RIICWD533E Student Guide Com
RIICWD533E Student Guide Com
This form is to be completed by the assessor and used a final record of student competency.
All student submissions including any associated checklists (outlined below) are to be attached to this cover sheet
before placing on the student’s file.
Student results are not to be entered onto the Student Database unless all relevant paperwork is completed and
attached to this form.
Student Name:
Student ID No:
Final Completion
Date:
Unit Code: RIICWD533E
Student
Feedback:
Student Name:
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature:
result. I also am aware of my appeal rights.
Date:
Assessor Name:
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable and flexible assessment with this Assessor Signature:
student, and I have provided appropriate feedback
Date:
Page 1 of 173
ASSESSMENT 1 – WRITTEN ASSESSMENT
Student Name:
Student ID No:
Final Completion
Date:
Purpose
The pre-assessment checklist helps students determine if they are ready for assessment. The Trainer/Assessor
must review the checklist with the student before the student attempts the assessment task. If any items of the
checklist are incomplete or not clear to the student, the Trainer/Assessor must provide relevant information to the
student to ensure they understand the requirements of the assessment task. The student must ensure they are
ready for the assessment task before undertaking it.
Please make sure the student has completed the necessary prior learning before attempting this
assessment.
Please make sure you as a Trainer/Assessor have clearly explained the assessment process and tasks to
be completed.
Please make sure the student understands what evidence is required to be collected and how.
Please make sure the student knows their rights and the complaints and appeal process.
Please make sure the student has discussed any special needs or reasonable adjustments to be
considered during the assessment (refer to the Reasonable Adjustments Strategy Matrix in unit
information pack document).
Please make sure the student has access to a computer and the internet (if they prefer to type the
answers).
Please ensure that your student must have all the required resources needed to complete this Unit
Assessment Task (UAT). (Refer to Training and assessment resources for more information).
Due date of this assessment task is according to the timetable.
In exceptional (compelling and compassionate) circumstances, an extension to submit an assessment
can be granted by the Trainer/Assessor.
Evidence of the compelling and compassionate circumstances must be provided together with the request
for extension to submit the assessment work.
Request for an extension to submit assessment work must be made before the due date of this
assessment task.
Page 2 of 173
Instructions for Trainers/Assessors:
The following forms the basis of specific evidence that you need to collect from students for assessment
in this assessment task.
The task and specific assessment requirements that are provided to students are also outlined.
Refer to all the red, bold, and italic text for a guide to suggested answers for assessments and for
instructions on how to use the assessment tools.
Ensure all outlined conditions of assessment requirements are met.
For each assessment task a Unit Assessment Result Sheet (UARS) form is to be completed. This is
located at the end of each assessment task.
This Unit Assessment Result Sheet (UARS) allows the Trainer/Assessor to record the following items
correctly:
o Outcome of the assessment task as either Satisfactory (S) or Not Satisfactory (NS).
o Feedback to candidate
o Student declaration
o Trainer/Assessor declaration
The Trainer/Assessor and the student must sign the Unit Assessment Result Sheet (UARS) to show that
the student was provided with the task outcome.
Once all assessment tasks allocated to this Unit of Competency have been undertaken, an Assessment
plan is to be completed to record the unit outcome. The outcome will be either Competent (C) or Not Yet
Competent (NYC).
The “Assessment Plan” is available with the Unit Assessment Pack (UAP) – Cover Sheet.
Each “Assessment Plan” should be referred to note the Unit Assessment Result Sheet (UARS) outcome
as Satisfactory (S) or Not Satisfactory (NS), and this information then transferred to the final result in the
“Assessment Plan” as Competent (C) or Not Yet Competent (NYC).
If all assessment tasks are deemed Satisfactory (S), then the unit outcome is Competent (C).
If at least one of the assessment tasks is deemed Not Satisfactory (NS), then the unit outcome is Not Yet
Competent (NYC).
Page 3 of 173
1 What legislation is required to prepare detailed design of civil concrete structures?
Various laws and standards must be followed in order to create precise designs for civil concrete
constructions. To guarantee structural safety, it is essential to follow regional building codes (like
the IBC and NCC) and concrete design guidelines (like ACI 318 and Euro code 2).
Environmentalrules reduce ecological damage, whereas health and safety requirements, like
OSHA or WHS, safeguard workers during construction. While quality management standards
like ISO 9001 assure consistency and dependability in construction operations, accessibility
requirements like the Americans with Disabilities Act (ADA) ensure that designs are inclusive.
Comments
Design Standards and Codes: Adhere to AS 3600, AS 1170, and AS/NZS 4671 for
strength and stability.
Safety Policies: Follow OHS/WHS policies to assess risks and ensure safe practices.
Environmental Procedures: Complete impact assessments and plans per EPBC Act
requirements.
authorities. These elements ensure designs are safe, compliant, and environmentally
sound.
Comments
Page 4 of 173
What policies, procedures and documentation required to prepare detailed design of
3
civil concrete structures, including those relating to cultural and heritage management?
Key regulations, methods, and documentation for designing civil concrete structures are:
Design Standards: For structural safety, use AS 3600, AS 1170, and so on.
Cultural Heritage Policies: Comply with heritage regulations and contact with
appropriate authorities.
Comments
What policies, procedures and documentation required to prepare detailed design of
4
civil concrete structures, including those relating to design approvals and review?
Follow standards like AS 3600 for concrete structures to ensure design safety.
Implement internal and external review processes to validate design accuracy and compliance.
Produce comprehensive drawings, specifications, and design calculations to support the design.
Obtain necessary permits, certifications, and approval records to confirm that all regulatory
requirements are met.
Comments
Page 5 of 173
What policies, procedures and documentation required to prepare detailed design of
5
civil concrete structures, including those relating to engineering surveys?
To prepare detailed designs for civil concrete structures, the following key policies, procedures, and
documentation related to engineering surveys are essential:
Survey Standards: Comply with AS 5488 and AS 2870 for accurate data collection.
Survey Procedures: Follow systematic methods for topographic, boundary, and geotechnical surveys.
Documentation: Maintain detailed records of survey data, including maps and reports.
Geotechnical Reports: Include soil investigation reports detailing soil properties and bearing capacity.
Regulatory Compliance: Ensure surveys meet local regulations and obtain necessary permits.
Comments
Environmental Standards: Comply with the Environmental Protection Act and relevant Australian
Standards.
Environmental Impact Assessments (EIA): Conduct EIAs to identify impacts and propose mitigation
measures.
Sustainability Policies: Implement practices that promote eco-friendly materials and waste reduction.
Permits and Approvals: Secure necessary environmental permits from local authorities.
Monitoring Procedures: Establish ongoing monitoring and compliance reporting throughout the project.
Comments
Page 6 of 173
What policies, procedures and documentation required to prepare detailed design of
7
civil concrete structures, including those relating to equipment safety requirements?
Safety Standards: Comply with AS/NZS 4801 for occupational health and safety.
Equipment Safety Policies: Implement policies for safe equipment use and maintenance.
These elements help maintain a safe working environment and ensure compliance with safety
requirements.
Comments
Site Investigations: Conduct geotechnical investigations to assess soil properties and bearing capacity.
Comments
Page 7 of 173
What policies, procedures and documentation required to prepare detailed design of
9 civil concrete structures, including those relating to hydrological and meteorological
management?
Standards Compliance: Adhere to guidelines like Australian Rainfall and Runoff (AR&R) for stormwater
design.
Site Assessments: Evaluate local hydrology, drainage patterns, and meteorological data.
Hydrological Reports: Document water flow, flood risk, and drainage solutions with design
recommendations.
Risk Management: Identify and mitigate hydrological and meteorological risks throughout the project.
Monitoring Plans: Establish ongoing monitoring for drainage systems and hydrological conditions.
Comments
Risk Assessments: Identify potential hazards and develop response strategies for incidents.
Emergency Plans: Create response plans detailing evacuation and communication procedures.
Documentation: Keep records of risk assessments, emergency plans, and training sessions.
Monitoring: Establish procedures for regular reviews and drills to ensure preparedness.
Comments
Page 8 of 173
What policies, procedures and documentation required to prepare detailed design of
11
civil concrete structures, including those relating to performance reviews?
Performance Standards: Comply with relevant standards, such as AS 3600 for concrete structures.
Design Reviews: Implement processes to systematically evaluate structural integrity and compliance.
Documentation: Keep records of design calculations, assumptions, and review outcomes for
accountability.
Quality Assurance: Establish measures to ensure materials and construction meet performance criteria.
Monitoring Plans: Develop plans for ongoing monitoring of structural performance post-construction.
Comments
What policies, procedures and documentation required to prepare detailed design of
12
civil concrete structures, including those relating to quality management?
Comply with standards like ISO 9001 for quality management in construction.
Implement procedures for design verification through peer reviews and audits.
Maintain records of design calculations, quality control measures, and changes for traceability.
Develop plans for inspecting materials and structures to verify quality standards.
Establish processes for evaluating outcomes and integrating lessons learned into future designs.
Comments
Page 9 of 173
What policies, procedures and documentation required to prepare detailed design of
13
civil concrete structures, including those relating to risk assessment and management?
Risk Assessment Procedures: Implement processes for identifying and evaluating potential design and
construction risks.
Risk Management Plans: Develop strategies for mitigating identified risks, including contingency
measures.
Documentation: Keep detailed records of risk assessments, decisions, and actions taken throughout the
project.
Regulatory Compliance: Adhere to relevant standards, such as AS/NZS 4360 for risk management.
Review and Monitoring: Establish procedures for regularly updating risk assessments based on project
changes.
Comments
What policies, procedures and documentation required to prepare detailed design of
14
civil concrete structures, including those relating to statutory compliance?
Regulatory Standards: Follow all applicable building regulations and standards, including the National
Construction Code (NCC) and AS 3600 for concrete structures.
Compliance Procedures: Establish methods to ensure that designs meet all legal and regulatory
standards throughout the project's lifecycle.
Documentation: Keep full records of all compliance evaluations, approvals, and permits required by local
authorities.
Design evaluations: Conduct regular evaluations to ensure that designs meet regulatory requirements
and industry standards.
Stakeholder Consultation: Communicate with regulatory agencies and stakeholders to clarify compliance
requirements and gather feedback.
Audit and Reporting: Develop procedures for performing compliance audits and reporting to ensure
continuous statutory compliance.
Comments
Page 10 of 173
What policies, procedures and documentation required to prepare detailed design of
15
civil concrete structures, including those relating to system close outs?
Create methodical closeout processes for finishing design components, such as final approvals and
reviews.
Assemble and complete all pertinent papers, including material specifications, design calculations,
and as-built drawings.
Prior to closeout, conduct quality control inspections to ensure adherence to established standards.
To ensure that all requirements have been fulfilled, get the required approvals from clients and
regulatory agencies, among other stakeholders.
To help guide future initiatives, document the knowledge and lessons gained during the design
process.
Write a closeout report outlining the project's results, requirements compliance, and any unresolved
problems or warranties.
Comments
What policies, procedures and documentation required to prepare detailed design of
16
civil concrete structures, including those relating to work health and safety?
Create thorough work health and safety (WHS) policies that spell out the dedication to safety during
the planning and building phases.
To find possible risks connected to the design and construction processes, conduct risk
assessments.
