Project Management Survival and Success
Project Management Survival and Success
©2018 by The Fairmont Press, Inc. All rights reserved. No part of this publication may
be reproduced or transmitted in any form or by any means, electronic or mechanical,
including photocopy, recording, or any information storage and retrieval system, without
permission in writing from the publisher.
While every effort is made to provide dependable information, the publisher, authors, and
editors cannot be held responsible for any errors or omissions.
The views expressed herein do not necessarily reflect those of the publisher.
Dedication
This book is dedicated to all the people I’ve worked with
and learned from, on and about projects, and it is my
way of paying it forward to the next generation of project
managers.
v
Table of Contents
Foreword. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi
Preface. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xiii
Chapter 2
Taking on the Challenge. . . . . . . . . . . . . . . . . . . . . . . . 17
The Construction Decision . . . . . . . . . . . . . . . . . . . 18
Key Considerations . . . . . . . . . . . . . . . . . . . . . . . 19
The Planning Process . . . . . . . . . . . . . . . . . . . . . . 23
Administering the Work. . . . . . . . . . . . . . . . . . . . . 26
Salvage Operations. . . . . . . . . . . . . . . . . . . . . . . . 27
Working with Contractors. . . . . . . . . . . . . . . . . . . . 28
Getting What You Pay For . . . . . . . . . . . . . . . . . . . 29
Chapter 3
Getting to Know Project Management . . . . . . . . . . . . . . . . 31
What is Project Management?. . . . . . . . . . . . . . . . . . 32
Types of Projects. . . . . . . . . . . . . . . . . . . . . . . . . 34
A Project’s Principals. . . . . . . . . . . . . . . . . . . . . . . 35
Possible Project Outcomes. . . . . . . . . . . . . . . . . . . . 37
Project Management Pitfalls. . . . . . . . . . . . . . . . . . . 39
The Information Super-Highway . . . . . . . . . . . . . . . . 41
vii
Project Management Terminology. . . . . . . . . . . . . . . . 43
Chapter 4
The Project Toolbox . . . . . . . . . . . . . . . . . . . . . . . . 47
Comparing Soft and Hard Skills . . . . . . . . . . . . . . . . 47
Business Productivity Software. . . . . . . . . . . . . . . . . . 48
Forms and Templates . . . . . . . . . . . . . . . . . . . . . . 50
Project Management Plans. . . . . . . . . . . . . . . . . . . . 53
Action Logs and Registers. . . . . . . . . . . . . . . . . . . . 64
Other Tools and Techniques. . . . . . . . . . . . . . . . . . . 67
Chapter 6
Effecting Project Communications. . . . . . . . . . . . . . . . . . . 85
Channels of Communication . . . . . . . . . . . . . . . . . . 86
Creating a Management Plan . . . . . . . . . . . . . . . . . . 88
Talking It Over (Meetings). . . . . . . . . . . . . . . . . . . . 90
Telling It Like It Is (Reports) . . . . . . . . . . . . . . . . . . 93
The Project File Cabinet (Records). . . . . . . . . . . . . . . . 94
Chapter 7
Dealing with the Stakeholders . . . . . . . . . . . . . . . . . . . . . 99
Understanding and Identifying Project Stakeholders . . . . . . 100
Planning to Manage the Stakeholders. . . . . . . . . . . . . 103
Managing the Engagement of the Stakeholders. . . . . . . . 104
Monitoring and Controlling Project Stakeholders. . . . . . . 108
Chapter 8
Issues, Conflict, Problems and Risks. . . . . . . . . . . . . . . . . 111
Managing Project Issues. . . . . . . . . . . . . . . . . . . . . 112
viii
Managing Project Conflicts. . . . . . . . . . . . . . . . . . . 116
Managing Project Problems . . . . . . . . . . . . . . . . . . . 119
Managing Project Risks . . . . . . . . . . . . . . . . . . . . . 121
Common Sense Troubleshooting . . . . . . . . . . . . . . . . 123
Chapter 10
Understanding the Framework. . . . . . . . . . . . . . . . . . . . 143
Exploring the Guide’s Anatomy. . . . . . . . . . . . . . . . 143
The Evolution of the Guide. . . . . . . . . . . . . . . . . . 147
Extensions to the PMBOK Guide. . . . . . . . . . . . . . . 150
Deriving the Documents . . . . . . . . . . . . . . . . . . . . 155
Managing Projects with the PMBOK Guide . . . . . . . . . . 161
Chapter 11
Experience is the Best Teacher. . . . . . . . . . . . . . . . . . . . 163
Installation of Equipment. . . . . . . . . . . . . . . . . . . 164
Software Implementation Programs . . . . . . . . . . . . . . 166
Organizational Facility and Program Management . . . . . . . 168
Commercial Construction Project(s). . . . . . . . . . . . . . 171
Government Contract Work. . . . . . . . . . . . . . . . . . 175
Chapter 12
Project Management Essentials. . . . . . . . . . . . . . . . . . . . 181
Lessons Learned . . . . . . . . . . . . . . . . . . . . . . . . 181
The Project Charter . . . . . . . . . . . . . . . . . . . . . . 182
The Project Management Plan (PMP). . . . . . . . . . . . . 184
The Work Breakdown Structure. . . . . . . . . . . . . . . . 186
The Gantt Chart. . . . . . . . . . . . . . . . . . . . . . . . 191
ix
Appendix
The Project Office. . . . . . . . . . . . . . . . . . . . . . . . . . . 199
Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . 199
PMO Implementation Strategies. . . . . . . . . . . . . . . . 204
PMO Maturity Levels. . . . . . . . . . . . . . . . . . . . . 204
PMO Charter . . . . . . . . . . . . . . . . . . . . . . . . . 206
PMO Phases of Development. . . . . . . . . . . . . . . . . 206
PM Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209
Bibliography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 229
Index. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 231
x
Foreword
xiii
and involvement in the profession through referenced examples
of actual performed project work. Though the focus of the work
deals with the evolution of the incidental project manager (from
novice to competent), their fellow project stakeholders (sponsors,
customers, team members, et al.) can benefit from the instruction
and advice offered herein as well.
xiv
Part I — The Novice
Chapter 1
Welcome to My World
Then I listed the things that the rear lot had that the front lot
did not:
• A cardboard box compactor
• A trash dumpster
• The loading dock
• A cage full of medical gas cylinders
Did I say “a little bit more to it?” Were there standards for
all of that? Were there construction rules and regulations? Were
there municipal (zoning) codes and statutes to contend with?
