Lung Kwu Tan Final Report Eng
Lung Kwu Tan Final Report Eng
CE27/2015(CE)
2018
Contents
Page
1 Introduction 1
1.1 Background 1
1.2 The Study 1
1.3 Main Objectives of the Study 2
1.4 Scope of “Final Report” 3
1.5 Structure of the Report 3
1.6 Nomenclature and Abbreviation 3
2 Site Description 6
2.1 North West New Territories 6
2.2 Tuen Mun West 8
2.3 Lung Kwu Tan Study Area 8
5 Next Step 59
Tables
Table 1.1 Abbreviations of Government Departments
Table 1.2 Abbreviations for Expressions Adopted in this Report
Table 3.1 Land Uses in Preliminary Land Use Themes
Table 4.1 Summary of Soil and Rock Stratigraphy from the Project Specific
Data within the Site
Table 4.2 Estimated Trip Generation of Preliminary Land Use Themes
Table 4.3 Summary of Fisheries Survey
Figures
Figure 1.1 Location of Lung Kwu Tan
246382/REP/024/02 |
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Figure 2.1 Tuen Mun West Area in North West New Territories
Figure 2.2 View of Lung Kwu Tan and Lung Kwu Sheung Tan from Headland
Figure 2.3 Industrial Operations at Lung Kwu Sheung Tan
Figure 2.4 Location of Lung Kwu Tan Village
Figure 2.5 Lung Kwu Tan Village
Figure 2.6 Clusters of Burial Grounds, Graves and Urns within Study Area
Figure 4.1 Potential Reclamation Extent
Figure 4.2 Layout of Existing Submarine Outfall
Figure 4.3 Topography of Study Area
Figure 4.4 Typical Sections of Proposed Seawall Scheme along Reclamation
Edge
Figure 4.5 Key Marine Traffic Movements
Figure 4.6 Wind Roses at Sha Chau and Tai Mo To Stations
Figure 4.7 Wind Rose at Hong Kong International Airport Station
Figure 4.8 Depth-averaged Current Speed (knots) in Flood Tides during Wet
Season
Figure 4.9 Depth-averaged Current Speed (knots) in Ebb Tides during Wet
Season
Figure 4.10 Proposed Road Improvement along Lung Mun Road and Siu Lang
Shui Road
Figure 4.11 Location of Proposed Slip Road connecting Tuen Mun Road
(Northbound) to Hoi Wing Road (Westbound)
Figure 4.12 Major Species Recorded in the Adult Fish Survey
Figure 4.13 Green Channel
Figure 4.14 CWD Tracklines acquired from Theodolite Tracking Survey
Figure 4.15 Location of Lung Kwu Tan Valley SSSI and Fung Shui Woods
Figure 4.16 Air Quality Exceedance Zone
Figure 4.17 Helipads and Noise Buffer Zone
Figure 4.18 Locations of Cultural Heritage Resources
Figure 4.19 Lau Ancestral Hall at Tuk Mei Chung
Figure 4.20 Tin Hau Temple
Drawings
246382/GEN/001 Potential Reclamation at Lung Kwu Tan
246382/REP/024/02 |
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
1 Introduction
1.1 Background
On 30 October 2015, Civil Engineering and Development Department
(CEDD) of the Government of the Hong Kong Special Administrative
Region commissioned Ove Arup and Partners Hong Kong Limited
(Arup) to provide consultancy services for Agreement No. CE 27/2015
(CE) “Technical Study on Reclamation at Lung Kwu Tan – Feasibility
Study” (the Study).
246382/REP/024/02 Page 1
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 2
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 3
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 4
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 5
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
2 Site Description
1
Tsuen Wan and Kwai Tsing are regarded as Metro Area in the analysis.
246382/REP/024/02 Page 6
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 7
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 8
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Figure 2.2 View of Lung Kwu Tan and Lung Kwu Sheung Tan
from Headland
246382/REP/024/02 Page 9
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
tourist spots include the Tin Hau Temple, Emperor's Cave (皇帝巖) and
Lau Ancestral Hall.
The development at LKT area is subject to the Airport Height
Restriction (AHR), i.e. the height restriction prescribed under the Hong
Kong Airport (Control of Obstructions) Ordinance (Cap. 301). Under
the current operation of the Two-Runway System at the Hong Kong
International Airport, the AHR over the potential reclamation varies
from +130mPD to +155mPD. However, more stringent height
restriction may be considered over the southern portion of the LKT area
for the future operation of the Expansion of Hong Kong International
Airport into a Three-Runway System (HKIA3RS).
246382/REP/024/02 Page 10
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
2.3.10 There are numerous private lots within LKT Village and some of them
are with building status which includes building licences/ New Grant/
Old Schedule house lots. In addition to private lots with building status,
there are private agricultural lots, structures for agricultural purposes
covered by letter of approval, and tolerated structures covered by
surveyed number at LKT.
246382/REP/024/02 Page 11
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 12
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 13
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 14
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 15
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 16
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 17
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 18
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
(CD) (i.e. -5.0mCD) [Note: Chart Datum is 0.146m below the Principal
Datum.]. Dredging might be required to provide adequate water depth
for vessel berthing and manoeuvring along this reclamation edge.
An existing submarine effluent outfall, maintained by the Drainage
Services Department (DSD), was identified within the northern portion
of the potential reclamation area as shown in Figure 4.2. This outfall
connects to the North West New Territories Sewage Tunnel to convey
and discharge the treated effluent from San Wai Sewage Treatment
Works (STW) to Urmston Road, serving the catchments of Yuen Long
peripheral area, North Tuen Mun and the Tuen Mun-Yuen Long
Corridor, Tin Shui Wai and Au Tau/Long Ping.