Put in place processes for creating and disseminating safety plans, including project-specific safe
work method statements (SWMS).
Make sure that the design complies with all applicable safety standards and laws, including AS
4801 for occupational health and safety management.
Make sure all project participants understand safety regulations and procedures by documenting
their safety training and induction programs.
To guarantee continued compliance and enhance safety procedures, keep track of safety audit,
inspection, and incident report records.
Encourage a culture of safety throughout the project by interacting with stakeholders to talk about
safety issues and solutions.
Comments
Page 11 of 173
What policies, procedures and documentation required to prepare detailed design of
17
civil concrete structures, including those relating to workplace recording and reporting?
Implement policies for accurate and timely recording of workplace activities, including design
processes and construction milestones.
Establish procedures for maintaining records of design changes, material specifications, and
compliance with standards.
Develop protocols for reporting project progress, including daily logs, incident reports, and meeting
minutes.
Ensure records are organized and accessible for stakeholders and regulatory authorities.
Maintain compliance with relevant legislation regarding workplace recording and reporting.
Comments
What types, characteristics, technical capabilities and limitations of materials, plant and
18
equipment are required for civil concrete structures design and construction?
Concrete: High compressive strength and durability; molds into shapes and is load-bearing, but has low
tensile strength and is prone to cracking.
Steel Reinforcement: High tensile strength and ductility enhance concrete's tensile capacity; however, it
risks corrosion and requires good bonding.
Aggregates: Varying sizes impact strength, improving stability, but quality affects concrete performance.
Admixtures: Chemical additives modify workability and curing; improper use can harm quality.
Concrete Mixers: Available in various capacities, ensuring uniform mixing but requiring maintenance and
can have mobility issues.
Concrete Pumps: Include boom or line designs that place concrete in hard-to-reach areas but need skilled
operators and can be affected by viscosity.
Formwork: Temporary structures providing shape and finish; costly and needs precise assembly.
Cranes: Various types that lift heavy materials and aid in placing precast elements, but are space-intensive
and weather-dependent.
Compactors: Includes plate and vibratory types that stabilize foundations; over-compaction can damage
soil.
Satisfactory Not Satisfactory
Comments
Page 12 of 173
What are the principles and techniques for preparing detailed design of civil concrete
19 structures, including: techniques for evaluating potential site hazards, constraints and
conditions techniques for identifying and evaluating design options?
Site Hazard Evaluation:
Conduct a site assessment to identify hazards like unstable soil and flooding.
Perform geotechnical investigations to understand soil properties.
Analyze historical data for past issues such as erosion or landslides.
Consider environmental factors like proximity to fault lines.
Constraints Identification:
Review zoning regulations and land use policies.
Assess existing infrastructure and utilities.
Consider environmental regulations impacting construction.
Risk Assessment:
Implement risk management strategies to identify potential failure modes.
Use hazard identification workshops to evaluate issues.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
20 structures, including data analysis techniques, including calculating loads?
Data Collection:
Gather site information, including soil reports and environmental data.
Load Calculation:
Calculate dead loads from materials and components.
Determine live loads based on usage and building codes.
Assess environmental loads like wind and seismic effects.
Structural Analysis:
Use software tools for complex calculations and hand calculations for simpler designs.
Safety Factors:
Include safety margins to cover uncertainties in materials and loads.
Design Optimization:
Compare design options to find the most cost-effective and efficient solution.
Comments
Page 13 of 173
What are the principles and techniques for preparing detailed design of civil concrete
21
structures, including data analysis techniques, including calculating shear forces?
Gather Data:
Collect information on site conditions, loads, and environmental factors.
Analyze Structure:
Use software for shear analysis; confirm with manual calculations.
Design Elements:
Select appropriate materials and sizes to handle shear forces.
Include shear reinforcement where necessary.
Check Safety:
Verify compliance with relevant codes and safety standards.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
22
structures, including data analysis techniques, including calculating bending moments?
Data Collection: Gather material properties and load conditions.
Bending Moment Calculation: Use diagrams and formulas or software to find bending moments at critical
points.
Structural Analysis: Perform static and dynamic analysis; validate with hand calculations.
Design Considerations: Choose concrete grades and reinforcement based on bending moment
calculations.
Compliance Check: Ensure design meets building codes and safety standards.
Comments
Page 14 of 173
What are the principles and techniques for preparing detailed design of civil concrete
23
structures, including data analysis techniques, including calculating stresses?
Use formulas to find stresses (compressive, tensile, shear) in concrete and reinforcement.
Check how loads impact the structure with static and dynamic analyses.
Choose suitable concrete and reinforcement based on stress results. Ensure the design meets
building codes and safety standards.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
24
structures, including data analysis techniques, including calculating areas?
Data collection: Compile precise measurements of the structural elements, such as the heights, widths,
and lengths of the beams, slabs, and columns.
Area Calculations: Apply geometric formulas to compute areas. For example, for rectangular slabs,
multiply length by width; for circular columns, use the formula 𝐴=𝜋𝑟2
Considerations for Load: Verify that the computed areas can sustain the required loads. This involves
taking into consideration both live (temporary/dynamic) and dead (permanent/static) loads.
Design Compliance: To guarantee structural integrity and safety, confirm that the computed areas comply
with applicable building codes and design standards.
Documentation: Keep track of all computations and design choices, along with any presumptions made
throughout the study. This documentation is used as a guide for future evaluations and building.
Comments
Page 15 of 173
What are the principles and techniques for preparing detailed design of civil concrete
25
structures, including data analysis techniques, including calculating volumes?
Gather dimensions (length, width, height) of structural components.
Use formulas:
Volume=length×width×height
Volume=𝜋𝑟2ℎ
For complex shapes, break them into simpler forms and sum their volumes.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
26
structures, including data analysis techniques, including calculating mass?
Gather Data: Collect dimensions and density of materials, such as concrete.
Calculate Volume: Use geometric formulas to find the volume of each component.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
27 structures, including data analysis techniques, including calculating sizes of
components for civil concrete structures?
Load Calculation
Structural Analysis
Design Optimization
Safety Factor Application
Material Selection
Code Compliance
Prototyping and Modeling
Iterative Design Process
Performance Evaluation
Page 16 of 173
What are the principles and techniques for preparing detailed design of civil concrete
28 structures, including data analysis techniques, including calculating geometric
requirements for civil concrete structures?
Define Design Criteria: Set requirements for dimensions and shape based on function and regulations.
Geometric Analysis: Assess spatial relationships to optimize layout and space use.
Load Analysis: Calculate loads to ensure the structure can safely support them.
Documentation: Create clear drawings and specifications with all geometric details.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
29
structures, including data analysis techniques, including cost estimation techniques?
Define Scope: Outline project requirements and specifications.
Unit Cost Estimation: Assign costs to each item based on market rates.
Cost-Benefit Analysis: Compare long-term benefits against costs for informed decisions.
Comments
Page 17 of 173
What are the principles and techniques for preparing detailed design of civil concrete
30
structures, including data analysis techniques, including requirements of a design plan?
Design Objectives: Define the project's goals, including functionality, aesthetics, and sustainability.
Site Analysis: Assess site conditions, including soil properties, environmental impact, and existing
structures.
Load Assessment: Calculate expected loads, including dead, live, wind, and seismic forces.
Material Selection: Choose appropriate materials based on strength, durability, and cost.
Design Models: Utilize software tools for structural modeling and analysis.
Documentation: Prepare detailed drawings, specifications, and reports for approval and construction.
Review and Revise: Conduct peer reviews and revise designs based on feedback.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
31 structures, including data analysis techniques, including design review and validation
techniques?
Define Objectives: Set clear project goals and requirements.
Analyze Performance: Apply methods like finite element analysis (FEA) to evaluate the structure.
Conduct Reviews: Regularly review the design with a team to ensure it meets requirements.
Validate Assumptions: Test or compare with existing structures to confirm design reliability.
Document Everything: Keep detailed records of the design process and decisions.
Comments
Page 18 of 173
What are the principles and techniques for preparing detailed design of civil concrete
32 structures, including data analysis techniques, including performance review
techniques?
Set Performance Goals: Define what success looks like.
Analyze Structure: Use methods or software to check how the structure will behave.
Comments
What are the principles and techniques for preparing detailed design of civil concrete
33 structures, including data analysis techniques, including techniques for using software
and technology to develop and present designs?
Select Software: Use appropriate design tools like AutoCAD or Revit for the project needs.
3D Modeling: Create accurate 3D models for better visualization and design iteration.
Data Input: Input material properties and loads to analyze structural behavior.
Simulation: Use simulation tools to optimize designs for safety and efficiency.
Visualization: Present designs with rendering and animations for effective communication.
Automated Documentation: Generate construction documents directly from the software to ensure
accuracy.
Comments
Page 19 of 173
What are the principles and techniques for preparing detailed design of civil concrete
34 structures, including data analysis techniques, including techniques for advising on
design implementation?
Compliance: Adhere to relevant codes and standards.
Material Selection: Choose appropriate materials for structural and environmental needs.
Comments
What are the principles and techniques for leading and coordinating teams in civil
35
concrete structure design?
Clear Communication: Maintain open communication for project goals and timelines.
Defined Roles: Assign specific roles to utilize strengths and ensure accountability.
Stakeholder Engagement: Involve stakeholders for valuable insights and needs alignment.
Comments
Page 20 of 173
What are the steps involved in preparing detailed designs of civil concrete bridge
36
structures?
Site Assessment
Preliminary Design
Load Analysis
Structural Analysis
Detailed Design
Material Selection
Compliance
Construction Documentation
Quality Control
Final Review
Comments
What are the general steps and principles that are typically followed in the design
37
process of a concrete bridge structure?
Define Objectives: Set project goals and requirements.
Comments
Page 21 of 173
8 What are the factors to consider when preparing a cost estimate for bridge?
Design Complexity: Affects labor and materials.
Comments
3 What are the steps in preparing a cost estimate for a concrete bridge?
9
Site Assessment
Design Development
Material Quantification
Labor Estimation
Equipment Costs
Contingency Allowance
Final Documentation
Comments
Page 22 of 173
40 What information would a soil report class S in Australia typically include?
A soil report classified as Class S (Shallow Soil) in Australia typically includes the following information:
Comments
What what are the steps to calculate the load of a concrete bridge design? Use the
41 following as an example:
a concrete bridge design 8 metres in length and 4.2 metres wide.
To calculate the load of a concrete bridge (8 meters long and 4.2 meters wide), follow these steps:
Combine Loads: Total Load = Dead Load + Live Load + Other Loads.
Load per Area: Divide total load by bridge area for load per square meter.
Comments
Page 23 of 173
Give the formulas for calculating the following:
• Loads
• Shear forces
• Bending moments
42 • Stresses
• Areas
• Volumes
• Mass
• Sizes of components for civil concrete structure
Loads
𝑊=𝑊𝑑+𝑊𝑙+𝑊𝑜
Shear Forces
𝑉=𝑑𝑀/𝑑𝑥
Bending Moments
𝑀=𝑤𝐿2/8
Stresses
𝜎=𝑀/𝑆
𝜏=𝑉/𝐴
Areas
𝐴=𝑏×ℎ
Volumes
𝑉=𝑏×ℎ×𝑑
Mass
𝑚=𝑉×𝜌
Sizes of Components
𝑑=𝐿/12 to 𝐿/16
Comments
Page 24 of 173
43 What information would a specification report for a concrete bridge typically include?
Project Overview: Purpose and scope.
