CA Inter Cost MTP May22 Hand Notes
CA Inter Cost MTP May22 Hand Notes
1 MTP May’22
Cost Sheet
The following data relates to the manufacturing project received for the budgeted output of
19,600 units. You are required to CALCULATE the selling price per unit covering a profit of 25%
on the selling price. [10]
Direct materials: 40 sq. m. per unit @ ₹ 10.60 per sq. m.
Direct wages: Bonding department 48 hours per unit @ ₹ 25 per hour
Finishing department 30 hours per unit @ ₹ 19 per hour
Budgeted costs and hours per annum- Variable overhead:
(₹) Total hours
Bonding department 15,00,000 10,00,000
Finishing department 6,00,000 6,00,000
Fixed overhead-
(₹)
Production 15,68,000
Selling and distribution 7,84,000
Administration (General) 3,92,000
Selling Price
Answer
Decision making Cost Sheet (per unit)
Amount Amount
Particulars
(₹) (₹)
Direct materials 40 m2 at ₹ 10.60 per m2 424
Direct wages:
Bonding department- 48 hours at ₹ 25 per hour 1,200
|1
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
2 MTP May’22
Standard Costing
Following are the details given:
Budgeted Days 25
Budgeted Fixed Overheads 1,00,000
Budgeted Production 800 units per day
Actual Production 21,000 units
Fixed Overheads are absorbed @ ₹ 10 per hour.
Fixed overheads efficiency variance 10,000A
Answer
(i) Fixed Overhead Cost Variance = (Std Fixed Overheads – Actual Fixed Overheads)
1, 00 , 000
= 21, 000 units Actual Fixed Overheads = 15,000A
20 , 000
= (1,05,000 - Actual Fixed Overheads) = 15,000A
=> Actual Fixed Overheads = 1,20,000
(ii) Fixed Overhead Calendar Variance = (Actual Days – Budgeted Days) × Budgeted rate per
day
1, 00 , 000
= (Actual Days – 25) × = 8,000F
25
= (Actual Days – 25) = 2
=> Actual Days = 27
(iii) Fixed Overhead Efficiency Variance = (Standard Hours for Actual Production – Actual
Hours) × Budgeted rate per hour
10 , 000
= 21, 000 Actual Hours 10 = 10,000A
20 , 000
= (10,500 – Actual Hours) = -1,000
=> Actual Hours = 11,500
(iv) Fixed overheads Expenditure variance = (Budgeted Fixed Overheads – Actual Fixed
Overheads)
|3
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
3 MTP May’22
Employee Cost
The standard time allowed for a certain piece of work is 240 hours. Normal wage rate is ₹ 75 per
hour.
The bonus system applicable to the work is as follows:
Percentage of time saved to time allowed (slab rate) Bonus
(i) Up to the first 20% of time allowed 25% of the corresponding saving in time.
(ii) For and within the next 30% of time allowed 40% of the corresponding saving in time.
(iii) For and within the next 30% of time allowed 30% of the corresponding saving in time.
(iv) For and within the next 20% of time allowed 10% of the corresponding saving in time.
CALCULATE the total earnings of a worker over the piece of work and his earnings per hour
when he takes -
(a) 256 hours,
(b) 120 hours, and
(c) 24 hours respectively. [10]
Answer
Calculation of total earnings and earnings per hour:
(a) Time taken is (b) Time taken is (c) Time taken is
Particulars
256 hours 120 hours 24 hours
A. Time Allowed 240 hours 240 hours 240 hours
B. Time taken 256 hours 120 hours 24 hours
4 MTP May’22
Marginal Costing
At budget activity of 80% of total capacity, a company earns a P/V ratio of 30% and a profit of
15% of total sales. Due to covid pandemic resulting in poor demand, the company has to reduce
its selling price by 10%. The company was able to achieve a production and sales volume for
the year equivalent to 50% of total capacity. The sales value at this level was ₹ 27,00,000 at a
reduced price of ₹ 18 per unit. Due to reduction in production, the actual variable cost went up
by 5% of the budget.
You are required to:
(i) PREPARE statement of profitability at budget and actual activity.
(ii) FIND P/V ratio and BES (in ₹ and unit of the actual sales activity). [10]
|5
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
Answer
Actual Sales ₹ 27,00,000
Actual Selling Price per unit 18
Actual units (50%)
27, 00 , 000 1,50,000
18
Therefore, budgeted units (80%)
80 2,40,000
1, 50 , 000
50
Budgeted Selling Price
18 20
90%
Fixed Cost
Break Even Sales (in Units) =
Contribution per unit
7,20,000
= = 2,18,182 Units
3.3*
4,95,000
*Contribution per unit = = 3.3 per unit
1,50,000 units
5 MTP May’22
Material Costing
DISTINGUISH clearly between Bin cards and Stores Ledger. [5]
Answer
Bin Card Stores Ledger
It is maintained by the storekeeper in the It is maintained in cost accounting
store. department.
It contains only quantitative details of material It contains information both in quantity and
received, issued and returned to stores. value.
