Actpw Gcc Gn Zz Ms w 00108
Actpw Gcc Gn Zz Ms w 00108
Actpw Gcc Gn Zz Ms w 00108
ALDAR PROJECTS
QUALITY SUBMITTAL TRANSMITTAL
PROJECT Design and Build Contract for Cycle Track – Route 3 & 4 in Abu Dhabi, U.A. E
CLIENT ALDAR Date 18 Oct 2024
ACTPW-GCC-GN-ZZ-MS-W-
PMC N/A Doc. Ref:
00108
CONSULTANT AtkinsRealis QST No. P00
CONTRACTOR Gulf Contractor Company
PROJECT Cycle Track Route 3 & 4
Method Statement for Erection of
SUBMITTAL TITLE Temporary Steel Support Towers (Gantry) DISCIPLINE: MS
for Bridge #1 at Cycle Track Route #3
DWG/SPECS/BO
ITEM No Description Type Remarks
Q Reference
Method Statement for Erection of
01 Temporary Steel Support Towers (Gantry) MS
for Bridge #1 at Cycle Track Route #3
□ Rejected (Code D)
HBM
10/10/2024
LEAD QA/QC Comments:
* Incomplete methodology submitted.
* Major activities such as, Foundation preparation, setting out, anchor bolts installation, connection details, torquing details are missing.
* Refer to the comments on the Method statement, ITP, checklist and Risk register and comply.
SJI
Code-C 10/10/2024
Page 1 of 1 Document Ref. : Click or tap here to enter text. Rev. 00 Printed on 11/1/2023 12:33:00 PM
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 1 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
Contractor’s Review:
Description QA/QC HSE C.M. T.M. P.M.
Name Gul Zada Haqiq Raheel Ahmad Shawar Haja Nizamuddin Ghader Aslani
Sr. Project
Designation QA/QC Manager HSE Manager Const. Manager Technical Manager
Manager
Signature
Date 18th Oct 2024 18th Oct 2024 18th Oct 2024 18th Oct 2024 18th Oct 2024
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 2 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
Table of Contents:
1. Purpose: ............................................................................................................................................... 3
2. Scope: .................................................................................................................................................. 3
3. Legislation and code of practice: ..................................................................................................... 3
4. Reference: ........................................................................................................................................... 4
5. Definitions: ........................................................................................................................................... 4
6. Resources: ........................................................................................................................................... 5
6.1 Materials:.......................................................................................................................................................... 5
6.2 Equipment’s: .................................................................................................................................................... 5
6.3 Human Resources & Assigned Responsibilities: .......................................................................................... 5
6.3.1 Project Manager: ................................................................................................................................................. 6
6.3.2 Site Engineer: ........................................................................................................................................................ 6
6.3.3 QC:........................................................................................................................................................................... 6
6.3.4 HSE Lead: ............................................................................................................................................................... 7
6.3.5 HSE Officer: ............................................................................................................................................................ 7
6.3.6 Surveyor: ................................................................................................................................................................ 7
6.3.7 Site Supervisor: ..................................................................................................................................................... 8
6.3.8 Site Foreman: ........................................................................................................................................................ 8
6.3.9 Workforce/Labors ................................................................................................................................................ 8
7. HSE Precautions ................................................................................................................................... 8
7.1 Task Sheet: ....................................................................................................................................................... 8
7.2 Risk Assessments: ............................................................................................................................................ 9
7.3 Emergency Response Procedure: ................................................................................................................ 9
8. Construction Methodology .............................................................................................................. 11
8.1 Prior Activities ................................................................................................................................................ 11
8.2 Safety Arrangements: ................................................................................................................................... 11
8.3 Concrete Foundation works ........................................................................................................................ 11
8.4 Erection of Steel Tower: ................................................................................................................................ 12
8.3.1 Steel columns, beams & bracings ................................................................................................................ 12
8.3.2 General Arrangements .................................................................................................................................... 13
8.3.3 Preparation prior to works ............................................................................................................................... 14
8.3.4 Delivery of steel .................................................................................................................................................. 14
8.3.5 Procedure of work installation ....................................................................................................................... 14
8.3.6 Installation of Columns, beams & bracings ................................................................................................ 15
8.3.7 Sequence and procedure of Installation .................................................................................................... 16
8.3.8 Method of Bolt Tightening ................................................................................................................................ 31
9. Inspection & Testing .......................................................................................................................... 31
10. Attachments ................................................................................................................................... 31
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 3 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
1. Purpose:
The purpose of this method statement is to ensure that all activities related to Installation of
Temporary steel support Towers (Gantry) at Bridge #1 of route #3 for Piers & Abutments are
carried out in accordance with the Project Specification, Approved Shop Drawing, Relevant
Authorities Requirements & Contractual Obligations.
The Installation of Temporary steel support Towers (Gantry) at Bridge #1 of route #3 for Piers &
Abutments of Cycle Track Route #3&4 will be carried out based on related HSE & quality
requirements.
This method statement shall provide guidance for the planning, supervision, Inspection
execution of the Installation of Temporary steel support Towers (Gantry) at Bridge #1 of route
#3 for Piers & Abutments of Cycle Track Route #3.
2. Scope:
This method statement covers all steps inline in the Installation of Temporary steel support
Towers (Gantry) for Bridge #1 of route #3 at Piers & Abutments. This will serve as temporary
support for installation for Precast Girders.
A. Site preparation
B. Foundation works
C. Pre-construction safety meeting.
D. Installation/Erection of structural steel.
E. Waste disposal.
4. Reference:
A. ADQCC Standard Specification Vol #1 Chapter 1: General requirements
B. ADDC Standard Specification for design and construction of buildings and construction
in Abu Dhabi
C. Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF)
D. Abu Dhabi Urban Planning Council (UPC) Codes
E. Abu Dhabi Department of Municipalities and Transport (DMT)
F. Abu Dhabi Quality and Conformity Council (QCC) Regulations
G. Related Risk assessment
H. Approved Shop drawing.
5. Definitions:
A. PM: Project Manager
B. CM: Construction Manager
C. PE/SE: Project Engineer / Site Engineer
D. ME: Material Engineer
E. QC: QA/QC Engineer
F. ST: Survey Team
G. ERT: Emergency Response team
H. SO: Safety Officer
I. PIC: Person in Charge
J. GS ADM General Specifications for Roads & Bridges.
K. PS: Contract Particular Specifications
L. MS: Method Statement
M. Vol #: Volume #
N. SS: Standard Specifications
O. ADM: Abu Dhabi Municipality
P. STN: Storm Water Network
Q. ADWEA: Abu Dhabi Water & Electricity Authority
R. Engineer: Consultant / Engineer
S. PPE: Personal Protective Equipment
T. TBT: Tools Box Meeting
U. OSHAD: Occupational Safety and Health Abu Dhabi
V. HSE: Health Safety and Environment
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 5 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