Comments
1. Have you re-checked your answers to make sure you are happy with your responses?
2. Have written/type your Name, Date Completed on the front page?
3. Have you completed the student declaration section below?
Student Name
Student Declaration: : I declare that the work
submitted is my own and has not been copied or Student Signature
plagiarised from any person or source.
Date
Comments
Page 25 of 173
Assessor Declaration: I declare that I have Assessor Name
conducted a fair, valid, reliable and flexible
Assessor Signature
assessment with this student, and I have provided
appropriate feedback. Date
Page 26 of 173
Assessment 2 – Project Task
Student Information
Purpose
The pre-assessment checklist helps students determine if they are ready for assessment. The Trainer/Assessor
must review the checklist with the student before the student attempts the assessment task. If any items of the
checklist are incomplete or not clear to the student, the Trainer/Assessor must provide relevant information to the
student to ensure they understand the requirements of the assessment task. The student must ensure they are
ready for the assessment task before undertaking it.
Section 1:
Information for Trainers/Assessors
Please make sure the student has completed the necessary prior learning before attempting this
assessment.
Please make sure you as a Trainer/Assessor have clearly explained the assessment process and tasks to
be completed.
Please make sure the student understands what evidence is required to be collected and how.
Please make sure the student knows their rights and the complaints and appeal process.
Please make sure the student has discussed any special needs or reasonable adjustments to be
considered during the assessment (refer to the Reasonable Adjustments Strategy Matrix).
Please make sure the student has access to a computer and the internet (if they prefer to type the
answers).
Please ensure that your student must have all the required resources needed to complete this Unit
Assessment Task (UAT). (Refer to Training and assessment resources for more information).
Due date of this assessment task is according to the timetable.
In exceptional (compelling and compassionate) circumstances, an extension to submit an assessment
can be granted by the Trainer/Assessor.
Evidence of the compelling and compassionate circumstances must be provided together with the request
for extension to submit the assessment work.
Request for an extension to submit assessment work must be made before the due date of this
assessment task.
Page 27 of 173
This Unit Assessment Result Sheet (UARS) allows the Trainer/Assessor to record the following items
correctly:
Outcome of the assessment task as either Satisfactory (S) or Not Satisfactory (NS).
Feedback to candidate
Student declaration
Trainer/Assessor declaration
The Trainer/Assessor and the student must sign the Unit Assessment Result Sheet (UARS) to show that
the student was provided with the task outcome.
The mapping document should be referred to identify what aspects of the Unit of Competency are being
addressed by each assessment task.
Once all assessment tasks allocated to this Unit of Competency have been undertaken, an Assessment
plan is to be completed to record the unit outcome. The outcome will be either Competent (C) or Not Yet
Competent (NYC).
The “Assessment Plan” is available with the Unit Assessment Pack (UAP) – Cover Sheet.
Each “Assessment Plan” should be referred to note the Unit Assessment Result Sheet (UARS) outcome as
Satisfactory (S) or Not Satisfactory (NS), and this information then transferred to the final result in the
“Assessment Plan” as Competent (C) or Not Yet Competent (NYC).
If all assessment tasks are deemed Satisfactory (S), then the unit outcome is Competent (C).
If at least one of the assessment tasks is deemed Not Satisfactory (NS), then the unit outcome is Not Yet
Competent (NYC).
Page 28 of 173
Assessment 2 – Project Task 1 Soil Report
Student Information
Your task.
Investigate and analyse the site (i.e., 103 -105 Redfern Street, Redfern) using the site investigation report
(Appendix A and B). You must identify and document the site features and available services to plan the site
preparation. This includes identifying the following:
Access
Batter/gradient
Earthworks and/or cut and fill
Existing services
Interpretation of topographical features
Orientation
Platforms
Retaining walls
Soil classification
Stormwater
Surface and subsoil drainage
Termite risk management
Trenches
From the soil engineer's report (Appendix A and B), you must identify and determine if the appropriate foundation is
used for the site. Specify the footing system and document any variations that could exist if the design is changed.
The footing systems include:
Bored piers
Dewatering
Driven piles
Ground stabilization
Pad and pedestal footings
Pier and beam
Raft slabs
Retaining walls
Tanking
Identify and document any environmental issues that may impact the site according to regulatory requirements.
How can this be controlled?
Resources required
You must complete this activity. Your trainer will provide feedback during this task and complete the performance
checklist.
Timeframe
You will be required to complete the activity in the timeframe decided by the company/trainer.
Page 29 of 173
Soil Report - Answer
Redfern Street 103-105 Soil Report
1. Introduction:
The results of the soil examination carried out at the address 103-105 Redfern Street, Redfern, NSW,
Australia, are presented in this report. This investigation's goals are to evaluate the soil's characteristics
and offer suggestions for the proposed construction's foundation design.
Redfern Street provides access to the site, and there is enough room for construction vehicles.
Batter/Gradient: There is a mild 5% southward slope to the location.
Earthworks: According to preliminary estimates, in order to attain the required grades, some 250 cubic
meters of earth will need to be cut and filled.
Current Services:
The water main runs along the eastern edge and is 1.5 meters below the surface.
Overhead power cables that run parallel to the southern border provide electricity.
Sewer: Two meters from the western side of the land is a sewer pipe.
Topographical Features: There are a few low-lying spots on the otherwise level land.
Orientation: To maximize solar exposure, the location faces north.
4. Soil Classification
Soil Types Identified:
Topsoil: 0.2 m deep, silty loam.
Clayey Sand: 1.5 m deep, characterized by a blend of fine sand and clay, with a liquid limit of 30% and a
plastic limit of 18%.
Clay: 2.0 m deep, with a plasticity index of 20%
5. Foundation Analysis
Based on the soil conditions observed, the following foundation systems are recommended:
Bored Piers:
Dewatering:
The level of groundwater was measured 2.5 meters below the surface. During construction,
dewatering will be required.
Piles that are driven:
In clay-containing locations, driven concrete piles (300 mm in diameter) can be used as an alternative;
however, they must be lowered at least 3.5 meters to provide sufficient load-bearing capability.
Slabs of Raft:
It is advised to reduce differential settlement problems if extensive sections of the structure are
planned.Stormwater Management
6. Stormwater Management
Surface Drainage:
A surface drainage system is required to redirect stormwater away from the foundation areas.
Subsoil Drainage:
Installation of perimeter drainage to manage groundwater infiltration, especially during heavy rains.
7. Environmental Considerations
Potential Issues:
Minor contamination risk from historical industrial use. Soil tests for heavy metals and hydrocarbons are
recommended.
Mitigation Strategies:
Implement erosion control measures during construction and consider soil remediation if contamination
levels exceed acceptable limits.
8. Conclusion:
For the planned building, the soil conditions at 103-105 Redfern Street are generally favorable. Because of
the groundwater conditions and clay layers, bored piers or driven piles are advised for the foundation
system. To guarantee the integrity of the building and the surrounding area, proper stormwater
management and environmental mitigation techniques should be implemented.
9. Appendices
Soil samples analyzed for grain size distribution and Atterberg limits.
Appendix B: Drawings
Drawing 1: Location of Tests
Drawing 2: Geological Cross Section A-A’
Resources Required
Geotechnical Report: Comprehensive analysis of soil properties.
Field Investigation Equipment: Standard drilling and sampling tools used during the investigation.
Page 30 of 173
Page 31 of 173
Page 32 of 173
Page 33 of 173
Page 34 of 173
Page 35 of 173
Page 36 of 173
Performance Criteria/Assessor Checklist: Task 1 Soil Report
Student Name:
Student ID No:
Final Completion
Date:
Does the candidate meet the following criteria
Did the student Investigate and analyse the given site investigation report
Yes No
(103 -105 Redfern Street, Redfern – Appendix A and B)
Access Yes No
Batter/gradient Yes No
Orientation Yes No
Platforms Yes No
Stormwater Yes No
From the soil report, did the student identify and determine if the appropriate
Yes No
foundation is being used for the site.
Did the student Specify the footing system and document any variations that
Yes No
could exist if the design is changed. The footing systems include:
Dewatering Yes No
Tanking Yes No
Page 37 of 173
Did the student access, interpret and apply documentation required for
detailed civil concrete structures design and confirm work activity is Yes No
compliant.
Did the student identify and confirm the geotechnical works project
Yes No
requirements and information.
Did the student interpret and analyse design options for civil concrete
Yes No
structures and recommend design option according to job requirements.
Did the student complete the required documentation for the design of civil
Yes No
concrete structures according to workplace requirements.
Did the student locate and apply relevant legislation, documentation, policies
Yes No
and procedures.
Plans Yes No
Drawings Yes No
Specifications Yes No
Did the student comply with written and verbal reporting requirements and
Yes No
procedures.
Did the student select and apply appropriate construction techniques. Yes No
Did the student interpret and analyse data to recommend options. Yes No
Did the student complete the task within the expected time frame. Yes No
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date
Page 38 of 173
Assessment 3 – Project Task Field Trip
Student Information
Your task.
Field Trip
You will be required to perform a field trip with your fellow students in a group of 4. In the field, several levelling
tasks will be undertaken, as listed below. You are to follow the guidelines below and record and submit the data.
Include all sketches and calculations with your assessment. Follow the instructions given and consult your trainer
when you have a query. Ensure you communicate clearly and concisely with your colleagues when clarifying
instructions and coordinating the work.
Aim:
To obtain a practical understanding of the leveling procedure, the use of the dumpy level and associated equipment
and the recording and reduction of data
Introduction:
A a leveling assignment
B measurement by tape to locate various physical features
C ‘hands on’ use of various ancillary-equipment and a small survey exercise
Section A:
A1 Equipment required:
1 Dumpy level and tripod
1 five metre staff and pill bubble
Marking chalk (for change points etc)
Field book
A2 Personnel
3 or 4 students will operate as a team:
1 with dumpy level
1 with staff
1 with field book
4th student to act as observer
(Students will rotate responsibilities as directed)
A3 Site
The triangle bounded by Exhibition, Victoria and Latrobe Streets
Refer to sketch plan provided
A6 Point ‘A’, ‘C’ and ‘E’ must be used as a change points
A7 Each combination of operations are to complete a side of the triangle each
A8 Close the level survey back to the PM and perform a field check before leaving the site
A9 Photocopy the field book sheets. Each student to reduce the whole assignment independently
A10 Photocopy the field book and submit the following:-
a) Original field sheets (or photocopy) showing all reductions
b) Tabular presentation of all results (in order)
e.g. Point RL Description
PM 31.412 Permanent Marker
A 33.333 Manhole cover
Page 39 of 173
Section B:
Section C:
C1 Abney Clinometer
Receive instructions on use of the clino – each student to read a slope as directed. Students will read slopes (in
both directions) for each leg of the triangle surveyed – to be used to reduce the slope distances to horizontal and
compare with reduction by Reduced Levels
C2 Optical square
Receive instructions on use of the Optical Square. Students will perform a small survey as instructed. Results to be
included with overall assignment
C3 Electronic distance measurement
Students will be shown some EDM equipment – both instrument attached and hand held
C4 Theodolite
Students will receive a demonstration of a theodolite and its uses. Students will have an opportunity to have a
‘hands on’ experience
C5 Compass & Plumb bob
Students will be shown various uses of compass and plumb bob
Page 40 of 173
Field Book Template
Name:
Resources Required
Your Trainer and Assessor will provide you with the following resources to complete this task:
Access to learner guide and other learning materials.
