Chapter 8 - Final
Chapter 8 - Final
1
a) Reliability prediction
2
Reliability prediction is important for the
following reasons:
It provides an early indication of a system’s potential
to meet the design reliability requirements.
It enables an assessment of life cycle costs to be
carried out.
It enables establishment of areas which contribute
major part system unreliability.
It enables the achievement of a given availability.
It provides prior knowledge as to the magnitude of
expected maintenance work load.
3
For the purpose of analysis, a large and complex plant
is regarded as a hierarchy of parts ranked according to
their function and replaceability.
The figure below shows how a plant can be divided to
its basic components.
4
Hierarchy of parts of a plant
-Performing major
UNITS plant functions
-Non-replaceable
ITEMS -Replaceable complex
-Replaceable simple
-Individual parts
COMPONENTS -Simple replaceable
5
Block Diagram Analysis
Block diagrams are logic diagrams which show the functional
relationship among the system elements.
7
Block interconnections
a) Series-connected components
For such a system to work all components must work. For a
system of two blocks failure of either block prevents operation
of the system.
A B
Rsy t R1 A
t R2 t Rn t
8
Reliability of a component is
Ri t exp i t dt
t
0
System reliability is
n t t n
Rsy t exp i t dt exp i t dt
i 1 0 0 i 1
1.00
R sy
n increasing
0.0
1.00 0.0
R unit
1.00
10
For constant failure rates, system MTBF is
n
MTBF Rt dt exp i t dt
t t 1
n
i 1
0 0
i
i 1
11
Example
12
Solution
13
Example
14
Solution
15
b) Parallel-connected components
For such a system,
A system failure
B constitutes failure of all
components. The system of two blocks fails if both
blocks fail.
A
17
Assuming the failure probabilities of components A and B to
be FA t and FB t , respectively, the probability that the
system fails is given by
Fsy t FA t FB t
The survival probability is then
Rsy t 1 Fsy t
If survival probabilities of the components are RA t and
RB t , the system reliability is given by
Rsy t RA t RB t RA t RB t
18
For n redundant units
Rsy 1 11.00
R1 t 1 R2 t0.0
1 Rn t
0.0
R unit
1.00
R sy n increasing
0.0
1.00 0.0
R unit
19
For full active redundancy and constant failure rate λ for
each component, system MTBF is
0
t
0
MTBF Rsy t dt 1 1 e dt
t n
n
1 1
i 1 i
20
Example
21
Solution
22
ii) Partial Active Redundancy
Partial active redundancy is also known as r-out-of-m
unit network. At least r units out of m active units must
function successfully for the system success. The system
reliability is given by
m t i
m
Rsy e t m i
1 e
i r r
m m!
r i!m i !
23
The MTBF of partially active redundant systems, with
constant failure rate λ, is given by
m m t i
MTBF e
t
1 e t
m i
dt
ir r
0
1 m 1
i r i
24
Example
25
Solution
26
iii) Parallel Redundant System in Standby
In the standby configuration one or more subsystems are ready to
senses the failure of the basic unit and turns on and connects the
standby unit.
B
27
In parallel systems in standby, the following assumptions are
initially made.
The means of sensing that failure has occurred and for
switching from the defective to the standby is assumed to
be failure free.
The standby subsystems are assumed to have identical,
constant failure rates to the main subsystem.
The standby subsystems are assumed not to fail while in the
idle state.
Defective subsystems are assumed to remain so, No repair is
28
effected until the system has failed.
The Poisson distribution is used to determine the reliability of
2!
For a system with n standby units, system reliability is
Rsy 1 t
t
2
t t
n 1
e
2 ! n 1 !
29
Assuming that the switching process does not affect the basic
unit, for one standby unit, the system reliability is given by
Rsy e t
Rsw t e t
Rsy e t
Rsw t
t
2
t t
n 1
e
2 ! n 1 !
30
MTBF of a system with n-1 standby units is
t
1 t
t
t
2 n
dt
0
2! n 1!
For a constant failure rate λ of all units, the reliability is
n
MTBF
31
Example
32
Solution
33
c) Composite connection
A
This is a combination of series and parallel connections. For the
B
A
34
d) Neither Series Nor Parallel Connections
These are cases in which the system configuration cannot be
A C B
A' B'
35
For such situations where uncertainty exists to the
System success requires that at least one of the paths AA’, BB’,
37
Hence, system reliability is given by the sum of the above
reliability terms
38
Thank you
If you have any questions ???
39
b) Maintainability prediction
In assigning any maintenance workload, it is important to
specify the time during which the job has to be accomplished.
Doing this will help optimize the resource allocation and will
help eliminating idle man-hour, idle machine time and so on.
41
The maintainability probability function for maximum
time is
t M max
M t M max 1 e MTTR
In general,
t M max
M t M max 1 1 e MTTR
This yields
t M max
ln
MTTR
42
Given
M t M max and knowing the MTTR of an
equipment, the maximum time required for a
maintenance task is
1 M t M max
43
Case of t not constant
44
Let
t dt v t dt dv
t
M t e dv e |
t
v v t
0
0
Upon simplification,
t
t dt
M t 1 e 0
45
Given M t and g t , the repair rate can be
determined from
g t
t
1 M t
46
For times-to-restore probability distribution is given by
Weibull pdf,
t
1
M t1 1 e
47
Thank you
If you have any questions ???
48