How could I provide for the functioning of the loading dock,
Welcome to My World 7
Parking Geometrics
There are a wide range of automobiles on the road from the
“minis” and “micros,” to light trucks and sport utility vehicles,
to conversion vans and multi-passenger pick-up trucks, and they
can vary by region. At the hospital, parking spaces served five
groups of users: patients, visitors, physicians, vendors and staff.
As before mentioned, the first three would be utilizing the front
lot, and the latter two would be relegated to the rear lot.
Circulation
One-way drive aisles provide better traffic flow than two-
way drive aisles because it is easier for users to enter and exit
parking spaces, and there is less circulation conflict. Two-way
traffic offers wider drive aisles, making for a safer environment
for pedestrians and passing vehicles. [See Figure 1-2.] Generally
speaking, it is preferred not to combine one-way and two-way
traffic flows within a single facility, but due to the problems con-
fronting us in the rear lot, we had little choice.
Lighting
For the sake of standardization, the same type of outdoor
lighting used in the front lot will be installed in the rear lot. A
contract will need to be entered into with the current company
that maintains and originally installed those lights. The light
standards (and illumination requirements) will comply with
the dictates of the National Electrical Code and other applicable
codes for exterior lighting. Light standards will not be located
inside the parking field, but will be located outside of the park-
ing lot perimeter and inside the lot’s island curbs.
Handicap Parking
Author’s note: Although the hospital (as a consequence of
the work they performed) did provide what were then referred
to as “handicap” parking spaces, it was operating under the
dictates of The Rehabilitation Act of 1973, built off of the Civil
Rights Act of 1964 and The Architectural Barriers Act (ABA,
1968). The Equal Opportunity for Individuals with Disabilities
Act (better known as the Americans with Disabilities Act, or
ADA) was signed into law and became effective on July 26, 1990
as 42 U.S.C., Chapter 136; Section 12101. The Rehabilitation Act
of 1973 prohibited discrimination on the basis of disability in
programs conducted by federal agencies and those receiving
federal financial assistance. ABA and the Rehabilitation Act es-
sentially extended certain civil rights to people with disabilities.
Like its predecessors, ADA is a civil rights law. And while not
specific to transportation, it is difficult to find a more far-reach-
ing transportation policy for the disabled within or outside of
the U.S. Unlike its predecessors, ADA applicability is not tied to
whether federal funding was involved in the construction of the
facility; hence, it applies broadly to any facility open to public
use.
14 Project Management: Survival and Success
Signage
All signage will be homogenous with existing facility sig-
nage and marking requirements.
LESSONS LEARNED
17
18 Project Management: Survival and Success
The trouble with project work is that no two jobs are ever
alike. Like ulcers, they come in all shapes and sizes; some you
must give serious consideration to while others are easily rem-
edied. By its nature, most project work is a one-shot deal that
requires staffing only until the work has been completed. There
are times when you’ll have projects scheduled back-to-back for
months on end, then have slack periods upwards of a year where
no major work needs to be performed. How should you staff your
department to accommodate these inconsistencies? Do you hire
full-time personnel in anticipation of the work? What happens
when the project is canceled? Do you hire a full-time crew on a
temporary basis? Good people are hard to come by unless you
offer them more secure employment. Do you use contractors?
Depending on the scope of the project this may become necessary,
but bear in mind you’ll pay a premium for the luxury of hiring
outside help. Can you use existing staff personnel? The truth is,
your staff should be capable of handling all but the most involved
projects confronting your department.
To a lesser degree, the knowledge needed for maintain-
ing your building and systems is essentially the same as the
knowledge required to construct and install them. Constructing
a building may entail the need for employing a contractor, but
renovations and small additions can be tackled in-house. The in-
stallation of a complex system may warrant the hiring of outside
help, but the modification of that system may be accomplishable
by your personnel. When department personnel double as con-
struction crews you save on the cost of premium wages paid to
outside vendors, you avoid the hiring and lay-off process, and
your people take pride in accomplishing the work themselves.
The choice to use them in this way is yours, barring any restric-
tions that may be imposed upon you by a bargaining agreement.
Just remember to change their job descriptions before attempting
to change their jobs.
Whatever triggers your need to doff your maintenance mantle
Taking on the Challenge 19
and don your contractor’s cap, rest assured you’ll have more ques-
tions than answers from the start. Initially, determinations must
be made regarding permitting, drawing approvals, inspection
requirements and whether or not to employ a registered architect
or professional engineer. Subsequently, a decision must be made
as to the extent of your operations involvement in the project.
Concurrently, a multitude of inquiries must be fielded and laid to
rest, from demolition through final acceptance. Such speculations
can be pure joy or torture depending on how you approach them.