Timeframe
Your Trainer/Assessor will assign you a timeframe to maintain commercially realistic speed, time, and productivity.
Page 41 of 173
Answer Activity 2:
Your task.
Name:
Page 42 of 173
Page 43 of 173
Field Book Template
Name:
Page 44 of 173
Page 45 of 173
Page 46 of 173
Page 47 of 173
Page 48 of 173
Page 49 of 173
Page 50 of 173
Page 51 of 173
Page 52 of 173
Page 53 of 173
Page 54 of 173
Page 55 of 173
Page 56 of 173
Page 57 of 173
Page 58 of 173
You will be required to complete.
Your trainer will observe you while performing this task and complete the performance checklist.
Timeframe
You will be required to complete the massage as per the timeframe decided by the salon.
Page 59 of 173
Performance Criteria/Assessor Checklist: Task 1 Field Trip
Student Name:
Student ID No:
Final Completion
Date:
Does the candidate meet the following criteria
Did the student implement the requirements, procedures and techniques for
Yes No
the safe and effective completion of the activity.
Did the student use the equipment effectively and appropriately. Yes No
Did the student obtain, interpret, clarify and confirm work requirements in the following documents
Plans Yes No
Drawings Yes No
Specifications Yes No
Did the student access and interpret the engineering survey and geotechnical
Yes No
information.
Did the student communicate clearly and concisely with others to receive and
Yes No
clarify work instructions.
Did the student communicate clearly and concisely with others to coordinate
Yes No
work activities.
Areas Yes No
Grades Yes No
Did the student use computer aided drafting design and drafting technology to complete a scaled drawing
of the Field Trip in a scale of 1:500 using CADD software, including
A legend Yes No
Points Yes No
Page 60 of 173
Description Yes No
Did the student identify and confirm the geotechnical works project
Yes No
requirements and information.
Did the student monitor and coordinate the progress of other team members
Yes No
involved in the design process.
Did the student use industry or government standard design software. Yes No
Did the student complete the activity in the allotted time and submit
Yes No
drawings, calculations and completed field sheet
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date
Page 61 of 173
Assessment 3 – Project Task Cut & Fill
Student Information
Your task.
From the sketches given below and the drawings (Appendix D) provided use a CAD software and the given formula
below in sketch 1 to obtain the cut and fill of the given site.
Note: convert the given measurements in the sketches from mm to m.
1000mm = 1m
100mm – 0.1m
10mm = 0.01m
1mm = 0.001m
A + B + C = Cut
D + E + F + G + H + I = Fill
G = H Width is 0.5m
A = bd/2 = 0.026 x 0.050/2 = 0.00065m2
B = bd = 1.000 x 0.090 = 0.050m2
C = bd/2 = 1.000 x 2.300/2 = 1.150m2
Total = 1.20065 x 0.500 = 0.60033m3 = 0.600m3
Therefore, Cut is 0.600m3
A = bd/2 = 2.800 x 1.000/2 = 1.400m2
Page 62 of 173
B = bd = 2.550 x 1.000 = 2.550m2
C = bd/2 = 2.550 x 1.000/2 = 1.275m2
G = bd = 0.200 x 1.000 = 0.200m2
H = bd = G = 0.200m2
I = bd/2 = 0.200 x 0.074/2 = 0.0074m2
Width is 0.5
Total = 5.6324 x 0.500 = 2.8162m3 = 2.816m3
Therefore, Fill is 2.816m3
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
Page 63 of 173
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
A + B + C = Cut
D + E + F = Fill
Width is 1.0m
Page 64 of 173
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 1.0m
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 1.0m
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 1.0m
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 1.0m
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 1.0m
Page 65 of 173
A + B + C = Cut
D + E + F + G + H + I = Fill
Width is 0.5m
Use the following Cut and Fill Table to record your results.
10
11
12
13
14
15
Total
Resources Required
Your Trainer and Assessor will provide you with the following resources to complete this task:
Access to learner guide and other learning materials.
Your trainer will observe you while performing this task and complete the performance checklist.
Timeframe
Your Trainer/Assessor will assign you a timeframe to maintain commercially realistic speed, time, and productivity.
Page 66 of 173
Answer
Page 67 of 173
Page 68 of 173
Page 69 of 173
Page 70 of 173
Page 71 of 173
Page 72 of 173
Page 73 of 173
Page 74 of 173
Page 75 of 173
Page 76 of 173
Page 77 of 173
Page 78 of 173
Page 79 of 173
Page 80 of 173
Page 81 of 173
Page 82 of 173
Page 83 of 173
Page 84 of 173
Page 85 of 173
Page 86 of 173
Page 87 of 173
Page 88 of 173
Cut and Fill Table
Page 89 of 173
6
10
11
12
13
14
15
Total
Page 90 of 173
Performance Criteria/Assessor Checklist: Task 3 Cut & Fill
Student Name:
Student ID No:
Final Completion
Date:
Does the candidate meet the following criteria
Did the student access and interpret the engineering survey and geotechnical
Yes No
information.
Did the student complete all calculations for cut and fill. Yes No
Did the student apply the appropriate construction technique and formulas
Yes No
for calculating the cut and fill.
Areas Yes No
Volumes Yes No
Did the student apply computer-aided drafting design (CADD) and drafting
Yes No
techniology.
Did the student complete sections and site plans for the samples (i.e. 1 to 15),
Yes No
including the contours and slope using CADD.
Did the student interpret and analyse data and do the following:
Did the student complete the activity in the allotted time and submit all CADD
Yes No
drawings, calculations and cut-and-fill table completed.
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date
Page 91 of 173
Assessment 4 – Project Task Geotechnical Design
Student Information
Your task.
Geotechnical Design
For the following Activity you are required to provide 2 geotechnical designs solutions for the foundation in Task 1
and Task 2. In the following tasks will you will be provided with the information and design of a Commercial Factory
on a given site. Use the information and data to provide to different geotechnical designs for the foundation of the
factory. You will be communicating with your Supervisor, colleagues and contractors throughout the work activities.
You will review your design with the Supervisor to obtain feedback with your design and make changes where
required.
Once you have completed you preliminary design you will be required to submit it to your Supervisor for approval.
At the close out of the task you will participate in a performance review with and independent expert, your
colleagues and Supervisor and obtain feedback and verification of the design work produced.
Task 1 (occasion 1)
Strip footings:
600d x 400w concrete with 4-12TM steel reinforcement top and bottom, 6 diameter ligatures at 750 centres,
minimum 40 cover over steel. Footings extended beneath portal columns minimum 250 beyond base plate on all
sides and with additional 12TM reinforcement provided in both directions below columns.
Floor:
Concrete slab 150mm thick reinforced with F82 steel mesh at top and bottom with 30 cover, set over moisture
membrane on 50 thick packing sand on compacted ground/fill, slab edge thickened to be 250 deep x 300 wide
including over pad footing below columns, incorporated construction joints at edges, incorporate 'hairpin' steel
reinforcing bars 20 diameter and 1000 long set diagonally into slab, site welded to column flanges
Task 2 (occasion 2)
Strip footings:
700d x 500w concrete with 4-12TM steel reinforcement top and bottom, 6 diameter ligatures at 750 centres,
minimum 40 cover over steel. Footings extended beneath portal columns minimum 250 beyond base plate on all
sides and with additional 12TM reinforcement provided in both directions below columns.
Floor:
Concrete slab 200mm thick reinforced with F82 steel mesh at top and bottom with 30 cover, set over moisture
membrane on 50 thick packing sand on compacted ground/fill, slab edge thickened to be 250 deep x 300 wide
including over pad footing below columns, incorporated construction joints at edges, incorporate 'hairpin' steel
reinforcing bars 20 diameter and 1000 long set diagonally into slab, site welded to column flanges
Your task will require you to perform the following:
Access and interpret the given plans, drawings, specification and design of the factory.
Use the relevant Australian Standards and other Standards that may apply.
Access and interpret Engineering and Geotechnical information and apply it to your design.
Access and interpret hydrological, meteorlogical and cultural and heritage data. Refer to your local council and
apply the aforementioned to your design.
Access and interpret tests results and works selection data from the geotechnical works construction.
Apply the appropriate graphical representation to the Engineering drawings using a CAD software.
Where required use calculations to obtain areas, volumes, mass, percentages or grades for the design.
You must submit the following drawings with your geotechnical design:
General Excavation Plan (Scale 1:100)
Spatial Plan (Scale 1:100)
Foundation Plan (Scale 1:100)
Detail of Portal Column Pad (Scale 1:10)
Footing and Strip Footing (Scale 1:10)
Detail of Slab and Strip Footing (Scale 1:10)
Page 92 of 173
Page 93 of 173
Page 94 of 173
Page 95 of 173
Page 96 of 173
Page 97 of 173
Page 98 of 173
Page 99 of 173
Page 100 of 173
Page 101 of 173
Page 102 of 173
The sketch design of the factory that has been provided is to be amended in accordance with the instructions to
the information below and as instructed. Note that this information will also be required to prepare the
geotechnical design for the factory including engineering detail drawing of the footings.
Factory design and general construction:
For the following design locate and apply relevant legislation, documentation, policies and procedures in all the
stages of the design process.
Soil Classification to be used:
Class Foundation
A Most sand and rock sites with little or no ground movement from moisture changes
S Slightly reactive clay sites with only slight ground movement from moisture changes
Moderately reactive clay or silt sites which can experience moderate ground movement from moisture
M
changes
H Highly reactive clay sites which can experience high ground movement from moisture changes
E Extremely reactive clay sites which can experience extreme ground movement from moisture changes
Sites which include soft soils, such as soft clay or silt or loose sands; landslip; mine subsidence;
P collapsing soils; soils subject to erosion; reactive sites subject to abnormal moisture conditions
or sites which cannot be classified otherwise
Note to Table 3.2.4.1: For classes M, H and E further division based on the depth of the expected movement is
required. For deep-seated movements, characteristic of dry climates and corresponding to a design depth of
suction change Hs, equal to or greater than 3 m, the classification shall be M-D, H-D or E-D as appropriate. For
example, H-D represents a highly reactive site with deep moisture changes, and H represents a highly reactive site
with shallow moisture changes
Factory length:
24600, with grid between portal column centrelines approximately 6000 (adjust bay spacing to nearest 5mm to suit)
Factory width:
18800, with grid between portal column centrelines (i.e. in portal span direction) reduced to approximately 18000.
Office and amenities are generally shown but with door provided between rear staff dining room and factory
(matching other internal doors, 800 wide). You are to design the office and amenity areas to your discretion.
