNB 1
TOD CNB

Rescheduling of trains – 12630 NZM-YPR will be rescheduled by 04 hrs. ex. NZM


JCO 20.12.24.

(d) Short-Termination/origination –
SN Train From-to Freq. Short terminate JCO Trips Remarks
no. /originate at/ex.
19.12.24 to --
1 19666 UDZ-KURJ Daily AGC 4
22.12.24
21.12.24 to 4 --
2 19665 KURJ-UDZ Daily AGC
24.12.24
20.12.24 to 3 Already
3 12280 NDLS-VGLJ Daily GWL
22.12.24 notified in
20.12.24 to 3 fog
4 12279 VGLJ-NDLS Daily GWL
22.12.24

Note- 1. Rake of 19666 JCO 19.12.24 short terminated at AGC on 20.12.24, arrange
to return back to UDZ as empty coaching rake.
2. One empty coaching rake of 19665 to be sent to AGC so as to reach
24.12.24 morning to run 19665 from AGC on 24.12.24.

(e) Regulation of trains-


(i) Coaching trains will take 15-20 minute extra time in UP direction due to Speed restriction
from D-2 to D+4.
(ii) Parcel and trains running out of path will be regulated accordingly from D-2 to
D+4.

(3) Freight Repercussion –

https://icms.indianrail.gov.in/icmsmail/mail/jhsdv.nsf/(%24Inbox)/D7AD645BFF4229BC65258BF80036500A/?OpenDocument&Form=h_PrintUI&P… 2/3
19/12/2024, 15:59 icms.indianrail.gov.in/icmsmail/mail/jhsdv.nsf/(%24Inbox)/D7AD645BFF4229BC65258BF80036500A/?OpenDocument&Form…

(i) Tentative interchange at DHO in UP direction during work-

Day T/O at DHO


19.12.24 10-12 Freight trains
20.12.24 08-10 Freight trains
21.12.24 to 10-12 Freight trains
24.12.24

4.Other Instruction-
(i) All loaded jumbo trains to be planned via GWL -GUNA or via Mathura-Kota-
Nagda.
(ii) ICMS, NTES & PRS shall be updated accordingly.
(iii) In the case of diverted trains every possible effort should be made to
minimize any delays encountered along the revised routes.

Railway Board’s instructions in regard to availability of officers at the site and


deployment of adequate resources in terms of materials and manpower may be
ensured so that there is no bursting of block and timeline. Effective utilization of
shadow block may be ensured. Division should ensure minimum detention to the
trains. The work may be executed keeping in view of safety, operational convenience
and prior intimation to the adjacent divisions and all concerned. Passengers must be
duly notified and informed in advance to ensure their convenience and awareness.

All concerned to please note and act accordingly. Wide publicity be given through electronic and print media,
public address system and station notice boards.

(Basant Kumar
Sharma)
CPTM/NCR
Copy – Secy. to GM for kind information of GM/NCR.
AGM and All PHODs for kind information please.
PED (Coaching), Railway Board
CPTMs/Zonal Railway
CCM/PS/NCR for necessary action please.
CPRO/NCR for publicity.
CHC(P)/HQ/NCR & all sister controls.