Traffic Engineering Unit 4 Traffic Signals
Traffic Engineering Unit 4 Traffic Signals
stop signal on the traffic signals of the road intersection, these signals give the
3. Special types of Signals Or Flashing Beacons: These signals are used to warn the
traffic. When there is a red flashing signal, the drivers of vehicles must stop before
entering the nearest cross walk at the intersection or at a stop line where marked.
Flashing of yellow signals are used to direct the drivers of the vehicular traffic to
proceed with caution.
TRAFFIC STUDIES
3. TRAFFIC ACTUATED SIGNALS: In these signals the timings of the phase and
cycle are changed according to traffic demand.
• In fully-actuated signals, computers assign the right of way for the traffic
movement on turn basis of traffic flow demand. These signals are suitable on
the intersections where both side traffic is heavy so there is necessity of placing
detectors on sides of roads
TRAFFIC STUDIES
Terminologies
• At grade Intersection: All roads are crossing at same level
• Grade Separated intersections: All roads are nor crossing at same level
• Crossing Conflict: The crossing of vehicle at right angle to each other
• Merging and Diverging Conflicts: The crossing of vehicle along same
alignment direction.
• Total Conflicts during right, Left and straight movement from four directions
are 4 x 3 =12. Reducing the conflict is the necessity of Signals
• Level of Controlling the Conflicts:
• Level 1 – Providing the Basic Signs
• Level 2 – Direct assignment of Right of way using STOP or YIELD sign
• Level 3 – Traffic Signals
• Level 4 – Grade Separated Intersections
TRAFFIC STUDIES
Terminologies
TRAFFIC STUDIES
Terminologies
• Cycle – It is the one complete rotation through which all the indications like RED, AMBER
and GREEN are provided
• Cycle Length – The time required to complete a full sequence of traffic movements.
• Signal Phase – The portion of a signal cycle that serves a combination of traffic movements.
• Phase Sequence – The order of appearance of signal phases during a signal cycle.
• Signal System – Two or more traffic control signals operating in signal coordination.
• Signal Timing – The amount of time allocated for the display of a signal indication.
• Split – A portion of the cycle length allocated to each phase that may occur.
• Interval – A portion of a signal cycle where signal indications do not change.
• Offset – The time duration between the initiation of the progressed movement (phase)
common to any two signals at the two intersections. It is generally measured at the
downstream intersection relative to the upstream intersection.
TRAFFIC STUDIES
• Green Band – The amount of green time available to a group of vehicles in a progressive
signal system.
• Yellow Interval – This interval follows the green interval and is a warning for motorists to
slow down before the red interval is displayed.
• Red Interval – A very short period in a signal phase where traffic is stopped in all directions
and all signals display a “RED BALL” or “RED ARROW”.
• Walk Time – The time provided for a pedestrian, crossing in a crosswalk, to safely cross the
roadway. A “WALK” and “DON”T WALK” signal is displayed to direct pedestrians to cross the
roadway.
• Crosswalk – Any portion of a roadway distinctly designated for pedestrian crossing by lines
or other markings on the surface.
• Actuated Operation – Type of traffic signal control operation in which some or all signal
phases are actuated from vehicle detectors.
• Semi-actuated Operation – A type of traffic control signal in which at least one, but not
all, signal phases function on the basis of actuation.
TRAFFIC STUDIES
Solution –
Ymax = Critical flow rate – It is the ratio of Approach Flow (q) to Saturation
Flow (s) = q / S
Prob. - Average normal flow of traffic on cross roads A and B during design
period are 400 and 250 PCU per hour, the saturation flow values on these
roads are estimated as 1250 and 1000 PCU per hour respectively. The all
Red time required for pedestrians is 12 sec. Design two phase Signal by
WEBSTER’s Method
Sol. – ya = qa /Sa = 400 / 1250 = 0.32
yb = qb / Sb = 250 / 1000 = 0.25
So, Ymax = Ya + yb = 0.32 + 0.25 = 0.57
L = 2*n + R (where n = No of Phase and R is All red time)
= 2 * 2 + 12 = 16 Sec
• Optimum Cycle Time (C0) = (1.5 L + 5) / (1 – Ymax)
(C0) = (1.5 * 16 +5) / (1- 0.57) = 67.5 Sec.
• Effective Green time for A phase = Ga = (ya / Y)x (C0 – L)
= Ga = (0.32 / 0.57) x (67.5 -16) = 29 Sec
• Effective Green time for B phase = Gb = (yb / Y)x (C0 – L)
= Gb = (0.25 / 0.57) x (67.5 -16) = 22.5 Sec
TRAFFIC STUDIES
0.58
TRAFFIC STUDIES
IRC Method:
• The green time required for Vehicular traffic on MAJOR road is increased
in proportion to the two approach roads.
• The minimum GREEN time required for vehicular traffic on any of the
approaches is limited to 16 sec.