You are on page 1/ 34

2009

Software Ninjas

[IMPLEMENTATION AND
TESTING REPORT]
By Wesley Williams, Trey Bland, Jacob Boniface, and Kyle Snell
April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

TEAM MEMBERS
Wesley Williams
Project Manager
Software Ninjas
[email protected]

Herbert “Trey” Bland


Chief Requirements Engineer
Software Ninjas
[email protected]

Jacob Boniface
Chief Designer
Software Ninjas
[email protected]

Kyle Snell
Quality Assurance Engineer
Software Ninjas
[email protected]

2 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

TABLE OF CONTENTS

Introduction
Purpose of report 5

Problem description 5

Scope and objectives 5

Success criteria 5

Software functions 6

Software project plan 7

Requirements analysis models 10

Design models 17

Design constraints 17

Architectural design 17

Architectural styles 17

Architectural description 17

Subsystem description 18

Subsystem design 18

Class diagrams 19

Sequence diagrams 20

State diagrams 23

Software Ninjas | Restaurant Management Software 3


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

Implementation and Testing 25

Functions Implemented 25

User interface 26

Test plan 31

Responsibilities 32

Major problems 33

Tools 33

Data dictionary 34

4 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

INTRODUCTION

PROBLEM DESCRIPTION

Restaurant management can be a daunting task. Management software in restaurants tends to be barely usable
with features that seem geared towards tracking money and profits rather than being easy and intuitive to use.
Another problem that tends to plague some restaurant management systems is weak or non-existent security. In
many systems, some of the needed functionality is only available to the manager, so employees are granted access
to the manager-level functions which could potentially spell trouble for the managers. Perhaps it is the designer’s
lack of domain knowledge, or the lack of user involvement in the design process. Our goal is create restaurant
software that is easy to navigate and use and still has the security and features expected from quality restaurant
management software.

This report provides a view of how the design will unfold. We begin with an outline of the restaurant management
system functions. We then move into the software project plan and the requirements models from the previous
report. Next, we cover architecture of the system and sub-systems. Included are class, activity, state, and
sequence diagrams that show what our software is supposed to do and when it does it. Then we move into
implementation with real screenshots of the running software. Finally we introduce test cases and testing
practices.

SCOPE AND OBJECTIVES

It is our main objective is to create software that is usable, intuitive, simple, and functions well consistently. Our
chief concern is that our software be user friendly which means making menus effortlessly navigable and grouping
UI components in a manner that makes them easy to find. Giving each employee the appropriate level of access to
the required components is also imperative for usability and security. Are main focus in this particular software
endeavor is create a single working “point of management” system that acts as both a terminal for taking orders
and a terminal for generating reports and making changes to employees or items on the menu.

The software is responsible for a host of functions. Our software must be able to add employees, edit their
information, and remove employees from the employee database. Menu items must be added, edited, and
deleted from the menu item database. Items that can be ordered must be able to be added and removed from an
order. All employees must be able to clock in and clock out. Servers must be able to do what all employees do as
well as take orders. Managers should be able to do what all employees do and be able to edit item and employee
information and generate reports. Reports that should be generated include sales reports showing sales by food
category and the total sales from the start of the day. Orders should also be stored in the database to be used to
calculate total sales. For a complete look at desired functionality see page six.

SUCCESS CRITERIA

Our software will be successful if we can create system that addresses each stakeholder’s concerns. The software
must be secure, reliable, and above all usable. It is will also be a great success if we continue to meet the
deadlines for deliverables. Ultimately, success will depend on how well our team succeeds during usability testing.

