Resource Labor Allocation
Resource Labor Allocation
Activity ID Activity Name Resource ID Name Start Finish July 2024 August 2024
07 14 21 28
Resource Type: Labor 28-May-24 A 19-Sep-24 Budgeted Units 150h 300h 310h
Budgeted Cost SAR4,200.00 SAR8,400.00 SAR8,800.00
A1170 Excavation R-31.Surveyor 17-Jul-24 08-Aug-24 Budgeted Units 30h 60h 60h
Budgeted Cost SAR780.00 SAR1,560.00 SAR1,560.00
A1170 Excavation R-32.surveyor helper 17-Jul-24 08-Aug-24 Budgeted Units 30h 60h 60h
Budgeted Cost SAR600.00 SAR1,200.00 SAR1,200.00
A1190 Form Work R-31.Surveyor 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1190 Form Work R-32.surveyor helper 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1190 Form Work R-41.Carpanter 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1190 Form Work R-15.Skilled labor 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1190 Form Work R-16.Site Engineer 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1190 Form Work R-43.Foreman 17-Aug-24 24-Aug-24 Budgeted Units
Budgeted Cost
A1200 Lean Concreat R-15.Skilled labor 25-Aug-24 26-Aug-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-15.Skilled labor 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-41.Carpanter 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-16.Site Engineer 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-43.Foreman 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-31.Surveyor 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
A1210 Form Work R-32.surveyor helper 28-Aug-24 02-Sep-24 Budgeted Units
Budgeted Cost
10h 10h
SAR400.00 SAR400.00
10h
SAR350.00
10h
SAR290.00
10h
SAR270.00
10h
SAR200.00
10h
SAR300.00
10h
SAR200.00
20h
SAR700.00
20h
SAR540.00
20h
SAR700.00
20h
SAR540.00