Unit - 9 Managing Contracts-Slides
Unit - 9 Managing Contracts-Slides
Introduction;
Types of Contract;
Stages in Contract Placement;
Typical Terms of a Contract;
Contract Management, Acceptance
Disadvantages are:
Higher prices to allow for contingency- The supplier absorbs the risk for any errors in the
estimates. To reduce the impact of this risk, the supplier will add a margin to the price quoted.
Difficulties in modifying requirements - The need to change the scope of the requirements may
become apparent during development – this may cause friction between the supplier and customer.
Upward pressure on the cost of changes- When competing against other potential suppliers, the
supplier will try to quote as low a price as possible. Once the contract is signed, if further
requirements are put forward, the supplier is in a strong position to demand a high price for these
changes.
Threat to system quality- The need to meet a fi xed price could mean that the quality of the
software suffers.
Because the supplier appears to be given a blank cheque, this approach does not find
favour with customers. However, the employment of contract development staff may
in effect involve this type of contract.
There are other options and permutations of options for payments. The implementation of a
specification could be at a fixed price, with any additions or changes to the requirements to be
charged per FP. Where the contractor has buy in equipment, the price of which may fluctuate,
it is possible to negotiate a contract where the final price contains a fixed portion for labour
plus an amount that depends on the actual cost of purchased components.
Unit 9: Managing Contracts
Types of Contract - Fixed price per unit delivered contracts
EXERCISE:
A contract stipulates that a computer application is to be designed, constructed and delivered
at a cost of $600 per FP. After acceptance testing, the customer asks for changes to some of the
functions in the system amounting to 500 FPs and some new functions which amount to 200
additional FPs. Using Table 10.2, calculate the additional charge.
1. Requirements analysis
2. Evaluation plan
3. Invitation to tender
4. Evaluation of proposals
Evaluation plan - Having drawn up a list of requirements, we now need a plan of how
the proposals are to be evaluated.
Unit 9: Managing Contracts
Stages in Contract Placement
Invitation to tender - Having produced the requirements and the evaluation plan, it
is now possible to issue the invitation to tender to prospective suppliers. Essentially,
this will be the requirement document with a supporting letter containing information
about how responses to the invitation are to be lodged. A deadline will be specifi ed
and it is hoped that by then a number of proposals with price quotations will have
been received.
Evaluation of proposals – Based on an evaluation plan describing how each proposal
will be checked against the selection criteria. This reduces risks of requirements being
missed and ensures that all proposals are treated consistently. It would be unfair to
favour a proposal because of the presence of a feature not requested in the original
requirement.
The process of evaluation may include:
Scrutiny of the proposal documents;
Interviewing suppliers’ representatives;
Demonstrations;
Site visits;
Practical tests.