Endsem Notes 5
Endsem Notes 5
Reference Text:
Supply Demand
Seasonal Peaks
1. Trend
2. Seasonality
3. Cyclical Element
4. Random Variation
Random Variations
Forecasting
■ Forecasting is (scientific) planning tool that helps the process of making predictions of
the future based on past and present data and most commonly by analysis of trends.
■ Quantitative methods
– When historical data exists e.g. for existing product or technology
– The situation is ‘stable’
– Involves mathematical modelling
How reliable/accurate is the forecasts?
■ It assumes that same underlying causal system of the past will persist
■ Forecasts are not perfect, allowances of error should be made
■ Forecasting Error = Actual Value − Forecasted Value
■ Time series observations are recorded at equal intervals (e.g. daily, weakly, monthly or
yearly basis)
■ Time is the one variable which is used to predict the other variable (e.g., sales) of interest.
■ Time series can be plotted on a two dimensional plane where X-axis represents the time
and the Y-axis represents the other variable such as demand or sales.
Associative Forecasting
■ This type of forecasting assumes that one values of one variable is influenced by the
values of another variable in the environment. E.g., Investment in advertisement is
used to predict future sales.
■ At least two different variables (other than time) are used where one variable acts as
predictor variable for the other which is predicted (or forecasted)
Time Series Forecasting Stationary Time Series Indicates:
• Constant Mean
• Constant Variance
• No Trend or Seasonality
■ Simple Moving Average
– Normally done with 6-12 month data,
weekly data are often used,
– Data pattern is stationary (i.e. no trend or
seasonality)
■ Weighted Moving Average & Simple
exponential Smoothing
– 5-10 observations are needed to start,
– Data pattern is stationary
■ Linear Regression
■ Trends and Seasonal Models
Simple Moving Average Method
Weights Period
Applied
3 Last Month
2 Two Months Ago
1 Three Months Ago
Total = 6
F t = α A t-1 + α (1-α) A t-2 + α (1-α)2A t-3 + (1-α)3F t-3 +……..+ (1-α)nF t-n
Impact of Smoothing Constant at Past Values
Choosing α:
The value which gives the lowest forecasting error
Ø H i g h va l u e o f a l p h a i s p r e fe r r e d w h e n
underlying average is likely to change
Ø L o w v a l u e o f a l p h a i s p r e fe r r e d w h e n
underlying average is likely to be stable
Forecasting Error
Compare the Forecasting Error
Compare the Forecasting Error
Computing Forecasting Error with Excel
Step 1: Compute Ft : Make the forecast that is not adjusted for trend, by using
previous forecast and prev. actual demand
Step 2: Compute Tt: Estimate the trend using the previous trend estimate
Step 3: Make new forecast that includes trend by using step 2 & 3.
Exponential Smoothing with Trend
t t-1 t t-1
Example
exponential smoothing trend smoothing
constant constant
Notes about Exponential Smoothing
■ Exponential smoothing should begin several periods back to enable forecasts to adjust to
the data, instead of starting one period back.
■ A number of different approaches can be used to obtain a starting forecast, such as
– the average of the first several periods,
■ using an average of, say, the first three values as a forecast for period 4 would provide a
better starting forecast
– a subjective estimate,
– A naïve approach
■ i.e., the first actual value (of period 1) as the forecast for period 2
Linear Regression Analysis: Trend Equation
■ A functional relationship between two or more correlated variables
■ Used to predict one variable by using the other
Associative Forecasting
Associative Forecasting
Standard Error of the Estimate
y – yc = Forecasting Error
Decomposition of a Time Series
■ Time series is a chronologically ordered data which contains more than one
components of data.
■ When demand has both seasonal and trend component:
■ If the demand in the next year is expected to be 1100 units, compute the demand in
respective quarters
Seasonality: Simple Proportion
Period/ Past Sales Total Average Sales for Each Season Seasonal Factor
Season Sales (Total Sales /Number of Periods)
Period/ Forecasted Total Average Sales for Each Season Seasonal Factor
Season Sales Sales (Total Sales /Number of Periods)
z = Number of
standard deviations
from the mean
Detecting Non-Random Errors
■ Control Charts:
Tracking Signal
■ Detects any bias in errors over time, ie. When a overcast is consistently low or high
■ Indicates whether a forecast average is keeping pace with genuine upward of
downward changes in demand.