Considering the importance of the existing submarine outfall to its
catchments and the significant challenges in re-provisioning of this
outfall at the heavily trafficked Urmston Road, the existing outfall
should be retained and kept intact. Reclaiming over the outfall is not
recommended as this would load the outfall and its surrounding soil that
they were not originally designed for. Due to the no-dredging
requirement near the outfall, on-shore berthing is not allowed in the
northern portion of the reclamation site in the preliminary layout.
Ground Condition
The potential reclamation area predominantly comprises a nearshore
area with coastal features such as headlands, narrow beaches and
reclaimed land located along the existing shore. Natural terrain hillsides
are present at several locations to the north, east and south of the
potential reclamation area respectively and are generally characterised
246382/REP/024/02 Page 19
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 20
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Natural Terrain
A number of natural terrain catchments are situated within the hillside
areas directly abutting the shoreline in the northern and central portions
of the potential reclamation area. Initial assessments, based on desktop
study, review of landslide records / inventory and boulder field
inventory kept by the Geotechnical Engineering Office (GEO),
indicated limited historical landslide activity within these catchments
but highlighted the presence of extensive rock outcrop and boulder
coverage within them.
A preliminary screening in accordance with Geotechnical Engineering
Office (GEO) Report No. 138 “Guidelines for Natural Terrain Hazard
Studies” (NTHS) was carried out for the credible flowpaths for each
natural terrain catchment. Some of these catchments, mostly near the
central portion of the potential reclamation area, were found meeting
“Alert Criteria” which will require an NTHS depending on the nature
246382/REP/024/02 Page 21
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
of the proposed developments and their locations from the toe of the
catchment. In the next stage studies when the land uses and detailed
facility layouts are available, the location and the extent of hillside
requiring a detailed NTHS will be reviewed. Subject to the results of
the detailed NTHS, mitigation measures will be designed and
considered in the land use planning. Possible mitigation measures, such
as the provision of flexible debris resisting barriers at the toe of
catchments and in-situ stabilisation of potential landslide source areas
using soil nails which can be determined following the prescriptive
approach outlined in GEO Technical Note (TGN) No. 37, were
identified for the relatively small-scale catchments.
The boulder fields in the proximity of the potential reclamation area
falls within areas that generally have very dense boulder coverage
(>75%), with “boulder” types recorded are predominantly tors and rock
outcrops. This information indicates that the bedrock may possibly be
quite shallow within the hillside areas abutting the site. In view of the
presence of numerous boulders and rock outcrops within the hillside
area overlooking the future development within the reclamation area,
assessment of the potential boulder fall / rockfall hazard will be required
in the next stage studies when the land uses and detailed facility layouts
are available. To mitigate the boulder / rockfall hazards which might
affect future developments within the potential reclamation area
adjacent to them, stabilisation works against such hazards will need to
be investigated in the detailed studies.
246382/REP/024/02 Page 22
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 23
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
actual ground treatment types and seawall scheme are subject to review
taking into account of the possible cost, programme constraints,
availability of plant, land uses requirements, etc. This will be reviewed
in the detailed studies and the detailed design stage.
246382/REP/024/02 Page 24
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 25
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 26
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 27
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
downtime, i.e. time that vessels cannot berth due to severe wave
conditions, were acceptable. This is consistent with the marine facilities
nearby, such as the jetties of CPPS, where vessels can berth against
without wave protection structures such as breakwater. However this
will need to be reviewed in the detailed studies when the land use at
waterfront and berthing requirement are determined.
246382/REP/024/02 Page 28
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 29
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
There would also be congestion problem at Wong Chu Road and the
slip road connecting Tuen Mun Road (northbound) to Wong Chu Road
(westbound). Due to the dense existing development on both sides of
Wong Chu Road, there is no room available for road improvement
works. Building a new slip road connecting Tuen Mun Road
(northbound) and Hoi Wing Road (westbound) to provide an alternative
route to Tuen Mun West is a possible measure to mitigate this
congestion problem.
However, based on the preliminary assessment done for different
preliminary land use themes, it was revealed that residential
development would generate much higher traffic flow than the
industrial uses, and aggravate the traffic condition in the already critical
traffic flow direction even if only part of the reclamation is reserved for
the purpose. With this new slip road, the traffic flow at Wong Chu Road
and its westbound slip road from Tuen Mun Road relative to their road
capacities, i.e. volume/capacity ratio, would be reduced to acceptable
levels in the preliminary land use themes B and C, in which residential
development was not considered. Meanwhile, despite the diversion of
traffic flow to Hoi Wing Road, it was assessed that the road itself, the
junction of Hoi Wing Road and Tuen Mun Rural Committee Road and
the junction of Hoi Wing Road and Castle Peak Road would still
operate satisfactorily with the increase in road traffic.
246382/REP/024/02 Page 31
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
The proposed road improvement works at Lung Mun Road, Siu Lang
Shui Road, Lung Fu Road and the proposed slip road connecting Tuen
Mun Road and Hoi Wing Road are under a number of natural terrain
catchments. Initial assessments, based on desktop study, review of
landslide records / inventory and boulder field inventory kept by GEO
indicated limited historical activity within these catchments. A
preliminary screening on the natural terrain catchments based on GEO
Report No. 138 found that some catchments meet the “Alert Criteria”
and a detailed NTHS is required for these catchments in the next stage
studies. In addition, there are numerous boulders and rock outcrops
within the hillside areas overlooking the proposed road improvement
works. An assessment of the potential boulder fall / rockfall hazard will
be required in the next stage. Subject to the result of detailed NTHS and
boulder fall / rockfall hazard assessment, if the hazard affecting the
widened sections are confirmed, mitigation measures against such
hazards will need to be investigated in the detailed studies.
A number of registered and non-registered man-made roadside features,
which consist of mainly man-made slopes, are along Lung Mun Road.