Software Ninjas | Restaurant Management Software 5


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

SOFTWARE FUNCTIONS

1. Employee functions
1.1. clock in
1.2. clock out
2. Server functions
2.1. employee functions
2.2. take orders
2.2.1. select order from list of existing orders
2.2.2. add items to existing order
2.2.3. remove items from existing order
2.2.4. create new order
2.2.5. close order
2.2.6. add tip to order
2.2.7. add tax to order (automatic)
2.2.8. total price of order (automatic)
3. Manager functions
3.1. employee functions
3.2. server functions
3.3. manage employees
3.3.1. add an employee
3.3.2. remove an employee
3.3.3. edit an employee
3.3.3.1. change name
3.3.3.2. change address
3.3.3.3. change phone
3.3.3.4. change wages
3.3.3.5. edit clock in/out times
3.4. manage menu items
3.4.1. add new menu item
3.4.2. remove menu item
3.4.3. edit menu item
3.4.3.1. change item name
3.4.3.2. change item price
3.4.4. change tax (all menu items)
3.5. generate reports
3.5.1. generate sales report
3.5.1.1. calculate sales for each category of item (entrée, drink, dessert, and appetizer)
3.5.1.2. calculate total sales
3.5.2. generate labor report
3.5.2.1. calculate labor costs
3.5.2.2. calculate labor to sales ratio
3.5.3. generate “clocked in” report

6 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

RESOURCE LIST

type name description availability price

hardware computers To write the code high $500

software Pre-made code to run special hardware medium $25


components

Card reader To read debit/credit cards and employee high $50


devices IDs

human programmers To write the code for the system medium $1,000 per
week

manager To oversee the creation and installation of low $2,500 per


software week

Employee ID Hold information about employees high $5 per card


cards

software Window Visio To write diagrams to plan out work high $30
schedules

eclipse To write java code high $0

C sharp To write C++ code high $0

Windows XP For main interface to make the code in high $300

Table 1: List of Resources

The hardware resources are the physical components such as the actual point of sale computer and monitor along
with any equipment needed for programming and testing. The human resources are the programmers, testers,
and technical writers. Software resources are all the required software needed in order to generate code and
charts and graphs that illustrate the progress of the work. Many of these resources will be provided free of charge.
In an effort to simulate real world cost considerations in software engineering, we have researched several
vendors to determine the typical price for the indicated resources. These prices are given in the table above.

Software Ninjas | Restaurant Management Software 7


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

RESOURCE ESTIMATION

The resource requirements for this project are minimal. Computers and software development tools are provided
for development at the University. The project is designed so that a team a four can accomplish the goals within
the two months allotted. Since several of the programmers have had domain experience in restaurant and point
of sale operations, there is no need to hire or interrogate a domain expert. To implement the system, only a
computer with Windows installed and a magnetic card reader is required. More computers and readers may be
required for larger restaurants. The design of the database and user interface will take the most time and will
require diligence on the part of the programmers to ensure all work is completed and meets the requirements.

Responsibility Matrix
Task Herbert Kyle Jacob Wesley

Database
Design Tables X
Design Queries X
Coding for Database X

Clock In/Out System X

Sales System
Accept Payment X
Taking Orders X
Modify Orders X
Canceling Orders X

Reporting System
Sales Reports X
Labor Report X
Inventory Report X

Configuring Data
Edit/add Employee X
Edit/Add Product X
Edit Time Clock Entry X

Table 2: Responsibility Matrix

8 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

RISK PLAN

Risk Prob. Impact Priority Actions


Losing a project member 2 9 10 Make sure every team member has updated
copies of work done by all team members.
Hardware breaking down 4 2 10 Make sure every team member has updated
copies of work done by all team members.
Task takes longer than 3 3 2 Trey will be free for helping other members
expected once the initial setup of the database is
complete.

Table 3: Risk Assessment

PERFORMANCE ISSUES

There are several performance issues that may arise with this project. There will be many users logged in to the
system at any time. If there are too many users on the system there may be both network issues and data
integrity issues. We will need to guarantee exclusive access to data to make sure it is not accessed by another part
of the software while being changed. We must also be sure to remove any exclusive lock on the stored data when
other users require access to that data.

