CEP Assignment 2-PSA&D Fall 2024
CEP Assignment 2-PSA&D Fall 2024
Generator Data
Bus number X1 X2 X0 Xn
1 0.15 0,15 0,20 0.05
3 0.12 0.15 0.15 0
To solve:
1, It is now required to assess the power flow conditions of the system described above with
both manual calculations and in simulation environment (Powerworld simulator) with the aid
of suitable Algorithm(s). Develop your step-by-step assessment report. Provide solution to any
deviation from normalcy, if identified. The voltage-controlled bus-3 has a target voltage of 1.05
p.u.
2. Create any unsymmetrical fault at any of the buses in the system and calculate the fault
current magnitude. Verify your calculated value by Simulation results in Powerworld simulator
Assessed CLO
------------------------------------------------------------------------------------------------------------------------------
This CEP covers the following range of Complex Problem-solving WPs: