Completion Again
Completion Again
ITEM NO. SCOPE OF WORK % WT. QUANTITY UNIT UNIT PRICE TOTAL AMOUNT
A.1.1(8) Provision of Field Office for the Engineer 0.11% 1.00 lot ₱ 34,208.89 ₱ 34,208.89
102(3)b ROADWAY EXCAVATION (SURPLUS ROCK) 1.16% 1,108.98 cu.m ₱ 330.84 ₱ 366,896.68
104(1)b Embankment from Roadway Excavation 1.35% 2,265.67 cu.m. ₱ 188.76 ₱ 427,668.14
200 Aggregate Sub-base Course 25.20% 2,203.20 cu.m. ₱ 3,628.08 ₱ 7,993,378.39
311(1) PCCP - (Plain) 31.74% 6120.00 sq.m. ₱ 1,644.69 ₱ 10,065,521.01
500(3) Lined Canal 25.04% 1224.00 l.m. ₱ 6,489.56 ₱ 7,943,225.30
506 Stone Masonry 1.79% 113.20 cu.m ₱ 5,003.65 ₱ 566,430.56
Estimated Project Cost: 100.00% ₱ 31,716,943.86
Approved by:
Item Scope of Work Unit Amount Wtd. % C.D. MONTH 1 MONTH 2 MONTH 3 MONTH 4 MON
1 2 3 4 5 6 7 8 ###
9 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1 2 3 4 5 6 7 8 ###
9 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1 2 3 4 5 6 7 8 ###
9 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1 2 3 4 5 6 7 8 ###
9 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1 2 3 4
₱ 34,208.89 0.11% 120.00
A.1.1(8) Provision of Field Office for the lot
Engineer
₱ 17,365.45 0.05% 1.00
B.5 Project Billboard/Signboard each
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
Republic of the Philippines
PROVINCE OF MISAMIS ORIENTAL
CONCRETING OF 1.0KM PUROK 1 TO PUROK 2 MINALWANG FMR
BARANGAY MINALWANG, CLAVERIA, MISAMIS ORIENTAL
A. MATERIALS
B. LABOR
C. RENTAL
A. MATERIALS
B. LABOR
C. EQUIPMENT
A. MATERIALS
B. LABOR
C. EQUIPMENT
Total of Equipment ₱ -
A. MATERIALS
B. LABOR
C. EQUIPMENT
Total of Equipment ₱ -
A. MATERIALS
Total of Materials ₱ -
B. LABOR
Total of Labor ₱ -
C. EQUIPMENT
A. MATERIALS
Total of Materials ₱ -
B. LABOR
C. EQUIPMENT
Volume : 387.20 cu.m. (Hauling Distance within 3km)
A. MATERIALS
B. LABOR
C. EQUIPMENT
Volume: 288.57 cu.m.
Equipment required:
1 unit Road Grader
Capability: 400 cu.m. per day spreading
Duration: 288.57 cu.m.
400 cu.m. per day spreading
= 1.00 days
1 unit Road roller
Capability 400 cu.m. per day compacting
Duration 288.57 cu.m.
400 cu.m. per day compacting
= 1.00 days
Volume for Hauling: 288.57 cu.m. (Hauling Distance within 3km)
A. MATERIALS
B. LABOR
C. EQUIPMENT
Name and Capacity Quantity No.of hours Unit Rate Amount (P)
Motorized Road Grader 1 0.05 ₱ 20,184.00 ₱ 1,009.20
Vibratory Roller (10 m.t.) 1 0.05 ₱ 16,168.00 ₱ 808.40
Water Truck (1000 gal.) 1 0.05 ₱ 21,840.00 ₱ 1,092.00
Backhoe (1.00 cu.m.) 1 0.05 ₱ 18,170.00 ₱ 908.50
Dumptruck (10 cu.m.) 1 0.05 ₱ 13,320.00 ₱ 666.00
Total of Equipment ₱ 4,484.10
Apron Slab
X= 4.020 m
Y= 4.020 m
Thickness = 0.150 m
Span Of Culvert = 6.900 m
Additional Length = 0.5 m
No. = 2
Area = 51.37 m.
TOTAL 15.411 cu.m.
A. MATERIALS
B. LABOR
C. EQUIPMENT
Capability: 70 bag/day
Duration: 163.00 bag
70.00 bag/day
say= 2.50 days
BOX CULVERT
thickness = 0.30 m.
clear height = 3.00 m.
clear span = 3.00 m.
concrete cover = 0.075 m.
no of barrel = 2.00 m.
length = 7.40 m.
WINGWALL
thickness A = 0.23 m. A1 = 0.159
thickness B = 0.30 m. Am = 0.517
height 1 = 3.30 m. A2 = 0.874
height 2 = 0.60 m.
no of wingwall = 4.00 m.
length = 5.68 m.
Volume = 11.74 cu.m.
WINGWALL FOOTING
thickness = 0.40 m.
width-1 = 1.20 m.
no of wingwall = 4.00 m.
length = 5.68 m.
Volume = 10.91 cu.m.
COPING
thickness = 0.60 m.
width = 0.30 m.
no of coping = 2.00 m.
length = 6.90 m.
Volume = 2.48 cu.m.
CUT-OFF WALL (VERTICAL) - R/L
thickness = 0.20 m.
height = 1.00 m.
length = 14.94 m.
no of wall = 1.00 m.
Volume = 2.99 cu.m.
BOX CULVERT
thickness = 0.30 m.
height = 3.00 m.
concrete cover = 0.075 m.
span = 3.00 m.
length = 7.40 m.