MANAGEMENT AND TECHNICAL CONSTRAINTS

The team is compromised of a group of individuals with diverse programming and technical backgrounds. Most
have experience programming in JAVA and .NET, so there are really very little constraints with expertise. Most
team members have a good grasp on the problem domain as many of them have worked in the restaurant industry
at some point in their lives.

Management is partially done via electronic means such as email and phone calls since many of the members have
different and often conflicting schedules. Each member holds the others accountable for the portion of work that
was assigned to them. The project manager schedules dates and times for meetings and organizes and assigns
tasks to team members. The main challenge will be communication, so the project manager will have to
communicate with team members on a near daily basis.

PROJECT MONITORING AND CONTROL MECHANISMS

To monitor status of the project at all times, electronic communication through email is necessary. Team
members are to update the other members with their portion of the work so that a consistent picture of the
software is available to all members. This ensures that the reports that are delivered depict an accurate snapshot
of the project at that time. Furthermore, the project manager schedules one meeting per week for face-to-face
communication and to verify the status of each task assigned to a member of the team. This is the time where a
team member can offer insight into task assigned to other members.

Software Ninjas | Restaurant Management Software 9


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

WORK BREAKDOWN STRUCTURE

1. Project Management
a. Monitor progress
i. Schedule meetings
ii. Peer evaluations
b. Estimate resources
i. Determine sources needed
ii. Check availability
c. Assess risks
i. Indentify risks
ii. Prepare contingencies
d. Evaluate results
i. Check to make sure everyone understands the requirements
ii. Identify weak areas and help strengthen them
2. Requirements
a. Analyzing Functional Requirements
i. Taking orders
ii. Keeping order history
iii. Tracking employees sales
iv. Generating sales reports
v. Tracking employee hours
b. Analyzing Non-functional requirements
i. Ease of use
ii. Security
3. System Design
a. User Interface Design
i. Logging on/off
ii. Clocking in/out
iii. Ordering food
iv. Accepting payment
v. Printing reports
vi. Configuring menu items
vii. Editing employee data
viii. Installing the software
ix. Removing the software
b. Database Design
i. Creating table of employees
ii. Creating table of orders
iii. Creating table of items
iv. Interfacing with UI
4. Testing/Debugging
5. Deployment

10 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Restaurant
Management
System Project

Project
Requirements System Design Testing/Debugging Deployment
Management

Analyze
Monitor Progress Functional User Interface
Requirements

Estimate Analyze non-


Database
Resources functional
requirements

Asses Risks

Work Breakdown Structure


(The First 2 Layers)

Evaluate Results

Figure 1: Work Breakdown Chart

Software Ninjas | Restaurant Management Software 11


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

GANTT CHART

Table 4: Gantt chart

Jan 2009 Feb 2009 Mar 2009 Apr 2009


ID Task Name Start Finish Duration
1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19

Group Formation and Project Selection


1 1/7/2009 1/15/2009 1.4w
Report Due
2 Requirements Engineering Report Due 1/16/2009 2/9/2009 3.4w

3 Create Use Cases and Models 2/9/2009 3/3/2009 3.4w

4 Software Design Report Due 2/9/2009 3/27/2009 7w

5 Create Program Database 3/2/2009 3/9/2009 1.2w

6 Prototyping 3/5/2009 3/24/2009 2.8w

7 Implement Sales 3/16/2009 3/30/2009 2.2w

8 Implement Manager Functions 3/16/2009 3/23/2009 1.2w

9 Testing 4/6/2009 4/27/2009 3.2w


Software Implementation and Testing
10 3/16/2009 4/27/2009 6.2w
Report Due

PERT CHART

Clock In/ Clock


Out

1 Week

2 Weeks 2 Weeks
3 Weeks 3 Weeks
Estimate
Design Sales Report
Resources / Sales Section
Database Section
Assess Risks

1 Week

2 Weeks

Manager Managers
Section Report Section

Figure: Pert Chart

12 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

ACTIVITY DIAGRAMS

[Exit Button Clicked]