These registered and non-registered features were preliminarily
assessed according to TGN No. 15, and features at Siu Lang Shui
Road/Lung Mun Road were found to be directly affected by the
proposed connecting roads. Detailed stability assessment and design of
slope modification works will be required. In addition, detailed review
and assessment should be conducted for all existing man-made features
which could affect or be affected by the road improvement works in the
next stage studies. Stability assessment will be conducted to ensure that
these features can meet the current safety standard and upgrading
measures will be designed as appropriate. Similar detailed assessment
246382/REP/024/02 Page 32
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
and design works would be required for the features at Tuen Mun Road/
Hoi Wing Road which would be directly affected by the proposed slip
road.
As for the congestion anticipated at Tuen Mun Road – Siu Lam Section,
long-term strategic traffic solution will be necessary to alleviate the
congestion along this strategic road. One possible solution is to
encourage more road users to use the Route 11 which is anticipated to
have spare capacity, for instance, by a more attractive toll level, such
that some traffic would be diverted from Tuen Mun Road – Siu Lam
Section and other strategic road links to Route 11. A proper toll strategy
for Route 11 would be essential to promote more balanced utilisation
of road capacity and help to relieve the problem at Tuen Mun Road –
Siu Lam Section.
The new slip road off Tuen Mun Road to Hoi Wing Road would not be
enough to alleviate the congestion problem at Wong Chu Road if the
residential development is pursued at LKT reclamation as in
preliminary land use theme A and D. The development scale and/or
trip generations should be reduced to avoid traffic impact if they are to
be pursued further. Alternatively, a new strategic road between Tuen
Mun West and Tuen Mun Road bypassing the Wong Chu Road was
considered necessary. Also, if extensive residential development was
proposed, alternative access other than Lung Mun Road should be
proposed to cater for emergency situations during which the Lung Mun
Road was blocked / closed. Therefore, significant input on new
transport infrastructure is anticipated if LKT reclamation goes for
residential development.
In short, industrial and special uses that generate lower traffic flow in
critical direction during peak hours than residential development are
preferable at LKT reclamation. In particular, uses that can optimise the
marine access provided at reclamation site, which in turn further reduce
the traffic flow, should be given priority to effectively utilise the vast
new land while minimising the burden on the key roads.
In the next detailed study stage when the future land uses on the
reclamation area are formulated, a comprehensive TTIA will need to be
carried out to demonstrate that no unacceptable traffic impacts will be
resulted from the proposed reclamation development, taking into
account the latest programme and project information of the key
proposed road links and other development projects in the area.
246382/REP/024/02 Page 33
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Water Quality
The potential reclamation site is located within the North Western
Water Control Zone (WCZ) and adjacent to the boundary of the Deep
Bay WCZ. The potential reclamation site is about 2 km from Sha Chau
and Lung Kwu Chau Marine Park and is close to the spawning ground
for commercial fisheries resources in the north of Lantau.
Preliminary water quality assessments for both operation and
construction phases were carried out.
Operation Phase
Preliminary hydrodynamic assessment and water quality assessment
were carried out to evaluate the impacts from the largest possible
reclamation area for LKT reclamation. The hydrodynamic assessment
showed that under such possible worst-case condition, LKT
reclamation would cause a change of flow of the nearest channel at
Urmston Road by 0.2% which was several times smaller than the
change caused by HKIA3RS (0.9%). Hence, it was anticipated that no
significant change in the hydrodynamic regime within the north-
246382/REP/024/02 Page 34
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Construction Phase
The major possible impact during the construction phase would be the
release of SS due to the marine construction works. Water quality
modelling for the construction phase was performed for the possible
worst case scenario which assumed, on top of filling activities for
reclamation, construction works such as 1) dredging works for berths at
the reclamation edge and 2) dredging works for the re-provisioning of
the existing submarine sewage outfall (hypothetical assumption only)
were implemented simultaneously. The quantitative assessment
showed that, with the implementation of environmentally friendly
construction method and mitigation measures such as non-dredged
seawall, leading seawall and silt curtain, SS release due to the marine
work for reclamation alone would not result in significant change in
water quality at the concerned Water Control Zones.
However, together with the concurrent projects, the SS releases could
result in exceedance in the Water Sensitive Receivers (WSRs) at The
Brothers Marine Park. A review showed that these exceedances were
mainly attributed to the substantial disposal rate of contaminated mud
pits assumed in the model which however was unlikely to occur by
comparing with the historical peak dumping rate. Also, the contribution
of the construction of LKT reclamation to these exceedances was less
than 0.6%. Hence, the exceedance was considered to be very unlikely
to occur and was not induced by LKT reclamation.
246382/REP/024/02 Page 35
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Pore water assessment and elutriate assessment were also carried out to
examine the amount of contaminant that could be released, if any, when
the marine sediment is disturbed during the filling and dredging
activities. Exceedances were observed in TIN and in UIA in the samples
for Pore Water Test and in As, TIN and UIA in the samples for Elutriate
Test. To evaluate the possible impact on the WSRs, quantitative
assessment was carried out based on the above test results. The
assessment showed that only exceedances in TIN would exist at WSRs.
However, significant impact is not expected as the N:P ratio would still
be much higher than the 16:1 Redfield Ratio, meaning that the algal
growth was limited by phosphorus and chance for algal growth and thus
red tide is low.
Based on the above, adverse water quality impact is not anticipated at
the nearby water bodies including the Sha Chau and Lung Kwu Chau
Marine Park and the spawning ground for commercial fisheries
resources during the operation and construction phases. The impact on
fisheries resources and marine ecology due to the water quality change
is expected to be insignificant.
Fisheries Resources
In order to supplement the existing information on fisheries resources
in the embayment areas of LKT and LKST, a preliminary fisheries
survey was carried out.