Entries are made when transaction takes It is always posted after the transaction.
place.
Each transaction is individually posted. Transactions may be summarized and then
posted.
Inter-department transfers do not appear in Material transfers from one job to another job
Bin Card. are recorded for costing purposes.
6 MTP May’22
Basics of Cost Accounting
Some of the items of PR Company, a manufacturer of corporate office furniture, are provided
below. As the company is in the process of developing a formal cost accounting system, you are
required to CLASSIFY the items into three categories namely: (i) Cost tracing (ii) Cost allocation
(iii) Non- manufacturing item. [5]
|7
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
Classification of items
Answer
Item Cost Tracing Cost Allocation Non-manufacturing
Carpenter wages √
Depreciation - office building √
Glue for assembly √
Lathe department supervisor √
Metal brackets for drawers √
Factory washroom supplies √
Lumber √
Samples for trade shows √
Lathe depreciation √
Lathe operator wages √
7 MTP May’22
Process Costing
WHAT is inter-process profit? STATE its advantages and disadvantages. [5]
Inter-process Profit
Answer
Inter-Process Profit: To control cost and to measure performance, different processes within an
organization are designated as separate profit centres. In this type of organizational structure,
the output of one process is transferred to the next process not at cost but at market value or
cost plus a percentage of profit. The difference between cost and the transfer price is known as
inter - process profits.
The advantages and disadvantages of using inter-process profit, in the case of process type
industries are as follows:
Advantages:
1. Comparison between the cost of output and its market price at the stage of completion is
facilitated.
2. Each process is made to stand by itself as to the profitability.
Disadvantages:
1. The use of inter-process profits involves complication.
2. The system shows profits which are not realised because of stock not sold out.
8 MTP May’22
Marginal Costing
Company manufacture and sell 3 types of mobile handset. It also manufactures wireless charger
for mobile. The company has worked out following estimates for next year.
Annual Demand Selling Price Material cost Labour cost
(in units) (₹ per unit) (₹ per unit) (₹ per unit)
X5 5,000 8,000 2,000 1,000
X6 4,000 9,000 2,500 1,500
X7 3,000 12,000 3,000 2,000
Wireless Charger 15,000 1,500 300 200
To encourage the sale of wireless charger a discount of 10% in its price is being offered if it were
to be purchased along with mobile. It is expected that customer buying mobile will also buy
the wireless charger. The company factory has an effective capacity of 35,000 labour hours. The
labour is paid @ ₹ 500 per hour. Overtime of labour has to be paid at double the normal rate.
Other variable cost work out to be 50% of direct labour cost and fixed cost is ₹ 1,00,00,000.
There will be no inventory at the end of the year.
PREPARE statement of profitability. [10]
Profitability Statement
Answer
Calculation of Labour overtime hours
Total hours required for production
X5 (5,000 x 2 hrs) 10,000
X6 (4,000 x 3 hrs) 12,000
|9
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
9 MTP May’22
Standard Costing
Rounak Minerals Ltd. operates in iron ore mining through open cast mining method. Explosives
and detonators are used for excavation of iron ores from the mines. The following are the details
of standard quantity of explosives materials used for mining:
Material Variances
Answer
Workings:
1. Calculation of Standard Qty. of Explosives and Detonators for actual output:
Overburden
Particulars Iron ore Total
(OB)
SME:
A Actual Output 20,000 tonne 58,000 M3
B Standard Qty per unit 2.4 kg./tonne 1.9 kg./M3
C Standard Qty. for actual production 48,000 kg. 1,10,200 kg. 1,58,200 kg.
[A × B]
Detonators:
D Standard Qty per unit 2 pcs/ tonne 2 pcs/ M3
E Standard Qty. for actual production 40,000 pcs. 1,16,000 pcs 1,56,000 pcs
[A × D]
| 11
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
Answer
(i) Computation of Value of Inventory as on 30th September 2021:
Date Particulars Units WAM (₹) FIFO (₹) LIFO (₹)
01-07-21 Opening Stock 12,500 75,00,000 75,00,000 75,00,000
(₹ 600×12,500) (₹ 600×12,500) (₹ 600×12,500)
01-07-21 Purchases 25,000 1,43,25,000 1,43,25,000 1,43,25,000
(₹ 573×25,000) (₹ 573×25,000) (₹ 573×25,000)
30-09-21 Purchases 12,500 78,75,000 78,75,000 78,75,000
(₹ 630×12,500) (₹ 630×12,500) (₹ 630×12,500)
01-07-21 Issues/ 34,000 2,01,96,000* 1,98,19,500** 2,01,94,500***
to Consumption
30-09-21 (Balancing
figure)
30-09-21 Closing Stock 16,000 95,04,000 98,80,500 95,05,500
` 75,00,000 ` 1, 43, 25, 000 ` 78 , 75, 000
Weighted average rate = = ₹ 594
12, 500 25, 000 12, 500 units
* ₹ 594 x 34,000 = ₹ 2,01,96,000
** ₹ 600 × 12,500 + ₹ 573 × 21,500 = ₹ 1,98,19,500
*** ₹ 630 × 12,500 + ₹ 573 × 21,500 = ₹ 2,01,94,500
(ii) Computation of Profit or Loss for the Quarter ended 30th September 2021
Particulars WAM (₹) FIFO (₹) LIFO (₹)
Sales 2,19,30,000 2,19,30,000 2,19,30,000
Less: Consumption 2,01,96,000 1,98,19,500 2,01,94,500
| 13
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
Answer
Workings:
1. Maximum number of bottles that can be processed in a batch:
5,000 ltrs
=
Bottle volume
Large Medium Small
Qty (ltr) Max bottles Qty (ltr) Max bottles Qty (ml) Max bottles
3 1,666 1.5 3,333 600 8,333
For simplicity of calculation small fractions has been ignored.