Main Menu Log In
[Log In
[Clock In Button Exit Program
Button Clicked] Clicked]

Clock In/Clock Out Menu Prompt for ID

[Invalid ID]

Prompt for UserID [Valid ID]

[Invalid ID] Prompt for Password

[Rejected]

[Valid ID]

[Accepted]

Prompt for Password

[Rejected] A

[Accepted]

Update Timesheet Database

Figure: Activity Diagram 1

Software Ninjas | Restaurant Management Software 13


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

[Exit Button Clicked]


A Internal Menu (A) Exit

[Administrative
[Else] [Sales Button Clicked]
Button [Else]
Clicked]
[Return
Button
Clicked] [If useraccountlevel >=2]
[If useraccountlevel >=1]

Sales Menu B

[Begin Sale]

Item Rung Up/UI Updated


[Add
Another
Item]

[Finish
Sale]

Complete Sale

Update Order/Item Database

Figure: Activity Diagram 2

14 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

[Return
Button
Clicked]

Administrative Menu
[Employee
[Reports Management
Button Button Clicked]
[Return
Clicked]
Button
Clicked] [Sales
Management
[Return Button
Button Clicked]
Clicked]
Reports Menu Sales Management Employee Management

[Sales [Edit
Report [Inventory ]
Clicked] Report Clicked]

[Changes [Add/
Made] Remove]
[Labor
Generate Sales Report Report Generate Inventory Report
Clicked]
Add/Remove Employee Edit Employee

Generate Labor Report


Edit Inventory

Save Employee Database Changes

Save Inventory/Sales Database Changes

Figure: Activity Diagram 3

Software Ninjas | Restaurant Management Software 15


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

USE CASE DIAGRAM

System

Clock out

Sign In

Clock In
«uses»

Employee

Access Database Database Admin


«uses» Remove Item
«uses» «extends»
«uses»

Edit Order
«extends»
«extends» Add Item
«uses» Add Order

Add Employee
Remove Employee

Edit Employee
Server Manage Employee

Add Item to
Inventory

Remove Item from


Manage Inventory Inventory

Edit Item in
Inventory
Manager

Figure: Use case diagram

16 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

DESIGN MODELS

DESIGN CONSTRAINTS

There are several design constraints that must be addressed. The software will be designed to run in a Windows
environment. In order for the user interface to be a simple and navigable, we will be limiting the amount of
submenus and components on the graphical user interface. One of our goals is also security so we must
accommodate user ids and/or passwords. We are limited on time, so we have decided not to include the
inventory functions which represent a marginal difference from our plans during the requirements phase.

ARCHITECTURAL DESIGN

The architectural styles that suit this project are the three-tiered style and the shared-repository style. They
naturally lend themselves to situations calling for a central or underlying database of information. In this case, the
information is orders, employees, and menu items. This information has to be retrieved from the database by the
various subsystems, rearranged and formatted for output to the UI where it will be displayed in some fashion.

Below is one of the suggested architectures for this project, the thee-tier design. This particular design has a
hierarchal aspect where “ordering system” is an aggregate of the “cashing out” and “taking orders” subsystems.
This style is much more organized and is easy to follow.

Figure 2: Three Tier Architecture

Software Ninjas | Restaurant Management Software 17


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

The next architecture is the shared repository style where each subprogram has access to the database(s). In this
architecture, we lose the hierarchal capacity. This architecture is far simpler than the previous one. In this
example, the subsystems communicate with the database like they do in the other, but there is no sense of
ordering or hierarchy.