6. Resources:
6.1 Materials:
A. Structural Steel sections, profiles and plates.
B. Connection bolts, Nuts & Washers
C. Anchor Bolts, Nuts & Washers
D. Rebar and shutter for foundation
6.2 Equipment’s:
A. Man Lift / Forklift / Boom loader (As required)
B. Concrete pump and mixers
C. vibratos and concrete finishing equipment’s.
D. TMA
E. Crane, Trailers, Pickup
F. Ladder / Scaffolding
G. Auger/Drilling Machine
H. Welding machine (As required)
I. Sub-base
J. Roller compactors
K. Binding wires, wire cutters etc.
L. Power tools, Toolbox Set
M. Portable Generator (As required)
N. Power Supply Extension Board, Electrical Socket
O. Flagging Tape / Warning Tape
P. Plastic Barrier for Covering Road, Safety Cones & Temporary Regulator Signs
Q. PPE (Hard hat, coverall, safety shoe, visibility vest, goggles, gloves etc)
R. Hand tools and others (If any additional as per site requirements)
6.3.3 QC:
❖ Develop and implement quality assurance and quality control (QA/QC)
❖ Ensure compliance with project specifications, codes, and industry standards.
❖ Establish quality control procedures and inspection protocols.
❖ Review and approve inspection and test plans.
❖ Monitor and document non-conformance and corrective actions.
❖ Review and approve material submittals and shop drawings.
❖ Provide guidance and training to the project team regarding quality requirements.
❖ Ensure proper documentation of quality control activities and records.
❖ Monitor the implementation of quality control measures on-site.
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 7 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
6.3.6 Surveyor:
❖ Establishing the control point consists of scouting existing reference points on site with
reference to existing control point defined and indicated by the ENGINEER.
❖ Conduct site surveys to gather accurate measurements and data related to the excavation
work.
❖ Interpret the design drawings and specifications to establish the precise locations and
dimensions of the excavation area.
❖ Set out reference points, gridlines, and benchmarks on the site to guide the excavation.
❖ Conduct as-built surveys upon the completion of the excavation works.
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 8 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
6.3.9 Workforce/Labors
❖ Follow safety rules and regulations
❖ Report any hazards in workplace
❖ Report any accident or near miss
❖ Identify risk in workplace and associated hazards
❖ The usage of issued PPE
❖ Report any defects in machinery and equipment
❖ Report any non-conformance identified at work site
7. HSE Precautions
7.1 Task Sheet:
A. All activities shall be carried out only under the supervision of competent personnel.
B. Regular task briefing prior to start of work at site by job supervisor related to the specific job.
C. Regular task briefing prior to start of work for any Traffic Management Control work.
D. Safety Induction, orientation, re-induction will be done at site in relation to personnel who
will be involved with execution of above-mentioned activity.
E. Competent flag Man will regulate to construction activity area. The Flag Man will direct and
in assist in reverse difficulties of vehicles that enter and exit from location.
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 9 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
F. All Safety / Traffic warning signs will be placed as per the approved Traffic Management
Plan and NOC wherever required, and will be checked during Detour patrolling.
G. Within site working area speed limits of all construction vehicles will be 20KM/hr and their
movement and speeds will be continuously monitored and reported, all warnings will be
recorded by site safety personnel.
H. All Near-miss, incidents, environmental occurrences shall be immediately reported to Project
HSE Engineer by Site Execution team / HSE officer.
I. Required safety signs to be clearly positioned, maintained clean & visible condition all times.
J. All PPEs are to be worn by personnel who handle equipment involved with concern activity.
K. Monitor noise, vibration and dust and take appropriate measures to reduce to within
allowable reasonable limit.
L. Ensure only competent and authorized personnel to operate.
M. Proper barricading and appropriate hazard signs will be displayed to inform the site
personnel/ road users/ and visitors to the site.
N. Traffic management system.
O. Banks man should be deployed for the movement of Plant & equipment
P. Prior to mobilizing all Plant &equipment to be inspected by Workshop and certified & record
shall be maintained and prior on operation at site shall be inspected by competent
personnel / HSE.
Q. Operators to carry out daily inspection prior to start work.
R. Flashing beacon& reverse alarm should be functional.
S. Vehicle Lights, windows and mirrors should be cleaned regularly to ensure a clear view.
T. Plant & pedestrian access to site be kept separated.
U. As per OSHAD sf CoP 44.0 Traffic Management & OSHAD sf CoP 53.0 OSH Management
during Construction work /53
V. Man, Machine Interface training for all operators and operatives.
It also identifies some key requirements that a project emergency plan must include as liaison
points and first aid rooms.
Through put the Emergency Service Meeting Points will be established, all individually numbered.
Each project must note the nearest point to them within their plan; these points will provide the
emergency services guidance when navigating the site to find the emergency.
In case an accident occurs on the site, provide possible first aid on the site and send to the
hospital. All accidents and near misses are to be recorded in the GCC accident file and
immediately reported to Project Management and HSE teams.
In case of minor and major accident call the emergency, contacts numbers listed below
8. Construction Methodology
Installation/Erection methodology covers activities to be followed.
G. The settlement should not exceed the design limits at specified loads, and the ultimate
bearing capacity should be sufficient for the foundation.
H. Once the area is ready and confirmed by the surveyor, rebar works shall proceed.
I. 1000Gauge polythene shall be laid on the prepared formation level.
J. Mark the positions for the rebar on the formwork or foundation bed. The rebar installation
shall commence according to the approved design drawings for foundation.
K. Ensure that proper concrete cover is maintained by using spacers and chairs. Conduct a
pre-pour inspection to verify rebar placement, spacing, and alignment with design
specifications.
L. Set up formwork based on the foundation layout provided in the design drawings, use
clamps, bolts, and other securing mechanisms to fasten the formwork properly and prevent
leakage of concrete. Ensure the formwork is plumb, level, and aligned with the dimensions
specified in the drawings.
M. Apply a release agent to the formwork surfaces that will come into contact with the
concrete to ensure easy removal after curing.
N. Place anchor bolts in the designated locations within the formwork, as shown in the structural
drawings. Ensure that the bolts are properly aligned and plumb. Fix the anchor bolts firmly to
prevent movement during the concrete pour, using templates or jigs if necessary.
O. The surveyor checks the verticality, alignment, and level of the anchor bolts. Any adjustments
must be made before concrete casting begins. The surveyor coordinates with Hadeed Steel
or the designated steel supplier to verify bolt positioning against the shop drawings.
P. Conduct an inspection to ensure that the formwork dimensions and rebar placement are
correct. Approved third party M/s. Bureau veritas shall verify the foundation works for rebar,
shutter and anchor bolts installations.
Q. After getting approval from third party, joint inspection between contractor and Engineer
shall be conducted prior to the concrete works and supplier shall be approved.
R. Pour the concrete uniformly and continuously to avoid cold joints. Use vibrators to remove
air pockets and ensure even compaction. Avoid excessive vibration, as it may cause
segregation of the mix.
S. Once the concrete is poured and compacted, use a screed board to level the surface.
❖ Safety Glasses.