If you have anywhere near the threshold for pain that I do, it will
behoove you to keep things simple. One way to do this is by con-
structing a decision tree to help you think through the process. For
instance, after establishing the scope and magnitude of the work,
categorize the project as either a (type 1) rudimentary renovation
that requires neither formal architectural drawings nor engineer-
ing to complete, such as a simple office relocation; a more complex
scheme (type 2) which calls for limited A and E assistance, such
as the construction of a small outbuilding to house your grounds
keeping equipment; or a more comprehensive design (type 3) that
mandates the need for extensive evaluations to be performed by
experts outside of your organization, such as the creation of a new
service wing which will tap into your building’s existing utilities.
At this point, a decision can be made as to what extent you might
use your people on the project. You can then proceed through the
next step to decide on which type of contract to let; i.e., design-bid-
build, design/build, construction management, owner/builder
and so on. (See Figure 2-1.)
KEY CONSIDERATIONS
Concurrent Occupancy
What extraordinary measures need to be taken to assure op-
erational continuity during construction?
Extraordinary Measures
Will any special equipment need to be employed such as
hiring of a crane to set roof-mounted units?
Materials Handling
Have you allocated storage space for building materials and
Taking on the Challenge 21
Conceptualization
Has the project been thought through to the end?
Temporary Services
Were arrangements made to assure against sudden acciden-
tal shutdowns?
Standardization
Standardize, standardize, standardize!
Functional Adjacencies
Will the new operation be compatible with the operation abut-
ting it?
22
Figure 2-2. Construction Project Management: Survival and Success
Cost Spreadsheet
Taking on the Challenge 23
Project Management
Do you have the time to devote to the project or should you
supplement your capabilities?
Interior Design
Is there an approval system in place to forego the displea-
sure syndrome?
Meetings/Minutes
Are timely meetings held between the project principles and
accurate minutes recorded?
Attic Shock
Have sufficient overages been built into the materials bud-
get to assure a maintenance stock?
Cost Overruns
Are expenditures strictly monitored, controlled and regular-
ly reported to upper management? (See Figure 2-2.)
and your personnel are the players. As usual, the owner is rele-
gated to picking up the tab. If a project can be equated to a game,
then all the projects completed in a year constitute a season. How
well you conceive and implement your individual game plans
determines whether you end each season as a contender or as an
also ran. Just as each opposing team poses a different challenge
causing you to alter your game plan, each project presents special
problems, which cause you to modify your work plan for com-
pleting it. Whereas all teams have basic plans, only those whose
plans are flexible enough to meet those challenges will wax victo-
rious.
SALVAGE OPERATIONS
Getting to Know
Project Management
TYPES OF PROJECTS
A PROJECT’S PRINCIPALS
Back in the day, before we had access to the internet, and or-
ganized project management was still in its infancy, there wasn’t
much information available on the subject; nor was it easily acces-
sible. That all changed in 1991 with the advent of the “World Wide
Web,” that went live on August 6th of that year. At the time, most
people (outside of the military) didn’t even know what the internet
was. Though the internet had been around for a number of years
(with its own function and purpose), the “web” provided a means
of accessing data online in the form of websites and hyperlinks.
It has popularized the internet among the public, and served to
develop the vast trove of information that we can now access on
a daily basis. Now there really is a whole world out there that de-
votes itself to the understanding and advancement of the project
management profession. Some sites require membership; some
don’t. Some of them charge a fee, and some are free.
There are a multitude of organizations, groups and individ-
uals so dedicated. Sites can be found for certifying schools (like
Villanova’s Masters in Applied Project Management), scores of
courses for certificate exam preparation (like Cheetah Learning’s
PMP exam prep course), case studies (like at PM Solutions) and
industry reports (like the Standish Group 2015 Chaos Report).
But, if I were limited to one particular organization from which to
get all of my materials, information and instruction, it would be
the Project Management Institute (PMI), for all the reasons cited
earlier in this text.
According to Wikipedia, PMI provides services including
the development of standards, research, education, publication,
42 Project Management: Survival and Success
Foundational Standards
• The Standard for Program Management—Third Edition
(2013). Recognized by ANSI as American National Standard
BSR/PMI 08-002-2013.
• The Standard for Portfolio Management—Third Edition
(2013). Recognized by ANSI as American National Standard
BSR/PMI 08-003-2013.
• Organizational Project Management Maturity Model
(OPM3) | Knowledge Foundation—Second Edition (2008).
Recognized by ANSI as ANSI/PMI 08-004-2008.
Action Plan—A plan that describes what and when things need
to be completed.
Activity—The work or effort needed to achieve a result.
Assumptions—Factors that are considered to be true, real, or
certain.
44 Project Management: Survival and Success
project’s objectives.
Risk Mitigation—Revising the project’s triple constraints in or-
der to reduce uncertainty.
Schedule—The planned dates for performing activities and for
meeting deliverables.
Scope—The sum of the products and services to be provided as
a project.
Scope Creep—The addition of new requirements to the original
product specifications.
Sponsor—The authority that provides the financial resources, for
the project.
Stakeholder—Individuals and organizations who affect or are
affected by the project.
Task—Well defined components of project work. Work package.
Team Member—The individuals responsible for some aspect of
the project’s activities.
Work Package—A deliverable at the lowest level of the work
breakdown structure.
Chapter 4
Initiating Forms
Initiating Process Group
Project Charter
Stakeholder Register
Stakeholder Analysis Matrix
Planning Forms
Requirements Documentation
Project Scope Statement
Assumption and Constraint Log
Milestone List
Cost Estimating Worksheet
Responsibility Assignment Matrix
Roles and Responsibilities
Executing Forms
Team Member Status Report
Change Request
Change Log
Decision Log
Team Directory
Issue Log
Closing Forms
Procurement Audit
Contract Close-Out
Project or Phase Close-Out
Lessons Learned
Author’s note: For those of you who are not yet members of
the Project Management Institute, there are a vast number of free
on-line resources available to the general public. One of the better
ones that houses a large (excellent) selection of free project man-
agement templates is a website titled PROJECT MANAGEMENT
DOCS that is easily accessed through Google.
At some point in your life you’ve probably heard the old ad-
age “If you fail to plan, you plan to fail.” Nowhere does this state-
Process Example:
• Any stakeholder can identify the need for a change by sub-
mitting a change request form to the project manager.
• The project manager logs the request into the change request
register.
sponsor and project team playing key roles for establishing and ap-
proving documentation using quality checklists and work perfor-
mance measurements. A project’s scope is built through a five-step
process wherein the project’s objective requirements are defined,
detailed product descriptions are developed, a work breakdown
structure (WBS) of work packages is created, the scope is accepted
by the sponsor, and the process is monitored.
The project charter is the basis from which the project re-
quirements are defined and clarified, enabling their measurement
once the project begins. The product description establishes the
project framework and includes all of its assumptions, con-
straints and deliverables. The WBS simplifies the scheduling,
costing, monitoring, and control of the project, breaking the de-
liverables into smaller (more manageable) work packages. In the
acceptance phase, the scope is verified and baselined before being
accepted. Continuous monitoring of the scope allows for control
of any variance from the established baseline (scope creep). Scope
changes may be initiated by the project manager or stakeholders
or any member of the project team. Change requests are submit-
ted to the project manager to provide estimates and impacts to
project schedules and costs. After evaluation, the PM submits
the scope change request to the change control board and project
sponsor for acceptance. When properly implemented, an SMP
helps manage the time, cost and quality. Well executed scope
management ensures that all (and only) the required work neces-
sary for completing the project is included in the project.
Assumptions Log
An assumption is something taken for granted—a suppo-
sition or a belief (based on your knowledge, experience or the
information at hand) of what you assume to be true for the fu-
ture. Assumptions are important considerations of any project.
In project work, they are anticipated events or circumstances
that are expected to happen during a project’s life cycle, which
The Project Toolbox 65
Risk Register
All projects include uncertainty over what will happen
during their life-cycle, and every assumption reduces the chanc-
es for a project’s success. It is the responsibility of the project
manager to ensure a project’s success by managing the risks
that are imposed on it. Risk registers are created early in the
project and are used to record identified project risks, their sta-
tus and history. They evolve over the project life-cycle as risks
are reviewed, revised, and updated—as the project progresses.
The registers enable project teams to take action on risks before
they have an opportunity to become “issues” that can have a
negative impact on the project. A best practice is to focus on
the causes of the risks, determine their probable impacts and
create a standardize process for dealing with them. A simple
analysis of the impacts can help to classify risks and prioritize
the actions needed for their mitigation. It is important to note
that when deviations occur in the plan, risks become issues that
must be addressed to keep the project on track.
Issue Log
Issues are basically any conditions that reduce the team’s
ability to execute the project plan. They are easily identified
because they cause obvious schedule slippage and extra work.
The issue log is where problems are recorded that were not ac-
66 Project Management: Survival and Success
counted for in the original plan and that threaten to delay the
project, push it off budget or affect its scope (triple constraint).
Project managers use issue logs to capture and monitor informa-
tion on a formally managed variety of problems, inconsistencies
or conflicts including change requests, performance reductions,
potential new risks, etc. A detailed log will provide clarity and a
point of future reference for actions, comments and resolutions
of issues.
The issues log records details of all the issues identified at
the beginning and during the life of the project, the action taken
to address each issue and the subsequent results. The informa-
tion it contains includes issue descriptions with individual ID
numbers, who raised the issue, the person or group responsible
for its resolution, an open/close status, and how the issue was
resolved.
Change Register
As previously stated in the change management plan, most
projects undergo changes from their originally intended config-
uration. Change management is one area of project management
which will cause serious problems if it is not carefully managed.
Without a deliberate change management effort, changes in de-
sign, scope, deliverables, and various other changes can easily
cause a project to fail. Failing to track changes and consider their
impact before they can be approved and enacted can cause critical
mistakes to be made that can result in poor project performance.
The register is a document wherein all notable changes made to
a project are recorded. Logging changes into a register helps to
keep processes organized and projects on track.
The change register is used by the project team to log
and track change requests throughout the life of the project. It
should be updated as new change requests are submitted or as
existing change requests are approved or rejected. The informa-
tion placed in the register will come directly from the change
request form. The register should be updated as needed and all
changes clearly communicated to all stakeholders.
The Project Toolbox 67
Submittal Log
Submittals refer to the written or physical information
provided by a responsible contractor of documents (such as
schedules) and/or physical items (such as ceiling tile samples)
that contractually require the approval of stakeholders. Submit-
tals in construction management include matters such as shop
drawings and blueprints, material data and samples, cut sheets
on equipment, product manuals and test reports. The project
manager is responsible for creating the initial submittal schedule
which contains all of the required project submissions (including
specifications and due dates). As submittals are received from the
contractors or vendors, they are added to a submittal package for
review. That information is given to the design team for review
and approval of equipment, materials, etc., to ensure that the
information complies with the project drawings and specifica-
tions before they are fabricated and delivered to the project. Once
approved, the submittal is returned to the contractor, signifying
that the work (or fabrication) is approved for construction. The
submittal log will be where all specification requirements will be
cataloged, dates of performance identified and actions by respon-
sible parties summarized.
Figure 5-1. They languished 5 months in Tahiti, waiting for the breadfruit
trees to ripen!
71
72 Project Management: Survival and Success
needed for the project (in both level and amount). Choose people
who can get along with each other and work together as a team.
Communications
Nothing can sabotage a project’s successful undertaking
more than poor or inadequate communications. If the team isn’t
totally aware of the entire goings on, they will have no way of
dealing with project conditions or situations and will be unable
to affect its status. It is the PM’s responsibility to ensure that the
team is apprised of and kept up to date on all project activities,
team interactions, any potential conflicts and all approved chang-
es. Problems or delays in one area can cause havoc in others. To
avoid them, set a tone of cooperation and discourage competi-
tion. The subject of effective communications will be detailed
more thoroughly in Chapter 6.
You’ve probably surmised by now that team building is not
a singular endeavor, but rather an ongoing effort by the project
manager to constantly refashion the team throughout the lifecy-
cle of their project, which is crucial if the project is to succeed.
The PM needs to bring a complete set of soft skills to the job—
knowing what intensity needs to be applied for a given situation,
76 Project Management: Survival and Success
tance of their ideas. Here they set down the rules that they will
follow to work together and resolve their differences. The team
members also start to make significant progress on the project
as they begin working together more effectively. The PM’s role
is to foster good communications between the members and en-
sure that they maintain the project’s focus. At this point, the PM
should allow the team more independence and start depending
on them for some decision making.
In the norming stage the team will begin to work more effec-
tively as a team, becoming conscious of their existence as a cohe-
sive group and accepting the rules that they have established for
themselves. They respect each other’s opinions, see the value of
their differences and consistently work toward a common goal.
At this juncture, they become more trusting of one another and
work together more effectively. The team is highly motivated to
get the job done. They can make decisions and problem solve
quickly and effectively. The project manager ensures that the
team promptly resolves any internal issues and maintains their
single-minded purpose. The PM can become less engaged in the
team’s day-to-day decision making and problem solving as the
team becomes more seasoned.
In the performing stage, teams function at a very high level.
The focus is on reaching the goal as a group. Team members
work effectively as a group and do not need the oversight that is
required at the other stages. The members have gotten to know
each other, trust each other and rely on each other. The individual
members of the team act as one. Everyone is on the same page
and focused on reaching the project’s goals. Each depends on the
others to deliver the goods uniformly. They are a team in every
sense of the word and have less need for intervention by the proj-
ect manager. The PM’s job now is to act as a go-between and keep
the stakeholders abreast of the team’s performance.
In the adjourning stage, the team is dismembered and will be
joining other teams and moving on to other work. The members
have a feeling of loss about having to move on, going their sepa-
rate ways, and they will miss the interactions they shared during
Assembling the Project Team 79
Effecting
Project Communications
CHANNELS OF COMMUNICATION
can the PM discuss the project with them and get more specific
about its goals and deliverables.
Stakeholders can be internal or external to an organization.
Internal stakeholders are those directly affected by the project,
such as staff members. External stakeholders are interested par-
ties that are not a part of the business, such as vendors, suppliers
or lenders. They may exhibit high or low powers of authority
and can exert positive or negative influences on a project, its de-
liverables, and its team in satisfying their own agendas. Positive
stakeholders see the project’s beneficial side and aid the project
management team to successfully complete the project. Negative
stakeholders see the downside of the project and are less likely to
add to the project’s success.
As mentioned, stakeholders are typically the project spon-
sors, members of a project team, project managers, executives,
management personnel, the media, contractors, sub-contractors,
consultants, community and government agencies, banks, sup-
pliers, customers, clients, and/or end users of a project’s product
or service. Key stakeholders will have to be involved early on to
get their input for the project overview, goals and deliverables.
To identify stakeholders that you may not have recognized as
such or at first, you may want to ask known stakeholders of their
awareness of others who might have an interest in the project
and who haven’t already been identified. Leaving out an import-
ant stakeholder could have an adverse effect on the project. The
sooner all of the stakeholders are identified, the sooner you can
communicate with and involve them in the project activity. Effec-
tive communication between stakeholders ensures that everyone
is on the same page and that the project will continue to move
forward.
It’s important for the project manager to know the stake-
holders’ interests and understand their roles in the project and
the organization. They help decide on issues from the beginning,
during planning and at execution of the project. PMs should
establish and nurture good working relationships with them, to
learn about their business concerns and needs, fostering easier
102 Project Management: Survival and Success
Issues, Conflict,
Problems and Risks
Depending on how they are used, these four words can have
similar connotations. Look them up in a thesaurus, and the terms
may at times seem interchangeable. But in reality, at least from a
project management perspective, their meanings are very diver-
gent and quite specific. Never the less, if not properly managed,
any one of the four can spell “trouble” for a project. Their com-
monality comes from the fact that each of them can be found in
every project. Here’s my shot at delineating their differences:
you choose that tact and fail to follow up, the magnitude of the
conflict could be compounded.
Trial and error—trying possible solutions until you find the one
that works.
(SOP) and safety and security manuals. All of which boded well
for me, qualifying me to take on free-lance project work (still
without the ever having a certification).
On one such contract I managed several projects at a New
Jersey based facility which included, reworking of their data cen-
ter cooling, replacement of the central bulk oxygen tank, removal
of an underground oil storage tank (UST) and up-grade modifi-
cations to the fire suppression system. Eventually there came a
time when the projects became so large and diverse that it became
paramount that I find a way of working “smarter instead of hard-
er.” Sure, I learned a lot of shortcuts and tricks along the way, ex-
perienced a great deal of achievement, and gained an appreciable
amount of insight into many processes, but (if I was to move on
to bigger and better undertakings) it was time to buckle down
and attain the formal education I needed to become certified.
That called for me to find the definitive organization that could
provide me with all of the knowledge and resources I would need
to establish myself as an expert in the field and expand my career
horizons. I set my sights on that goal and learned everything I
could about adopting a methodology, choosing a professional
project management software program, determining best practic-
es, putting together a formal project plan and filling in any gaps I
had in my understanding of project management processes.
are carried out under certain constraints, the major ones being
schedule (time), cost (budget) and scope. That “triple constraint”
forms the basis for what project managers need to monitor and
control in every project. When managing small and simple proj-
ects, of limited scope and duration, the skills and tools they al-
ready possess and utilize in their everyday activities may suffice
to begin a project, execute it and bring it to a satisfactory close.