Figure 3: Shared Repository Architecture

SUBSYSTEMS

Each subsystem involves one of the primary functions of restaurant management. The clock in and clock out
subsystem is responsible for clocking in and clocking out employees as well as signing in employees to take orders
or manage the restaurant. The “taking orders” subsystem is responsible for creating new orders as well as adding
and removing menu items from an order. The “cashing out” subsystem will be responsible for accepting payment
and closing the order. The “editing employees” subsystem allows a user with manager privileges to add, remove,
or edit existing information about an employee. And finally the “editing items” subsystem will govern the adding,
removing, and editing of menu items. Class diagrams follow.

18 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

EmployeeUI SignInUI

OrderingUI ManageUI Compare

1 -displays 1 -displays

Clock 1 -displays 1 -returnsBoolean


1 -displays

1 -updates
1 -updates 1 -updates 1 -updates
-updateTime 1 1
1 MainSystem OrderManagement Manage
-Instantiates
-verifiesInput

1 1
1 -Queries 1 1 -Queries
1 1 -Instantiates
-Queries

1 1
-Responds -Responds

-Responds DatabaseManagement

Figure 4: Class Diagram of Subsystems

Clock
1
-hours : int
-minutes : int
-seconds : int

1..*

Employee
-Name : string 1 * Order
-Address : string
-Items[] : Item
-Wage : double
-Phone : int

1..*

Item
-Name : string
-Price : double

Figure 5: Class Diagram of objects

Software Ninjas | Restaurant Management Software 19


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

SEQUENCE DIAGRAMS

The edit Employee and edit Item functions were very simple design. First the user logs in to the management
menu then either selects an item or a employee and selects the edit button and proceeds to either the item or
employee edit menu. Then the user fills in whatever categories that are going to be changed and clicks OK or clicks
cancel to not make any changes at all (note: no change will be made if nothing is filled in). If changes are made
then the database for the item or employee is updated. The user will remain in the loop between the menus until
the user hits done which logs them out of the system.

Management Edit Employee Employee


Login Menu
Menu Menu Database

Login() [Done=false]
loop
SelectEmployeeAddHitEditButton()

alt
[Choice=cancel]
Cancel()

[Choice=enter]
EnterChangesAndPressOK()

OK()

Done()

Management
Login Menu Edit Item Menu Item Database
Menu

Login() loop [Done=false]

SelectItemAndHitEditbutton()

alt [Choice=cancel]
Cancel()

[Choice=enter] EnterChangesAndPressOK()

OK()

Done()

Figure 6: Edit employee (top) and edit item (bottom) sequence diagrams

20 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

To add and remove employees, the user logs in to the management menu, and in the case of removing an
item or employee, simply selecting an employee or item from the list on the screen and click the delete button
underneath the list. To add employees or item the user clicks add under the appropriate list, then the user is
prompted to enter data for the employee or item being added. The user keeps in this loop making these four
decisions until they select done which exits the loop and logs the user out.

Management Employee
Login Menu Item Database
Menu Database

Login()

loop [Choice!=done]

alt
[Choice=removeitem]

SelectItemAndHitOK()

[Choice=removeemployee]

SelectEmployeeAndHitOK()

[Choice=additem]

TypeDataAndHitOK()

[Choice=addemployee]

TypeDataAndHitOK()

Done()

Figure 7: Add/Remove Sequence Diagram

Software Ninjas | Restaurant Management Software 21


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

To take orders the user first logs into the Ordering System menu there once there the user selects from the lists
available what items are being order and clicks the add button under the specific list. If necessary the user can
select an item from the order list click the remove button below it to remove an item. When the user is finished
the user clicks the done button and to exit the loop. The user is logged off and the item and order databases are
updated.

Login Order Menu Order List Order Database Items Database

Loop

Login()

Alt [choice=Drink]

HitDrinkAdd()

[choice=Appetizer]

HitAppetizerAdd()

[choice=Entrees]

HitEntreesAdd()

[choice=Desserts]

HitDessertsAdd()

[choice=remove]
HitRemove()
Remove()

Update() UpdateOrderDatabase()

UpdateItemDatabase()
Done()

Figure 8: Ordering System

22 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

STATE DIAGRAMS

Below are state diagrams for the overall software as well as for the subsystems.