■ Demanding customers
– Looking for more than just satisfaction
– More knowledgeable
– Risk of negative reviews
– Liability ■ Business advantages
– High Customer Loyalty
– Positive Recommendation
– High Social Reputation
– Lower Marketing Cost
– Competitive advantage
– Quality is a source of differentiation
Modern Quality Management Gurus
GURUS Key Contributions
W. Edwards Deming Causes of Variation - special cause vs common causes; 14 Points in Quality
Management
Philip Crosby ‘Do it right the first time’; zero defects, ‘quality is free’
■ Performance (e.g., Long battery life, HD pictures, should not heat up, etc. )
■ Aesthetics (e.g., design)
■ Features (e.g., additional functions, GPS, compass, Apps, etc.)
■ Conformance (e.g., adequate storage space, etc.)
■ Reliability (e.g., no sudden reboots/shut down, less numbers of repair etc.)
■ Durability (e.g., it should last for x years without any loss of performance)
■ Perceived Quality or Reputation (e.g., brand, purchased by many, etc.)
■ Serviceability (e.g., easy to repair)
■ Consistency (quality claims doesn’t vary from product to product)
Dimensions of Quality
Service Quality
■ Failure costs:
– Internal failures : Occur during the production process; costs include rework costs,
problem solving, material and product losses, scrap, and downtime
– External failures: Occur after delivery; costs include cost of returned goods, warranty
costs, loss of goodwill, liability claims and penalties.
QUALITY MANAGEMENT
TOOLS
Quality Management Tools
(American Society for Quality)
1. Stratification
2. Fishbone diagram
3. Check Sheets
4. Histogram
5. Pareto chart
6. Scatter diagram
7. Control chart
Stratification
• Stratification: The act of into
.
(American Society for Quality)
• Systematically segregated and sorted data can reveal the patterns for managerial decision making
100
99.8
Process 1 Process 2 Process 3
Input (x) Output (y) Input (x) Output (y) Input (x) Output (y) 99.6
– Equipment
– When data come from several sources or
conditions, such as shifts, days of the week, – Shifts
suppliers, or population groups. – Departments
– Materials
– When data analysis may require separating – Suppliers
different sources or conditions – Day of the week
– Time of day
– Products
Flow Charts
➢ When data can be observed and collected repeatedly by the same person or at the same
location
➢ When collecting data on the frequency or patterns of events, problems, defects, defect
location, defect causes, or similar issues
➢ When collecting data from a production process
Histograms
Use Histograms when you need to know:
• Central Tendency of the distribution
• Variation in the distribution
• Compare the two different
distribution
• If the shape of the distribution is
normal What if there
• if the data is falling in a are two peaks
predetermined pattern
Pareto Charts
■ The assumption:
– Often referred to as the 80–20 rule, the Pareto concept states that
approximately 80 percent of the problems come from 20 percent of the items.
For instance, 80 percent of machine breakdowns come from 20 percent of the
machines, and 80 percent of the product defects come from 20 percent of the
causes of defects.
■ When to use pareto Chart:
– When analyzing data about the frequency of problems or causes in a process
– When there are many problems or causes and you want to focus on the most
significant
– When analyzing broad causes by looking at their specific components
Pareto Charts
• Comparing current data to historical control limits leads to conclusions about whether the process
variation is consistent (in control) or is unpredictable (out of control, affected by special causes of
variation).
■ Preventive or corrective ?
Quality Appraisal
■ Inspection:
– Inspection is an appraisal activity that compares goods or services to a
given standard.
Process Control
Acceptance Sampling
Statistical Sampling to determine where to
accept or reject the production lot.
Inspection Methods
Non-destructive test
Destructive testing
How much inspection is adequate ?
■ How much effort one should make in inspection ?
■ Acceptance Sampling
– Used to infer the quality of a batch of products by sampling a specified number of items for testing.
– Collect Sample for measurement (one or multiple random samples)
– Size of sample and number of samples depend on how much risk is assiciated with the product
■ Process Control
– Define the type of measurements
– Variables: Measures on a continuous scale (e.g., 23.5mm, 0.35 gms, 36 seconds. )
– Attributes: Measured on a discrete scale (e.g., pass-fail, fraction of defectives, number of defects on
a surface, etc.)
