Embankment 2
Embankment 2
Embankment 2
1.0 INTRODUCTION
The construction of embankment (including reclamation with hydraulic fills) over
very soft compressible alluvial deposits (e.g. Clay, silty Clay, clayey Silt etc.) is increasing
due to lack of suitable land for infrastructures and other developments. The choice of
construction method in this formation is not only governed by direct costs, but also the long
term maintenance costs, duration of completion and cost benefits.
2.0 GEOLOGY
OF SOFT
ALLUVIAL CLAY
IN PENINSULAR
MALAYSIA
The behaviour of soft
alluvial soils is influenced by
Figure 1 : Quaternary Sediments in Peninsular Malaysia
(after Stauffer, 1973)
Page 1
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
the source of the parent material, depositional processes, erosion, redeposition, consolidation
and fluctuations in groundwater levels.
Page 2
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Multi-Stage Loading
The advantage of multi-stage is that the subsoil is allowed to increase in strength as
consolidation take place under the embankment load. However, the rate of increase
in loading needs to be limited so that the ratio of the load to the available strength of
the subsoil is within the acceptable factor of safety. This method also requires longer
time of construction.
s
FOS =
τ
Where s = Average shear strength available along the failure surface.
τ = Average shear stress applied along the failure surface.
Many computer programs that offer different methods of limit equilibrium stability
analysis are commonly available. Table 1 below summarises the different methods of
stability analysis together with the comments.
In general, there are three types of methods in modelling the soil in the stability
analysis and they are :
(a) Total Stress Analysis
(b) Effective Stress Analysis
(c) Undrained Strength Analysis
s = c’ + σn’tanφ’
where c’ and φ’define the Mohr-Coulomb effective stress failure envelope
and
σ n ’ = σ n - ur
where σn is the total normal stress and ur is the pore pressure at failure.
It should be noted that effective stress analysis will lead to a more favourable
(optimistic, higher FOS) assessment of the stability than the use of undrained analysis
(Ladd, 1991).
Page 4
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
b) su(mob)/σp’ = 0.22;
where su(mob) is the undrained shear strength mobilised on the failure
surface in the field, and σp’ is the preconsolidation pressure (yield
stress) (Mesri, 1988).
Unlike effective stress method, the pore water pressures set up during
shearing to failure need not be estimated, thus eliminating an unknown in the design
procedure. This method is most commonly used in the analysis of short term stability
and design of staged construction.
Generally in practice, the factor of safety on shear strength (FOS) from total
stress or undrained strength analyses used in temporary stage is usually taken as between
1.2 to 1.3. FOS of 1.4 and 1.5 are normally adopted in effective stress analyses of
embankment for permanent stage. It should be noted that designing with low FOS
increases the possibility of large vertical and lateral ground deformations and also risk of
failure.
Page 5
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
4.3.1 Magnitude of
Settlement
When a load of
finite dimensions is
Figure 3 : Influence Chart for Vertical Stress rapidly applied to a
Embankment Loading – Infinite Extent saturated clay, the
(from Osterberg, 1957) resulting settlement can
be conveniently divided
into three stages :
Page 6
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
(A) Initial
Settlement, ρi
A useful chart is given by Osterberg (1957) and shown in Figure 3. The chart
allows estimation of the initial settlement of the embankment.
With time, the excess pore water pressures dissipate as drainage occurs and
the clay undergoes further settlement due to volume changes as stress is
transferred from pore pressure u to effective stress. The rate of volume
change and corresponding settlement is governed by how fast the water can
drain out of the clay under the induced hydraulic gradients.
Page 7
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Values of Δ σ’v at the centre of each soil layer due to embankment loading can be estimated
using elastic theory, Poulos and Davis (1974). The parameters σ’p, eo, CC and CR can be
obtained from oedometer consolidation tests. The notation and terminology used are shown
in Figure 4.
n
C
ρs = ∑[1 + αe
i =1
log(t )]H i
p
where
ρs = Secondary Compression
Magnitude (m)
Hi = Initial thickness of incremental
soil layer, i of n.
ep = Voids ratio at the end of primary
Figure 5 : Relationship between
consolidation
Secondary Compression Ration and
Cα = Secondary Compression Index.
Water Content (from Mesri, 1973)
t = Time for calculation.
Other than oedometer tests, the secondary compression ratio or Modified Secondary
Compression Index, (Cα /(1+ ep)) can be estimated from the relationship proposed by
Mesri (1973) as shown in Figure 5.
Tv = cv t / HD2
Where cv = Coefficient of consolidation (m2/year)
Page 8
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
cv = k / (mv γw)
where k = permeability from field permeability tests (m/sec)
mv = coefficient of compressibility (m2/kN)
γw = density of water (kN/m3)
The use of field values of k will give a better representative effects of large
scale soil structure and permeability, not able to be reflected in laboratory tests.