Main State Diagram


Button [value == exit]

Button [value == exit]

Ordering System

User [type == server]

Clock In / Out Report System


Button [value ==
Ordering System]
Button [value == exit]

Manager System
User [type == manager] Button [value ==
Report System]

Button [value == exit]

Figure 9: Main State Diagram

Software Ninjas | Restaurant Management Software 23


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

Idle
Id [value == noEmployee]

Employee [type == manager]


Is A Valid Employee B To Manager_System

Employee [type == server]

To Ordering_System A

Figure 10: Login System

Ordering State Diagram

Choose Table
Button [value == next]

Add Drinks
Button [value == next]

Button [value == add_next]


Add Appetizers
Button [value == next]

Add Entree
Button [value == add_next] Button [value == next]

Add Desert
Button [value == add_next]

Button [value == add_next]

Figure 11: Ordering System state diagram

24 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Load Employee Data

Mode [value == edit]

button [value == cancel]


mode wait Enter Employee Data
Mode [value == new]

button [value == ok]

Save Employee Data

Figure 12: Add/Edit Employee State Diagram

IMPLEMENTATION

The implementation phase of the project has by far been the most challenging of the phases of this project. Many
hopes and dreams were shattered. Because of the significant time constraint, many functions that initially seemed
trivial to implement became very time consuming to implement. Much functionality has been left out either due
to time or to manpower as many project members had other projects during the same period of time. Below is a
list of functions that we intended to implement. The highlighted ones are the ones that were actually
implemented as of the time of this writing.

FUNCTIONS IMPLEMENTED (HIGHLIGTED)

1. Employee functions
1.1. clock in
1.2. clock out
1.3. sign in
1.4. sign out
2. Server functions
2.1. employee functions
2.2. take orders
2.2.1. select order from list of existing orders
2.2.2. add items to existing order
2.2.3. remove items from existing order
2.2.4. create new order
2.2.5. close order
2.2.6. add tip to order
2.2.7. add tax to order (automatic)
2.2.8. total price of order (automatic)

Software Ninjas | Restaurant Management Software 25


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

3. Manager functions
3.1. employee functions
3.2. server functions
3.3. manage employees
3.3.1. add an employee
3.3.2. remove an employee
3.3.3. edit an employee
3.3.3.1. change name
3.3.3.2. change id
3.3.3.3. change wages
3.3.3.4. edit clock in/out times
3.4. manage menu items
3.4.1. add new menu item
3.4.2. remove menu item
3.4.3. edit menu item
3.4.3.1. change item name
3.4.3.2. change item price
3.4.4. change tax (all menu items)
3.5. generate reports
3.5.1. generate sales report
3.5.1.1. calculate sales for each category of item (entrée, drink, dessert, and appetizer)
3.5.1.2. calculate total sales
3.5.2. generate labor report
3.5.2.1. calculate labor costs
3.5.2.2. calculate labor to sales ratio
3.5.3. generate “clocked in” report

Despite the many functions that were not implemented, much of the framework for the unimplemented functions
exists and can easily be added to in the future. The graphical user interface was by far the most time consuming
task of the entire project. Perhaps using a builder of some sort, would have proven more efficient.

USER INTERFACE DESIGN

Because of the nature of our project, an intuitive graphical user interface is required. Initially designed by Jacob
Boniface, the user interface design below is the JAVA Swing equivalent of the earlier design. There are a few
alterations that had to be made. The buttons on the far right side on each screen have been removed and put
onto a single menu accessible after login. On the first screen visible to the user we have removed all buttons
except the sign in button. The functionality that was originally on this particular screen has been moved to
subsequent menus and screens. In addition, we have added the clock functionality to every screen in the program
so that no matter which screen an employee is viewing, he or she will be able to keep track of time.