WINGWALL REINFORCEMENT
BAR -1 12 mm DRB
Heigth = 3.00 m,
Thickness = 0.30 m,
H+t-0.600 = 2.70 m,
L2 = 0.53
L1 = 5.27 From Plan
X2 = 4.75 m,
X3 = 4.22 m,
X4 = 3.69 m,
X5 = 3.17 m,
X6 = 2.64 m,
X7 = 2.12 m,
L3 = 5.64 m,
L4 = 5.64 m,
No.of Wall = 4.00
total Length = 297.05 m,
Total No.of DRB = 50.00 lgth
BAR-2 12 mm DRB
AT SPAN
AT SPAN 1.585 m 1.40 m AT SPAN 2.655 m
Y-1 3.66 Y-2 2.947 Y-3 2.187
Y= 0.07 Y 0.139 Y 0.163
Y1 3.59 Y1 2.808 Y1 2.024
Y2 3.52 Y2 2.669 Y2 1.861
Y3 3.45 Y3 2.53 Y3 1.698
Y4 3.38 Y4 2.391 Y4 1.535
Y5 3.31 Y5 2.252 Y5 1.372
Y6 3.24 Y6 2.113 Y6 1.209
Y7 3.17 Y7 1.974 Y7 1.046
Y8 3.10 Y8 0.883
Y9 3.02 Y9 0.72
Y10 2.95 Y10 0.557
Y11 2.88 Y11 0.394
WINGWALL FOOTING
BAR 3 12 mm DRB
Bar Length = 6.00
Cut bar 5.68
= 1.00 lgth
No. of wall = 4.00
Total No. cut = 24.00
Total No.DRB = 24.00 Lgth
APRON SLAB
Bar 3 & 4 12 mm DRB
Bar Length= 6.00
Cut length = 4.67
= 1.00
Length = 14.94 m
Total No.of Cut = 51.00
Total No. of DRB = 102.00 Lgth
BAR 2 12 mm DRB
Bar length = 6.00
height = 1.00
Cut Length = 14.94
3.00 lgth
Total No. Cut = 4.00
Total No. DRB = 48.00 lgth
COPING
thickness = 0.20 m.
height = 0.60 m.
concrete cover = 0.075 m.
length = 6.90 m.
side = 2.00
A. MATERIALS
B. LABOR
C. EQUIPMENT
Equipment Required:
2 Transit Mixer (5cu.m capacity)
Capability: 60 cu.m/day
Duration: 101.67 cu.m
60 cu.m/day
say= 2.00 days
A. MATERIALS
Total of Materials ₱ -
B. LABOR
C. EQUIPMENT
Road Cut Volume for excavation : 1,108.98 cu.m. (Hauling Distance within 3km)
Road Cut Volume to be transferred : 1,723.11 cu.m. (Hauling Distance within 3km)
A. MATERIALS
Total of Materials ₱ -
B. LABOR
A. MATERIALS
B. LABOR
C. EQUIPMENT
Volume: 2,534.00 cu.m.
Equipment required:
1 unit Road Grader
Capability: 400 cu.m. per day spreading
Duration: 2,534.00 cu.m.
400 cu.m. per day spreading
= 6.50 days
1 unit Road roller
Capability 400 cu.m. per day compacting
Duration 2,534.00 cu.m.
400 cu.m. per day compacting
= 6.50 days
A. MATERIALS
B. LABOR
C. EQUIPMENT
Equipment Required:
2 Transit Mixer (5cu.m capacity)
Capability: 300 sq.m./day
Duration: 6,120.00 sq.m.
300 sq.m./day
say= 20.50 days
LINED CANAL
Cross sectional area of gravel bedding : 0.070 sq.m.
Length of gravel bed : 1,224.00 m.
Volume of gravel bedding : 85.68 cu.m.
A. MATERIALS
B. LABOR
C. EQUIPMENT
A. MATERIALS
B. LABOR
C. EQUIPMENT
Standard Form Number: SF-INFR-01 Location of the Contract : BRGY. HINAPLANAN, CLAVERIA, MISAMIS ORIENTAL
MARK-UPS Total
1 2 3 4 5 6 7 8 9
(5)(6) (5)(7) (8)(5+10+11) Municipal Tax (10+11+12) (5)+(14)+(13) (15)/(3)
B.5 Project Billboard/Signboard 2.00 each 5,755.00 12% 8% 5% 25% 690.60 460.40 345.30 40.89 1,496.30 7,292.19 3,646.10
B.7(1) Occupational Safety and Health 2205.30 man-days 126,399.66 0% 8% 5% 13% - 10,111.97 6,825.58 808.34 16,937.55 144,145.55 65.36
B.8(2) Traffic Management 257.24 cu.m. #REF! 0% 8% 5% 13% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
B.9 Mobilization/Demobilization #NAME? #NAME? #REF! 0% 0% 5% 5% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Temporary Diversion of
B.17 34.72 cu.m. #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Waterways
B.15 Detour/Access Road #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ROADWAY EXCAVATION
103(3) #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
(SURPLUS ROCK)
407(8) Lean Concrete #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
(900)2 Reinforced Concrete #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ROADWAY EXCAVATION
102(3)b #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
(SURPLUS ROCK)
Embankment from Roadway
104(1)b #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Excavation
200 Aggregate Sub-base Course #NAME? #NAME? #REF! 12% 8% 5% 25% #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ENGR. CHRISTY QUEEN U. PAMPLONA ENGR. ROLANDO M. ALFANTA HON. MERALUNA SALVALEON- ABROGAR
Project In-Charge Municipal Engineer Municipal Mayor