❖ Full Body Safety Harness for the erectors.
J. Ensure the lifting gears are strong enough to lift the load that will be imposed.
K. Check that slings are to be fixed considering the center of gravity of the load.
L. Never replace bolts, shackles, etc., without consulting the approved authorities. Never
throw or use defective lifting gears.
M. Attached logistics plan for the arrangement of mobile cranes during installation of gantries.
(Attachment G)
C. Step 02
Installation of knee bracing on the installed column as shown below,
Knee
B
r
a
c
i
n
g
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 17 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
D. Step 03
Install the 2nd column as shown below,
E. Step 04
After installation of the 2nd column, install the horizontal bracing between the column
as shown,
Horizontal Bracing
between the
columns
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 18 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
F. Step 05
Install the remaining columns and horizontal bracings as shown sequentially,
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 19 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
G. Step 06
After installation of all the columns on the grid, install the 2nd knee bracing,
Knee
B
r
a
c
i
n
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 20 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
H. Step 07
Start installing the column on the other grid and corresponding horizontal bracing as
shown,
Column
Horizontal Bracing
I. Step 08
Start installing the column on the other grid and corresponding horizontal bracings
sequentially as shown,
Installed 2nd
column
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 21 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
J. Step 09
K. Step 10
Start installing the horizontal bracings on top side,
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 24 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 25 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
L. Step 11
Once all the columns and horizontal bracings are installed, start installation of
secondary beams,
Secondary beam
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 26 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
All the secondary beams are installed and put into place.
M. Step 12
Install the angle bracings, sequential methodology are as shown,
Angle bracings
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 27 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
After all the structures are installed, install the top horizontal beam as shown above.
N. Beam clamps will be safer in lifting operations than the chain slings, and always inspect
beam clamps and accessories before use and before placing them into storage.
O. Ensure the supporting structure is adequate for the full load that will be imposed and
suitable for the application.
P. Check the clamp is of the correct profile and size, or correctly adjusted, for the beam
width and that it seats correctly on the beam flange.
Q. Ensure the beam clamp is strong enough for the full load that will be imposed.
R. Check that the clamp is directly fixed on the center of gravity of the load.
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 29 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
In the design, the shim plate thickness is considered as 12mm. In case if required to adjust
the height, 12mm plate can be removed & lowered and maximum of 30mm plate can
be inserted to achieve an increased height of 18mm. Height adjustment can be
maintained in between (-) 12mm to (+) 18mm as per the approved drawing (00311-GCC-
ST-R4-DW-X-00105) Rev P00
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 30 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
SHIM PLATE
10. Attachments
Appendix “A” - HSE Risk Assessment
Appendix “B” - Inspection and Test Plan (ITP)
Appendix “C” – Check list (CHL)
Appendix “D” – Shop drawing (SD)
Appendix “E” – Quality Risk Register (QRA)
Appendix “F” – Gantry’ Design approval of Third-Party (BV)
Appendix “G” –Crane Arrangement Plan
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 32 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
APPENDIX “A”
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
05 Traffic Diversions / • Moving Vehicles Personal Injury 4 3 12 • Pre-task briefings shall be conducted on Road 4 1 4 Project
Installation of Road • Plants / Machineries Property Safety Awareness. Engineer,
Detours maneuvering damage • All Personnel safety inducted. Project HSE
• Poor visibility / lighting Traffic • Competent supervision must be available full
Manager,
• Adverse weather incidents time.
• ITC Permits shall be requested and obtained Logistics team,
• Vehicle collisions
and understood prior to planning the activity Site Engineer,
which require Road Detours. /Safety Officer &
• Adequate resources as per ITC permit Foreman
requirements shall be arranged prior to starting
road detours.
• Standard practices shall be followed while
placing road detours.
• Road detours shall be fixed as per ITC Permit
requirements.
• All personnel involved in the activity must wear
mandatory PPEs. Hi viz vests shall be in good
condition.
• TMA Vehicle shall be placed before starting
activity on the required areas.
• All flashers, safety cones, signboards shall be
in good condition and visible.
• During installation, ITC permit drawing
requirements must be considered.
• REF: COP 33.0 Working near live roads, Work Zone
Traffic Management Manual
06 Assembly of Cranes / • Crane failure / Personal injury 4 3 12 • Assembly operations to be supervised by 4 1 4 Mechanic, Crane
Crane Installation overturn Property trained / competent persons Operator, Site
• Failure of lifting damage • Cranes used for assembly to have valid 3rd Engineer,
equipment Adverse party inspection certification
/Safety Officer &
• Rigging Environmental • Use Licensed / 3rd party certified crane
operators only Foreman
• Equipment & impact
Material • All lifting equipment shall be 3rd party
Handling inspected and certified as fit for purpose
• Potential Works • All rigging activities shall be conducted by
at height trained and 3rd party certified rigger
• Diesel / Oil • Lifting tackle color coded
Spillages • Crane set up on firm and level ground
• Load pads under all outriggers (where
• Adverse weather
applicable)
• Poor Lighting /
• Lift plan established for all lifting operations
Visibility
• Selection of correct crane for task (SWL etc.).
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
records.
• Selection of correct crane for task (SWL etc.).
• Weights of loads known before lifting
• Exclusion zones created around lifting
operations.
• Daily pre use checks by operator recorded
• No work in strong winds (38km/h) or poor
visibility.
• Specific lift paths will be created to avoid any
overhead lifting and whistle mans used to avoid
and alert any personnel coming under the load.
• Tag lines used for all lifting activities
• Training & Supervision
• No onsite works without lifting supervisor.
• Pre-Work briefings / Tool box Talks
• Selection and use of appropriate PPE in
accordance with project minimum standards.
• Install anemometers to check wind speed on
cranes / site
• Crane supervisor authorized to suspend all lift
operations project wide.
REF: COP 34.0 Safe use of Lifting Equipment and Lifting
Accessories.
08 Man, Machine • Vehicle & Personal Injury • Ensure Approved Method Statement and Risk Construction
Interface Machinery Property Damaged Assessment are in place Manager,
Movement Fire • Wear PPEs (Cover all, High visibly jacket, hard Project
• Physical hazard. hat, Safety Goggle, safety Shoe) (As per area Engineer,
• Struck by machinery. requirement). Project HSE
• Over speeding. • All drivers must be holders of valid UAE driving
4 4 16 1 4 4 Manager, Site
• Careless operation. License.
•
Engineer,
• Incompetent drivers/ All equipment should have
/safety Officer &
workers/Operators. Registration/operators 3RD party certificate and
license. Foreman
• Proper signage’s and barricading in place.
• Road Safety Procedure to be strictly adhered.
• Appropriate Fire Extinguisher (DCP) shall be
available on all vehicles/equipment and in site
in an easily accessible location.
• Ensure effective supervision and conduct
inspection.
• Vehicle to be inspected for safety.
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
11 Forklift Operation • Falling load from Physical 3 4 12 • Valid 3rd Party inspection certificate for 1 4 4 Construction
forks injury due forklift Manager,
• Low clearance from to fall of • Forklifts to be used in strict accordance with Project
the new bridge deck material manufacturer’s guidelines (SWL not to be Engineer,
slab Fatality exceeded) Project HSE
• Incorrect machine for Personal • No travelling with forks raised.
Manager, Site
the job injury. • No raising/lowering forks with/without loads
• Overloading of the Crush when on sloping or uneven surfaces;
Engineer,
forklift injuries. • Audible reversing alarm and flashing amber /Safety Officer &
• Obstructed view due to Damage to beacon to be fitted Foreman
property. • Access to all loading/off-loading points will
the special lifting frame
Equipment damage. be levelled, suitable and clear of obstruction.
• Forklifts must be accompanied by a
trained/competent banksman at all times
when moving around the site
• Keys will be removed and the machine
locked when left unattended. Under no
circumstances will fork lift trucks be operated
by an unauthorised person.
• All overhead obstructions including cables
will be identified and protected where
necessary
• The location of the overhead services would
be discussed in the Toolbox.
• Provide warning signage for overhead
hazard, lifting in progress and Men at work
around the work area.
• Guidance to be provided to the operators
and Forklifts must be accompanied by a
trained/competent banksman at all times
when moving around the site
• To ensure that the machine used are 3rd
party certified.
• Inspect that the machine is free from any
damages, leakages etc
• Ensure to check the maintenance checklist
of the forklift
• Ensure that the proper warnings are in working
condition
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
12 Working near /Over • Mechanical Fatalities/ Major 4 4 16 • Approved traffic diversion shall be prepared 1 4 4 Construction
the Live traffic Breakdowns of injury, Property and ready for use before start the work. Manager,
vehicles/TMA on live damages • Ensure that catch net or mesh is provided Project
traffic roads can lead around the live traffic area to prevent any Engineer,
to collision Vehicle collision material from falling on to the road. Project HSE
• Noncompliance with • Prepare the traffic diversion as per approved
the approved traffic
Manager, Site
drawings.
layout drawing • Ensure all the traffic measures are in place
Engineer,
• Not meeting the before start the work. /Safety Officer &
design and • Ensure that no worker crosses the road. Foreman
requirements in • Ensure all workers are working in
diversion road designated working zone.
construction and use • Call Dubai RTA for help in case of traffic
of traffic devices. closures as per approved NOC.
• Diversions in visibility • Ensure that a coned-off safety zone exits
restricted areas around the work.
(sudden approach to • Ensure that the required safety warning
diversion) signboards and flagman are provided to alert
• Collision while entering / slowdown the oncoming traffic.
and exiting to works • Crossing the live highways is strictly
prohibited.
• Adequate reflective clothing / jacket must be
worn by all team members.
• In case of any site accident –Police -999 and
Ambulance 992 to be contacted during
external Emergency situation.
• All key personal contact Tel are contacted
as per protocol.
• All the team members shall be inducted and
aware of legal requirements, procedures.
• Competent supervision must be in place
•
13 Working at Height • Untrained workers Personal Injury 5 1 5 • Competent supervision 1 4 4 Construction
• Fall of men / Property damage • SWL shall be followed or maximum 2 personnel Manager,
materials Musculoskeletal with materials can go in man lift. Project
• Man Lift Failures disorder • Manlift shall be 3rd party certified. Engineer,
• Struck by overhead Fatality • Manlift operator shall be 3rd party certified and Project HSE
structures competent to operate the manlift. Manager, Site
• Man lift overturning • Only trained and authorized personnel can
Engineer,
• Rigging enter and operate man lift.
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
• Inadequate traffic flow Confusion, missed • -Designate safe pedestrian routes illuminated
management leading to directions with proper lighting.
congestion or delays • Provide illuminated signage and markings for
during the night shift
pedestrian crossings and walkways.
• Insufficient
• -Implement temporary traffic control measures,
communication between
workers, drivers, and such as detours or alternate routes, to minimize
traffic control during the traffic disruptions.
night shift • Monitor and adjust traffic management
strategies as needed.
• Establish clear communication protocols and
provide training on effective communication
within the work zone.
• Use proper communication devices (e.g., radios,
illuminated hand signals).
• Use illuminated signage to indicate traffic
patterns, lane closures, and detours.
• \Ensure illuminated signs are placed at proper
heights and angles for maximum visibility.
• Minimize distractions within the work zone by
restricting nonessential activities and
maintaining a well-lit, organized work area.
• Educate workers and drivers on focusing on the
road, especially during night shifts.
• Develop and communicate emergency response
procedures to all workers and ensure they are
familiar with emergency contact information.
• Ensure illuminated emergency access points are
clear and easily visible.
15 Check and repair •
Hot engine, engine 3 3 9 • Trained mechanic, safety induction & TBT shall 1 3 3 Mechanic , Site
engine parts of oils, manifolds, be provided Engineer,
vehicle, oil change, radiator. • Ensure that engine is switch off /safety Officer &
lubrication for plant • Sharp edges & parts • Only trained/ competent person to carry out Foreman
and equipment of the engine. maintenance works
• Unprotected rotating • Ensure that all rotating parts of the engine are
parts, blades, fan belts. Oil properly guarded.
• Do not remove radiator caps when extremely
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
22 Moving vehicles & • Poorly maintained injuries to workers 4 3 12 • Ensure Plant/equipment have valid operating 3rd
Plant/Equipment plant/equipment and property party Certificates
• Toppling of equipment damaged • Ensure the plant are properly outrigged to
• Hit by equipment prevent toppling or turning over.
• Ensure area is clear for plant operator.
Construction
• Check the maintenance records of all
Manager, Project
plant/equipment prior to use
Engineer, Project
• Make sure reverse alarm is working properly 1 3 3
HSE Manager, Site
• Banksman shall present at site to guide the
Engineer, /safety
operator
Officer & Foreman
• Nobody is allowed to work close to the running
heavy equipment.
• Always stop the equipment to a complete halt,
stop the engine and remove the ignition key
before descending from the equipment.