26 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Figure 13: First user screen

The next screen is where the employee can choose which tasks he or she wants to do. Options that appear grayed
out are not available for the user that has logged in. Managers have all options, servers have all options except the
management button, and finally normal employee are only granted access to system to log in and log out. All
orders that are currently “owned” by this particular employee are listed in the list above the “add” and “edit”
buttons. Below are three screenshots that show this.

Figure 14: Employee Task Menu

Software Ninjas | Restaurant Management Software 27


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

Figure 15: Server Task Menu

Figure 16: Manager Task Menu

Management menu functions include the ability to add and remove employees as well as items. Although our
group did not implement report generation, report generation would be completed from the management menu.
Below are screenshots of the management menu and the various submenus for editing employees and items.

28 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Figure 17: Ordering menu

Figure 18: Edit Employee

Software Ninjas | Restaurant Management Software 29


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

Figure 19: Edit Item Menu

Figure 20: Item Type Selection

The ordering screen allows a server or manager to create an order by selecting from four lists that represent the
four types of food: beverage, appetizer, entrée, or dessert. When the item is selected, pressing the add button
below the list adds the item to a fifth list which is the actual customer order. When the screen is exited, the
information is stored in the database. All the screens are periodically updated with the current contents of the
database. The figure below is the ordering screen.

30 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Figure 21: Ordering Screen

TEST PLAN

The test plan for the Adios system can be summed up into our three major goals: reliability, security, and usability.
Reliability is the first of the goals. The software must be able to do the requested function and perform in a
predictable way. The second goal is security. The program must provide the correct functionality to the employee
authorized to execute those functions. Lastly, the third and most important goal is usability. We want to make
sure our product does more the simply work; we want it to be usable.

Reliability and security testing can be accommodated by merely constructing a few test cases and comparing what
the result should be versus what the result is. Usability testing, however, is completely different. Usability testing
would require some domain experts to use the software and perhaps even deploy the software in a restaurant
environment. Due to the time constraints of the project we were unable to perform any formal usability testing.

Test cases were created to test adding, deleting, and editing both items and employees. Specifically these test
cases make certain that employee and items are stored and retrieved from the database correctly. Test cases
were also generated to perform boundary testing on how many entries could be successfully added or updated. In
addition, test cases where created to verify the function of the compare class, which is used to validate input. The
table of test cases listed on the following page shows what kinds of tests were performed on the “add new
employee” function, the intended results, and the actual results.

Software Ninjas | Restaurant Management Software 31


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

Test Case # Description Intended result Actual result Completed by


1 Add new employee (0, Employee(1, Devon, Employee(1, Wesley Williams
Devon, Simmonds, 12.35, Simmonds, 12.35, 3245) Devon, Simmonds,
3245) MANAGER 12.35, 3245)
MANAGER
2 Add new employee (0, Employee(2,John, Smith, Employee(2,John, Wesley Williams
John, Smith, 21.55, 1245) 21.55, 1245) Smith, 21.55, 1245)
SERVER SERVER
3 Add new employee (0, Employee(3, Dan, Rather, Employee(3, Dan, Wesley Williams
Dan, Rather, 14.35, 378) 14.35, 378) NORMAL Rather, 14.35, 378)
NORMAL
4 Add new employee(0, 45, Error Employee(0, 45, Wesley Williams
54, 23.12, 234) 54, 23.12, 234)
NORMAL
5 Add new employee(0, Error Error Wesley Williams
Hugh, Laurie, -13.45, 546)
6 Add new employee(0, Error Error Wesley Williams
William, Shatner, 27.68, -
1532)
7 Add new employee(0, Error Employee(0, Wesley Williams
Hernan, Cortez, 5.68, 10) Hernan, Cortez,
5.68, 10)

As you can see, two of the test cases above did not pass. There are some bugs with the compare class that need to
be worked out. Namely, the compare class should be able to refuse any sales ID (the last argument in the method
signature) that is less than three digits and it should prevent a user from entering numbers as the only characters
in names. Further testing is required to verify complete operation. These bugs and bugs found in other tests would
need to be fixed and retested before release.

