Overview Pressure Vessel
Overview Pressure Vessel
2
3
Question
3
4
• 2019
• Revision become Mandatory 6 months after the date of issuance , except the
Boiler and Pressure Vessels contracted for prior to the end of the 6-month
period
© Intertek Group 4
What
5 is Authorized Inspection?
ASME
- Develop Codes
- Accreditation of AIAs
- Issue Certificates of Authorization
AUTHORIZED INSPECTION AGENCY
- Conducts Joint Review
- Writes Boiler & PV Insurance - Conducts Investigations Jurisdiction
- Employs & Designates Inspectors
- Employs & Designates Supervisors - Adopts Code
- Provide Support for Field - Enforces ASME Code
Activities - Function as AIA
- Certify ASME Data Reports
- Conduct Joint Reviews
U S - Conduct Investigations
H A
FABRICATORS
- Agreement with AIA National Board
- Q.C. Program/ Manual
- Commission Authorized Inspectors
- Certificate of Authorization
- Register Data Reports
- Comply with Code
- Conduct Joint Reviews
- Certify ASME Data Reports
- Conduct Investigations
- Register Items with The National Board
- Issues The NBIC
-“R” Stamp Program
6
Approvals
© Intertek Group 6
7
may recommendations or
can exemptions from prohibitions
should recommendations
ASME CODE SEC VIII
9
Forword
Introduction: U-1, U-2, U-3, U-4
Subsection A: UG – General Requirements
Subsection B: Methods of Fabrication
UW – welded pressure vessels
UF – forged pressure vessels
UB – brazed pressure vessels
Subsection C: Classes of Material - SpecialConstructions
Materials: UCS - Carbon and Low Alloy Steel
UNF - Non ferrous Materials
UHA - High Alloy Steel
UCI - Cast Iron
UCL - Cladding and Lining
UCD - Cast Ductile Iron
UHT - Ferritic Steels with Heat Treatment
ULW - Layered Constructions
ULT - Low Temperature Service
UHX - Shell and Tube Heat Exchanger
Question
© Intertek Group 11
12
© Intertek Group 12
13
© Intertek Group 13
14
CODE OF CONSTRUCTION
ASME SEC VIII DIV 1 (Rules for Construction of Pressure Vessels.)
ASME SEC VIII DIV 2 Alternative Rules (Rules for Construction of Pressure Vessels.)
ASME SEC II Part A ( Ferrous Material Specification).
ASME SEC II Part B ( Nonferrous Material Specification)
ASME SEC II Part C (Specification for Welding rods, electrodes & Filler Materials)
ASME SEC V ( Non Destructive Examination.)
ASME SEC IX ( Qualification Standard for welding and Brazing.)
© Intertek Group 14
15
➢ DISHED END
© Intertek Group 16
17
SCOPE OF INSPECTION
Quality Plan ,Drawing and project specification Reviewing.
Material identification and Test Certificate Reviewing for related material.
NDT ( PT, RT, MT & UT ) procedure & personal qualification review.
Test Procedure ( Hydro test, Pneumatic test ) review.
WPS / PQR, weld plan, PWHT procedure review
Dished end Inspection after forming.
Fit up ( Long seam, Circ Seam, Nozzle) Inspection.
Welding inspection ( Before, During and After)
NDT ( VT, RT, PT, MT, UT) Examination.
Visual Inspection & NDT from Inside Before closing dished end fit up.
RF Pad pneumatic test inspection.
Final dimensions verification.
PWHT verification if required
NDT after PWHT if required.
Hydro test Inspection.
Shot Blasting & Painting.
Packing inspection
© Intertek Group 17
18
Inspector Need to Review Quality Plan and correlates with Code & Specification, If
any discrepancies observed must be Highlighted In Flash report / Inspection Report.
© Intertek Group 18
19
MATERIAL IDENTIFICATION
• Materials ( Generally Pressure Parts) identification shall be as below.
• Manufacturer MTC shall be reviewed for Heat no / Lot no, size. NDT, Heat
Treatment. ( Approval of Manufacturer if specified by client).