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
Gulf contractors (L&D) CO. LLC
Risk Assessment for Erection of Temporary Steel Support Towers (Gantry) for Bridges Girders Installation
Project Name: Design and build contract for cycle track- Route 3 & 4 Contractor: GCCLD Consultant: ATKINSREALIS Client: ALDAR
Location Abu Dhabi, UAE Prepare Date: 18-OCT-2024 MS Ref.No: ACTPW-GCC-GN-ZZ-MS-W-00108-P00
Risk Risk
S/ Consequence / Classificati Classifica Responsible
Activity Element Significant potential Hazards on Action to be Taken to Reduce Risk tion
N Impacts Person/Action by
P S R P S R
SEVERITY
PROBABILITY Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent/Almost Certain (5) 5 10 15 20 25
15 – 25 Extreme Risk Absolutely unacceptably High
Activity or process should not proceed in current form
Unacceptably High
8 – 12 High Risk Activity or process should be modified to include remedial planning and action and be subject to detailed OSH/EHS risk assessment
4–6 Moderate Risk Acceptable but must be managed at “As Low As Reasonably Practicable”(ALARP) Activity or process can operate subject to management and /
or modification
1-3 Low Risk Acceptable without required further action
No action required unless escalation of risk is possible
Prepared By: Reviewed By:
Name: Mr. Raheel Ahmad Eng. Ghader Aslani
Designation: OSH Manager Sr. Project Manager
Signature:
Doc No: Form - GCC/RS/02 Issue: A Initial Date: 2016 Revised: 03 Revision date: 2022 OSH Department
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 33 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
APPENDIX “B”
ALDAR PROJECTS
INSPECTION AND TEST PLAN
PROJECT TITLE: DESIGN AND BUILD CONTRACT FOR CYCLE TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE PROJECT NO: P151119/2022/C/008 DATE: 18 Oct 2024
CLIENT/ PMC: ALDAR PROJECTS CONSULTANT: ATKINSREALIS DOC. REF: ACTPW-GCC-GN-ZZ-ITP-C-00108
CONTRACTOR: GULF CONTRACTORS COMPANY (GCCLD) MANUFACTURER: HADED STEEL REV NO: REV-P00
SUBCONTRACTOR: KABRI INT. PREPARED BY: KABRI INT. ITP NO: ACTPW-GCC-GN-ZZ-ITP-C-00108
DESCRIPTION: INSPECTION AND TEST PLAN (ITP) FOR INSTALLATION OF TEMPORARY SUPPORT TOWERS-GANTRIES AT BRIDGE DISCIPLINE: CIVIL/Installation of Supporting
APPROVED BY: ATKINSREALIS
#1 PIERS & ABUTMENTS FOR CYCLE TRACK ROUTE 3 Towers (Gantries)
1.4 Approval of Method statements Approval Engineer’s Approval SD, MS, MSS, ITP, RA Specs, Drawings A R/W p
2.0 Fabricated of Gantry Pre Engineering Steel Structure
Page 1 of 2
ALDAR PROJECTS
INSPECTION AND TEST PLAN
PROJECT TITLE: DESIGN AND BUILD CONTRACT FOR CYCLE TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE PROJECT NO: P151119/2022/C/008 DATE: 18 Oct 2024
CLIENT/ PMC: ALDAR PROJECTS CONSULTANT: ATKINSREALIS DOC. REF: ACTPW-GCC-GN-ZZ-ITP-C-00108
CONTRACTOR: GULF CONTRACTORS COMPANY (GCCLD) MANUFACTURER: HADED STEEL REV NO: REV-P00
SUBCONTRACTOR: KABRI INT. PREPARED BY: KABRI INT. ITP NO: ACTPW-GCC-GN-ZZ-ITP-C-00108
DESCRIPTION: INSPECTION AND TEST PLAN (ITP) FOR INSTALLATION OF TEMPORARY SUPPORT TOWERS-GANTRIES AT BRIDGE DISCIPLINE: CIVIL/Installation of Supporting
APPROVED BY: ATKINSREALIS
#1 PIERS & ABUTMENTS FOR CYCLE TRACK ROUTE 3 Towers (Gantries)
Page 2 of 2
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 34 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
APPENDIX “C”
DESIGN AND BUILD CONTRACT FOR CYCLE TRACK- ROUTE 3 & 4 IN ABU DHABI,
PROJECT TITLE:
UNITED ARAB EMIRATES
CLIENT/EMPLOYER: ALDAR PROJECTS
CONSULTANT: ATKINS
CONTRACTOR: Gulf Contractors Company (GCCLD)
CONTRACT NO.: P151119/2022/C/008
SUBCONTRACTOR: KABRI INTERNATIONAL
APPLICATOR: HADEED STEEL
Checklist Title: Erection of Temporary Steel Support Towers for Bridge #1 at Route #3
Checklist No. ACTPW-GCC-EW-ZZ-CHL-W-00108 Discipline: Civil
Works Location:
Status/Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
1.0 Prior Activities / Documents & Certifications:
1.1 Obtained NOC from related authorities
1.2 Obtain Permit & Coordination with Traffic Department
1.3 Acceptance of Sketches drawing for Positioning of Crane
1.4 Approval of Method statements
2.0 Materials Approvals
2.1 Approved Concrete Mix Design
2.2 Approved Reinfocement Steel
2.3 Approval of Gantry Design by third Party
3.0 Setting out and Survey Works
3.1 Check and Ensure Referance Point/Bench Marks are Verified
3.2 Check & ensure the Co-ordinates & Elevations are Checked & accurate
3.3 Check and ensure the Calibration of the instruments are Checked and valid
3.4 Check and ensure the Drawing & Survey Data are Attached.
4.0 Erection of Temporary Steel Support Towers for Bridges
4.1 Check and Ensure Cranes are Positioned as Shown in Accepted Skitch Drawing
4.2 Check and Ensure All safety Parameter has been applied.
4.3 Check and Ensure the Center of Gravity of Girder During uplifting elements are marked
Check and Ensure Cranes are Third Party Certified, Slings are Certified, All Safety Requirements
4.4
are applied
4.5 Check and Ensure Hooks are Properly installed to the Girder Prior to lifting
4.6 Check and Ensure to Gradually Up lift the elements in Control Manner
4.7 Check and Ensure to Control the Swing the Load Safely, Slowly and Gradually.
4.8 Make sure Propper Coordination in-between Crane operator, Riggers and Traffic Control Team
4.9 Check and Ensure Proper placement of Gantry Elements at required location.
General Comments/Remarks:
Signatures
Date
Works Location:
Status/Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
1.0 Prior Activities
1.1 Approved NOC Authority Approval
1.2 Approved Prequalification
1.3 Approved Method Statements
1.4 Approved Shop Drawings
1.5 Equipment Calibration certificates
2.0 Materials Approvals
2.1 Approved Concrete Mix Design
2.2 Approved Reinfocement Steel
2.3 Approval of Gantry Design by third Party
3.0 Cast in Situ Concrete for Gantry Foundations
3.1 Pre-Pour Inspection
3.1.1 Check & Ensure Moulds are fixed, dimensions checked, must be in tollarance, (±5mm)
3.1.2 Check & Ensure Angular distortion of mould not more than 7mm overall
3.1.3 Check & Ensure Reinforcement & Dowel bars placement are Correct.
3.1.4 Check & Ensure Formwork and support are adequate.
3.1.5 Check & Ensure Placement of embedded are as per drawing.
3.1.6 Check & Ensure the alignment for Installation of form and Shutters.
3.1.7 Check & Ensure the Release Agent applied on mold but not on rebars
3.1.8 Check & Ensure the Rebar Clear Cover as per drawing to rebar
3.2 Concrete Casting Inspection
3.2.1 Check & Ensure the Mix design utilization and monitor Concrete Pour record
3.2.2 Check & Ensure Concrete placement, workmanship are as per Standard.
3.2.3 Check & Ensure Concrete slump and temperature found satisfactory
Check & Ensure Proper usage of Vibrator, avoid segregation of Concrete, Ensure adequate
3.2.4
Compaction of Concrete.