External Walls:
Exposed concrete block masonry, module 400x200x200, hollow blocks used reinforced vertically with 12 diameter
steel bars/concrete fill at minimum 1200 centres including beside opening with reinforcing tied to starter bars set in
the concrete strip footing, walls extended up as a level parapet on all sides minimum 75 above roof, 'Colorbond'
sheet bent steel capping over.
steel or aluminium frames, openings 3600 wide by 1200 high, window sill 1200 above floor level, personnel entry
doors incorporated with window openings, doors 900 wide, solid timber 32 thick
Internal Clearance:
Height to underside of UB haunch of portal rafter to be 6500 from factory floor level. Ceiling height of amenities area
below mezzanine to be 2700.
Roof:
Roof slope 6 degrees, roof cladding: 'Lysaght Klip-lok 406'steel decking with 'Zincalume' finish, fixed to purlins over
draped reflective foil insulation and safety mesh
Box Gutter:
Bent 'Zincalume'/steel sheet 400 wide x 75 deep over 'Lysaght Spandeck' gutterboard supported by 'Duragal 50 x
50 x 5 EA at maximum 800 centres fixed to wall and hung from roof purlins, minimum gutter fall 1:100 to 300 x 300
x 300 rain water head outlets connected to stormwater drains in ground
Internal lining:
Plasterboard, except where tiled in wet areas and where exposed externally adjacent the entry door where fibre
cement sheet used
Mezzanine Stair:
Steel framing with timber treads, width 800, stair handrail 780 above nosing, mezzanine handrail 1000 above floor
the sizes of the frame members and related components are as follows:
Portal columns:
410 UB 53.7
20 thick, extended 10 beyond column edges, welds: 8 CFW. Clearance height of 30 required over concrete footing
to underside of base plates, gap grouted. Hold down bolts: 20 diameter, 4 required near corners, centres 40 from
base plate edges, tied to bottom reinforcement in footing. Bolt centres: 40 from outer edges of plates, 60 from
flanges, webs and stiffening plates. Concrete pad footing: integrated with concrete strip footings external masonry
wall.
Portal rafters:
360 UB 50.7 including for haunch, haunch length 2000. Portal connection plates: 20 thick, welds: 8 CFW, bolts:
M16, minimum 8 per connection, location of plates to be decided (either at column head and ridge or at 1/4 of portal
rafter span). Stiffening plates: 12 thick, welds 6 CFW.
Corner columns:
310 UB 32.0
230 PFC
150 UC 18.0, 3 required at maximum 4500 centres, 2 base plate hold down bolts required, 20 diameter. Cleats: 10
thick steel plate, size to suit requirements, welds: 6 CFW
Fan bracing from portal columns to concrete block wall at maximum 3000 centres in wall height: 50 x 50 x 6 EA,
M12 bolt fixing, cleats: 6 thick plate or 16 diameter steel rod cross bracing to outer bays, capable of being tightened
from 75 x 75 x 6 EA welded to centre of webs of portal columns.
Eaves ties:
150 PFC bolted to masonry wall 500 each side of portal columns, roof ties: 150 CHS at 4500 centres in braced
bays, 9000 centres in other bays.
16 diameter steel rod cross bracing to outer bays between eaves ties/roof ties, capable of being tightened from 75 x
75 x 6 EA welded to centre of rafter webs or columns. Roof purlins: Z20024 at maximum 1500 centres generally,
1200 at edges of building, bridging required at mid-span, fly bracing to portal rafters at maximum 3000 centres: 50 x
50 x 6 EA, M12 bolt fixing, cleats: 6 plate.
Mezzanine structure:
Steel 90 x 90 x 6 SHS columns at maximum 4000 centres supporting 150 x 50 x 6 RHS or 150 PFC beams at
maximum 2000 centres with C10019 as floor joists over, fixed to cleats at 600 centres, galvanised finish.
Mezzanine floor:
Particleboard sheet flooring with hardwood edge-strips at exposed outer edge Window/door lintels: fabricated to suit
250 high x 175 wide 10 thick steel plate minimum bearing 300 on masonry at each end, galvanised finish.
'Lysaght Supraframe' steel studwork 90 wide. Stair to mezzanine: fabricated steel string beams 150 x 50 x 6 RHS
or 150 PFC with 50 x 50 x 5 EA welded to inside faces with 6 CFW supporting KDHW treads: 290 x 40 fixed with 2
M8 galvanised coach bolts at each end
42.4 x 3.2 CHS or 40 x 40 x 3 SHS, 6 CFW bolted or site welded to top of stringers, stair finish: painted
Design of factory:
One office for a secretary and director 16-20 sqm: 2 Toilets (male and female): Showers and Locker Room (male
and female): Dining room with kitchenette for 8 employees: Entry and exit according to BCA standards: One entry
for deliveries and dispatch of goods: Natural Lighting from front and rear elevation, and: Minimum 4 parking spaces
at the front of the factory
Note again that the engineering drawing method used depicts structural members by simple bold lines with gaps left
where connections are to be made on site. Each member type is given a 'mark' (or designation), which is linked to a
schedule describing its characteristics (e.g. shape and size) with other comments necessary (e.g. span, spacing).
The location of members is shown related to a dimensioned grid on the layout plan using initials on way and
numbers the other way. The grid is also shown on the elevations and sections. The main vertical dimensions are
shown on the sections and elevations. Parts of the building are selected and drawn more realistically as structural
details. These are referenced from the layout plans, sections and elevations using faint circles about the area
involved. An initial is given to each detail together with the sheet number from which it is derived. Section and plan
details of a particular area may also be referenced from other detail views using section lines with arrows and when
this is done the detail is identifies by a number so that the source is easily recognised as being different. For further
information refer to notes with examples of engineering drawings supplied at the lecture.
Your task now is to prepare a drawing showing engineering details of your geotechnical design for the factory
building at selected locations. This involves showing the structural materials and components such as the
steelwork, the reinforced concrete footings and the concrete block walls for which the engineer is responsible. (Note
that detail of non-structural components such as window and door frames, roof cladding, flashings, gutters, wall
linings, insulation and the like are shown on the architectural documentation drawings. However such items may be
included on engineering details in simple outline with a note attached).
Select at least six junctions of the building for detailing including the following:
Prepare the architectural documentation drawing of the ground floor plan of the factory based on the sketch plan
and notes previously provided and the engineering layout and detail drawings already begun. The overall section
drawings and plan details are to be referenced from this floor plan.
Note that documentation drawings show only the materials and components to be built as part of the construction
contract (i.e. they do not show loose furniture, landscape planting and the like). Architectural documentation
drawings of industrial, commercial, institutional or multi-storey residential projects are usually set out and
dimensioned in the same manner as engineering drawings (i.e. using a structural grid). The locations of other
components can then be dimensioned from a gridline. As noted previously the grid is designated alphabetically one-
way (i.e. 1, 2, 3 etc.) and numerically (i.e. A, B, C, etc.) the other so that any intersection can be quickly located.
The gridlines are drawn very faintly as ‘chain lines’ with alternating long and short dashes and the designation is put
in a circle beyond the dimensions. Overall lengths of the building are also given each way, as may individual
dimensions when deemed necessary. Materials cut in plan (horizontal section) are represented according to
architectural conventions (i.e. they are strongly outlined with appropriate hatching drawn lightly within). Continuous
lines represent edges of objects seen in the view (e.g. edge of floor slab, sill of windows) and dashed lines
represent hidden elements (e.g. extent of stair above plan cut-off height). Architectural documentation drawings
usually omit or simplify much of the engineering content. For example the footings may be drawn in outline only (i.e.
not hatched and without the steel reinforcing shown) with a note referring the reader to the engineering drawings.
This is to ensure that the building contractor uses the appropriate drawings for construction and that the
professional concerned is responsible for their part of the design. It also simplifies and quickens the task of altering
drawings when variations have to be made, as the other consultant is not affected unless major changes to the
structure occur. However in drawings for this part of the work you are to combine all information, as your
understanding of both the engineering and architectural aspects and how they are integrated is being learnt. Include
all items described in the introduction to the factory project provided in week 4 (see ‘factory design and general
construction’ and ‘structural framing requirements’) that are cut and seen in plan at approximately 1500 above floor
level. This includes the external concrete block wall, steel columns, doors and windows, the mezzanine walls,
plumbing fittings, the internal stair, downpipes and the like. Also show the construction joints in the concrete block
walls and in the concrete infill slab floor. Faint dashed lines can be used to show important hidden information such
as the footing location below the floor and the extent of the mezzanine stair above the height of 1500. This plan
should occupy one A3 sheet including the necessary horizontal dimensions, references to other architectural
drawings (overall sections and plan details), and notes regarding the main materials and components used. Include
a full title block if space permits; otherwise provide the minimum title information required to adequately describe
the drawing as part of the documentation set for this subject (i.e. subject name, drawing title, scale used, north
point, your name and sheet number). Note that this is sheet 6 in the set of drawings for the subject but also sheet
A1 of the architectural documentation drawings for the factory project.
Now you can begin to prepare the documentation drawings showing a section through the factory building each
way. Each section is to be referenced from the floor plan using section reference lines cutting the outer walls with
arrows showing the direction viewed. Materials and components are to be represented in the same way as on the
plans, strongly outlined with fine hatching between where they are cut and only in outline seen beyond. Each view
should show the mezzanine: the ‘cross section’ cutting through the mezzanine and the ‘longitudinal section’
(preferably cutting through the factory delivery door) viewing it in elevation within the building. The stair and handrail
will need to be shown in each section (handrail heights previously given, treads [goings] to be minimum 250 wide,
risers minimum 150 and maximum 190 high). Note also that the mezzanine is an open storage area (i.e. has no
partition walls). Each section should occupy one A3 sheet. As for the floor plan the main materials and components
used are described using concise notes. More comprehensive information will be eventually given on the section
details drawn at a larger scale. The locations of the section details will be referenced from these drawings and this
is best done using fine circles about the area selected. Vertical dimensions are to be included related to the factory
floor level. Note that in this case the critical height for the steelwork is to the underside of the portal rafter at the
column connection (i.e. 6500 beneath the haunch) and the ceiling level below the mezzanine (2700) so that you will
have to determine the height of the top of the parapet wall and the mezzanine floor using the depths/heights of the
components, roof slope etc. using information from the ‘factory design and general construction’ and ‘structural
framing requirements’ data previously provided. Battens supporting the plasterboard ceiling in the amenities area
beneath the mezzanine can be assumed to be 45 x 70 F5 seasoned pine at maximum 600 centres. Note that the
structural information given for the mezzanine area needs amending as the maximum span given for beams (4000)
would result in having to provide internal columns within the office, male toilet and lunchroom areas which is
undesirable. To overcome this problem the engineer advises that the beams (either 150 x 50 x 6 RHS or 150 PFC)
can span up to 4500 provided the maximum spacing between them is reduced to 1800 (previous maximum given
was 2000). As these beams will also need support from the external concrete block wall it is proposed that a
continuous steel angle (100 x 100 x 8 EA) be fixed to the wall between the columns at maximum 1200 centres
using masonry anchors (12 diameter). Cleats (8 thick) will need to be welded to the angles to provide bolted
connections to the beams (2 M12 bolts required per connection).
Identify and use the relevant documentation drawings showing plan and section details at selected locations of the
factory building. The materials and components required for construction are in accordance with architectural detail
drawing conventions (i.e. hatching of materials, back lining in section, notes describing the materials and
components, sizes etc.). Include the engineering and the structural information provided (i.e. only basic information
on welding and bolting detail and steel finishes etc. is required and without a schedule of structural members). Each
detail drawing is to be referenced from the appropriate overall plan or section (drawings [A3]) by drafting a fine
circle about the area concerned.
Plan detail
As the most critical connections occur at the main portal column and the columns at the end walls this is the
minimum requirement for this drawing. Other details required would occur at the corner of the building, at the jamb
of a doorway and at the jamb of a typical window and this information is desirable. A detail of the bracing of the
columns to the concrete block wall or lateral cross bracing would also be helpful, but as this may be confusing if
also included on these plans it may be omitted. Considering this, select at least two locations from the ground floor
plan (drawing [A3]) for detailing at the scale required.
Section details
In this case two details are required preferably referenced from the cross section (drawing [A3]):
Footing/wall detail (showing the junction of the floor to the wall and the base of the portal column)
Wall/roof detail (showing the portal column/rafter [haunch] connection, the roofing, the parapet and
the box gutter). The ridge detail may be included if it will fit on the sheet.
Documentation drawing shows construction details of the mezzanine area within the factory. Both plan and section
details. Also included are details of the steel/timber stair and mezzanine handrail. Note that ‘wet area’ details of the
staff amenity areas (toilets, showers and kitchen) with associated joinery (benches and cupboards) would be shown
on other drawings for the project but are not required for this unit. Each detail is referenced from the ground floor
Determine and document the performance requirements in the design review template provided further below, that
apply to the project, which include:
Cost
Detail relating to availability of material
Heritage factors
Nominated subcontractors
Provision of site access/facilities
Quality Assurance
Standard procedures
Standards of work
Work schedule
Planning Permit – use the link provided to complete this (to be
submitted)(https://www.planning.vic.gov.au/ data/assets/pdf_file/0016/6271/Application-for-a-
VicSmart-Planning-Permit_July-2017.pdf)
Note: each shift is equivalent to 1 days work. Allocate the number people you will require as Labour. Allocate the
Plant to be used. The number of shifts will be equivalent to 1 month, therefore work out the number of working days
(i.e., shifts) the project will take.
Geotechnical
Design
Soil report
Consultants
Sub-contractors
Planning Permit
Application
Inputs
Trench Width m
Total volume of
M3
excavated material
Production rate M per shift
Duration shifts
Calculations:
Labour
Supervisor shift
Plant
Excavator shift
Tipper shift
Ute shift
Materials
Concrete M3 $200
Steel m $90
Bedding and backfill
M3 $50
material
Use the template provided to complete your design review included feedback from external expert or colleagues. (to
be submitted)
3.
Solution example:
Sample Specification
The scope of work is as detailed in this specification, the contract drawings, the schedule (if appropriate) and the
purchase order. The client must assume responsibility for the accuracy and completeness of the information
supplied to the Consultant and upon which this design is based. The limit of this design is as set out in the
documents. No other warranty, express or implied is made in respect of the professional advice contained herein.
Copyright
These documents and the information contained herein are the property of the Consultant and may not be copied
in any form without the written permission of the copyright owner. Permission is granted to:
The Client as identified herein and their contractors and subcontractors, for purposes of carrying out
construction of the particular project identified herein.
The relevant local authorities for purposes expressly required under the provisions of the
Environmental Planning and Assessment Act or other relevant legislation.
Acknowledgements
The Consultant acknowledges that information on the foundations, retained soil, site boundaries, levels and
structures contained in documents prepared by others, and supplied to The Consultant by the client, has been
used in this design. The client must assume responsibility for the copyright, accuracy and completeness of the
information supplied to The Consultant and upon which this design is based.
The Contractor shall ensure that the work is performed and directly supervised by appropriately qualified and
experienced personnel.
Quality Assurance
Suppliers and contractors shall provide assurance of the quality of all goods, materials and services to be
provided. The following are deemed to meet this requirement:
a quality assurance system complying with AS/NZS ISO 9001, or
a quality control system approved by the Consultant.
Dimensions
All work shall be installed in accordance with the contract drawings, which show the general layout. The main
setting out dimensions shown on architectural drawings take precedence over those shown on engineering
drawings, which have been included to assist the detailing. Dimensions on sections through structural
components such as slabs, footings or retaining walls shown on engineering drawings take precedence over
those shown on architectural drawings. The Contractor shall check for any conflict between works as constructed,
the relevant engineering drawings or sections and the relevant architectural drawings or sections. If conflicts are
detected, they shall be reported to the Consultant for resolution before work proceeds.
The Contractor shall ensure that the work is executed in accordance with the drawings and specifications, and
any additional relevant requirements of the Building Code of Australia, the Building Regulations, applicable
Australian Standards and supplier’s instructions.
Completion
When work has reached the stage of requiring inspection, the Contractor shall advise the Consultant, before
proceeding to cover, close or complete the work. On completion of all works the Contractor shall formally advise
the Consultant of practical completion. Where the contract is staged, this advice shall be given at completion of
each major stage of the works.
Development Applications
It is advised that all residential developments concerning external or structural components of a dwelling should
be lodged with the appropriate council departments for approval, before construction is commenced.
Potential problems and solutions
Leaks
If plumbing fittings are not correctly sealed and tightened, they may leak. Ensure that the correct gasket material
or plumbers tape is used and that all fittings are tightened. Inspect each pipeline for leaks before the plumber
leaves the job.
Scope
This specification covers the installation of a disabled toilet on Level 4, 446 Collins Street, Melbourne, Victoria,
3000.
Approvals
The Contractor shall obtain all relevant approvals and provide to the Builder the appropriate certificates. When the
Approval Authority requires variations, they shall be confirmed by the Builder before work proceeds.
All components and installation shall comply with the Building Code of Australia (BCA) and the relevant Australian
Standards, including AS/NZS 3500 and the standards listed therein.
Commencement
Existing Services
The Contractor shall disconnect, terminate and remove any obsolete parts of existing services. When required to
divert existing services that obstruct new building work, at least three day’s notice shall be given to the Builder.
Samples
When the contract requires the Contractor to supply the fittings, one sample of each shall be submitted to the
Builder for approval before placing the order.
Materials
Plumbing and drainage components shall comply with the relevant Australian Standards and shall be compatible
with the corresponding pipes.
Installation
All plumbing and drainage components and installation shall comply with the Building Code of Australia and the
relevant Australian Standards, including the following standards:
Water supply AS/NZS 3500.1
Sanitary plumbing and sanitary drainage AS/NZS 3500.2
Stormwater drainage AS/NZS 3500.3
Hot water supply AS/NZS 3500.4
PVC pipes and fittings shall have solvent welded joints in accordance with AS/NZS 3879.
The Contractor shall give notice on completion of each stage of the work and arrange for the appropriate
inspections and tests required by the Builder and Approval Authority. The Contractor shall supply all required
equipment and materials and perform all relevant tests. All new work shall remain open until it has been
inspected, tested and approved by the Builder and Approval Authority. The following inspections and tests shall
be performed.
Construction Inspections
Notes
All tolerances shall be as shown, except where overridden by AS/NZS 3500 or AS 3740.
Wastes
Length:
Width:
Vanity Units Height:
Basins:
Plumbing:
Material:
The specified commercial building complies with statutory requirements for fire separation and Deemed-to-Satisfy
(DTS) provisions of the Building Code of Australia. This includes:
Fire resistance levels
Fire source features
Class of building
Multi-residential timber-framed construction
Concrete, blockwork, brickwork AAC, lightweight construction, e.g. plasterboard
Protection of openings
Sole occupancy units
Paths of travel
Fire stairs and isolated stairs
Non-combustible materials
Housing in bushfire areas according to regional regulations
The design has safe movement and access in accordance with the Building Code of Australia and relevant
Australian Standards. The safe movement and access include:
Access for maintenance (i.e. roof access, built in provision of roof hatch ladders, walk platforms,
roof mounted services, fall arrest systems)
Adequate lighting for daily use and emergencies
Balustrade
Page 116 of 173
Handrails
Stair tread nosings
Stair construction
Tactile indicators
If there is any further information that you require or if you have questions, use clear and direct communication to
confirm/share the requirements with your supervisor or other personnel.
Resources Required
Your Trainer and Assessor will provide you with the following resources to complete this task:
Access to learner guide and other learning materials.
Your trainer will observe you while performing this task and complete the performance checklist.
Timeframe
Your Trainer/Assessor will assign you a timeframe to maintain commercially realistic speed, time, and productivity.
Student ID No:
Final Completion
Date:
Part 1
Did the student locate and apply relevant legislation, documentation, policies
Yes No
and procedures.
Did the student implement the requirements, procedures and techniques for
Yes No
the safe and effective completion of the activity.
Did the student use the equipment effectively and appropriately. Yes No
Plans Yes No
Drawings Yes No
Specifications Yes No
Did the student communicate clearly and concisely with others to receive and
Yes No
clarify work instructions.
Did the student ensure the geotechnical design was compliant. Yes No
Areas Yes No
Volumes Yes No
Densities Yes No
Percentages Yes No
Grades Yes No
Did the student submit all the work for the activity including relevant notes
Yes No
such as calculations and sketches.
Did the student complete the following CADD Drawings using industry or government standard design
software:
Did the student obtain, read, interpret, clarify and confirm work requirements. Yes No
Was the design plan prepared with the best available resources. Yes No
Did the student identify and confirm the requirements and information for the
Yes No
geotechnical works project.
Did the student obtain, interpret and analyse required data and identify design options for civil concrete
structures according to job requirements to do the following:
Did the student close out all systems according to workplace requirements. Yes No
Did the student interpret and analyse data to recommend options. Yes No
Did the student communicate and coordinate with personnel involved in the
design process according to workplace requirements and within the scope of Yes No
own role.
Did the student complete the activity in the allotted time and submit
Yes No
drawings, calculations and completed field sheet
Part 2
Did the student locate and apply relevant legislation, documentation, policies
Yes No
and procedures.
Did the student implement the requirements, procedures and techniques for
Yes No
the safe and effective completion of the activity.
Did the student use the equipment effectively and appropriately. Yes No
Plans Yes No
Drawings Yes No
Specifications Yes No
Did the student communicate clearly and concisely with others to receive and
Yes No
clarify work instructions.
Did the student ensure the geotechnical design was compliant. Yes No
Did the student complete a design cost and reporting requirements and
Yes No
deliver to required stakeholders.
Did the student apply the given design plans and develop a geotechnical
Yes No
design of the foundation.
Did the student participate in a design review with others according to
Yes No
workplace requirements.
Did the student seek feedback that contributed to the final design including
recommended changes to the design for continuous improvement as well as Yes No
verification according to workplace requirements.
Did the student obtain design approval that satisfied all authorities,
Yes No
requirements and legislation.
Did the student submit an application for the development of the geotechnical
Yes No
design.
Did the student submit a planning permit and contribute to the validation of
Yes No
the design as required to meet job requirements.
Areas Yes No
Volumes Yes No
Densities Yes No
Percentages Yes No
Grades Yes No
Did the student submit all the work for the activity including relevant notes
Yes No
such as calculations and sketches.
Did the student complete the following CADD Drawings using industry or government standard design
software:
Did the student obtain, read, interpret, clarify and confirm work requirements. Yes No
Was the design plan prepared with the best available resources. Yes No
Did the student identify and confirm the requirements and information for the
Yes No
geotechnical works project.