2. Number of batches to be run:
Large Medium Small Total
A Demand 3,00,000 7,50,000 20,00,000
B Bottles per batch (Refer WN-1) 1,666 3,333 8,333
C No. of batches [A÷B] 180 225 240 645
For simplicity of calculation small fractions has been ignored.
3. Quantity of Material-W and Material C required to meet demand:
Particulars Large Medium Small Total
A Demand (bottle) 3,00,000 7,50,000 20,00,000
B Qty per bottle (Litre) 3 1.5 0.6
C Output (Litre) [A × B] 9,00,000 11,25,000 12,00,000 32,25,000
D Material-W per litre of output 14 14 14
(Litre)
E Material-W required (Litre) 1,26,00,000 1,57,50,000 1,68,00,000 4,51,50,000
[C × D]
F Material-C required per litre of 25 25 25
output (ml)
G Material-C required (Litre) 22,500 28,125 30,000 80,625
[(C × F) ÷ 1000]
4. No. of Man-shift required:
Large Medium Small Total
A No. of batches 180 225 240 645
B Hours required per batch (Hours) 2 2 2
C Total hours required (Hours) [A×B] 360 450 480 1,290
D No. of shifts required [C÷8] 45 57 60 162
E Total manshift [D×20 workers] 900 1,140 1,200 3,240
For simplicity of calculation small fractions has been ignored.
| 15
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
| 17
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
(iii) Operator Wages (Two operators and each operator is in charge of two machines)
₹ 10,000 per month (per Operator)
(iv) Fixed repairs and maintenance charges per machine ₹ 2,000 per quarter
(v) Insurance premium for the machine (Annual) 3% of cost
(vi) Forman’s salary (Devoted 1/6th of his time to this factory) ₹ 2,500 per month
(vii) Other factory overhead (Annual) ₹ 40,000
(viii) Power Consumption per machine per hour 80 units
(ix) Rate of Power ₹ 150 for 100 units
(x) Unproductive Hours lost during repairs 50 per annum
(xi) Unproductive Hours Lost while Job Setting 650 per annum
You are required to COMPUTE a comprehensive machine hour rate assuming power is used
during operating time only. [10]
Answer
Computation of Comprehensive Machine Hour Rate per Machine
Per Per Hour
Particulars
Annum (₹) (₹)
Standing Charges:
Depreciation (Working Note 2) 50,000
Factory Rent (₹ 5,000 x 12 months / 4) 15,000
Lighting of Factory (₹ 3,000 x 12 months / 4) 9,000
Operator Wages (₹ 10,000 x 12 months / 2) 60,000
Repairs and maintenance (₹ 2,000 x 4) 8,000
Insurance premium (₹ 5,00,000 x 3%) 15,000
Forman’s salary (₹ 2,500 x 12 x 1/6 / 4) 1,250
Other factory overhead (₹ 40,000 / 4) 10,000
1,68,250
Standing Charges per hour (₹ 1,68,250 / 1,500 hours) 112.17
Running Charges:
Power (80 units x ₹ 150 / 100) 120.00
Comprehensive Machine Hour Rate 232.17
Working Notes:
1. Computation of Total Operative Hours
Total Running Hours: 2,200
Less: Unproductive hours lost during repairs 50
Less: Unproductive hours Lost while Job Setting 650
Total Operative Hours 1,500 per annum
2. Calculation of Annual Depreciation
Purchase Cost − Estimated Scrap Value
Annual Depreciation =
Effective Life in Years
` 5, 00 , 000 − ` 50 , 000
=
9 Years
= ₹ 50,000
Answer
Advantages Disadvantages
1. Time rate is guaranteed while there is 1. Incentive is not so strong as with piece
opportunity for increasing earnings by rate system. In fact the harder the worker
increasing production. works, the lesser he gets per piece.
2. The system is equitable in as much as 2. The sharing principle may not be liked by
the employer gets a direct return for his employees.
efforts in improving production methods
and providing better equipment.
| 19
CA Inter Cost
Divya Jadi Booti
CA Inter Cost DJB
Methods of Costing
Answer
S. No. Industry Method of costing
(i) Sugar manufacturing Process costing
(ii) Bridge Construction Contract Costing
(iii) Advertising Job costing
(iv) Car Assembly Multiple Costing (Combination of any method)