IMPLEMENTATION AND TESTING PHASE RESPONSIBILITES

Most of the coding was done in CIS 2004. This is a computer lab located in the Computer Information Systems
building at the University of North Carolina at Wilmington. The lab was the chosen place for meetings because
along with computers installed with the software we required, the room afforded us the opportunity to use the
white board for drawing diagrams and clarifying implementation details. Implementation and testing started in
th
early April and continued until April 26 . Below is a table of responsibilities. It includes what was done as well as
who completed it.

Task Herbert Kyle Jacob Wesley

UI
Design X X X X
Coding X

Database
Table Design X X X X
Query Design X

32 CSC 450 Software Engineering | Software Ninjas


[IMPLEMENTATION AND TESTING REPORT] April 27, 2009

Coding X

Program
Sales System X X
Management System X
Logon System X
Input Validation X X

Testing
Testing Approach X X X X
Test Cases X X

Presentation
PowerPoint X
Report X X X X

Table 5: Implementation responsibility matrix

IMPLEMENTATION & TESTING - MAJOR PROBLEMS

By far the biggest challenge encountered was time constraints. Implementation takes an extraordinary amount of
time and a large amount of coordination. Scheduling project meetings around every group member’s schedule has
been nearly impossible. Many of the group members were unable to devote the amount of focus that the
implementation stage required. Both the former and the latter problem may be more of an issue in the academic
environment where priorities of the different group members are skewed in a variety of directions. Another issue
that cropped up was knowledge of the JAVA programming language. At least two of the four group members were
unfamiliar with JAVA’s Swing API, which is JAVA’s primary user interface package. Again, this may not be as much
of an issue in software engineering outside the academic arena.

One of tools we found very useful, in situations where member responsibilities need to be hashed out, is the
responsibility matrix. It has really been the only tool that has allowed us to continue making progress. Everyone is
assigned a task, and everyone is held accountable for the completion of their assigned task. It also allows us to
track tasks that need to be done. The responsibility matrix has proven to be an invaluable tool in the software
engineering process

TOOLS

Tool Description
Computer MS Windows XP, 2 GB DDR2 RAM
Eclipse JAVA integrated development environment
GIMP Graphics design program
MS Word Word processor

Table 6: Tools Required in Implementation

Software Ninjas | Restaurant Management Software 33


April 27, 2009 [IMPLEMENTATION AND TESTING REPORT]

DATA DICTIONARY

Clock in (out)
To keep track of hours worked, an employee must clock in with an ID.
Item
Item is anything that is sold though the POS. Item attributes include name, id number, price and quantity. Any
item will also have a location that it prints when it is ordered and a category that it belongs to on the menu.
This will also include any ingredients that other products are made.
Item type
An item type is an enumerated variable that holds string constants representing the different kinds of
items that can be ordered. For instance, a soda would be listed under the BEVERAGE item type, and mozzarella
would be listed under the APPETIZER item type.
Employee
Employee is anyone that has access to the system. Employee attributes include id number, name,
address, phone number, current pay rate, password and level of authorization (for system security purpose
only)
Employee type
An employee type is an enumerated variable that holds string constants representing the different
levels of employment within the restaurant. There are three possible strings, MANAGER, SERVER, and NORMAL.
Orders
An order is a collection of items. Order attributes include an id number, an employee that ordered the item and
the id of the item ordered. An order would be similar to a receipt grouping in a retail point-of-sale system.
Sign in (out)
To receive the functionality granted to servers and managers, an authorized employee must sign in to
the system so that all transactions that occur are presented as being from said employee

34 CSC 450 Software Engineering | Software Ninjas