新建文件夹Electrical Scope of Work Progress for NOCB -11-Dec-2024
新建文件夹Electrical Scope of Work Progress for NOCB -11-Dec-2024
新建文件夹Electrical Scope of Work Progress for NOCB -11-Dec-2024
A- Engineering
No Describtion
A1 DESIGN BASIS SUBMITTION AND APPROVAL
A2
SINGLE LINE DIAGRAM SUBMITTION AND APPROVAL
SINGLE LINE DIAGRAM FOR AC UPS SUBMITTION AND
A3 APPROVAL
ELECTRICAL EQUIPMENT LAYOUT SUBMITTIONAND
A4 APPROVAL
POWER CABLE LAYOUT FOR NOCB SUBMITTION AND
A5 APPROVAL
EARTHING LAYOUT FOR NOCB SUBMITTION AND
A6 APPROVAL
TYPICAL INSTALLATION DETAILS-CABLING
A7 SUBMITTIONAND APPROVAL
TYPICAL INSTALLATION DETAILS-LIGHTING SUBMITTION
A8
AND APPROVAL
D1
CONDUITS INSTALLATION
D2 SWITCHES AND SOCKETS INSTALLATION
D3 WIRING WORKS
D4 LIGHTING INSTALLATION
D5 CABLING SYSTEM WORKS
D6 MAIN INDOOR DISTRIBUTION BOARD INSTALLATION
D7 LIGHTING DISTRIBUTION BOARDS INSTALLATION
D8 EARTHING NETWORK WORKS
F- Pre-COMMISSIONING & COMMISSIONING
No Describtion
F1 COMMISSIONING
F2 PUNCH LIST CLOSE-OUT
F3 SUBMISSION OF AS-BUILT DRAWING
F4 FINAL DOCUMENTATION AND HANDOVER DOSSIER
F5 DEMOBILIZATION
F6
F7
Electrical Scope of Work Progress for NOCB project
01-Mar-2024 08-Mar-2024
NOCB-NOC-MTC-EA-4012-0002 ~ NOCB-NOC-MTC-EA-4012-0003
06-Mar-2024 12-Mar-2024
NOCB-NOC-MTC-EA-4012-0004
04-Mar-2024 13-Mar-2024
NOCB-NOC-MTC-EA-4012-0005 ~ NOCB-NOC-MTC-EA-4012-0012
05-Mar-2024 12-Mar-2024
08-Mar-2024 14-Mar-2024
NOCB-NOC-MTC-EA-4012-0015, NOCB-NOC-MTC-EA-4012-0016
06-Mar-2024 12-Mar-2024
NOCB-NOC-MTC-EA-3328-0001
08-Mar-2024 14-Mar-2024
NOCB-NOC-MTC-EA-3328-0003
11-Mar-2024 17-Mar-2024
NOCB-NOC-MTC-EA-3328-0005
15-Mar-2024 22-Mar-2024
18-Mar-2024 25-Mar-2024
20-Mar-2024 27-Mar-2024
15-Mar-2024 22-Mar-2024
11-Mar-2024 18-Mar-2024
21-Mar-2024 27-Mar-2024
21-Mar-2024 27-Mar-2024
13-Mar-2024 21-Mar-2024
NOCB-NOC-MTC-EA-1380-0002
13-Mar-2024 20-Mar-2024
26-May-2025 20-May-2025
23-May-2025 25-May-2025
30-Jan-2025 15-May-2025
26-Oct-2024 13-May-2025
02-Jun-2025 01-Jul-2025
02-Jul-2025 31-Jul-2025
01-Aug-2025 30-Aug-2025
26-Sep-2025 25-Oct-2025
18-May-2025 21-Jun-2025
28-Aug-2025 16-Sep-2025
28-Aug-2025 20-Sep-2025
18-May-2025 11-Jun-2025
Status Notes
Pending Not submitted yet
AFC Approved
AFC Approved
AFC Approved
AFC Approved
AFC Approved
AFC Approved
AFC Approved
AFC Approved
Status Notes
complete The materials were received ahead of schedule, and work commenced prior to the specified start date.
Not Started
Not Started
Not Started
Status Notes
On-Going The materials were received ahead of schedule, and work commenced prior to the specified start date.
Not Started
Not Started
Not Started
Not Started
Not Started
Not Started
Not Started
Status Notes
Not Started
Not Started
Not Started
Not Started
Not Started