PROCEDURE FOR
CONVENTIONAL FORMWORK
TABLE OF CONTENTS
Chapter Page
Title of chapter
No. No.
1 Purpose 2
2 Scope 2
3 Responsibility 3
4 Flow Chart 3
5 Materials 5
6 Procedure 14
7 Typical Cycle 24
8 Tools and Tackles 26
9 Referance 27
10 Tolerance and Acceptance Criteria 27
11 Do’s and Don’ts 28
1. PURPOSE:
2. SCOPE:
2
3. RESPONSIBILITY:
Task Responsibility
Completion of works as per relevant WPM
(work procedure manual), latest GFC Building In-charges / MLDL,
drawings, latest approved revision of PQP Contractor
(Project Quality Plan)
Engineer In charge - Main
Inspection & approval of work as per this
Contractor Engineer in charge
SOP
- MLDL
Random checking and inspection QC in charge/ MLDL.
Stage Clearance for next activity, Training QC In charge ,MLDL Project
& Awareness on SOP Head
4. FLOW CHART:
START
3
4
5.0 MATERIALS:
Height Self - Axial Load
Prop
Closed Extended Closed Extended
¡
5
£
£
Height Self - Axial Load (kg)
Closed Extended Closed Extended
¢
Total load Permissible clear span for center line spacing (in mm)
including 180
kg/sq.m. for 300 mm 450 mm 600 mm 800 mm 900 mm 1150 mm
Slab Thickness
shuttering & spacing spacing spacing spacing spacing spacing
live load
Kg/sq.m.
¡
¡
¡ ¡
¡ ¡
¡
¡ ¡
¡
¡
¡
¡ ¡ ¡ ¡
6
¤
¤
¥
7
¢ ¢
¢
¢
¢ ¥
£
£¦¡
¦
¦
£
£ ¦
£
£
8
£ ¦
£
£
¦
¦
££££
£
£
¦
£
£
£
£
£
£
¥ £
¥ £
¥ £
9
¤
Form work Frequency of
Inspection Acceptance criteria
material inspection
10
Frequency of
Material Inspection Acceptance criteria inspection
§
¨
¢
¥¥
¢
£
¡
¥
¢
£
£
£
11
¥
£
£
£
£
12
¤£
£
£
¢ ©
£
¥
£¥
£
ª£
¥£
£
13
5. PROCEDURE:
¢
¥
¡ §
¢
14
¤
¢
¥
¥
¥
¥
¥
¢ ¢ ¢
¥
¡ ¥
¥
§
15
¥
«
¬
« ®
¯¯«°¯°¯
¯¯«°¯
16
17
18
ª
£
19
¥
¥
¥
¢
¥
ª¢
ª
¡
¥
¥
20
¥
¢
¥
¡
¡
¢
¤
21
¥
¥
¥
¥
±
±
22
Formwork De- shuttering Period
¦
¦
¦
¢
¢
23
7. TYPICAL CYCLE:
24
25
8. TOOLS AND TACKLES:
26
9. REFERANCE:
¥
¥
10. TOLERANCES AND ACCEPTANCE CRITERIA:
Walls, columns and vertical
16 to 24 hrs. or as directed by Engineer In Charge
sides of beam.
Slab props left under 7 days
Beam soffit props left under 10 days
1. Spanning up to 4.5 m - 10 days
Removal of Slab Props:
2. Spanning over 4.5 m - 14 days
Removal of props for beams 1. Spanning up to 6 m - 14 days
and Arched: 2. Spanning over 6 m - 21 days
1) Formwork must be free from defects
2) Before concreting, the interior must be free of debris
3) All formwork joints must not have gaps to prevent slurry
Condition of formwork, Props, leakage.
and bracing 4) There must be adequate support, bracing and tie-back for
the formwork (as per formwork shop drawings approved by
structural engineer) to prevent bulging or displacement of
structural elements.
27
9. DO’S AND DON’TS:
¢
¢
¢
DO’S DONT’S
28