Check & Ensure the Concrete mix temperature at pouring shall not exceed 32°C as measured
3.2.5
immediately prior to placement.
Check for stripping of Form work / Supports etc, after specified duration of stripping time (as
3.2.6
per specification)
3.3 Post Pour Inspection
3.3.1 Ensure proper and Safe Removal of Mold & Shutters
3.3.2 Check and ensure proper Level & alignments of pre-casted Panles
3.3.3 Check and ensure Curing has been done continuously for 14 days as per Panles
3.3.4 Visual inspection of surface appearance
3.3.5 Check & Ensure Concrete filled to concrete level
3.3.6 Check & Ensure Proper Curing for Concrete
3.3.7 Surface defects if any, are identified and rectified to the acceptance of consultant
General Comments/Remarks:
Signatures
Date
APPENDIX “D”
100
KEY PLAN
Millimetres
6 5 4 3 2 1
10
0
DRAWING STATUS
C SHOP DRAWING
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-01
NODE PLAN & JOINT REACTIONS
Original Scale: Drawn: Checked: Size
RH AH
NTS Approved: Date:
27-SEP-2024
A1
AT
DATE:
KEY PLAN
6 5 4 3 2 1
Millimetres
D
10
0
D
TYPICAL BASE CONNECTION FOR
SHS180x180x6
E
E
E
E
C
REV.NO DATE DESCRIPTION STATUS
P00 27-SEP-2024 SUBMITTED FOR APPROVAL
B
DRAWING STATUS
SHOP DRAWING
PROJECT TITLE
EMPLOYER/ DEVELOPER
C
ANCHOR BOLT PLAN
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-01
SECTION D-D SECTION C-C ANCHOR BOLT PLAN & DETAILS
TYPICAL ADDITIONAL REINFORCEMENT
TYPICAL BASE CONNECTION FOR Original Scale: Drawn: Checked: Size
UNDER COLUMNS HEA260, HEA240, SHS180X180X6 RH AH
HE240A NTS Approved: Date: A1
AT 27-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10114 P00
100
KEY PLAN
B' B B' C
A B C A
Millimetres
DET-B
DET-B
10
0
DET-A DET-A
DET-C
DET-C
DET-L
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
2 2
3
5 5
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
SECTION 3-3
3
September 19, 2024
DETAIL-A DETAIL-B
Tel.: +971 6 76 72 76 1/2/3/4
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-01
ELEVATION AT GRID-1,6&DETAILS
SECTION 2-2 DETAIL-C SECTION 4-4 SECTION 5-5 Original Scale: Drawn: Checked: Size
SECTION 1-1 NTS
RH
Approved: Date:
AH
A1
AT 27-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10115 P00
100
KEY PLAN
Millimetres
DET-M
DET-K
DRAWING STATUS
SHOP DRAWING
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
2
1
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
3
5 1
2 2 4 4
5 1 3
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
DETAIL-M SECTION 5-5 DETAIL-K SECTION 1-1 DETAIL-L SECTION 2-2 DETAIL-K SECTION 1-1 SECTION 2-2 DETAIL-L SECTION 3-3 SECTION 4-4 ABUTMENT-01
ELEVATION AT GRID-2 TO 5 & DETAILS
Original Scale: Drawn: Checked: Size
RH AH
(TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) (TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) NTS Approved: Date: A1
AT 27-SEP-2024
(OPTION 01) (OPTION 01) (OPTION 02) (OPTION 02)
DATE:
00235-GCC-TW-R3-DW-X-10116 P00
100
KEY PLAN
Millimetres
10
A A A A
6 5 4 3 2 1 6 5 4 3 2 1
0
DET-N
DET-N
DRAWING STATUS
B B SHOP DRAWING
6 5 4 3 2 1 PROJECT TITLE
16.07.2024
5 5 5 5 EMPLOYER/ DEVELOPER
SUB CONTRACTOR
3
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
1 4
2 2
1 1 1 1 1
1 1
September 19, 2024
4
1 DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-01
SIDE VIEWS AT AXIS-B, B',C & DETAILS
Drawn:
SECTION 1-1 DETAIL-C SECTION 2-2 SECTION 3-3 SECTION 4-4 DETAIL-D SECTION 1-1 DETAIL-N SECTION 1-1 Original Scale:
RH
Checked:
AH
Size
KEY PLAN
Millimetres
6 5 4 3 2 1
10
0
DET-G DET-H
B'
DET-J
SECTION A-A
4 SHOP DRAWING
3
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
3 4 TELEPHONE
FAX
+971 26271500
+971 26270999
EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
SUB CONTRACTOR
1 2
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
B'
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
SECTION B-B 1 2 ABUTMENT-01
SECTIONS&DETAILS
00235-GCC-TW-R3-DW-X-10118 P00
100
KEY PLAN
Millimetres
10
0
K'
DRAWING STATUS
M SHOP DRAWING
PROJECT TITLE
MAIN CONTRACTOR
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-02
NODE PLAN & JOINT REACTIONS
Original Scale: Drawn: Checked: Size
RH AH
NTS Approved: Date:
27-SEP-2024
A1
AT
DATE:
00235-GCC-TW-R3-DW-X-10119 P00
100
KEY PLAN
Millimetres
C
10
0
K'
L
C
E
E
TYPICAL BASE CONNECTION FOR
SHS180x180x6
E
E
D
DRAWING STATUS
SHOP DRAWING
PROJECT TITLE
M CLIENT
EMPLOYER/ DEVELOPER
6 5 4 3 2 1 MAIN CONTRACTOR
SECTION E-E
ANCHOR BOLT PLAN
D
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-02
SECTION D-D SECTION C-C ANCHOR BOLT PLAN & DETAILS
TYPICAL ADDITIONAL REINFORCEMENT
TYPICAL BASE CONNECTION FOR Original Scale: Drawn: Checked: Size
UNDER COLUMNS HEA260, HEA240, SHS180X180X6 RH AH
HE240A NTS Approved: Date: A1
AT 27-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10120 P00
100
KEY PLAN
Millimetres
K K' L M K K' L M
DET-B
DET-B
DET-A DET-A
10
0
DET-C DET-C
DET-L
DET-L
DRAWING STATUS
SHOP DRAWING
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
2 2
3
5 5
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
SECTION 3-3
3
September 19, 2024
DETAIL-B
Tel.: +971 6 76 72 76 1/2/3/4
DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-02
ELEVATION AT GRID-1,6&DETAILS
SECTION 2-2 DETAIL-C SECTION 4-4 SECTION 5-5 Original Scale: Drawn: Checked: Size
SECTION 1-1 NTS
RH
Approved: Date:
AH
A1
AT 27-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10121 P00
100
KEY PLAN
Millimetres
K K' L K K' L
K K' L K K' L
10
0
DET-M DET-M
DET-K
DRAWING STATUS
SHOP DRAWING
16.07.2024
PROJECT TITLE
ELEVATION VIEW @ GRID -2 ELEVATION VIEW @ GRID -3 ELEVATION VIEW @ GRID -4 ELEVATION VIEW @ GRID -5 CONSULTANCY SERVICES FOR STUDY AND
DESIGN OF ABU DHABI CYCLING NETWORK
- MAINLAND ABU DHABI (202200235)
CLIENT
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
2
1
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
3
5 1
2 2 4 4
5 1 3
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
DETAIL-M SECTION 5-5 DETAIL-K SECTION 1-1 DETAIL-L SECTION 2-2 DETAIL-K SECTION 1-1 SECTION 2-2 DETAIL-L SECTION 3-3 SECTION 4-4 ABUTMENT-02
ELEVATION AT GRID-2 TO 5&DETAILS
Original Scale: Drawn: Checked: Size
RH AH
(TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) (TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) NTS Approved: Date: A1
AT 27-SEP-2024
(OPTION 01) (OPTION 01) (OPTION 02) (OPTION 02)
DATE:
00235-GCC-TW-R3-DW-X-10122 P00
100
KEY PLAN
Millimetres
10
6 5 4 3 2 1 6 5 4 3 2 1
0
C C C C
DET-N DET-N
DRAWING STATUS
SHOP DRAWING
6 5 4 3 2 1 16.07.2024
PROJECT TITLE
5 5 5
5 EMPLOYER/ DEVELOPER
SUB CONTRACTOR
3
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
1 4
2 2
1 1 1 1 1
1 1
September 19, 2024
4
1 DRAWING TITLE
ROUTE 03 - BRIDGE 01
ABUTMENT-02
SIDE VIEWS AT AXIS-K, K' ,L&DETAILS
Drawn:
SECTION 1-1 DETAIL-C SECTION 2-2 SECTION 3-3 SECTION 4-4 DETAIL-D SECTION 1-1 DETAIL-N SECTION 1-1 Original Scale:
RH
Checked:
AH
Size
KEY PLAN
DET-H
DET-G
Millimetres
F
10
0
F'
DET-J
6 5 4 3 2 1
SECTION C-C
F' 3
DRAWING STATUS
4 SHOP DRAWING
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
3 4 TELEPHONE
FAX
+971 26271500
+971 26270999
EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
SUB CONTRACTOR
2
1
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
6 5 4 3 2 1
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
1 2 ABUTMENT-02
SECTION D-D SECTIONS&DETAILS
00235-GCC-TW-R3-DW-X-10124 P00
100
KEY PLAN
Millimetres
10
0
E'
F
REV.NO DATE DESCRIPTION STATUS
00 28-SEP-2024 SUBMITTED FOR APPROVAL
DRAWING STATUS
6 5 4 3 2 1
SHOP DRAWING
PROJECT TITLE
EMPLOYER/ DEVELOPER
NODE PLAN
FAX +971 26270999
EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 01
NODE PLAN & JOINT REACTIONS
Original Scale: Drawn: Checked: Size
RH AH
NTS Approved: Date:
28-SEP-2024
A1
AT
DATE:
00235-GCC-TW-R3-DW-X-10125 01
100
KEY PLAN
Millimetres
A
10
0
E'
F
A
6 5 4 3 2 1
DRAWING STATUS
SHOP DRAWING
ANCHOR BOLT PLAN PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
SECTION A-A
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 01
ANCHOR BOLT PLAN & DETAILS
TYPICAL ADDITIONAL REINFORCEMENT
TYPICAL BASE CONNECTION FOR Original Scale: Drawn: Checked: Size
UNDER COLUMNS HEA260, HEA240, RH AH
HE240A NTS Approved: Date: A1
AT 28-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10126 01
100
KEY PLAN
E E' F E E' F
Millimetres
DET-A DET-A
10
0
DET-C DET-C
DET-L DET-L
SHOP DRAWING
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
3
ABU DHABI MALL,
WEST TOWER, 3rd FLOOR,
P O BOX 7562, ABU DHABI
UNITED ARAB EMIRATES
1 TELEPHONE
FAX
+971 26271500
+971 26270999
1 EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
2 2
4
5 5
SUB CONTRACTOR
SECTION 1-1
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
4
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 01
ELEVATION AT GRID-1,6&DETAILS
DETAIL-A SECTION 2-2 SECTION 3-3 DETAIL-C SECTION 4-4 SECTION 5-5 Original Scale: Drawn:
RH
Checked:
AH
Size
00235-GCC-TW-R3-DW-X-10127 01
100
KEY PLAN
Millimetres
E E' F
E E' F E E' F E E' F
10
0
DRAWING STATUS
SHOP DRAWING
16.07.2024
ELEVATION VIEW @ GRID -4 ELEVATION VIEW @ GRID -3 ELEVATION VIEW @ GRID -2 PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
4
2
1
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
3
5 1
5
2 2 4 4
1 3
4
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
DETAIL-B SECTION 4-4 DETAIL-K SECTION 1-1 DETAIL-L SECTION 2-2 DETAIL-K SECTION 1-1 SECTION 2-2 DETAIL-L SECTION 3-3 SECTION 4-4 PIER01-NEAR TO ABUTMENT 01
ELEVATION AT GRID-2 TO 5 & DETAILS
Original Scale: Drawn: Checked: Size
RH AH
(TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) (TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) NTS Approved: Date: A1
AT 28-SEP-2024
(OPTION 01) (OPTION 01) (OPTION 02) (OPTION 02)
DATE:
00235-GCC-TW-R3-DW-X-10128 01
100
KEY PLAN
Millimetres
10
A A A A
6 5 4 3 2 1 6 5 4 3 2 1
0
DET-N DET-N
DRAWING STATUS
SHOP DRAWING
6 5 4 3 2 1 16.07.2024
PROJECT TITLE
5 5 5 5 EMPLOYER/ DEVELOPER
SUB CONTRACTOR
3
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
1 4
2 2
1 1 1 1 1
1 1
September 19, 2024
4
1 DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 01
SIDE VIEWS AT AXIS-E, E',F&DETAILS
Drawn:
SECTION 1-1 DETAIL-C SECTION 2-2 SECTION 3-3 SECTION 4-4 DETAIL-D SECTION 1-1 DETAIL-N SECTION 1-1 Original Scale:
RH
Checked:
AH
Size
KEY PLAN
Millimetres
DET-G
DET-H
10
E
0
DET-J
E'
6 5 4 3 2 1
SECTION A-A
DRAWING STATUS
4 SHOP DRAWING
3
16.07.2024
E' PROJECT TITLE
EMPLOYER/ DEVELOPER
6 5 4 3 2 1
FAX +971 26270999
EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
SUB CONTRACTOR
1 2
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
