VRF Installation Guide - HVAC & Engineering
VRF Installation Guide - HVAC & Engineering
VRF installation is not similar to split ac installation, some important guidelines you must
follow if you are planning for your VRF installation process.
Installation Flowchart
Once pipe sizes are selected, piping routes are finalized, & indoor & outdoor unit locations
are freezed, now its time to start installation process. Let’s see some important tips before
Main tools
Copper Piping storage Tips
If pipes will be used soon, nozzle should be sealed by plastic bag or tape.
If pipes will be stored for a long time, the pipes should be charged with 0.2~0.5MPa
Nitrogen and the nozzle should be sealed by welding.
Supports must be strong enough. The supports should be full thread hooks, and their
diameters should be ≥ 10mm.
Dual nuts should be adopted to fix the indoor unit under the ceiling.
Use level meter to keep the indoor unit horizontally to reduce the running noise and avoid
the condensate water spill from the water collector.
Pack the indoor unit with plastic bag after hoisting to protect them from dust entering.
Typical mistakes
Access hole-Access hole for easy maintenance and service.
Location
Provide sufficient space around the unit for servicing and air circulation.
Make sure the installation site withstands the unit’s weight and vibration.
Make sure the area is well ventilated. Do NOT block any ventilation openings.
Make sure the unit is level.
All the outdoor units in one combination should be on the same level.
Depending on the height of adjacent walls relative to the height of the units, ducting
may be required to ensure proper air discharge. In the situation depicted in below
figure, the vertical section of ducting should be at least H-h high.
In systems with multiple outdoor units, the units should be placed in order from
largest capacity unit to smallest capacity unit. The largest capacity unit must be placed
on the first branch, and be set as the master unit, while the others should be set as
slave units.
All the outdoor units in one combination should be on the same level.
Base structures
3.Piping installation
Pipe cutting
Pipe insulation
Purpose
Caution: After finishing gastight test, the insulation work should be done
on the pipe connection parts and branch pipes.
Refrigerant piping insulation should be closed-cell foam of B1 fire
resistance rating that can withstand a constant temperature of over 120oC
and that complies with all applicable legislation.
The insulating material should be a suitable thickness and the inner diameter should
match the size of refrigerant pipes
Block the nozzle of the pipe when make it through the insulation material.
The gap between two parts should be well insulated by additional insulation material.
The insulation of liquid pipe and gas pipe must be separate.
The insulation work must be done on every part of the refrigerant pipes.
Pipe hanging
When the liquid pipe and gas pipe are hung up together, it is determined by the
diameter of liquid pipe.
Record the actual liquid pipe length for future reference when charging additional
refrigerant.
Pipe connection
To avoid accumulation of oil in the outdoor units, outdoor branch joints should be
installed horizontally and must not be higher than the outdoor unit refrigerant outlets.
Horizontal branch joints must be installed at an angle to the horizontal not exceeding
10o in order to avoid uneven distribution of refrigerant and possible malfunction.
Welding
Never flow oxygen through piping as doing so aids oxidation and could easily lead to
explosion and as such is extremely dangerous.
Use a pressure reducing valve to flow nitrogen through copper piping at 0.02-0.03MPa
during welding.
Start the flow before brazing starts and ensure that the nitrogen continuously passes
through the section being welded until the welding is complete and the copper has
cooled down completely.
4.Flushing
Purpose: to remove dust, other particles and moisture, which could cause
compressor malfunction.
Flushing should be performed once the piping connections have been completed with
the exception of the final connections to the indoor units.
Only use nitrogen for flushing.
Procedure:
The liquid and gas sides can be flushed simultaneously; alternatively, one side can be flushed
first and then for the other side
1. Use blind plugs to block all liquid (gas) side openings, except for the opening at the
indoor unit which is farthest from the outdoor units .
2. Flush the pipe with 0.5 MPa Nitrogen.
3. Use your hand to block the opening, when the pressure is too high to block, then
remove your hand.
4. Repeat the step 3 until on further dirt or moisture is emitted from the piping. Seal the
opening once it has been flushed.
5. Flushing the other openings in the same manner, working in sequence from the
farthest indoor unit towards the outdoor unit.
6. After flushing, seal all the openings.
5.Gas tightness test
Correcting formula:
Actual value
Example:
= 3.8MPa -0.02MPa
= 3.78MPa
If the actual pressure after 24hours is lower than 3.78MPa, you need to check
leakage.
6.Vacuum
Only charge refrigerant after performing a gastightness test and vacuum drying.
Never charge more refrigerant than required as doing so can lead to liquid
hammering.
Only use refrigerant R410A, use tools and equipment designed for use with R410A.
Always use protective gloves and protect your eyes when charging refrigerant.
The additional refrigerant charge required depends on the lengths and diameters of
the outdoor and indoor liquid pipes.
Assume 0.5m for the equivalent pipe length of each branch joint.
11. Drain Piping
Caution:
Some kinds of indoor units have built-in drain pump, the pumping head is 750mm at
most.
Lifting the drainage pipe outlet to form the slope.
To avoid the water flow back to the indoor unit, branch drain piping should join main
drain piping from the top.
To avoid backflow and other potential complications, two horizontal drain pipes should
not meet at the same level.
Air vents should be fitted at the highest point of each drain piping system to ensure
that condensation is discharged smoothly.
U-bends or elbow joints should be used such that the vents face downwards, to
prevent dust entering the piping.
Air vents should not be installed too close to indoor unit lift pumps.
Watertightness test- Fill the piping with water and test for leakages over a 24-hour
period.
Water flow test (natural drainage test)– Slowly fill the drainage pan of each indoor
unit with at least 600ml of water through the inspection port and check that the water
is discharged through the outlet of the drain piping.
All the indoor units which connected to one outdoor system must be connected to
one power supply
Why should all the indoor units which belong to one system have same power supply?
If an indoor unit that is running were to suddenly power off whilst the other indoor
units continued running, the evaporator of the powered-off unit would freeze since
refrigerant would continue flowing to that unit (its expansion valve would still be open)
but its fan would have stopped. The indoor units that remain running would not get
sufficient refrigerant so their performance would suffer.
Additionally, liquid refrigerant returning directly to the compressor from the powered-
off unit would cause liquid hammering, potentially damaging the compressor.
For indoor / outdoor unit power wire sizing and circuit breaker sizing, refer to indoor /
outdoor unit “Electrical Characteristics” of respective machines as per manual provided
by manufacturer.
Select wire size based on the value of MCA in “Electrical Characteristics”.
Select overcurrent circuit breakers and residual-current circuit breakers based on the
value of MFA in “Electrical Characteristics”.
Communication wiring
Precautions:
To prevent signal interference, the power wiring and communication wiring should not
be run in the same conduit.
If the power supply is less than 10A, a separation of at least 300mm between power
wiring and communication wiring conduits should be maintained
If the power supply is in the range 10A to 50A then a separation of at least 500mm
should be maintained.