Process Variability
■ Random Variations
– Chance or common causes inherent in every process
– Deviation in the process output are natural in every
process
– Created by countless minor factors
■ Non-Random Variations
– Deviations in the process output can be clearly identified
and managed
– Systematic or assignable causes present in the preocess
– Process need a corrective actions
– In manufacturing set-ups, some of the causes are variation
primarily include - operational inputs such as raw materials,
personnel, equipment, measurement methods, etc. and the
environmental conditions.
Statistical Process Control (SPC)
■ Periodic samples of process output are taken
■ Sample statistics, (e.g., sample means) are measured.
■ For example, if you have taken n = 50 samples, having a sample size of 100 units
– Their means may be denoted by �1, �2, �3, … �50,
– The variability in sampling statistics (��)can be described by its sampling distribution.
Sampling distribution
Sampling Distribution:
Non random
Variation
LCL: Lower Control Limit
*
*
*
(for ± 3σ)
values
*
*
*
*
*
*
LCL: Lower Control Limit
Non random Sample ID (sample number/time order)
Variation
Variation due to
random/chance causes
– Also known as
■ producer’s risk Normal
■ false rejection (Random)
■ There is always a probability that a value will fall inside the limits even though non-random variations are
present.
■ Type 2 Error:
– Concluding
■ non-random variations are not present, when they are
■ a process is in control when it is really out of control
– Also known as
■ consumer’s risk
■ false pass
§ The costs of making each error should be balanced by their
■ false acceptance probabilities
■ false negative
§ In practice, two-sigma limits and three-sigma limits are commonly
used as reference.
The Control Process
■ Define: The set of characteristics which are suppose to be controlled
■ Measure: Establish the measurement method
■ Compare: With the quality standard (e.g., upper and lower control limits)
■ Evaluate: Establish a definition of ‘out of control’
– Distinguish random from non-random variability
– Non-random variability indicates that the process is out of control
■ Correct: Eliminate the cause of non-random variability
■ Monitor: To ensure that corrective action has a sustained effect
Statistical Stability of a process
■ Type 1 Error:
– Probability that a value will fall outside the limits Normal
even though only random variations are present (Random)
– Concluding that non-random variations are
present even though only random variations are
present
– Concluding a process is not in control when it α: Probability of making type 1 error
actually is. = sum of probabilities in the two tails
– Also known as producer’s risk
Type 1 and Type 2 Errors
■ There is always a probability that a value will fall inside the limits even though non-random
variations are present.
■ Type 2 Error:
– Concluding non-random variations are not present, when they are
– Concluding a process is in control when it is really out of control
– Also known as consumer’s risk
Control Charts
■ Control chart detects variation in processing and warns if there is any deviation from the specified control
limit (Voice of the Process)
■ The purpose is to monitor and stabilize the process through detecting and controlling the non-random
causes of variations.
■ What to monitor ?
– Variable data: Measured (usually on a continuous scale amount of time needed to complete a task,
length or width of a component)
– Attribute data: Counted (e.g., the number of defective parts in a sample, the number of calls per
day)
Control
Charts
Control
Control Chart
Charts for
for Attributes
Variables
• p-chart • c-chart
• np-chart • U-chart
• When items are classified in two categories: • When items can’t be classified in two categories:
• e.g.; good/bad; pass/fail, acceptable & unacceptable, • e.g., number of accidents per year, number of bacterea in a
conforming & non-conforming, defective/nondefective water sample, number of scrateches on a polished surface, etc.
etc.
Grand Average
x-bar (mean) chart: When Process Deviation is not known
Sample Average
Sample Range R
Results are similar to the earlier case when
Average of process deviation was known
Sample
Range
Example: Range Charts
Control Limits for the Range Charts Control Limits for the Range Charts when
process Standard Deviation is known
Sample Range of
five samples are
§ Control limits are obtained on the basis of about 20-25 samples and standard deviation
from the samples is calculated for further production control.
p-chart continued
Control limits:
Where, ‘p’ is fraction defective in the population
If p is unknown:
§ it can be estimated from samples
§ p̅replaces p in the preceding formulas
Example:
An inspector counted the number of defective monthly billing statements of a telephone company in
each of 20 samples. Using the following information, construct a control chart that will describe 99.74
percent of the chance variation in the process when the process is in control. Each sample contained
100 statements.
?
