Topic 02 - Detection and Analysis of Claims Events (1)
Topic 02 - Detection and Analysis of Claims Events (1)
Topic 02 - Detection and Analysis of Claims Events (1)
1
This Topic and the following Topic explore the detection
and analysis of the following samples of claim events:
Delayed Drawings or Instructions
Delay in Giving Possession of the Site
Suspension of Work
Unforeseeable Physical Conditions
Delayed Payment
Fossils
Setting-Out Errors
Nominated Subcontractors
Ambiguities/discrepancies in Contract documents
Variations
The last claim event is explored in the following Topic.
2
Normal entitlement to Contractor:
extension of time
additional payment
If failure is substantial, could result in termination
3
Is the Contractor required to do boreholes during
the tender period? In such case, who is responsible
for the risks of unforeseeable physical conditions?
Is the Contractor required to do boreholes after the
award of the Contract? In such case, who is
responsible for the risks of unforeseeable physical
conditions?
11
12
4
What are the normal remedies in case of delayed
payments?
Interest/Financing Charges
Termination
13
16
5
The Contractor shall set out the Works in relation to
original points, lines and levels of reference
specified in the Contract or notified by the Engineer.
The Employer shall be responsible for any errors in
these specified or notified items of reference, but
the Contractor shall use reasonable efforts to verify
their accuracy before they are used.
If the Contractor suffers delay and/or incurs cost as
a result of an error in these items of reference, and
an experienced contractor could not reasonably
have discovered such error, the Contractor shall be
entitled to extension of time and additional payment.
18
6
The Contractor shall not be under an obligation to
employ a nominated Subcontractor against whom
the Contractor raises reasonable objection.
An objection shall be deemed reasonable if it arises
from any of the following matters:
(a) the Subcontractor does not have sufficient
competence or resources
(b) the subcontract does not specify that the
nominated Subcontractor shall indemnify the
Contractor against any failure by the Subcontractor
to perform his obligations
20
21
7
The contractor would have to find an alternative
sub-contractor to carry out the work. If there is a
difference in price, such difference between the
original and new price would have to be met by the
Contractor.
22
8
A phrase could have more than one meaning.
No one section will be read alone in such a manner
to make it inconsistent and defeat the uniform
purpose of all the sections interpreted as a whole.
No single phrase will be interpreted out of context
with the rest of the contract.
A sample clause in this context, Clause 1.5 of FIDIC
99 “The documents forming the Contract are to be
taken as mutually explanatory of one another.”
9
Computer furniture design
Design of furniture using computers;
The design of computer furniture (by whatever means)
Disabled Parking
Disabled Parking literally means that the parking has
been disabled – it is not able to be used.
However, in ‘street language’, this phrase means (and
should read as) “parking for disabled (people)”.
To recap
“To recap” is, literally, to put the cap back on.
In street language, it is almost always used as an
abbreviation for “to recapitulate” – “to go over again; to
summarise”
28
30
10
The non-drafting party did not have such an
opportunity; they reasonably assumed that the
contract language meant a certain thing, and in
court that interpretation must prevail.
However, the court will not apply the contra
proferentum rule to a standard form of contract that
has been agreed between professional bodies and
trade associations representing both sides to the
contract.
31
32
11
The starting point for any consideration of the
meaning of a contract must be the words used.
Language is usually given its ordinary meaning.
Hence, when terms have a plain meaning, the
courts will not look beyond them to construe what
the parties meant.
33
37
12
If a word or phrase has a commonly accepted
meaning in the construction industry, that meaning
must be applied when reading and interpreting
construction contracts.
If the provision is clear, then trade custom or usage
is irrelevant. That is true even if the trade custom or
usage is in direct conflict with the contract provision.
But if the provision is, in fact, ambiguous, then trade
custom or usage becomes an important factor in
determining the meaning of the provision.
39
40
13
Many contracts include an order-of-precedence
clause. Such clause establishes an order of
priority between the various documents when an
ambiguity occurs between the documents.
42
14
Where the parties have reduced their agreement to a
written contract, all prior negotiations and understandings
are deemed to be merged into the written document.
Prior negotiations or agreements cannot be relied upon to
vary the terms of the contract.
The main reason for excluding prior negotiations is that
the parties’ intentions do not become crystallised until the
deal is eventually agreed.
The conversations or exchanges between the parties
during the negotiation stages leading up to the contract
might alter right up until the contract is agreed.
44
45
15
Specific terms govern over general terms (special
conditions govern over general conditions)
Written words prevail over printed words
Written words prevail over figures
49
16
Section 1: “The Contractor shall perform the
finishing works as per drawings A, B and C”
Section 2: “The Contractor shall perform the
finishing works as per drawings A and C and
Specifications Section 1.13”
Section 2 has a higher priority than Section 1.
In accordance with what should the Contractor
perform the finishing works? Explain your answer.
51
17
Solve Case Studies 3 and 4
18