Adult Fish Gill netting and 2 times in dry February and March
Survey cage trapping season and 2 2016 (dry season);
times in wet May and June 2016
season (wet season)
Juvenile Seine netting 3 times in wet April, May and June
Fish seasons 2016
Survey
Fishing Observed on- Perform February to June 2016
Operation board for 10 concurrently
survey minutes at each with the above
sampling survey and
location marine ground
investigation
Gill netting and cage trapping are common fishing methods adopted by
local fishermen on small vessels. These methods together with juvenile
fish survey by small seine net were adopted for this preliminary field
survey. Fishing operation survey was carried out concurrently with
other fish surveys and during the marine ground investigation
conducted between 8 April and 31 May 2016, aiming to record the
commercial fishing activities inside and in the vicinity of potential
246382/REP/024/02 Page 36
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 37
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Marine Ecology
LKT reclamation will cause direct loss of coastal water habitat,
intertidal habitat and stream outlet. Based on the information obtained
from literature review and site surveys done in the Land Supply Study,
no species of conservation importance were found at the said habitat.
Nonetheless, to mitigate the impact of habitat loss for other marine
organisms such as fishes, mitigation or enhancement measures such as
eco-shoreline could be added to support marine lives.
Eco-shoreline can be implemented at the sheltered area of the
reclamation edge to enhance the ecological condition around the
reclamation site. It provides a sheltered habitat and a higher diversity of
plant species for juvenile terrestrial and marine organisms. It can also
serve as access to the sea side and provide food sources for wildlife.
This will help establish food chain to enhance the ecological
equilibrium locally.
The drainage system, in the form of either open channel or multi-cell
box culvert, will be constructed on the reclamation area (see Section
4.6) to receive surface runoff from the development and the foothills
and mountains in the east of the potential reclamation, via the existing
246382/REP/024/02 Page 38
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 39
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Kwu Chau Marine Park. Similar CWD distribution was recorded from
the theodolite tracking surveys carried out in this Study. The activites
of dolphins sighted were recorded during the survey, and dolphins were
found to be travelling at most of the time.
246382/REP/024/02 Page 40
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Impacts on the Existing Sha Chau and Lung Kwu Chau Marine Park
(Indirect Impact in Construction Phase)
4.5.34 Sha Chau and Lung Kwu Cha Marine Park (SCLKCMP) is located at
about 2km from the potential reclamation at LKT. Lung Kwu Chau is
known to be the major feeding area and the highest density area for
dolphins in all of northwest Lantau, and not all of this habitat is
protected by the marine park. Given LKT reclamation is at a reasonable
distance from SCLKCMP, the direct impact on the marine park is not
expected to be significant. However, indirect impacts such as water
quality impact due to the increase in SS level during dredging activities
(to provide enough water depth for on-shore berth required by industrial
uses and C&DMHF) may disturb and reduce prey availability for
dolphins using the waters of SCLKCMP. If CWDs avoided the general
area, including the waters of SCLKCMP, then this indirect impact from
LKT reclamation could be significant.
246382/REP/024/02 Page 41
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 42
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Figure 4.15 Location of Lung Kwu Tan Valley SSSI and Fung
Shui Woods
The development confined to the reclamation area should not have any
significant effect to the SSSI as it is far away from the SSSI. However,
outside the reclamation area, it may be of ecological interest to preserve
the existing villages, as any transformation there will inevitably affect
the SSSI and the Fung Shui Woods due to their close vicinity.
Disturbance (e.g. dust and noise) generated during construction phase
might affect the SSSI and the Fung Shui Woods and the utilisation of
these areas by wildlife.
It is of scientific interest that butterflies growth could be affected by the
presence of artificial lights. It is recommended that the development in
the southern portion of the reclamation site should not have strong flood
light. Territorial facilities which may be lit up in the evenings should
avoid sitting at the southern portion of the reclamation close to the SSSI.
Rather, they can sit at the northern portion of the reclamation, where
the facilities would be over 1 km away from the SSSI, and the potential
impact to the wildlife is expected to be low.
Air Quality
With the heavy industrial setting around LKT, the relatively high
emissions from the fixed plant sources, in particular from CPPS and
BPPS, may be of concern.
246382/REP/024/02 Page 43
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
There may be concern over odour nuisance from some land uses such
as the new on-site STW. It is anticipated that with the implementation
of appropriate mitigation measures commonly adopted in Hong Kong
(e.g. enclosing the odourous facilities, maintaining negative pressure to
prevent foul air from escaping the building, provision of deodouriser at
the ventilation exhaust, orienting exhaust of deodouriser away from
sensitive receivers and vertically upwards, and conducting regular
maintenance of deodouriser to ensure good condition), the potential
odour impact on nearby air sensitive uses could be properly controlled.
246382/REP/024/02 Page 44
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Noise
Various sources of noise during the operation phase were considered in
the noise impact assessment; this included road traffic noise, fixed plant
noise, aircraft noise, helicopter noise and marine traffic noise.
246382/REP/024/02 Page 45
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Aircraft Noise.
The site is in the proximity of the Hong Kong International Airport, in
particular the third runway under construction. According to HKIA3RS
EIA (EIA – 223/2015), the potential reclamation will be located outside
the Noise Exposure Forecast (NEF) 25 contours. Although the potential
reclamation is outside the NEF25 contours and adverse aircraft noise
impact on the development at the potential reclamation is not
anticipated, given its close proximity to the departure and arrival flight
paths of the planned third runway of the HKIA, which is a very busy
airport operating on a 24-hour basis, considerations should be given in
the future detailed planning on the type of land uses and design of
buildings to alleviate the aircraft noise impact. For areas with concerns,
non-noise sensitive use would be considered. Industrial-based
developments are recommended on this reclamation, and these would
be less noise-sensitive in general.
