Unit- 8 Monitoring and Control-slides(0)
Unit- 8 Monitoring and Control-slides(0)
Introduction;
Creating the Framework;
Collecting the Data;
Visualizing Progress;
Earned Value Analysis ;
Change Control;
Software Configuration Management
Unit 8: Monitoring and Control
When you have completed this chapter you will be able to:
monitor the progress of projects;
assess the risk of slippage;
visualize and assess the state of a project;
revise targets to correct or counteract drift;
control changes to a project’s requirements.
Unit 8: Monitoring and Control
Introduction
After publishing work schedules and initiating a project, it is crucial to shift attention
towards monitoring progress. This involves comparing actual achievements with the
established schedule and, if necessary, adjusting plans to realign the project with its
targets. Emphasizing the importance of creating monitorable plans with clearly
defined completion points.
This chapter explores the gathering of information on project progress and
outlines actions necessary to ensure goal attainment.
Additionally, it addresses strategies for managing external changes, specifically
alterations in project requirements.
Unit 8: Monitoring and Control
Categories of reporting
Visualizing Progress
"Visualizing progress" refers to the act of using visual tools, techniques, or
representations to track, illustrate, or communicate the advancement of a task,
project, or goal. The idea is to make abstract or complex progress data easier
to understand through charts, graphs, diagrams, dashboards, timelines, or other
visual formats.
64+20
79
Figure shows earned value analysis at the start of week 12 of the project. Note that here both
PV and EV are measured in ‘work-days’ and that the 0/100 rule is being applied. The earned
value (EV) is clearly lagging behind the baseline budget, indicating that the project is behind
schedule. By studying Figure, can you tell exactly what has gone wrong with her project and
what the consequences might be?
This indicates the difference between the earned value or budgeted cost and
the actual cost of completed work.
Say that when the SV above was calculated as –£5,000, £55,000 had actually
been spent to get the EV. The CV in this case would have been £35,000 –
£55,000 or –£20,000.
It can also be an indicator of the accuracy of the original cost estimates. A
negative CV means that the project is over cost.
Unit 8: Monitoring and Control
Performance Ratios:
Two ratios are commonly tracked:
Cost Performance Index (CPI) = EV/AC
Schedule Performance Index (SPI) = EV/PV
Using the examples above, CPI would be £35,000/£55,000, that is, 0.64, and
SPI would be £35,000/£40,000, that is, 0.88. The two ratios can be thought of
as a ‘value-for-money’ indices. A value greater than one indicates that work is
being completed better than planned, whereas a value of less than one means
that work is costing more than and/or proceeding more slowly than planned.
Change Control
Change Control Procedures
Changes in Scope of a System
Unit 8: Monitoring and Control
Change Control
Change control refers to the process of managing and controlling changes to a
project's scope, schedule, and resources. Change is inevitable in any project, but
effective change control ensures that modifications are carefully evaluated, approved,
and implemented to minimize negative impacts on the project's success.