3.1 EXAMPLE STDM PROBLEMS - Q&a
3.1 EXAMPLE STDM PROBLEMS - Q&a
Thus the production mix or plan of the company will be 400 units of B and only 200 units of
A.
1
2- THEORY OF CONSTRAINT & THROUGHPUT ACCOUNTING: Illustration
A company produces three products using three different machines. The following information
is available for a period:
Product X Y Z Total
Contribution (Sales –Variable RM12 RM10 RM6
cost)
Machine hours required per unit:
- Machine 1 6 2 1
- Machine 2 9 3 1.5
- Machine 3 3 1 1.5
Estimated sales demand 200 200 200
Required machine hours:
- Machine 1 1200 400 200 1800
- Machine 2 1800 600 300 2700
- Machine 3 600 200 300 1100
Machine capacity for each machine is limited to 1600 hours. Total factory cost for the period
is RM3,200
Required:
a) Identify which one is bottleneck activity.
b) Calculate the contribution per bottleneck hour to rank the products produced by the
bottleneck operation
Suggested Solution:
a) Machine utilization is as follows:
Machine 1 112% (1800/1600*100)
2 169% (2700/1600*100)
3 69% (1100/1600*100)
Machine 2 represents the bottleneck activity because it has the highest machine utilization.
b) We calculate the contribution per hour for machine 2 for each product. The result would
be as follows:
Product X Product Y Product Z
Contribution per unit RM12 RM10 RM6
Machine 2 hours required 9 3 1.5
Contribution per machine hour RM1.33 RM3.33 RM4
Ranking 3 2 1
The allocation of the 1600 hours for the bottleneck activity is:
Machine hours Balance of hours
Used available
Production
200 units of Z 300 1300
200 units of Y 600 700
77 units of X 700 -
Total cost comprises of 2/3 variable and the remainder fixed. The management is considering
whether to discontinue the production and sale of product Kaka. If this product is
discontinued, half of its fixed cost can be saved. Advise them.
Suggested solution:
If drop Kaka, the relevant cost will be net contribution lost from its sale i.e.
= Sales –VC
= 32,000 – 24,000
= 8,000
However, the relevant benefit will be the savings that will be made i.e.
= ½ x RM12,000
= 6,000
Thus, relevant cost of discontinuing exceeds its relevant benefit by RM 2,000 and so this
product should not be discontinued.
1. If continue: Is it the best way to utilize resources? How reliable are the projected figures
such as future demand?
2. If shut down / delete: What about the redundant employees? Some customers may be
frustrated, will there be any effect on customer goodwill?
4- SPECIAL ORDER DECISION: Illustration
A company produces a single product and has the capacity to produce 100,000 units for the
next period. The cost estimates per unit is as follows:
RM
Direct Material 2.00
Direct Labor 6.00
Variable Overhead 2.00
Fixed Overhead 4.00
14.00
The company is currently producing at 80% of capacity and is able to sell at RM 25 each. A
customer has approach the company to purchase the excess capacity at RM 20 each.
Should the company accept the offer?
Suggested solution:
If the special order is accepted:
RM
Additional Revenue = (20% X 100,000) X 20 400,000
Less: Relevant Costs:
Direct Material (2 X 20,000) (40,000)
Direct Labor (6 X 20,000 ) (120,000)
Variable Overhead (2 x 20,000) (40,000)
200,000
Since the incremental benefit is RM (400,000 – 200,000) = RM200,000, thus the order should
be accepted.
Qualitative factors:
a. Stability of price in the future
b. Customer loyalty
c. Sufficient capacity or not
d. Is the special order the best way to utilize the excess capacity?
5- MAKE OR BUY DECISION: Illustration
B Bhd. is considering whether to continue manufacturing component X or purchase it from
outside. The estimated cost of producing the components is as follows:
Material RM3,000
Labor RM1,000
Variable OH RM 500
Fixed OH RM2,000
Total RM6,500
The outside supplier has quoted a figure of RM5,000 to supply the components. If the
components are bought from outsiders, the company is able to rent out the free factory space
for RM5,000 per month. Transportation costs from the vendor will be RM500 and this will be
borne by B. Bhd.
Suggested solution
Relevant cost of making:
= variable costs of manufacturing + any other incremental costs + opportunity cost (any)
= Material 3,000 + Labour 1,000 + VOH 500 + OC 5,000
= RM9,500
Questions:
If allocate the joint cost according to relative sales value method, how would the cost be split?
Does the allocation of joint cost make it relevant for the decision about processing further
Cocoa powder to become Instant cocoa mix?
Suggested solution:
No, because the RM1,100 joint cost will not change in total whether further process takes
place or not. Hence it is irrelevant.
Should consider only the incremental costs and incremental benefits of further processing.
RM
Incremental revenue: 2,000
Less Relevant cost:
Incremental cost: (800)
Opportunity cost:
Revenue lost at split off point (500)
Net incremental benefit: 700
Decision: Cocoa powder should be processed further to become Instant cocoa mix since has
net benefit by RM700
8