Since the permeability and compressibility of the soil reduce with increase in
effective stress (under embankment loading), the value of cv should be modified to
reflect the state of stress over the period during which settlement rates are being
calculated.
In the cost conscious market of today, usually a cost comparison between the various
methods which are technically feasible will be required by an engineer throughout the
design. Figure 8 shows the basic framework for assessing various factors that can influence
the cost. Only by carrying out analysis of the costs and benefits of different methods, will
the engineer able to identify where possible modification to the initial constraints can be
undertaken.
The following sections of the paper describes some of the commonly used
embankment construction methods
Page 9
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
No
Stability satisfactory?
Yes
No Settlements
satisfactory?
Yes
Consider alternative
construction methods
MODIFY THE EMBANKMENT PROVIDE ADDITIONAL STRUCTURAL IMPROVE THE GROUND UNDER
LOAD ON THE GROUND SUPPORT TO THE EMBANKMENT THE EMBANKMENT
y Flatter slopes y Internal reinforcement y Pre-load the ground
y Berms y Support piles y Surcharge the embankment
y Lightweight fills y Sheet piles y Staged construction
y excavate and replace soft
soil
y Vertical drains
Reject unsuitable methods y Stone columns
y Vibro - concrete columns
y Lime columns
y Jet grouting
Identity potential combinations of methods
No
Stability satisfactory?
No
Yes
Yes No
No
Reject method
Other constraints
satisfactory?
Yes
No
Fig. 6.1 Flow Chart Showing the Recommended Procedure for the Selection of Construction Methods for Embankments on Soft Alluvial Soils
Figure 7 : Procedure for the Selection of Construction Method (from
O’Riordan & Seaman, 1993)
Page 10
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Page 11
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
This method will be more difficult if the groundwater level is high. If pumping of
water not practical, then compacted suitable material cannot be used and underwater
replacement materials (granular materials) should be used. These materials shall be of a
grading that it is effectively self-compacting. The main disadvantage of the method is the
amount of soft soil which needs to be disposed.
Vertical drains will only be effective when using in conjunction with another
technique, such as pre-loading, surcharging and staged construction (to be discussed in the
following sections) and the design is governed by the time allowed in the construction
programme for consolidation to occur. The average degree of consolidation for radial
consolidation by Barron’s theory is given by Hansbo (1981) as :
⎛ − 8Th ⎞
Uh = 1 - exp⎜⎜ ⎟⎟ for Th = ch t / D2
⎝ μ ⎠
n 2
3n 2 − 1
Where μ= 2 ln(n) −
n −1 4n 2
The average degree for combined vertical and radial consolidation is obtained from
Carillo’s theorem (1942) :
Page 12
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
U = 1 – (1-Uv)(1-Uh)
The vertical drains should have sufficient capacity to enable the water to discharge to
layers above and below the consolidating layer. Granular materials are laid above the
ground surface as platform for the movement of the plant and also as drainage layer. Pre-
fabricated drains are usually left about 150mm above the initial drainage layer prior to
placing further drainage material.
Page 13
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
The use of the staged construction method requires close liaison and communication
between the design engineer, contractor and supervising engineer. Instruments like
settlement markers, displacement markers, piezometers, etc. need to be placed to monitor the
performance of the embankment during construction to prevent failure. In more sensitive
cases, confirmation of gain in strength is needed before the application of the next stage of
loading.
Page 14
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
6.2 Control of
Embankment
Stability
It has been widely
recognised that the failure of
a soft ground is closely
related to the magnitude and
history of the deformation
which taken place before the
final failure. This makes the
use of the information
obtained from the practically
possible measurements in the
field to control the
construction of embankment
to be safe and efficient.
If a soft ground is
under loading, not only
consolidation will occur but
also plastic horizontal flow
(shear deformation). This
fact makes it difficult to
theoretically distinguish the
Figure 11 : Layout of Instrumentation Scheme
relationship between the
(MHA, 1989) displacement and the failure
Page 15
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Assuming the
settlement, ρt at the centre of
the embankment as an index
of consolidation settlement
and the lateral displacement,
δ of the embankment as an
index of the shear
deformation, the progress of
δ in relation to ρt can be used
Figure 12 : Modified Matsuo Stability Plot as an indicator of
embankment stability.
Matsuo et. al. (1977) proposed his plot after observing the deformation of many
embankments and plotted the process of displacement during construction of each
embankment. As reported, it is astonishing that although the section and the unit weight of
each embankment, the soil properties and the thickness of each soft layer and other
surroundings are different from each other, but many embankments under such different
conditions failed near the one curve which can be regarded as the “Failure Criterion Line” as
shown in Figure 12. Therefore the failure of the embankment can be predicted by plotting
the observed settlements and horizontal displacements on this diagram
Page 16
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
From the figure, we can predict the long term settlement with time. However
the final settlement estimated through this method by using the measured data of early
period after loading may be on the high side.