1 2 PIER01-NEAR TO ABUTMENT 01
SECTIONS&DETAILS
00235-GCC-TW-R3-DW-X-10130 01
100
KEY PLAN
Millimetres
10
0
G'
DRAWING STATUS
SHOP DRAWING
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
NODE PLAN
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 02
NODE PLAN & JOINT REACTIONS
Original Scale: Drawn: Checked: Size
RH AH
NTS Approved: Date:
28-SEP-2024
A1
AT
DATE:
KEY PLAN
Millimetres
10
0
G'
DRAWING STATUS
6 5 4 3 2 1 SHOP DRAWING
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
SECTION A-A
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 02
ANCHOR BOLT PLAN & DETAILS
TYPICAL ADDITIONAL REINFORCEMENT
TYPICAL BASE CONNECTION FOR Original Scale: Drawn: Checked: Size
UNDER COLUMNS HEA260, HEA240, RH AH
HE240A NTS Approved: Date: A1
AT 28-SEP-2024
DATE:
00235-GCC-TW-R3-DW-X-10132 01
100
KEY PLAN
G G' H G G' H
Millimetres
DET-A
DET-A
10
0
DET-C
DET-C
DET-L
DET-L
DRAWING STATUS
EMPLOYER/ DEVELOPER
3
ABU DHABI MALL,
WEST TOWER, 3rd FLOOR,
P O BOX 7562, ABU DHABI
UNITED ARAB EMIRATES
1 TELEPHONE
FAX
+971 26271500
+971 26270999
1 EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
2 2
4
5 5
SUB CONTRACTOR
SECTION 1-1
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
4
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 02
ELEVATION AT GRID-1,6 & DETAILS
DETAIL-A SECTION 2-2 SECTION 3-3 DETAIL-C SECTION 4-4 SECTION 5-5 Original Scale: Drawn:
RH
Checked:
AH
Size
00235-GCC-TW-R3-DW-X-10133 01
100
KEY PLAN
Millimetres
DRAWING STATUS
SHOP DRAWING
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
MAIN CONTRACTOR
4
2
1
SUB CONTRACTOR
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
3
1
5 5
2 2 4 4
1 3
4
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
DETAIL-B SECTION 4-4 DETAIL-K SECTION 1-1 DETAIL-L SECTION 2-2 DETAIL-K SECTION 1-1 SECTION 2-2 DETAIL-L SECTION 3-3 SECTION 4-4 PIER01-NEAR TO ABUTMENT 02
ELEVATION AT GRID-2 TO 5 & DETAILS
Original Scale: Drawn: Checked: Size
RH AH
(TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) (TYPICAL SPLICE CONNECTION FOR HE260A) (TYPICAL SPLICE CONNECTION FOR HE240A) NTS Approved: Date: A1
AT 28-SEP-2024
(OPTION 01) (OPTION 01) (OPTION 02) (OPTION 02)
DATE:
00235-GCC-TW-R3-DW-X-10134 01
100
KEY PLAN
Millimetres
10
6 5 4 3 2 1 6 5 4 3 2 1
0
C C C C
DET-N DET-N
DRAWING STATUS
SHOP DRAWING
16.07.2024
6 5 4 3 2 1 PROJECT TITLE
5 5 5 5 EMPLOYER/ DEVELOPER
SUB CONTRACTOR
3
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
1 4
2 2
1 1 1 1 1
1 1
September 19, 2024
4
1 DRAWING TITLE
ROUTE 03 - BRIDGE 01
PIER01-NEAR TO ABUTMENT 02
SIDE VIEWS AT AXIS-G, G',H & DETAILS
Drawn:
SECTION 1-1 DETAIL-C SECTION 2-2 SECTION 3-3 SECTION 4-4 DETAIL-D SECTION 1-1 DETAIL-N SECTION 1-1 Original Scale:
RH
Checked:
AH
Size
KEY PLAN
Millimetres
10
0
DET-G
DET-H
G'
DET-J
6 5 4 3 2 1
SECTION C-C
DRAWING STATUS
4 SHOP DRAWING
3
16.07.2024
PROJECT TITLE
EMPLOYER/ DEVELOPER
3 4 TELEPHONE
FAX
+971 26271500
+971 26270999
EMAIL [email protected]
Copyright C Atkins Limited
MAIN CONTRACTOR
G'
SUB CONTRACTOR
1 2
FILE NAME: J365-ABUTMENT 01 STEEL DRAWINGS-R00
September 19, 2024
DRAWING TITLE
ROUTE 03 - BRIDGE 01
SECTION D-D 1 2 PIER01-NEAR TO ABUTMENT 02
SECTIONS&DETAILS
00235-GCC-TW-R3-DW-X-10136 01
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 36 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
APPENDIX “E”
Project Title: DESIGN AND BUILD CONTRACT FOR CYCLE TRACK- ROUTE 3 & 4 IN ABU DHABI, UNITED ARAB EMIRATES
Contract: P151119/2022/C/008
Employer: ALDAR PROJECTS
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI INTERNATIONAL
APPLICATOR: HADEED STEEL
Doc Title: QUALITY RISK ASSESSMENT REGISTER
Reference No: ACTPW-GCC-GN-ZZ-QRA-W-00108-P00 Page#: 1
QUALITY RISK ASSESSMENT MATRIX FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRY) FOR BRIDGE #1 FOR PRECAST GIRDERS INSTALLATION OF CYCLE TRACK ROUTE 3
Past After mitigation
Prior Mitigation Action Effect
Occurrence Risk Risk Action plan Residual
No. Description of Risk Mitigation Actions Responsibility Remarks
Type Rating LT/MT/ST Severity Risk
Yes/No Severity (R) Probability Probability
(R)
QUALITY RISK DIRECT
1. Engagement of competent supervisor Production of
Deviation from specification coordinated shop drawings and obtaining approval from
and/or approved drawings engineer prior to execution of works. Project based
A1 Yes Internal Major Often 16 LT 2. Provision of trainings to supervisor and execution staff prior Major Rare 4
management
to start of works.
3. Use of control forms for inspection & approval
Severity
Probability
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Rejection of completed works (5) 5 10 15 20 25
4-6 Moderate Risk Acceptable but must be managed at 'As low as reasonably practicable'
APPENDIX “F”
Design is Under Review by Third-Party (BV)
DESIGN AND BUILD CONTRACT FOR CYCLE
Project Title:
TRACK- ROUTE 3 & 4 IN ABU DHABI, UAE
Contract: P151119/2022/008
Employer: ALDAR PROPERTIES
Engineer: ATKINSREALIS
Contractor: GULF CONTRACTORS COMPANY (GCCLD)
Subcontractor KABRI International Cont. LLC
Applicator: Hadeed Steel
Ref. No: ACTPW-GCC-EW-ZZ-MS-W-00108-P00 Ref: KP0136-KIC-GCC-MS-036 Date: 18th Oct-2024 Page 38 of 38
METHOD STATEMENT FOR ERECTION OF TEMPORARY STEEL SUPPORT TOWERS (GANTRI) FOR BRIDGE#1 AT ROUTE #3
APPENDIX “G”