Helicopter Noise
CPPS, BPPS and Black Point Radar Station are equipped with helipads
to meet operation needs. Helicopters will generate noise when flying
through, approaching, taking-off from or hovering and idling above the
helipads. Due to the close proximity to the reclamation site, the
potential noise impact from the helicopters on future development was
considered. Helicopter types and flight routes were obtained from the
operators providing service at the helipads, including the Government
Flying Service (GFS) and Heliservices (HK) Ltd. The helicopter noise
impacts under various modes of operation were assessed; these modes
can mainly be classified into two categories – one with lateral
movement (i.e. approach and departure) and the other one without (i.e.
hovering and idling). Based on the types of helicopter (including Super
puma AS332 L2, EC155 B1, EC175 and MD 902 Explorer), the
helicopter noise data for both with and without lateral movement were
obtained from the International Civil Aviation Organization (ICAO)
and the approved Environmental Impact Assessment Study for Helipad
at Yung Shue Wan, Lamma Island (EIA-114/2005). Together with the
flight routes, the noise standards of helicopters were used to establish
the corresponding buffer zone for each helicopter at each helipad using
the general acoustic principles.
For helicopter with lateral movement (i.e. approaching to and departing
from the helipads), a buffer distance from the flight path is required to
meet the “Lmax less than 85dB(A)” noise criteria for daytime (0700 –
246382/REP/024/02 Page 46
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
1900). For helicopter approach and departing at the helipad at the Black
Point Radar Station, a horizontal distance of 880m is required to
achieve the required buffer of 180m from the flight path for daytime.
Whilst for the helipad at CPPS, a horizontal distance of 1150m is
required to achieve the required buffer of 120m from the flight path for
daytime. The buffer zone on the potential reclamation area was
determined based on these required horizontal buffer distances.
Development(s) of noise sensitive use would be subject to height
restriction or should be avoided altogether within the buffer zones due
to the possible exceedance of noise level.
For helicopters without lateral movement, assessments show that a
buffer distance of 400m from the helipads are required to achieve the
noise level of less than Lmax 85dB(A) criteria for daytime (0700 – 1900).
Development(s) of noise sensitive use should be avoided within this
400m radius buffer zone.
246382/REP/024/02 Page 47
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 48
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Cultural Heritage
The impacts on cultural heritage were preliminarily assessed in this
Study. While the reclamation works would be carried out on the sea,
there may be concerns over the works on land associated with
development, or the indirect impact such as visual intrusion. Some key
areas were highlighted for attention in the next stage of detailed studies.
It is noted that the consultation of local community is an important step
in assessing the impact on cultural heritage. Relevant stakeholders
should be consulted earlier when carrying out the detailed studies to
gauge their views and address their concerns at appropriate juncture.
Terrestrial Archaeology
The reclamation works would be carried out on the sea and thus is not
expected to directly affect the identified heritage resources including
the LKST Site of Archaeological Interest and LKT Site of
Archaeological Interest.
However, both Sites of Archaeological Interest (SAI) may be affected
by the associated work to occur on land to meet the infrastructure needs
(road improvements, drainage works, utilities, etc.). The archaeological
deposits may be directly and adversely affected by the excavation
works. During the design stage, impacts to the SAI should be avoided
or kept to a minimum. An Archaeological Impact Assessment, with
field investigation if required, would be required to identify the extent
of archaeological deposits affected.
More specifically at this stage, transformation of existing land uses
within the SAI (i.e. open storage or industrial workshop at LKST and
villages at LKT) will adversely and directly affect the archaeological
deposits during the construction phase unless alternative proposals are
formulated in a way which could avoid subsurface works.
246382/REP/024/02 Page 49
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 50
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 51
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Marine Archaeology
The Marine Archaeological Review of marine archaeological potential
within the Study Area was conducted based on historical evidence and
review of previous Marine Archaeological Investigation (MAI) Studies.
No actual marine archaeological resources were identified within the
potential reclamation area. However, the two previous MAI studies
taken reference in the baseline review covered very small sections of
the potential reclamation area. It is recommended that MAI will be
carried out in the EIA during the next stage of detailed studies and will
need to cover the whole reclamation area and the construction space
including the related marine works affecting the seabed.
4.6 Infrastructure
General
To identify if there will be any constraint on the development or future
land use planning with respect to infrastructure capacity, the need for
some key infrastructures including drainage, sewerage and water
supply was broadly assessed in this Study based on various assumptions
on the types or combinations of land uses. As discussed previously in
this Report, the preliminary land use themes formulated in this Study
were proposed for the purpose of assessment only. The actual land uses
composition and their planning parameters, including residing and
working populations, Gross Floor Area, etc. will be determined in the
next stage detailed studies.
Drainage
The existing lands at LKT and LKST are bounded by the mountain
range of Castle Peak, and runoff from the mountain is collected and
discharged at four (4) points/outfalls along the shore to the sea.
Drainage system needs to be provided on the reclamation area to collect
and divert the runoff from these upstream catchments. The runoff at
these four existing points/outfalls were estimated for a 200-year design
event, and the peak runoff varies from about 7m3/s to 50m3/s.
In view of the size of the reclamation, 4 nos. of drainage structures, in
the form of either open channel or multi-cell box culvert, are
recommended to collect the surface runoff from the reclamation and the
existing hillside catchments. They should be connected to the four
existing runoff discharge points/outfalls along the shore.
Apart from acting as a storm drain, i.e. dimensioned to provide the
necessary capacity to discharge the runoff collected, an open channel
can be designed as a water feature to enhance the environment within
the development site. In order to maximise the opportunities of
developing mangrove communities on gentle sloping bed, the width of
water space between the natural shoreline and the new reclamation edge
would be approximately 40m. Compared with box culverts, open
channels would occupy more surface land and have a much greater land
246382/REP/024/02 Page 52
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Sewerage
The existing sewerage infrastructure in the vicinity of the potential
reclamation at LKT includes Pillar Point STW and San Wai STW. As
advised by EPD, both STWs have no spare capacity to take up sewage
flow from the new development at LKT reclamation. A new on-site
STW is therefore required. The new STW should handle the sewage
discharged from the existing villages as well to bring about
environmental enhancement.
The footprint of the STW depends on the estimated sewage flows,
which in turn relate to the land uses and the size of contributing
population, and the treatment level. For the purpose of estimating the
land demand of the new on-site STW, the sewage flow that might be
generated from the LKT reclamation development were estimated
based on the preliminary land use themes. Also, a tertiary treatment
level STW was assumed for a conservative assessment of the STW
footprint.
With reference to “EPD Guidelines for Estimating Sewage Flows for
Sewage Infrastructure Planning No. EPD/TP/1/105”, the estimated
Average Dry Weather Flow ranges from about 24,700m3/day to
58,400m3/day amongst the five preliminary land use themes. The
corresponding peak flows were estimated to be 830L/s to 1860L/s. If a
tertiary treatment level STW was provided, a site area of 11 to 14
hectare would be required.
In order to achieve the objective of Total Water Management and to
minimise the pollution to water bodies, consideration should be given
to re-use the treated effluent from the STW for non-potable uses such
as toilet flushing, irrigation, street washing, etc. The excess effluent will
be discharged to the sea via an outlet at reclamation edge. Considering
the marine traffic risk involved in carrying out the marine works for a
new submarine outfall laid across the heavily trafficked Urmston Road,
the feasibility of discharging the treated effluent nearshore was
investigated. The preliminary water quality model revealed that
discharging at the seawall would not have any impact on the water
sensitive receivers near the reclamation site if the effluent has gone
through a treatment of secondary level or above.
246382/REP/024/02 Page 53
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Water Supply
The freshwater and flushing water demands for the potential
development were broadly estimated based on the unit water demands
in Water Supplies Department (WSD) Departmental Instruction (DI)
1309. The flushing water demand was then adjusted based on the actual
and design capacities of the existing Tuen Mun Salt Water Pumping
Station
The fresh water demand was estimated to vary from 53,000m3/day to
69,000m3/day for the five preliminary land use themes. The flushing
water demand was estimated to vary from 12,000m3/day to
16,000m3/day based on WSD DI 1309; these increases to 14,880m3/day
to 19,840m3/day to include an additional 24% allowance as the
committed flushing water demand exceeds the planned demand of the
Tuen Mun Salt Water Pumping Station supply zone. Generally, water
demands for industrial land use were found to be higher than those for
residential land use when referring to the water demand for industrial
land use in Tuen Mun New Town. The actual water demand for
industrial land varies quite a lot with the type of industries adopted. This
should be reviewed in the detailed studies for estimating the water
demands.
Tuen Mun district is currently served by Tuen Mun Water Treatment
Works (WTW) at Fu Tei in the north of Tuen Mun. As advised by WSD,
it would not have any spare capacity for the development on LKT
reclamation. The capacity of the existing Tuen Mun WTW should be
increased or a new WTW will be required to cope with the water
demand arisen.
Tuen Mun WTW is identified as one of the government facilities that
could be relocated to caverns under the Preliminary Land Use Study for
Lam Tei Quarry and the Adjoining Areas (the Lam Tei Quarry Study).
If pursued, the relocated WTW could be designed to cater for additional
water demand of the LKT reclamation development. Alternatively, the
capacity of the Tuen Mun WTW can be increased by expanding it in
caverns near the existing WTW.
Based on a mean daily demand (MDD) of 69,000m3/day for freshwater,
the design capacity of the expanded part of WTW is 103,500m3/day,
i.e. 1.5 times the MDD. The footprint of the expanded part of WTW
was estimated to be 1 to 2 hectares (whilst the cavern size is yet to be
determined) and it is preferably to be located close to the existing Tuen
Mun WTW to enhance efficient and to facilitate share use of some
facilities. Other waterworks required may include new fresh water
primary service reservoir, fresh water service reservoirs, fresh water
pumping station, trunk transfer and distribution mains.
For flushing water, both seawater and reclaimed water (if tertiary
treatment is adopted in the new STW) are possible and available sources
locally. Again, new service reservoirs, new pumping station and
distribution mains will be required but the scale of works will be smaller
as compared with freshwater supply.
246382/REP/024/02 Page 54
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
246382/REP/024/02 Page 55
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
This assessment shows that both PLUT-B and PLUT-C have above-
average performance in all guiding principles, meaning that they can
best balance all the needs. PLUT-B and PLUT-C can meet the territorial
needs in providing industrial uses that can be synergic with the existing
development in Tuen Mun West and NWNT and in providing new
employment opportunities in the region. In particular, for facilities
requiring marine access for transportation of materials and products that
can only be located near the waterfront, LKT reclamation would be one
of the major sources for such uses. Moreover, they are largely
compatible with the nearby village and industries.
Whilst for other PLUTs, there are some major issues to be overcome if
pursued further. For instance, traffic issues should be properly
246382/REP/024/02 Page 56
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Addendum No. 1
246382/REP/024/02 Page 57
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Addendum No. 1
246382/REP/024/02 Page 58
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
5 Next Step
246382/REP/024/02 Page 59
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Other key constraints on future land use will include the air quality
exceedance zone at the southern end of the potential reclamation area
adjacent to the CPPS. The future land uses should avoid any air
sensitive use within this exceedance zone.
The building height of the future development should be limited to
below the ridgeline of the surrounding hillslopes and key vantage
points, with due consideration of other restriction in view of the
potential helicopter noise, operation of Black Point Radar Station and
visual impact as well.
The locals could benefit from the development by additional
community facilities in the neighbourhood, and more choices of new
public transport services. New roads provided on reclamation site
could, depending on the management and operation requirement,
provide an alternative route for refuse vehicles to reduce the nuisance
from refuse vehicles on existing residents along Lung Kwu Tan Road.