Did the student obtain, interpret and analyse required data and identify design options for civil concrete
structures according to job requirements to do the following:
Did the student close out all systems according to workplace requirements. Yes No
Did the student interpret and analyse data to recommend options. Yes No
Did the student communicate and coordinate with personnel involved in the
design process according to workplace requirements and within the scope of Yes No
own role.
Did the student complete the activity in the allotted time and submit
Yes No
drawings, calculations and completed field sheet
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date
Using the Geotechnical Report (Includes Appendix A and B) provided, write a report in your own words and include
the information in the relevant sections of the template below.
Using the Geotechnical Report provided, write a report in your own words and include drawings, photographs and
recommendations. Identify and include all relevant geotechnical-related information.
1. INTRODUCTION
a. Project description
b. Scope of work
2. GEOLOGY
a. Regional Geology
b. Site Geology
3. EXISTING GEOTECHNICAL INFORMATION
4. SUBSURFACE EXPLORATION PROGRAM
a. Subsurface Exploration Procedures
b. Laboratory Testing
5. SUBSURFACE CONDITIONS
a. Topography
b. Stratigraphy
c. Soil Properties
d. Groundwater Conditions
6. RECOMMENDATIONS FOR BRIDGE FOUNDATIONS
a. Design Alternatives
b. Group Effects
c. Foundation Settlement
d. Downdrag
e. Lateral Loading
f. Construction Considerations
g. Pile Testing
7. RECOMMENDATIONS FOR EARTH RETAINING STRUCTURES
a. Suitable Types
b. Design and Construction Considerations
8. ROADWAY RECOMMENDATIONS
a. Embankments and Embankment Foundations
b. Cuts
c. Pavement
9. SEISMIC CONSIDERATIONS
a. Seismicity
b. Seismic Hazard Criteria
c. Liquefaction Potential
10. CONSTRUCTION RECOMMENDATIONS
11. APPENDICES
Appendix A and B
Student ID No:
Final Completion
Date:
Does the candidate meet the following criteria
Did the student interpret and analyse data to recommend options. Yes No
Plans Yes No
Drawings Yes No
Specifications Yes No
Did the student comply with written and verbal reporting requirements and
Yes No
procedures.
Did the student select and apply the appropriate construction techniques. Yes No
Did the student interpret and analyse data to recommend options. Yes No
Did the student complete the activity in the allotted time. Yes No
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date
The design solution is to include the advantages of your design. In your answer, include a reference to its
construction method, durability, council guidelines, and other benefits. (Question 2)
You are to follow and complete the following requirements:
Using CADD software, draw detailed construction drawings for each solution on a scale of 1:10 or 1:10.
The final design for the site is to be certified.
Follow all WHS requirements during the bridge design, including the site investigation, construction and
operations.
Your design must follow the state and local council guidelines. Note that councils adopt different practices
according to their policies and procedures, ensure you apply practices accordingly.
Seek advice and guidance from your Supervisor to successfully develop the bridge solution for your site.
The design will utilise information and data gathered from the research and investigation, including information
gathered from the site investigation. Assume your site investigation resulted in a Class S soil type.
Soil Classification to be used:
Class Foundation
A Most sand and rock sites with little or no ground movement from moisture changes
Moderately reactive clay or silt sites which can experience moderate ground movement
M
from moisture changes
Highly reactive clay sites which can experience high-ground movement from moisture
H
changes
Extremely reactive clay sites which can experience extreme ground movement from
E
moisture changes
Sites that include soft soils, such as soft clay or silt or loose sands; landslip; mine
P subsidence; collapsing soils; soils subject to erosion; reactive sites subject to abnormal
moisture conditions or sites that cannot be classified otherwise
Note: For classes M, H and E, a further division based on the depth of the expected movement is required. For
deep-seated movements, characteristic of dry climates and corresponding to a design depth of suction change Hs,
equal to or greater than 3 m, the classification shall be M-D, H-D or E-D as appropriate. For example, H-D
represents a highly reactive site with deep moisture changes, and H represents a highly reactive site with shallow
moisture changes
Identify the sequence of the process of designing and constructing the bridge.
(Question 3)
The bridge's design must be certified by the relevant authorities (Note: in this case, your Trainer will assume the
position of the relevant authority).
As the designer, you must ensure that all loads are transmitted to the foundation.
Other tasks you will need to carry out are:
Obtain waterway and geotechnical information specific to your site (Research the internet to obtain geotechnical
information relevant to your site)
Obtain traffic and road design information related to the area to identify the volume of traffic using the existing
bridge.
Complete all bridge design drawings using CADD. Draw an Elevation of the bridge on a scale of 1:100 and a
Typical Section of your bridge design on a scale of 1:10 or 1:20 including all dimensions. Submit all sketches and
photos in the development of your design.
Below is a sample of a Site Plan with contours. Your site must include a similar plan.
Design Review
Colleagues – Stakeholders
You will undergo design review stages with stakeholders (Note: your colleagues will assume this role). The stages
will include the following:
Stage 2: 80% detailed design showing major completion of the bridge design with notes and dimensions; council
and stakeholders will provide feedback.
The feedback is to be collected and provided in the register of design comments table provided below
Ensure all design work and documentation is submitted and filed according to company policy and procedure.
Use the template below to record a design review plan. (to be submitted)
Use the template below to record a design review plan. (to be submitted)
Example:
Use the template provided to complete your design review, including feedback from stakeholders, council
authority, experts or colleagues. (to be submitted)
Ite Date Review Aspect Design Sheet/S Revie Respo Respon Sta Close
m er(s) (e.g. D- Component/ ection w nse Respo se date tus out
initials Design, Discipline com and nse (initial
C- ment action by s&
CADD/Dr (Disci date)
afting) pline
and
initial
s)
Example:
To be
compl
eted
by
Drafting To be Super
20/01/ anothe 27/01/2 01/02/
1. RL D Design N/A compl visor - 0
2023 r 023 2023
solution eted JC
person
in a
discipli
ne
2.
3.
(Question 4)
Bearing
In-situ concrete closure strip
Dowels
Grout
Internal precast concrete module
Precast reinforced concrete pier headstock
Thrie beam
External precast concrete module
Shear key plinth
Sealant deck joint
Thrie beam connection bracket
Sill beam and wingwall projected reinforcement for in-situ concrete stitch pour
Precast reinforced concrete driven pile
Abutment curtain wall
Precast concrete deck module
Module holding down bracket
Precast reinforced concrete abutment sill beam
Low-performance level steel traffic barrier railing
Deck Modules – The deck modules you must consider in your design should be a minimum of 600mm deep
precast prestressed concrete double T deck modules, as shown in the diagram. Ensure the width and length of your
bridge design is appropriate and according to the design criteria.
Traffic Barriers – The bridge design will assume a low risk and adopt a low-performance level barrier. The traffic
barrier will follow AS 5100.
Bearings – The bearings are to be mounted on gout pads. These will be levelled on-site to facilitate the installation.
Holding Down and Restraint Brackets – The restraint brackets will be prefabricated and made of galvanised steel
sections. They will be anchored to the deck and headstock using bolts and provide vertical restraint and, if
necessary lateral and longitudinal restraint if your design requires it.
Precast headstocks – The precast concrete pier headstocks are to be 850mm wide and 800mm deep. The number
of piles to be used will depend on the length of your bridge design and must satisfy AS 5100.
Precast Abutment Sill Beam – The precast abutment sill beam is 800mm wide and 800mm deep. They should be
used in your bridge design to suit the number of block outs and pile/column support.
Precast Wingwall – The precast wingwall will be made from reinforced concrete. They will be mounted on the traffic
barriers and should be designed for cantilever lengths of 3.5m to 4.5m.
Note: All notes are to be included in the drawings in a box under the heading Notes.
1. The design with the single lane with closure pour will have the following details:
Two precast prestressed concrete double-T modules.
The carriageway will be 4.2m in width and carry one traffic lane.
The curb will be 150mm high.
The traffic barrier will be 800mm in height.
The foundation will be according to the site conditions, and you will use the developed substructure of 4
Nos 450mm square precast driven piles.
3. The design with the single lane without closure pour will have the following details:
Two precast prestressed concrete double-T modules.
The carriageway will be 4.2m in width and carry one traffic lane.
The curb will be 150mm high.
The traffic barrier will be 800mm in height.
The foundation will be according to the site conditions, and you will use the developed substructure of 4
Nos 450mm square precast reinforced concrete driven piles.
Elevation
Once all your design drawings have been completed, they must be certified by the Engineer (i.e., your Trainer).
Safety Considerations
Ensure you consider all the risks associated with the design. Ensure you follow all safety guidelines and
requirements. Establish any hazards or risks identified throughout your bridge design process and recommend how
they can be resolved in the review process.
Resources Required
Your Trainer and Assessor will provide you with the following resources to complete this task:
Access to learner guide and other learning materials.
Timeframe
Your Trainer/Assessor will assign you a timeframe to maintain commercially realistic speed, time, and productivity.
Question 1:
The Australian Standard AS 5100 - Bridge Design is applicable to this bridge design assessment. This
standard outlines the design criteria for various types of bridges, including structural loads, safety
requirements, and maintenance considerations. Compliance with AS 5100 ensures that the bridge will meet
the necessary safety and performance standards in Australia.
Question 2:
Durability:
Precast pre-stressed concrete has high durability and resistance to environmental factors,
reducing long-term maintenance costs.
Council Guidelines:
Aligns with council guidelines for using modular systems, ensuring compliance with local
regulations and standards.
Other Benefits:
1. Initial Planning:
o Conduct a site investigation and gather geotechnical data.
2. Soil Testing and Classification:
o Perform soil testing to confirm classification and design foundations accordingly.
3. Design Concept Development:
o Develop initial bridge design concepts and use CADD software to create detailed drawings.
4. Preliminary Design Review:
o Review the concept with stakeholders and modify based on feedback.
5. Detailed Structural Analysis:
o Conduct structural analysis to ensure the design meets load-bearing requirements.
6. Final Design Documentation:
o Prepare final construction drawings and documentation for council and engineering
certification.
7. Approval and Certification:
o Submit the design for council approval and certification by a licensed engineer.
8. Construction Planning:
o Create a construction schedule and establish WHS safety measures.
9. Foundation and Substructure Construction:
o Construct the foundation and substructure according to the design, based on soil conditions.
10. Superstructure Assembly:
o Assemble or cast superstructure components on-site or use pre-fabricated parts.
11. Final Inspection and Certification:
o Inspect completed construction to ensure compliance with design and safety standards.
12. Site Cleanup and Handover:
o Clear the site and conduct a final inspection before opening the bridge to the public.
The modular bridge system incorporates precast components that are assembled on-site. This innovative
installation method enables rapid construction while minimizing disruption to the surrounding environment.
In designing this modular bridge, the following specific considerations are included:
1. Barrier Impact
o Given the location and regional traffic characteristics, the bridge design will assume a low-
performance barrier, as the majority of the traffic consists of light vehicles. The design
incorporates safety features to accommodate this classification, focusing on low-impact
loads.
2. Seismic Activity and Earthquake Resilience
o The bridge will be designed to withstand seismic forces according to local earthquake risk
levels. This includes implementing flexible joints and reinforced connections to handle
potential lateral and vertical movement, ensuring stability and integrity under seismic
activity.
