Method of Statement - Concrete Works
Method of Statement - Concrete Works
Concrete Works
TABLEOF CONTENTS
1
SECTION ITEM PAGE NO.
1.0 INTRODUCTION 3
5.0 RESPONSIBILITIES 4
7.0 PROGRAM 13
2
12.0 HEALTH SAFETY & ENVIRONMENT 15
13.0 APPENDICES 17
A3. Checklist
1. INTRODUCTION:
This document defines the methodology, sequence, control measures, safety and quality control
requirements, and equipment to be used in performing the works as established in the project
specifications and relevant referenced documents.
2. Scope of Works.
- The scope of work described in this method statement is applicable for Concrete Works.
For Proposed G+19 (G+3P+16F+R) Residential Building, Business Bay, Dubai,
UAE.
3. Reference.
Prior to works commencing, the Site Engineer shall ensure that the following activities have been completed and
signed-off by the Consultant:
> Project Specification
> IFC Drawings / Approved DM Drawings
> Shop drawings submittal
> Bill of Quantities (BOQ)
> Project Quality Plan
3
> Project HSE Plan
> DDA & DEWA requirements
5. Responsibilities.
A full and detailed description of the roles and responsibilities of all contractor staff is included
within the Project Quality Plan. For the works as covered by this method statement.
- Project Director
To ensure that the work procedure is safe & activities are carried out according to approved MS,
shop drawing and specified quality is achieved to the Engineer's satisfaction.
Overall Management of the Site Team and Project Programs, including the
current subject. He is responsible to plan and manage all tasks related to submittals /execution
of this activity to the completion and to take the requested corrective action related to any
raised NCR. He is also responsible to coordinate with the Consultant and with other concerned
persons to finalize any variation/ problem related to this activity.
- The SE/Foreman
Is responsible to organize the work in a safe and efficient manner, including
all safety requirements and PPE, implementation of the work as per the MS and the ITP.
5
- Subcontractors
1-Specific responsibilities include:
-To undertake their works as specified.
-To work in a safe manner.
-To ensure all operatives are adequately training in their respective works.
-Report any unsafe practices on site to the contractor site team.
6.1 EQUIPMENTS
- Uni-loader (Bobcat) - Water Hose
- Survey total station (to mark the layout - Chalk Markers, Pen Markers
- Generator - Sprit level
- Saw cutting machine - String line
- Abrasive grinder - Hand trowel with notched edge
- Concrete chipping tools (light vibration) - Air compressor
- Chisel - Slump Cone
- Transit Mixers - Thermometer
- Concrete Pump - Measuring Jar
- Water Tanks (5000/3000 gallons) - Spirit Level, Right Angle, and Plumb Bob
- Air Compressor - Total Station
- Mechanical Vibrator - Wheel Barrows
- Masonry tools (trowels & hand tools) - Cube Moulds
- Auto Level - Drill machine
- Power float/Polythene sheet
6.2 Materials
Concrete as per approved mix design Form ties, form release agent, curing
compound,
spacers other materials as per approved
drawings
Potable water Approved type of cover block
Reinforcement Binding wire of approved type (As per
approval)
Binding wire of approved type (As per
approval)
6.3 Resources
PROJECT MANAGER Steel fixer
CONSTRUCTION MANAGER Carpenter
6
PROJECT ENGINEER Plumber
SITE ENGINEER Helper
SITE Supervisor Operators
FORMAN Drivers
MEP ENGINEER Mechanics
QA/QC Engineer
Concrete technicians
- The surface to receive the blinding concrete has to be free of loose particles & dust.
- Blinding concrete level will be marked as per the drawing, once the surface has achieved the
7.2 Reinforcement
- Area will be surveyed by SCEGC surveyor and mark as per the approved layout and shop
drawings.
Only approved bar bending schedule & shop drawings will be used for cutting and bending of
rebar's. Concrete cover blocks will be fixed (Same strength of concrete) to the reinforcement at
proper spacing as per mentioned size in the relevant drawings.
- Care will be taken to ensure that the tie wire used and are trimmed properly
- Spacing and sizes of rebar, line and Levels, will be checked prior to placement of concrete, as a
part of Inspection procedure.
- Only approved material for MEP embedded items as per specification & relevant drawings will be
used. All the embedded items will be properly secured in position and levels shown in approved
7
shop drawings before placing of concrete and will be checked.
8 PPROGRAM
9 QA/QC
The complete work shall be inspected by the consultant and approval shall be obtained for the
same. The following shall be maintained to control the Quality of work:
- Inspection &Test Plan
- Inspection Request
- Check Sheets
Method Statements shall be reviewed and approved internally by the Project Manager and
HSE Lead Engineer being issued for site operation. The assigned Construction Manager shall
ensure that the method statement and risk assessments are communicated to the site
execution team. Records and signatures shall be maintained by the Construction Manager.
3- Risk Assessments
The Project Manager and HSE Manager shall identify the potential hazards before starting
any activities on project site and they will plan a proper safety procedures and measures to
mitigate or eliminate these defined hazards. Also risks assessment shall be carried out
whereby various activities are identified along with their possible dangers and hazards. The
existing controls are checked for adequacy and fit requires an additional controls and
resources to mitigate the consequences of possible incident, SCEGC shall deploy and provide
such measures.
Risk assessments shall be produced for all tasks described in this method statement. Risk
assessments shall be communicated to the workforce prior to commencement of works.
Risk assessment is attached as with this method statement.
10
7- Competence and certification
UG services operators shall be 3rd party trained and competent.
All drivers shall be holding valid UAE incense and defensive driving training.
All Plant and Equipment operators shall be holding valid UAE driving license and approved
Third Party Certificate.
All Plant and Equipment shall have a valid Third-Party Inspection Certificate
Flagman- Internal Flagman training course.
12
11- Training
The Project Health and Safety Plan contains the HSE Training Matrix for the project. The
Project Manager responsible for ensuring that time is allocated for the delivery of the project
training matrix. The HSE Manager/Engineer is responsible for the delivery of the training. All
necessary training and certifications will be obtained for operatives and supervisors prior to
the commencement of activities. If Employer/Supervising Consultant inspection are needed,
Employers/Supervising Consultant inspectors will be provided with necessary training and
briefing prior to the commencement of inspection and training/briefing records must be sent
to Supervising Consultant HSE representative.
Third Party certification training is required for all person operating service locator equipment.
Full list of Environment, Health and Safety training requirement are listed on the Project Health
and Safety Plan.
14- Environmental
Waste shall be controlled by disposal into designated covered skips/ containers.
Waste collection, transportation and disposal shall be carried out only by companies
registered with ECS Dubai Municipality:
Wastes generated during the Dewatering works (food wastes and other) shall be collected at
site and disposed through waste skips. The construction teams shall be responsible for
ensuring this happens. Fuel and oils will be stored in bounded tanks and waste oils will be
collected and disposed of by a licensed specialist contractor. Static plant,i.e. compressors,
generators and pumps, will be sited overdrives. Approval will be obtaining approval (permit
for discharge point) for discharge of water pumped through dewatering Ground water shall be
13
pumped away and disposed of as directed in the discharge license. Refueling of plant will not
be carried out adjacent to water courses or rivers and mobile refueling browsers will be
equipped with spillage kits, containing absorbent mats and granules etc., for which specific
training in their use has been provided by the manufacturer. Maintenance of plant all vehicle,
plant and equipment will be carried out at designated places, Spill kits will be carried by the
maintenance team.
16
APPENDICES
A1 RISK ASSESSMENTS
A2 INSPECTION AND TEST PLAN (ITP)
A3 CHECKLIST
17
A1 RISK ASSESSMENTS
18
A2 INSPECTION AND TEST PLAN (ITP)
19
A3 CHECKLIST
20