Land resumption should be avoided as far as possible. Apart from the
concerns over the impact on the villagers, it would induce uncertainty
to the implementation programme of the development. Moreover, it
may be of ecological interest to preserve the existing villages, as any
transformation there will inevitably affect the Lung Kwu Tan Valley
SSSI and the Fung Shui Woods due to their close vicinity. The
subsurface works that may be required during construction will also
adversely and directly affect the archaeological deposits of the LKT
SAI underneath the villages.
Future Studies
This Technical Study provided only a broadbrush assessment of various
aspects and identifies constraints and key issues that will need to be
addressed in the detailed studies and EIA. To pursue the reclamation
proposal further, more detailed investigation and assessments should be
carried out to firm up the development proposal and land use planning.
Statutory EIA should be carried out to ascertain the environmental
acceptability of the development proposal and to explore further
mitigation / enhancement measures.
Some key areas in respect of geotechnical appraisal and reclamation
study, marine traffic, traffic and transport, environmental assessments,
infrastructures and building height restriction which require attention in
the detailed studies are summarised below. Need to have consultation
of the local community is also highlighted.
246382/REP/024/02 Page 60
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Marine Traffic
A comprehensive MTIA should be undertaken with a more certain
traffic pattern of both the reclamation development and other projects
in the vicinity. A full navigation simulation should be included to
simulate the vessel manoeuvring between Urmston Road and the future
246382/REP/024/02 Page 61
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Environmental Assessments
The preliminary environmental assessments completed were based on
the best available information at the time of the assessment and a
number of assumptions under some conservative assessment scenarios.
The assessment assumptions, potential environmental issues, and
proposed mitigation options should be further investigated and
followed up in subsequent detailed studies and assessment for LKT
Reclamation. Assessment assumptions should be reviewed when more
detailed information on the development proposals of LKT
Reclamation and other interfacing projects becomes available in future
studies.
Some key issues to be followed up in future statutory EIA are listed
below:
(a) Review and adopt the latest details of all the potential interfacing
and concurrent projects in vicinity of the proposed reclamation site,
which may have cumulative environmental impacts during its
construction and operation stages.
(b) Review and update on emission inventories in PATH for air quality
impact assessment, particularly those local industrial emission
sources in the vicinity of the proposed reclamation site.
246382/REP/024/02 Page 62
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
(c) Review and update the pollution load inventory and construction
methods to carry out the water quality assessment.
(d) Revisit the helicopter noise assessment based on updated helicopter
operation details of the helipads occupied by GFS and CLP at
northern and southern side of the proposed reclamation site,
including type of helicopters, approach and departure areas, etc.
(e) Explore measures to reduce traffic volume and speed of
construction vessels to reduce disturbance on CWD and the indirect
impact on SCLKCMP which is an important CWD feeding habitat.
(f) Carry out the detailed ecological survey and assessments to explore
suitable arrangement for eco-shoreline and green channel to retain
the natural shoreline and explore opportunities for ecological
enhancement.
(g) Conduct another fisheries survey to provide a more areal
investigation of the embayment area over a longer period of survey
time, with particular attention to CWD prey species to review the
potential impact to CWDs.
(h) Explore further mitigation measures in the reclamation proposal
(e.g. introducing enough open space, limiting building height and
roof planting for industrial buildings / science park buildings) to
minimise the visual impact as far as possible.
(i) Carry out a built heritage survey, a built heritage impact assessment
and an archaeological impact assessment when the extent of the
associated works to occur on land is defined.
(j) Carry out a MAI which should cover the whole reclamation area
and the construction space including the related marine works
affecting the seabed, particularly a geophysical survey is
recommended to confirm that no wreckage of archaeological
importance is within the reclamation extent.
(k) Carry out a hazard assessment, if required, for the proposed land
uses and the interface with nearby existing and proposed
developments.
Infrastructures
Further studies on the water supply infrastructure, including water
treatment works, service reservoirs and pumping station, will be
required to formulate the implementation programme to ensure that this
essential infrastructure could be completed on time to tie in with the
target commissioning year of development at LKT reclamation.
246382/REP/024/02 Page 63
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Consultation
Apart from the needs of the society, views of the local community are
equally important in determining the development theme of the LKT
reclamation. The locals and villages concerned should be engaged in
the process of formulating the land use proposals.
Consultation of local community is an important step in assessing the
impact on cultural heritage. Relevant stakeholders should be consulted
earlier to gauge their views and address their concerns.
246382/REP/024/02 Page 64
Civil Engineering and Development Department Agreement No. CE27/2015(CE) Technical Study on Reclamation
at Lung Kwu Tan - Feasibility Study
Final Final Report
Drawings
246382/REP/024/02 Page 65
Æ 1
1.7 15.5 Z 0
0
1.7 10.3 ¸
806000 E
807000 E
808000 E
809000 E
810000 E
811000 E
DO NOT SCALE DRAWING. CHECK 4.8
ALL DIMENSIONS ON SITE.
4.2
ALL RIGHTS RESERVED.