3. Water Flow Forces and Flooding
o The bridge is designed to resist water forces, including potential flooding. Considerations for
water flow include elevating the bridge slightly above the known flood line and incorporating
drainage systems that divert water away from the structure. This helps maintain bridge
durability and prevents damage from water accumulation.
4. Heavy Braking Forces and Traffic Loading (SM1600 Standard)
o To handle heavy braking forces from vehicles, the bridge design follows the SM1600 traffic
loading standard. This ensures that the load from heavy vehicles does not exceed the bridge's
design limits. Reinforcements are incorporated to accommodate the potential impact from
vehicles decelerating abruptly.
Each component plays a specific role in ensuring the structural integrity, durability, and safety of the bridge.
Below is the allocation of components for the bridge design:
Bearing: Provides support and allows for controlled movement to accommodate temperature
changes and load shifts.
In-situ Concrete Closure Strip: Joins precast modules and improves the bridge’s structural
continuity.
Dowels: Used to connect different precast components, ensuring load transfer and stability.
Grout: Fills gaps between precast modules, creating a seamless bond and improving structural
cohesion.
Internal Precast Concrete Module: Core component for structural stability, positioned internally
for load-bearing.
Precast Reinforced Concrete Pier Headstock: Supports the deck and distributes load to the piles,
providing a strong structural foundation.
Thrie Beam: Installed as part of the traffic barrier for additional vehicle containment.
External Precast Concrete Module: Positioned on the bridge's exterior to provide structural
balance and lateral support.
Shear Key Plinth: Prevents lateral movement between precast components, adding stability.
Sealant Deck Joint: Seals deck joints to prevent water ingress and allow for thermal expansion.
Thrie Beam Connection Bracket: Connects the thrie beam to the main structure, securing the
barrier in place.
Sill Beam and Wingwall Projected Reinforcement for In-situ Concrete Stitch Pour: Provides
additional reinforcement and load distribution to the bridge abutments.
Precast Reinforced Concrete Driven Pile: Foundation element that transfers the bridge load to the
ground, ensuring stability.
Abutment Curtain Wall: Serves as a retaining wall at the bridge ends, supporting lateral loads.
Precast Concrete Deck Module: Forms the bridge deck, providing the primary platform for
vehicular traffic.
Module Holding Down Bracket: Secures precast modules to prevent displacement.
Precast Reinforced Concrete Abutment Sill Beam: Acts as a base for the abutment, distributing
loads to the foundation.
Low-Performance Level Steel Traffic Barrier Railing: Provides vehicle containment and safety,
aligned with the bridge’s low-performance barrier requirements.
Each of these components works together to create a safe, efficient, and durable bridge structure that meets
local design requirements and minimizes environmental impact. The modular design approach allows for
streamlined assembly, enhances quality control, and ensures compliance with local council guidelines.
_____________________________________________________________________________________
Question 4: Step-by-Step Process for the Design and Construction of a Modular Bridge with Assumed
Analysis
Designing and constructing a modular bridge involves several critical steps, from initial planning to final
certification. The following details each phase, incorporating an assumed analysis based on the site’s Class
S soil classification.
Site Analysis and Soil Classification: Begin by conducting a thorough site investigation. Assume
a Class S soil type, which consists of slightly reactive clay with minimal ground movement from
moisture changes. This soil type allows for a stable foundation but requires design considerations
for slight seasonal moisture variations. The investigation also gathers data on the water table,
environmental factors, and load-bearing capacity.
Regulatory Compliance: Ensure the design aligns with local council guidelines, state regulations,
and Work Health and Safety (WHS) standards. Compliance is crucial to address environmental
impact, load requirements, and safety regulations specific to bridge construction.
2. Structural Analysis
Load Analysis: Given the assumed soil classification, the design must account for SM1600 loading
conditions to support light vehicle traffic. Analyze and incorporate assumptions on load-bearing
requirements and potential seasonal moisture shifts affecting the soil, which could result in minimal
ground movement.
Geotechnical Analysis: Assume minor soil displacement due to moisture variation; design
foundations and joints to allow for slight expansion and contraction. Ensure that abutments, decks,
and other critical components are resistant to minor ground movements.
Material Assumptions: Select precast concrete as the primary material for its durability and
suitability for modular systems. Ensure each component meets required safety factors, particularly
at joints and load-bearing connections, to handle expected load stresses.
3. Design Development
Bridge Type Selection: Opt for a modular bridge structure that leverages precast components,
minimizing on-site work and disruption to the surrounding area.
Component Detailing: Develop scaled, detailed drawings (1:10) for each modular component,
including abutments, piers, deck modules, and barriers. Each drawing should reflect compliance
with Class S soil standards, ensuring components are designed to handle slight ground
movements.
Barrier and Load Requirements: The bridge will include low-performance barriers suited for light
traffic. Design these barriers with adequate strength to manage SM1600 loads while considering
any potential effects of ground movement due to moisture.
Review and Certification: Submit the final design for certification, ensuring it meets all regulatory
standards for soil stability, load-bearing, and durability.
4. Preconstruction Preparation
5. Foundation Construction
Piling and Foundation Setup: Install driven concrete piles to provide a stable foundation, taking
into account the assumed minor soil movement from moisture variations. Reinforce piles to handle
slight horizontal shifts without compromising structural integrity.
Abutment Installation: Construct reinforced concrete abutments using precast sill beams, ensuring
they are properly secured to resist minor ground movement. These will serve as stable endpoints
for the deck modules.
Curtain Walls: Build curtain walls for each abutment to retain soil and prevent lateral movement
that might occur due to slight seasonal soil shifts.
6. Superstructure Assembly
Deck Module Placement: Sequentially position precast deck modules on the foundation, ensuring
proper alignment and secure fastening. Modules are designed to accommodate slight movement,
maintaining stability even with Class S soil conditions.
Component Connections: Use in-situ concrete closure strips, dowels, and grout to connect
modules, allowing for flexibility and movement while maintaining load-bearing integrity.
Sealing and Joints: Apply flexible sealant at deck joints to prevent moisture ingress and
accommodate minor thermal expansion and contraction due to soil movement. Shear key plinths
are also used to secure the deck and prevent lateral shifts.
Traffic Barrier Installation: Install modular traffic barriers on each side of the bridge, reinforced to
handle minor ground movement without compromising safety.
Safety Inspections: Conduct safety checks for barrier stability, alignment, and adherence to
council and safety standards.
8. Final Finishes and Quality Control
Surface Finishing: Complete surface treatments to improve slip resistance and protect against
environmental wear.
Quality Control Checks: Perform final checks on all joints, barriers, and connections to confirm
compliance with load-bearing and Class S soil standards.
Environmental Cleanup: Dismantle temporary environmental controls and restore surrounding
land to its pre-construction state.
Certification: Obtain final approval and certification from relevant local authorities, confirming the
bridge’s compliance with all regulations, including stability under Class S soil conditions.
Handover: Officially transfer control of the bridge to local authorities for public use.
Post-Construction Monitoring: Set up a monitoring schedule to observe the bridge’s performance,
with attention to any minor shifts in soil conditions over time.
_______________________________________________________________________________________
Example:
Use the template provided to complete your design review, including feedback from stakeholders, council authority,
experts or colleagues.
Resp
Aspect onse
Close
(e.g. D- Revie Respo by
Design Respo out
Ite Review Design, Sheet/S w nse (Disci Sta
Date Component/D nse (initia
m er(s) C- ection com and pline tus
iscipline date ls &
initials CADD/D ment action and
date)
rafting) initial
s)
Example:
To be
comple
ted by
Drafting To be anothe Super
20/01/ 27/01/2 01/02/
1. D Design N/A compl r visor - 0
2023 RL 023 2023
solution eted person JC
in a
discipli
ne
2.
3.
Student ID No:
Final Completion
Date:
Does the candidate meet the following criteria
Did the student locate and apply relevant legislation, documentation, policies
Yes No
and procedures.
Did the student implement the requirements, procedures and techniques for
Yes No
the safe and effective completion of the activity.
3. Did the student use the equipment effectively and appropriately. Yes No
plans Yes No
drawings Yes No
specifications Yes No
Did the student communicate clearly and concisely with others to receive and
Yes No
clarify work instructions.
Did the student select and apply appropriate construction techniques. Yes No
Did the student provide clarification and advice in the design process. Yes No
Did the student comply with written and verbal reporting requirements and
Yes No
procedures.
Did the student ensure the geotechnical design was compliant. Yes No
Did the student apply the given design plans and develop a geotechnical
Yes No
design of the foundation.
Did the student seek feedback that contributed to the final design including
Yes No
recommended changes to the design for continuous improvement.
Did the student obtain design approval that satisfied all requirements and
Yes No
legislation.
Did the student submit an application for the development of the geotechnical
Yes No
design.
Did the student submit a planning permit and contribute to the validation of
Yes No
the design.
Areas Yes No
Volumes Yes No
Densities Yes No
Percentages Yes No
Grades Yes No
Did the student submit all the work for the activity including relevant notes
Yes No
such as calculations, sketches and photos.
Section of the bridge for each solution (i.e. three) in Scale 1:10 or 1:20 Yes No
Did the student obtain, read, interpret, clarify and confirm work requirements. Yes No
Did the student Obtain, interpret, clarify and confirm work requirements Yes No
Did the student Access, interpret and apply documentation required for
detailed civil concrete structures design and confirm work activity is Yes No
compliant
Did the student Prepare design plan according to resourcing and design
Yes No
requirements
Did the student Obtain, interpret and analyse required data and identify
Yes No
design options for civil concrete structures according to job requirements
Did the student Interpret and analyse design options for civil concrete
Yes No
structures and recommend design option according to job requirements
Did the student Develop and complete detailed design of civil concrete
Yes No
structures according to job requirements
Did the student Prepare cost estimate for implementing design of civil
Yes No
concrete structures
Did the student Gain design approval from required authorities Yes No
Did the student Confirm design records are filed according to workplace
Yes No
requirements
Did the student Complete design cost and reporting requirements and deliver
Yes No
to required stakeholders
Did the student Participate in performance review of design process
Yes No
according to workplace requirements
Did the student Review client feedback and contribute to design verification
Yes No
according to workplace requirements
Did the student Close out systems according to workplace requirements Yes No
Did the student evaluate design options for civil concrete structures Yes No
loads Yes No
stresses Yes No
areas Yes No
volumes Yes No
mass Yes No
Was the design plan prepared with the best available resources. Yes No
Did the student identify and confirm the requirements and information for the
Yes No
geotechnical works project.
Did the student interpret and analyse data and do the following:
Did the student work with others to prepare detailed designs of civil concrete structures in a way that
meets required outcomes, including:
Did the student interpret and analyse data to recommend options. Yes No
Did the student complete the activity in the allotted time and submit
Yes No
drawings, calculations and completed field sheet
Comments
Student Name
Student Declaration: I declare that I have been
assessed in this unit, and I have been advised of my Student Signature
result. I also am aware of my appeal rights.
Date
Assessor Name
Assessor Declaration: I declare that I have conducted
a fair, valid, reliable, and flexible assessment with this Assessor Signature
student, and I have provided appropriate feedback
Date