Control Chat for Attributes: c-chart
§ Works with count type data, e.g. total number of nonconformities per unit
?
Are all variations within the control limit random ?
Trend
Bias
High Dispersion
– The number of runs up (U) and down (D) (The first value does not receive either a U or a D
■ U/D Runs =3 because nothing precedes it.)
7 runs
8 runs
Run Test
■ Transform the data into both As and Bs and Us and Ds
■ Count the actual number of runs (r) in for N observations
■ Calculate the expected number of runs (Er)
■ Calculate the standard deviation of number of runs (σ)
■ Calculate the z-score
■ Decide on the basis of z-score (assuming acceptable limit lies between +2 to -2)
Number or observations ?
N =20
Number or runs ?
Process Capability
At any given instance, the output of a process may or may not conform to
specifications even though the process may be in statistical control
• Process capability refers to the inherent variability of process output relative to the variation allowed by
the design specifications
• If the random variations that a process is capable to produce lies within an acceptable specifications,
the process is said to be “capable.” If it is not, the manager must decide how to correct the situation.
Capability Analysis
Voice of the Process Voice of the Customers
8.5 10 11.5
8.5 10 11.5
a) LSL = 8.5 & USL = 11.5 b) LSL = 7 & USL = 13
LCL= 8.5 & UCL = 11.5
LCL= 8.5 & UCL = 11.5
Lower Upper
Specification Specification
Process capability index a) Cp= 3/3 = 1
b) Cp= 6/3 = 2
c) Cp= 2/3 = 0.67
8.5 10 11.5
c) LSL = 9 & USL = 11
LCL= 8.5 & UCL = 11.5
Only B is capable (Cp ≥ 1.33)
■ Cpk = Smaller of
,
7.5
Process mean is centred between USL & LSL
4.6
= Smaller of
capable
Not capable
Not capable
In order to be capable, Cp & Cp k must be at least 1.33
INVENTORY MANAGEMENT
Reference Text:
▪ Inventory is an array of raw materials, consumables, partially finished goods, finished goods
(both, in-stock & in-transit), spare parts, defective parts, scrap etc.
▪ Inventory can include small things (such as safety pins) to large items (such as trucks and
airplanes).
Different Types of Inventory
The different kinds of inventories include :
MRO inventory:
■ Raw materials and purchased parts. Chemicals, lubricants, gaskets,
cleaners, Office supplies
■ Partially completed goods, called work-in-process
Repair tools, hand tools
(WIP).
Safety equipment, Gloves,
■ Finished-goods inventories (manufacturing firms) or cloaks and workwear
merchandise (retail stores). Batteries, Furniture, fixtures
Compressors, valves, pumps,
■ Maintenance, repairs & overhauling (MRO) belts, motors, Computer
inventory. equipment, computerized tools
■ Goods-in-transit to warehouses, distributors, or Etc.
customers (pipeline inventory).
Importance of Inventories
Why is it important to pay attention at Inventory Management ?
Annual consumption/usage value = Annual number of items sold x Cost per item
You are managing a particular item. The item is important enough to your customers that you want to
carry enough inventory to avoid stocking out. However, the item is also expensive enough that you also
want to minimize the amount of cash tied up in inventory. The process of ordering replenishment stock
is expensive and cumbersome that you also want to minimize the number of purchase orders. You also
have a limited space in your organization to store the items. Demand for the item is unpredictable.
Inventory Ordering Policies
Key Inventory Management Decisions :
1. How much should you order?
▪ Specify the optimal order quantity
2. When to place an order ?
▪ Orders may be triggered by time
▪ Orders may be triggered by quantity (currrent inventory level)
Key Inputs:
1. Updated forcast
2. Current inventory level
3. Inventory cost estimates
4. Lead time
Inventory Cycle
✓ A cycle begins with receipt of an order of Q (=350) units, which are
withdrawn at a constant rate (50 units per day) over time.
Average Inventory
= Q/2 =175
Order Size Vs Order Frequency
In which case the average inventory is high; with high order frequeny or low order frequency
?
Order Size is Inversely Proportional to Order Frequency
Inventory
Average
Inventory
Average
Economic Order Quantity (EOQ)
■ The EOQ provides a model for calculating the appropriate reorder point and the optimal reorder
quantity to ensure the instantaneous replenishment of inventory with no shortages
– EOQ identifies the ‘fixed’ order size which can the annual (inventory) cost
– The two main cost components are involved –
A. Inventory Carrying cost
B. Ordering Cost
Total Cost =
Carrying Cost
Ordering Cost
What will the lenght of reorder cycle ?