0.9
NOTES
ADAD
c OVE ARUP & PARTNERS HONG KONG LIMITED. 11.3
13.8 6
RO
805000 E
9.7 O
18.1 R 1. ALL CO-ORDINATES ARE IN ACCORDANCE WITH HK(1980)
2.7 7.6 ¹q¤ NN
WAA
2.2
100 GRID CO-ORDINATE SYSTEM.
20 N Power Station 2
7.8
M W 0
NIM
16.8 4.7 0
7.7 I
2.3 20.5
12.2
BLACK POINT N
2. THE TOE LEVEL OF SEAWALL IS NOT SHOWN.
2.6
7.4 3.8
6.8
5.8
POWER STATION LEGEND
2.4
0.9
16.1
1.5
281
13.2 11.5
7.3 19.9
18 7.9
1.8 INDICATIVE EXISTING SEABED LEVEL
2.1 19.1
(METRE BELOW CHART DATUM)
10.7
6.7
2.3
830000 N
OPEN STORAGE OR WORKSHOP
2.8 9.5
16.2
8 BLACK POINT
20.4 14 4.1
RADAR STATION °t¤
2.3 16 Ser Res LUNG KWU TAN VILLAGE
8.6 100 20
19.2
7.2 100 0
2.4
11
2.3 18.7 POTENTIAL RECLAMATION AREA
135
1
2 3.9 21
16 Äê¨ 0
0 FOR INDUSTRIAL-BASED DEVELOPMENT
À
5.5 2
Black Point
1.5 (Lan Kok Tsui)
ROAD CONNECTION TO THE ADJOINING AREA
2.6 12.1
8.3 2.2
HELIPAD
16 13.9
1
9.3 15.2 -0.3
19.2
¹ 20.5
19.1
6.3
2.8
1.6
0.8
0.6
3.8
-0.5
LUNG KWU
Às¹ª
Lung Kwu
2.1
1.3
SHEUNG
Sheung TAN
Tan
3.8
1
11.9 1.8 0.7 LAU ANCESTRAL HALL
2.2
2.4
2.1 7.7
16.9
19.6
¤ 20.8
17 13.7
8 3 2.1
3
0.5
1.1
-0.3 -0.2
829000 N
13.7
1.7
2.1 -0.4
20.8
LU
16.1
1.7
N
9.5 11
5.9
G
1.6 1.2
-0.3
2.6 15.8
-0.2
13.6
LUN
KW G K
17.9 3
3.7
1.4
4.5 1.5 0.7
18.4
U
7.2
20.2
54
TAN TAN
11.6 13.3
WU
2.5
7.4 20.4
3.5
R O ROAD
2.4 200
2.2
17.8 1.6 1
AD
18.1
2
8.5 8
3 TIN HAU TEMPLE
20.4
Às
14
12.6
20.3
EXISTING LUNG KWU TAN
1.7 2.5
2.7 3.4 ÁA±
¹ª
15.4
SUBMARINE OUTFALL
12
4.5
2.9
0.6 Lookout VALLEY SSSI
2.8 7.9 19.7
15.8 7.9
6 ¥_
19.4
17.6
1.7
Pak Long 0
¤j§
828000 N 1.5 2.4
1.1 10
20.6 TAI LANG SHUI
ÀsÀÜ
16.6 13.3 7.5 1.7
Dragon
3.5
12.5 -0.4 Cove
«n
3.1
3.9
6.4
7.4 20.4
1.6
1.7 LUNG Nam Long
20.8 2.7
¨F® Às¹ The reclamation extent shown is
2.4 16.6 -0.3 KWU
Sha Po
1.5
0.6
LUNG KWU TAN preliminary only and is subject
21 18.9 11.3
7 1.4 Kong
TAN
20 0
17 to review in the next detailed
1.7 1.6 ¿w§
3.8
18.7 Tuk Mei studies including Environmental
6.1 4 1.5
8.2
Chung Impact Assessment.
U
7.8
1.5 LAU ANCESTRAL HALL
3.1
17 3
Lung Tsai
13 1.6
(GRADE 3 HISTORIC
5.4 19.4 -0.3 BUILDING)
M
4.8
21
12 3.3 1.8 1.8
8.2 12.7 0.4
Rev Description By Date
T
3.8 12.3
21
4.4 827000 N 1 19.6
Consultant
16.2 17.9
8 8.7
4.7 0.9
18.5
O
9 0.8
4.5
7.6 2.6
21 2.4 -0.5
50 -0.3
4.1 13.7
4.3
0 2.8
N
21
2 20.3
9.6
0.9
Contract No. and Title
20.2
2.6
U
3.3
13.8 14 ½ñ¥ -0.4
Agreement No. CE27/2015(CE)
R
7.1 18.8
75 4
M
7.5 18 6.1
1.7
Tap Shek
0.4 1 Kok
S
2.7
Technical Study on
T
21.5 1.1
0.5
O
N
7.7
13.8
Reclamation at Lung Kwu Tan -
1.4 12.3
R
0.5
8.3
LUNG KWU CHAU Feasibility Study
O
1.6 20.9
CASTLE PEAK
A
7.9
7.8 5.6
Às¹
J:\246382\ARUP\GEO\246382_GEN001.dgn
17.5 20.8
D
3.6 17
6.7 1.2 4.4
7 18
A
4.4 2.9 20.9 0.1
6.7 20
1.8 16.5 21
6.1
19.7
13.8 LUNG KWU TAN
826000 N
3.3
D 14.9
2.8
18.7
3.3 21 15.6
6.9 11.3 21
1.3
5.3
17.8 2.7
68 20.8 13.4
5.6
1.8 ¤ôª
3 20.2 Cement Works
13.7 20.6
6 5.8 17
17.3 16.9 Às MUN R
3.7 12.7 1 ª UNG
L
O
D AD
UN ROA
3.1 Drawing no. Rev.
5.6 LUNG M
7.6
246382/GEN/001 -
30/04/2018
13.4
18.9 21.5
4.8 8.5 11.9 ¿U®
10.5 Fuel Tank Drawn Date Checked Approved
20.6 19.9 17.3
4.7
4.5 20.3 RL 04/18 TL AC
5.4
3.6 Scale Status
4.6 11.9 10.6 5.4 1:20000 @ A3 PRELIMINARY
5.6
4.9 14.2
19.6 22 Àô«
6 21 7.6 COPYRIGHT RESERVED
19.7 17.8
EcoPark
SHA CHAU AND LUNG KWU CHAU MARINE PARK
nted by :
3.9 9.7
20.1
19.3 20.1
0 200 400 600 800 1000
4.1
4.6 4.8 Civil Engineering and
14.1 19.6 20.6
10.7
16.1 5.6 Development Department
5.2 METRES
Pri
l
6.7 13.5
Fi
1 : 20000
14.2
4.1 16.1