Examples might be: using spreadsheets to create a timeline, using
their accounting acumen to control costs, and writing all their
documents and reports using word processing software. Besides
those measureable constraints, project managers are confronted
with countless other success criteria, such as product quality,
meeting safety standards, achieving the project’s purpose and
providing sustainable reliability. As their projects become length-
ier and more complex, they will need to use more powerful
software applications which contain more features and possess a
higher level of sophistication. Software features may include, but
not be limited to:
• Budget management
• Calendar
• Collaboration
• Communication
• Cost control
• Departments and contacts
• Documentation
• Gantt charts
• Issue management
• IT project management
• Milestone tracking
• Percent-complete tracking
• Reporting
• Resource allocation
• Portfolio management
• Project planning
• Requirements management
134 Project Management: Survival and Success
• Resource management
• Scheduling
• Status tracking
• Task management
• Time and expense tracking
hasn’t been on the scene for that long, but during its short his-
tory its structure, application and methods used for managing
it, have grown by leaps and bounds. Many methodologies have
been developed and evolved to effectively manage the profusion
of different project types and complexities. There is no “one size
fits all” method for managing projects, and each approach has its
own strengths and weaknesses. A project management method-
ology should be chosen for its ability to best meet organizational
goals and values, address the risks involved, take into consider-
ation the needs of the stakeholders and deliver the best bang for
your buck. Although there are many more choices available, four
of the most popular today are Agile, critical path method (CPM),
PMI/PMBOK (though not everyone agrees that the guide is a
methodology), and Waterfall. Here is a little background on each
of them:
Watch out for scope creep from both minor (small chang-
es that accumulate over time) and major changes (totally new
functions or deliverables) being added to the project, which can
adversely impact your project, increasing its costs and extending
its completion date.
of the profession, and the guide was improved through the re-
moval of errors found in the prior edition. In the 3rd version, as
a consequence of PMI’s editorial committee review of thousands
of suggestions for improvements to the guide, they integrated
many of the recommendations and published an upgrade in 2004.
A more consistent and accessible 4th edition was published five
years after that, where a clear distinction was made between the
project documents and the project management plan. The 5th
edition, released in 2013, represents PMI’s latest update to the
project management body of knowledge, just short of the 6th
edition upgrade. The PMBOK® Guide 6th edition (published in
September of 2017) incorporates Agile (one of the fastest growing
methodologies) in its module, as well as the PMI Talent Trian-
gle (Leadership, Technical Project Management, Business and
Strategic Management) and includes some minor changes in the
process groups and processes.
Note: Earlier versions of the PMBOK Guide were recog-
nized as standards by the American National Standards Institute
(ANSI) which assigns standards in the United States (ANSI/PMI
99-001-2008) and the Institute of Electrical and Electronics Engi-
neers (IEEE 1490-2011).
Author’s note: Although the PMBOK Guide is not a step-
by-step manual for implementing projects, the information it
contains can augment a project manager’s understanding of the
entire accumulated project management body of knowledge, en-
abling them to choose and use an appropriate methodology.
The history of the Project Management Institute (PMI®)
began with its inception at its first meeting held in Atlanta, Geor-
gia, in 1969. The first credential issued by PMI was the Project
Management Professional (PMP), awarded in 1984 with the ad-
ministration of the first PMP® exams. In 1987, the “Project Man-
agement Body of Knowledge” was released (sections A through
H, 5-6 pages in each section). In August of 1994 a 64-page expo-
sure draft of the PMBOK® Guide was released that contained
eight knowledge areas. The exam consisted of 320 questions (40
from each of the eight knowledge areas), and the test taker was
Understanding the Framework 149
dem with the latest edition of the PMBOK® Guide. The current
edition follows the structure of its previous editions and keeps
the chapter structure of the parent guide, with preface, introduc-
tory chapters, knowledge areas, annexes, and appendixes. The
organization of the knowledge areas follows the process groups’
scheme of initiating, planning, executing, monitoring and con-
trolling, and closing. The first chapter establishes the framework
for the remainder of the document. Chapter 2 homes in on the
context, addressing specific topics such as types of projects, deliv-
ery methods, and organizational environmental factors. Chapter
3 begins by mirroring the same type of content as its equivalent in
the PMBOK® Guide, giving a brief introduction to the content of
each knowledge area before presenting some important trends in
the industry and advances in construction project management.
This section features topics such as building information model-
ing (BIM), integrated project delivery (IPD), global markets, and
ethics. In the knowledge areas, integration management includes
a topic on construction administration; cost management covers
escalation, inflation, and currency exchange; scope management
argues the need to establish clear limits; schedule management
highlights the linear scheduling method; resource management
addresses human resources, machinery, tools, equipment, and
materials; communications management explores document
control issues; risk management talks about insurance; quality
management speaks to non-conformance; procurement manage-
ment emphasizes the hierarchies of buyers and sellers; and stake-
holder management looks at the prominence of labor unions and
insurance providers. The back matter lists PMI’s references and
a glossary of construction terms and acronyms (complementary
to the ones featured in the PMBOK® Guide) that are used in the
extension.
INSTALLATION OF EQUIPMENT
Project(s) Title:
Installation of Diagnostic and Emergency Power Equipment
Summary Description:
Construction of concrete pads and installation of 480V ser-
vice entrances (Crouse-Hinds) electrical umbilical (with
weatherproof entryways)
Staging of trailer mounted CT (computer tomography) and
magnetic resonance imaging (MRI), scanners and litho-
tripters
Experience is the Best Teacher 165
My Position:
Project Manager
Associated Duties:
Solicited AEC (architect, engineering and construction)
firms
Prepared RFPs (requests for proposals) for the purchase of
equipment
Acquired and reviewed blueprints
Coordinated installations with appropriate department
heads
Oversaw construction activity
Preparation:
Explored contract types
Researched applicable codes
Studied equipment primers
Met with contractors and department heads
Documentation:
Activity cost estimates
Activity resources
Cost management plan
Issue log
Procurement documents
Project charter
166 Project Management: Survival and Success
Quality checklists
Schedule management plan
Scope statement
Learning Opportunities:
Study of high-voltage electricity
Study of diesel engines
Interactions with AEC personnel
Study of gauss units and fiberglass rebar (reinforcement
rods for insertion in concrete) for avoidance of magnetic
field exposure problems
Project Title(s):
Preventative Maintenance Program(s)
Summary Description:
Installation and implementation of multiple iterations of
Infor, Maximo, Panda Plus and Hems CMMS (computerized
maintenance management system) software programs, for
Experience is the Best Teacher 167
My Position(s):
Participant/Project Manager
Associated Duties:
Data collection from building equipment
Transfer of information from written records
Establishment of policies and procedures
Preparation:
Researched costs and features of available software
Queried companies regarding software maintenance poli-
cies
Included operator training in the purchase price
Put together an in-house conversion plan
Documentation:
Activity resources
Human resource management plan
Procurement document
Project communications
Project management plan
Project schedule
Work breakdown structure
Learning Opportunities:
Trained on the abilities and use of CMMS software
Increased my understanding of computer operations
Updated my knowledge of preventative maintenance
168 Project Management: Survival and Success
Project Title:
1. Internet Service Exchange (ISX) Build Outs—[DATA CEN-
TERS]
2. Facility Organization Infrastructure
Summary Description:
1. Complete the gutting of six existing structures (closed de-
partment stores and supermarket) and Greenfield construc-
tion of comprehensive physical plant infrastructures for
housing internet service providers. Author’s note: A Green-
field project is one that lacks constraints imposed by prior
work. The analogy is to that of construction on Greenfield
land where there is no need to work within the constraints
of existing buildings or infrastructures.
My Position(s):
East Coast Regional Facility Director/Construction Coordi-
nator
Experience is the Best Teacher 169
Preparation:
Separate kickoff meetings with the construction arm of the
organization and the West Coast Regional Director
Attendance at weekly construction progress meetings
Frequent visits to the intended worksites
Preliminary coordination with the electrical utility compa-
nies
Interviewed potential facility manager candidates for over-
sight of the data centers
Documentation:
Activity lists
Agreements
Change log
Communication management plan
Human resource management plan
Issue log
Project management plan
Quality checklists
Schedule management plan
Team performance assessments
Work breakdown structure
Learning opportunities:
Observational visits to existing data centers
Conferences with data center facility managers
Familiarization with the national BOCA (Building Officials
Code Administrators) and SBCCI (Southern Building Codes
Congress, Inc.) building codes
Familiarization with AIA (American Institute of Architec-
ture) standards
Experience is the Best Teacher 171
Project Title:
1. Women’s (OB/GYN) Pavilion
2. In-house Laboratory Expansion
My Position:
Project Manager
Summary Description:
1. Construction of a 30,000-square-foot women’s medical ser-
vices wing
2. Expansion of the existing medical laboratory
Associated Duties:
Reviewed and approved all drawings (partials/as-builts)
172 Project Management: Survival and Success
Preparation:
Solicited bid requests
Selected the A&E firms
Approved final contract award
Oversaw construction and approved project completion
Developed an in-house (high-end) construction capability
Documentation:
Agreements
Change, issue and risk logs
Experience is the Best Teacher 173
Learning Opportunities:
Familiarization with materials submittals
Study of RFIs (requests for information) intent and proce-
dure
Study of various types of construction contracts and the use
of subcontractors
Taking of detail and progress pictures
University courses on construction supervision
Project Title:
Medical Center Restoration
Summary Description:
Total gutting and restoration of a 230-bed hospital structure
My Position(s):
Interim vice-president/administrative liaison
Associated Duties:
Provided technical direction during the course of the project,
through the licensing, re-opening and accreditation of the
institution
174 Project Management: Survival and Success
Preparation:
Relied heavily on my past work and management experienc-
es
Met with all stakeholders of the project (including county
commissioners, hospital administration and trade union
reps)
Researched applicable regulatory requirements
Solicited bid requests
Selected the AEC (architectural, engineering and construc-
tion) firms
Approved final contract award
Oversaw construction and approved completion of the proj-
ect
Documentation:
Agreements
Change requests
Cost management plan
Project management plan (theirs)
Quality assurance plan (theirs)
Experience is the Best Teacher 175
Learning Opportunities:
Insight into county government and trade union processes,
politics and procedures
All the prior work (and many more projects that I left
unmentioned) paid dividends when I finally entered into the
government contract arena. Here I became familiar with the
government bidding process, and learned to work under IDIQ
(indefinite delivery-indefinite quantity), cost plus fixed fee and
fixed cost plus award fee contract delivery arrangements. Having
worked with POC’s (points of contact) from the DoD (Depart-
ment of Defense) and NASA (National Aeronautics and Space
Administration), I also became familiar with the Federal Regis-
ter; the CFR (Code of Federal Regulations); and the FAR (Federal
Acquisitions Regulations). The three government based projects
I’ve chosen to share are: a (second phase of an overall $83 million
project), plant improvement of a federal security facility and a
naval air station recapitulation program.
