Key Plan

From LT Distribution panel of substation

REFERENCE:
01
3Rx1x185 NYY rm (3P) + 2Rx1x185 rm NYY (P+N) 02
1Rx1x185 rm NYY (E) 03
04
05

GENERAL NOTS

MCB
ON OFF TRIP TP

MCCB
800A, TP
36KA R Y B REV. DATE: DESCRIPTION:
I>
LSI protection 00 15.06.17 ISSUED FOR CONSTRUCTION
01 29.08.17 ISSUED FOR CONSTRUCTION

800/5A MFM
Cl: 0.5 PROJECT:

BITUMEN PLANT
FOR BASHUNDHARA OIL AND GAS COMPANT LTD.
AT HAZARIBAG, KONDA, KERANIGANJ, DHAKA.
415V,1000A, 3P+N+E, 50Hz,36KA for 3 sec Copper Bus Bar

OWNER :

BASHUNDHARA
OIL AND GAS COMPANY LTD.
MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCB MCB MCB
400A, TP 250A, TP 100A, TP 100A, TP 100A, TP 100A, TP 63A, TP 100A, TP 100A, TP 63A, TP MCB
32A, TP 16A, DP 20A, DP
36KA 36KA 25KA 25KA 25KA 25KA 16KA 25KA 25KA 16KA 32A, TP
I> I> I> I> 10KA 10KA 10KA PROJECT CONSULTANT :
LSI protection I> LSI protection LI protection LI protection LI protection LI protection I>
LI protection I>
LI protection I>
LI protection I>
LI protection I> 10KA
SHANDONG ZHONGTIAN TECHNOLOGY
& ENGINEERING CO., LTD.
1Rx1x185rm (3P) +1Rx1x185 rm (N)

ARCHITECTURAL DESIGN BY :

3Rx1x16rm + 1Rx1x16rm (4C)

3Rx1x16rm + 1Rx1x16rm (4C)


3Rx1x35rm + 1Rx1x16rm (4C)

3Rx1x35rm + 1Rx1x16rm (4C)


3Rx1x95rm + 1Rx1x50rm (4C)

3Rx1x35rm + 1Rx1x16rm (4C)

3Rx1x35rm + 1Rx1x16rm (4C)

3Rx1x35rm + 1Rx1x16rm (4C)

3Rx1x35rm + 1Rx1x16rm (4C)

3Rx1x6rm + 1Rx1x6rm (4C)

3Rx1x6rm + 1Rx1x6rm (4C)

1Rx1x4rm + 1Rx1x4rm (2C)

1Rx1x6rm + 1Rx1x6rm (2C)


MD. AZAD HOSSAIN
Dy. Chief Engineer, Design

1Rx1x1.5rm BYA (E)


1Rx1x2.5rm BYA (E)

1Rx1x2.5rm BYA (E)

1Rx1x2.5rm BYA (E)


1Rx1x6rm BYA (E)

1Rx1x6rm BYA (E)


1Rx1x95rm NYY (E)

1Rx1x10rm BYA (E)

1Rx1x10rm BYA (E)


1Rx1x10rm BYA (E)

1Rx1x10rm BYA (E)

1Rx1x10rm BYA (E)

1Rx1x10rm BYA (E)


1Rx1x95rm NYY (E)

STRUCTURAL DESIGN :

KHANDAKER KHAIRUL ALAM


B.Sc. in Civil Engg. (BUET)
Chief Engineer, BOGCL

ELECTRICAL DESIGN :

MOHAMMAD IQBAL HOSSAIN

SDB-IT HVAC-DB SDB-Grnd SDB-1st SDB-2nd SDB-3rd SDB-Lift SPARE-01 SPARE-02 SPARE-03 SPARE-04 SPARE-05 PUMP SPARE-06 DRAWING TITLE:
(Power Room)
Ground Floor Main
Electrical Distribution

DRAWING NUM: SHT. NO:

SCALE : Date: Rev.

as shown