(Time between two consecutive orders)
= Q0/D
Cost Components
Length of Order Cycle (Q0/D)
= 100 / 3600 per year
= 12/36 month
= 1/3 month
Hence;
Order Frequency = Thrice a month
Assumptions:
– Annual demand is known and demand rate is constant
– Inventory ordering and usage occur in cycles.
– Ordering costs are constant
– Price per unit is constant What if we relax this assumption of the basic EOQ Model ?
– The usage rate and the lead time do not vary
– The order will be received at the precise instant that the inventory on hand falls to
zero
– Inventory holding cost is based on average inventory
– All demand for the product will be satisfied (i.e., no backorders are allowed)
– There are no quantity discounts
■ Given: Annual Demand (D) = 1000 units
Inclusion of unit price in the total-cost computation in that case would merely increase the total cost by the amount P*D.
Impact of Unit Price (or Purchase Cost) on EOQ
Purchase cost
Impact of Unit Price (or Purchase Cost) on EOQ
Purchase cost
Quantity Discounts
■ Determination of EOQ does not involve the purchasing cost because of the assumption that
under no quantity discounts, price per unit is the same for all order sizes.
■ If quantity discounts are available, Manager must think of the following concerns:
– Availability of storage space for additional items
– Issue of obsolescence and deterioration
– Availability of fund to invest in additional inventory
Quantity Discounts
■ When quantity discounts are offered, there is a
separate U-shaped total-cost curve for each unit
price.
Given: D = 816 cases per year; S = $12; H = $4 per case per year
Given: D = 816 cases per year; S = $12; H = $4 per case per year
Infeasible
I max
Maximum Inventory
Economic Production Quantity (EPQ)
Objective: Minimize the total cost
[Annual Set up Cost + Annual Holding Cost + Annual Production Cost ]
Q0
Run (Batch) Size
I max
Maximum Inventory
Economic Production Quantity (EPQ)
Qp
Run (Batch) Size
I max
Maximum Inventory
Economic Production Quantity (EPQ)
■ Imax = (p - u) * Q0/p
■ Carrying Cost = ( Imax/ 2 ) H
■ Number of Production Runs
= D/Q0 Where, D = annual demand,
■ Set Up Cost
= (Number of Production Runs * Set Up cost per Production Run) = (D/Q0)S
Key Metrics
Cost estimation
– Resource requirement Performance targets
Quality goals
Project Lifecycle
1. Work breakdown structure: An initial planning tool that is needed to develop a list of
activities, activity sequences, and a realistic budget
2. Project Scheduling
– Gantt charts: A visual aid used to plan and monitor individual activities
3. Network diagram: A “big picture” visual aid that is used to estimate project duration,
identify activities that are critical for timely project completion, identify areas where
slack time exists, and develop activity schedules
Level-2
Level-3
Illustration:
Work Breakdown Structure
WORK BREAKDOWN STRUCTURE
■ To get estimated cost of each activities and hence the total cost of the project
■ Identify the precedence rule or dependencies of activities on each other
■ Develop a schedule for each activity
■ Assign roles and responsibilities
■ Track the progress of each activity
■ Identify project risks.
PROJECT SCHEDULING
Gantt Charts (Schedule Chart)
■ Gantt chart is a list of the activities mapped with is a suitable time scale at the right.
■ Each activity is represented by a bar; the position and length of the bar reflects the start date, duration and
end date of the activity.
▪ How long any activity can be delayed without delaying the project?
NETWORK DIAGRAM
PERT and CPM
■ Slack: It reflects the difference between the length of a given path and the length of the
critical path.
Network Conventions
Condition Representation
(AOA)
Separate activities that have same
starting and ending nodes
Example: AON
f
a
d
Start End
b e g
Example: AOA
1 c 3
a
f
Start
b d
2 4
e
5
Example: AOA
1 c
a
f
3
Start
b d End
2
e
g
4
Example: AOA
1 c
a
3 f
Start d
End
b
2
e g
4
Critical Path (AOA)
• Critical path the longest possible path in the network diagram;
• This is a path with zero slack;
• If activity any activity on the critical path is delayed, the entire project will be delayed.