Project Title(s):
1. Phase two (2) of an $83 million Federal Institute power plant
expansion
2. Construction of a free-standing electrical power substation
building
Summary Description:
1. Close out of Phase I of the power plant expansion which
included the addition of five 5,000-ton centrifugal chillers,
176 Project Management: Survival and Success
My Position:
Senior project manager
Associated Duties:
Administered a construction management team consisting
of a project manager, cost estimator, scheduler, contract spe-
cialist, inspector and clerical personnel
Acted as liaison between the construction company and the
government project officer
Conducted bi-weekly project review meetings
Wrote and distributed progress reports
Performed quality assurance audits and site inspections
Prescribed the parameters to be utilized in the commission-
ing process
Attended witness-testing activities on completed installa-
tions
Completed re-negotiation activities for reconciliation of
budgets
Reviewed and approved (or denied) contractor pay requests,
change order requests and submittals
Preparation:
Researched the Federal Register, the CFR (Code of Federal
Regulations) and the FAR (Federal Acquisitions Regulations) sec-
tions, relevant to both project pieces
Experience is the Best Teacher 177
Documentation:
Utilized the vast majority of documents available
Learning Opportunities:
Masters level university courses in applied project manage-
ment
Extended studies of government contracting and construc-
tion management
Project Title:
Naval Air Station Recapitulation Plan
Summary Description:
Analysis of hangar and runway pavement capacities and condi-
tion
Suggested possible relocation of operations tower
Recapitalization plan for hangars, including assessment of exist-
ing building support systems and utilities
Capital improvements plan, including flight line ground elec-
tronics systems
My Position(s):
Subject matter expert/advisor
Associated Duties:
As a sub-contractor: provided modification and replacement
opinions on facility structures, pavements, electrical, me-
chanical and fire protection systems and utilities service
Determined environmental impacts
Assisted with preparation and submission of the required
DoD (Department of Defense) documents for acquiring Mil-
Con (military construction) funding
Preparation:
Met with the contractor and formulated a plan for initiating
the project
178 Project Management: Survival and Success
Documentation:
All of my work was performed within the constraints of the
contractor’s direction and management plan
Learning Opportunities:
Familiarity with the Defense Department’s means and meth-
ods
Insight into the layout of military bases
Project Title:
Central Plant Management Improvement Plan
Summary Description:
Oversight and evaluation of all utilities and physical plant
equipment
Creation of a plant improvement program for each of the
buildings on the compound
Post occupancy evaluation (POE) of physical plant manage-
ment, systems and equipment
Assessment and corrective actions on all facets of the opera-
tion
My Position(s):
Central Plant Manager/Assessor
Preparation:
Review of several (smaller) prior POEs
Physical survey of the entire facility
Study of the plants historical operations
Review of equipment maintenance documents
Documentation:
Project charter
Project management plan
Equipment operating instruction manuals
Learning Opportunities:
Insight into the intricacies of government security activities
Study of existing policies and procedures
Updates on equipment and systems
Chapter 12
LESSONS LEARNED
etc.) and decide how much detail to give to each. It might also
include the processes for identifying and approving changes
to the project scope, and specify any required resources as well
as the project manager’s authority to manage them. On small
department-based projects someone from management is the
sponsor, the department manager is the primary stakeholder, for-
mal project approval is not required, and a short overview of the
plan might include the scope, deliverables, risks, resources and
project manager ’s authority. On medium-sized endeavors, an
effort should be made to identify the stakeholders, the project’s
priority over other projects should be justified, and project accep-
tance criteria, business justification and rough estimates of the
resource requirements should be addressed. Large organizational
projects affecting all departments should identify internal and
external stakeholders, document and justify the level of financial
and human resources required, and detail the risks, benefits, and
strategic impacts the project can have on the total organization.
In their simplest form, all project charters should contain the
following information shown in Table 12-2.
Figure 12-7. Tracking Gantt Showing the Critical Path and Percent Complete
Project Management: Survival and Success
Appendix
OVERVIEW
Strategy Drivers
PM maturity
PMO charter
Perception of value
Sponsor and management support
Evolutionary/Incremental
Lower implementation risks
Lower start-up costs
Will take longer to demonstrate ROI
More suitable if high resistance to change and low manage-
ment support
Revolutionary/Wholesale
Higher implementation risks
Higher startup costs
May be able to demonstrate ROI quicker
More suitable if recognition at high level that change is im-
perative
PMO CHARTER
Charter Scope
Business needs
Sponsor
Public vs. commercial
PM maturity
Charter Document
Mission/vision
Goals/objectives
Sponsor
Service offering
PMO governance
Key performance metrics
Funding model
229
230 Project Management: Survival and Success
E I
earned value reports 48 identification of risk 60
end users 21 identifying project stakeholders 100
enterprise asset management (EAM) incidental 14
166 incidental project managers 4
estimators 74 industrial 35
executing 33 initiating 33
process group 144 phase 104
existing systems 21 process group 144
extensions to the PMBOK guide 150 inputs 59, 143
external stakeholders 101 installation of equipment 164
internal stakeholders 101
F International Project Management
FAR (Federal Acquisitions Regula- Association 3
tions) 175 issue log 65, 113
feasibility studies 23, 182 issues 65, 100, 111
Finish to Finish (FF) 192 register 146
Finish to Start (FS) 192 ITTO (inputs, tools and techniques,
formal presentations 90 outputs) 102
forming stage 77
K
forms 52
key stakeholders 101
forms and templates 50
kickoff meetings 90
foundational standards 42
knowledge areas 33, 38, 144
framework 60, 143, 183
L
G lessons learned 181
Gantt chart 3, 191 life-cycle 59, 61, 104
goals 73, 75, 106 light standards 13
and objectives 36 logs and registers 64
goal setting 73
government extension 152 M
ground rules 80 management plan 88
managerial 35
H managing projects 161
handicap 13 manufacturing 35
Index 233