• Mechanical ( YS, TS, Elongation, Impact, Hardness) & Chemical
Properties.
• Hydro Test, Flattening Test, Macro Test for Pipes / Tubes.
• Carbon equivalent shall be calculated as: CE=
C+Mn/6+(Cr+Mo+V)/5+(Ni+Cu)/15 should not be exceed than
specified.
• Materials ( Plate, pipe, flanges, fittings), shall be visually examined for
free from defects.
• Heat No / Lot No, Specification, Company Logo, on Materials shall be
confirmed to MTC.
• Materials size shall be verified in correlation with Drawing & specification
© Intertek Group 19
20
© Intertek Group 20
21
QUESTION.
• Where specified Plate dimension tolerances for Carbon steel Plate and Stainless Steel
Plate. ( AS per ASME)
© Intertek Group 21
22
ANSWER
• For Carbon steel Plate- ASME SA 20.
• For Stainless Steel Plate- ASME SA 480.ess Steel Plate.
© Intertek Group 22
23
© Intertek Group 23
24
© Intertek Group 24
25
▪ All joints must be covered with joint category with supporting WPS /
PQR.
▪ All WPS must be fulfill the requirement of mentioned joint.
▪ All WPS shall be approved by any recognized inspection agency.
© Intertek Group 25
26
© Intertek Group 26
27
Allowable Forming
© Intertek Group 27
28
Head Spinning
© Intertek Group 28
29
Hot Forming
© Intertek Group 29
30
© Intertek Group 30
31
© Intertek Group 31
32
© Intertek Group 32
33
© Intertek Group 33
34
ANSWER
Inner surface of Tori spherical, tori conical, hemispherical, or ellipsoidal shall not
deviate out side of the specified shape by more than 1 ¼ % of D, nor inside the
specified shape by more than 5/8% of D ( D= Nominal inside diameter)
© Intertek Group 34
35
Head Measurement
© Intertek Group 35
36
FIT UP INSPECTION
Fit up Inspection to be carried out for Long seam, Circ Seam, Pipe to flange, Nozzle to shell / dished
end as below.
1) Shell length for long seam fit up & Circumference to be measured at both ends of shell.
2) Bevel edge to be welded shall be uniform and smooth and freed of all loose scale and slag
accumulations before welding. ( Bevel edge should be as per WPS / Drawing)
3)Tack weld to secure alignment whether removed or left in place shall be made using fillet or but
weld, procedure qualified in accordance with section IX.
4) Tack welds shall be examined visually / NDT for defects and if found to be defective shall be
removed.
5) Bevel angle, root gap, root face shall be measured to comply with drawing / WPS.
6) Off set to be checked for weld joint according to UW 31, 32 & 33 of ASME Sec VIII Div I.
7) Out of roundness to be checked according to UG 80, Difference between maximum & minimun
inside diameter in any section shall not exceed 1% of the nominal diameter.
8) Thickness to be checked at various location , reduction in thickness shall not exceed 1mm or 10%
of nominal thickness whichever is less as per UW 33.
9) Long seam between courses ( During CS F/U) shall be staggered at a distance at least 5 times the
thickness of the thicker plate or 4” of the joints on each side of the girth seam shall be radio graphed
as per UW 9
10) If impact test is required by service or thickness, then production test coupon will be required and
welded with long seam / circ seam according to UG 84
11- Butt joints of unequal thickness shall have a tapered transition of not less than 3:1 when
the difference in thickness varies more than 1/4t (thinner plate) or 1/8”, whichever is less
© Intertek Group 36
37
© Intertek Group 37
38
© Intertek Group 39
40
© Intertek Group 40
41
Welder Qualification
■ Welders must be qualified when welding pressure parts or load-
carrying, nonpressure- bearing parts
© Intertek Group 41
42
QUESTION
■ What Types of SS Filler Material commonly used to Join SS 304 to
Carbon steel as a first Layer.
■ If Pressure Vessel being built according to ASME, What is the
governing specification for Welding.
© Intertek Group 42
43
ANSWER
■ E 309 Electrode shall be used to Join SS 304 to Carbon steel as
a first Layer.
■ ASME Sec IX.
© Intertek Group 43
44
© Intertek Group 45
46
© Intertek Group 46
47
Root Area
© Intertek Group 47
48
© Intertek Group 48
49
Attachments
■ Non-pressure retaining parts welded over pressure
retaining welds must be notched or the weld ground flush
© Intertek Group 49
50
© Intertek Group 50
51
NOTCHED SUPPORT
© Intertek Group 52
53
© Intertek Group 53
54
© Intertek Group 54
55
© Intertek Group 55
56
© Intertek Group 56
57
Welder Traceability
© Intertek Group 57
58
REQUIRMENT OF RT
© Intertek Group 58
59
© Intertek Group 59
60
QUESTION ON RT.
© Intertek Group 60
61
ANSWER
© Intertek Group 61
62
© Intertek Group 62
63
© Intertek Group 63
64
© Intertek Group 64
65
© Intertek Group 66
67
RT FILM SENSITIVITY
© Intertek Group 67
68
© Intertek Group 69
70
© Intertek Group 70
71
© Intertek Group 71
72
HYDRO TEST-UG 99
• A hydrostatic test shall be conducted on all vessels after: (a) all fabrication
has been completed . (b) all examination have been performed except
those required after hydro test.
• Vessel designed for internal pressure shall be subjected to a hydrostatic
test pressure that at every point in the vessel is at least equal to 1.3 times
the maximum allowable working pressure multiplied by the lowest stress
ratio (LSR)
• It is recommended that the metal temperature during hydro test be
maintained at least 17deg cent above the minimum design metal
temperature but need not exceed 48deg cent to minimize the risk of
brittle fracture.
• Water test certificate shall be reviewed for chlorine contents.
© Intertek Group 72
73
© Intertek Group 73
74
© Intertek Group 74
75
PAINTING INSPECTION
© Intertek Group 75
76
PACKING INSPECTION
• Packing Procedure must be reviewed, and following stages / points to be
verified.
• Nitrogen purging or Desiccant
• All Nozzle opening shall be blanking with metallic blind flanges.
warning sign FILLED WITH N2 & Vessel Post weld Heat Treated.
• Shipping mark ( ‘CG’ mark, sling mark, country of origin.)
• Orientation marking at 0, 90, 180, 270 Deg.
• Name Plate ( manufacturer & ASME ‘U’ stamp).
© Intertek Group 76
77
LESSON LEARNT-1
• Nozzle with RF pad to shell being welded without proper pre heating &
Back chip- during surveillance visit it was observed, NCR was issued.
Disposition: Complete weld was removed, performed proper pre heating as
per WPS / PQR and re welded with related NDT,
• Weld encroach (Toe to Toe welding ) observed- same was being NDT
examined. ( Toe to Toe minimum 50 mm. is required)
• During Hydro test it was observed that Equipment temperature was less
than specified ( 17 deg above MDMT).
Disposition: Hydro test was hold, since not meeting the requirement of
ASME Sec VIII Div I.
© Intertek Group 77
78
WELD ENCROACHMENT
NDT Examination for Encroachment. NDT Examination for Encroachment.
© Intertek Group 78
79
LESSON LEARNT-2
As per Aramco specification Lifting Lug should be Full Penetration weld with
UT tested, however Vendor performed only Fillet weld with LPT
examination.
Disposition: Same issue was high lighted to Aramco, and same was accepted
by CSD ( Consulting Services Department) after calculation of weld strength
and warn Vendor to compliance 32 SAMSS 004 in future.
During Final Inspection Orientation ( 0, 90, 180, 270 deg) was not marked,
since procedure was not called to do same, however later procedure revised
for Orientation Marking.
© Intertek Group 79
80
LESSON LEARNT-3
RF Pad Tell tale hole was observed at Horizontal position, however tell tale
hole for RF Pads required Vertically lower Bottom side.
Disposition: NCR was issued, however same was accepted by Client.
© Intertek Group 80
81
Thank You!
© Intertek Group