■ Path Lengths
1. Path I: 1-2-4-5-6 = 18 Weeks 4
2. Path II: 1-2-5-6 = 20 Weeks Critical Path 2
3. Path III: 1-3-5-6 = 14 Weeks
■ Expected Length of The Project= 20 Weeks
g
■ Amount of slack time: 1 5 (1 week) 6
■ Slack = Length of Critical Path - Length of Selected
Path
– Path I : Slack = 20 – 18 = 2 Weeks 3
– Path II : Slack = 20 – 20 = 0 Slack = 0 for the Critical Path
– Path III : Slack = 20 – 14 = 6 Weeks
Critical Path (AON)
■ Path Lengths:
▪ EF2-4 = 8 + 6 = 14 3
▪ EF2-5 = 8+11 = 19
▪ EF3-5 = 4 + 9 = 13
Computing Algorithm (AOA)
4
2
▪ ES4-5 = EF2-4 = 14
▪ EF4-5 = ES4-5 + 3 = 14 + 3 = 17
g
ES5-6 = ? 1 5 (1 week) 6
▪ EF2-5 = 8+11 = 19
▪ EF3-5 = 4 + 9 = 13
3
Computing Algorithm (AOA)
4
2
▪ EF2-4 = 8 + 6 = 14 = ES4-5
▪ EF4-5 = ES4-5 + 3 = 14 + 3 = 17
ES5-6 = 19 g
Largest of 1 5 (1 week) 6
▪ EF2-5 = 8+11 = 19 EF4-5, EF2-5 & EF3-5
▪ EF3-5 = 4 + 9 = 13
3
▪ EF5-6 = 19 + 1 = 20
Computing Algorithm (AOA)
Backward Pass
Computing Algorithm (AOA)
Backward Pass
■ LF5-6 = EF5-6 = 20
■ LS5-6 = LF5-6 – 1 = 20 – 1 = 19
Computing Algorithm (AOA)
■ LF4-5 = ? ; LF2-5 = ?; LF3-5 = ?
■ LF4-5 = LF2-5 = LF3-5 = LS5-6 = 19
■ LS4-5 = ? ; LS2-5 = ?; LS3-5 = ?
■ LS4-5 = 19 – 3 = 16
■ LS2-5 = 19 – 11 = 8
■ LS3-5 = 19 – 9 = 10
Computing Algorithm (AOA)
■ Follow the same approach to compute the LS or preceding activities
If an activity has multiple following activity, its LF will be equal to the smallest of LS of the following activities
Activity on Node
Activity on Node
Forward Pass Backward Pass
Computing Slack Times
■ Slack = LS − ES or LF − EF
Critical Activities
■ Slack times for activities on the critical
path will be zero.
■ Critical activities are: 1-2; 2-5; & 5-6
■ Managers may shorten, or crash, certain activities by increasing direct expenses to speed
up the project.
■ Activities should be crashed according to crashing costs, i.e., Crash those with the lowest
crash costs first.
■ Crashing should continue as long as the cost to crash is less than the benefits derived from
crashing.
Example
Crash Candidates
(0)
(2)
(1) Possible
(0) candidates
(3)
(1)
(1)
■ Crash activity f by one day
(0)
(2) Possible
(0) candidates:
(0)
b&e
(3)
(1)
(0)
■ The probabilistic approach involves three time estimates for each activity:
– Optimistic-time (to) : Length of time required under optimal conditions
– Pessimistic-time (tp): Length of time required under the worst con
– Most Likely time (tm): The most probable length of time for an activity
The fundamental question: What is the probability of the project completion within a given time ‘T’ ?
Time Estimates (beta-distribution)
Activity Level
Path Level
Path Mean = The expected duration of a path
= Sum of expected times of all the activities on the path
Example
• One can have the probabilistic estimate of project completion time by knowing expected path times.
(te) (ts)
te ts
■ Z-scores of each path will provide the path probability values (for a specified completion time)
■ The more positive the value of z, the better.
– Rule of thumb: If the value of z is +3.00 or more, the path probability is close to 100 percent
(for z = +3.00, the probability is .9987)
– A negative value of z indicates that the specified time is earlier than the expected path
duration; i.e., a certain delay in completion
Same Example
Critical Path
Critical Path