Tan (1992) proposes the use of Hyperbolic method for field estimation of
total primary settlement of subsoil treated with vertical drains and surcharge. The
procedure for use of the method involves four simple steps as outlined below :
Step 1 : Plot the the field settlement data as (t/ρ) vs t, where t is the
time and ρ is the settlement from the beginning of surcharge load application. This
method is not applicable if the construction time of the embankment with surcharge is
more than the time to achieve 60% consolidation.
Page 17
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Step 2 : The settlement values ρ1, ρ2, ρ3, ….. are plotted as points (ρi-1,
ρi) in a coordinate system with axes ρi-1 and, ρi, as shown in Figure 16(b). The 45o line ρi
= ρi-1 shall also be drawn.
Page 18
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Step 3 : A straight line (I) is fitted through the points. The point where
this line intersects the 45 line gives the final consolidation settlement, ρC. The slope β1
o
is related to the coefficient of consolidation, cv and can be used to calculate the rate of
settlement as follows :
cv= − 5 h 2 ln β1
12 Δt
The graphical method above is limited to a single layer with one-way or two-
way drainage.
7.0 CONCLUSION
The basic requirements
for a successful construction of
embankment over very soft
compressible alluvial deposits
are summarized below ;
• Awareness of the project
requirements in terms of
serviceability criteria
(deformation tolerances,
bearing capacity, etc.), costs
(construction cost and
maintenance cost), site
constraint and time
(construction time, service
period).
• Knowledge on the site and
subsoil conditions through
proper desk study, gathering of
geological information and
well planned and supervised
subsurface investigation and
laboratory testing to acquire
the necessary reliable
parameters for geotechnical
designs.
• Proper geotechnical design to
Figure 16 : Graphical Method of Asaoka address both stability of the
embankment and control of
deformation.
• Full time supervision of the
construction works by
qualified personnel / engineer.
• Careful and proper monitoring
on the performance of the
embankment during and after
construction through
instrumentation scheme.
Page 19
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
REFERENCES
Asaoka, A. (1978) “Observational Procedure of Settlement Prediction”. Soils and
Foundations, 18(4), pp87-101.
Balasubramaniam, A.S. & Brenner, R.P. (1981) “Consolidation and Settlement of Soft
Clay”. Soft Clay Engineering (Development in Geotechnical Engineering), V.20,
Elsevier Scientific Publishing Company, pp 481-527
Barron, R.A. (1948) “Consolidation of Fine-Grained Soils by Drains Wells”. Trans ASCE,
113, pp718-754.
Bishop, A.W. (1955) “The use of the Slip Circle in the Stability Analysis of Slopes”.
Geotechnique, Vol 5, pp 7-17.
Bosch, J.H.A. (1988) “The Quaternary Deposits in the Coastal Plains of Peninsular
Malaysia”. Quat. Geol. Sect., Report QG/1, Geol. Survey Malaysia, p.87.
Davis, E.H. & Poulos, H.G. (1972) “Rate of Settlement under Two- and Three-Dimensional
Conditions”. Geotechnique, London, Vol.22, pp.95-114.
Davis, E.H. & Poulos, H.G. (1968) “The use of Elastic Theory for Settlement Prediction
under Three-Dimensional Conditions”. Geotechnique, London, Vol.18.
Emmel, F.J. and Curray, J.R. (1982) “A Submierged Late Pleistocene Delta and Other
Features Related to Sea-Level Changes in the Malacca Strait”. Marine Geol., Vol. 47,
pp.197-216.
Gue, S.S. (1999) ”Selection of Geotechnical Parameters for Design”. Short Course on Soil
Investigation and Design for Slope (SCOFG99), 11 & 12th May, 1999, Kuala Lumpur.
Gue, S.S. & Tan, Y.C. “Subsurface Investigation and Interpretation of Test Results for
Foundation Design in Soft Clay”. Seminar on Ground Improvement – Soft Clay
(SOGISC), 23rd & 24th August 2000, Kuala Lumpur.
Ladd, C.C. (1991) “Stability Evaluation during Staged Construction”. ASCE, JGED,
Vol.117, No.4, pp.540-615.
Ladd, C.C. & Foott, R.F. (1974) “New Design Procedure for Stability of Soft Clays”.
ASCE, JGED, Vol.117, No.4, pp.540-615.
Page 20
SOGISC-Seminar on Ground Improvement-Soft Clay
Design and Construction Control of Embankment over Soft Cohesive Soils
By : Ir. Tan Yean Chin & Ir. Dr. Gue See Sew 23 – 24 August 2000
Morgenstern, N.R. & Price, V.E. (1965) “The Analysis of the Stability of General Slip
Surfaces”. Geotechnique, Vol.15, pp.79-93.
Neoh, C.A. (1999) ”Planning of Site Investigation and Insitu Testing”. Short Course on Soil
Investigation and Design for Slope (SCOFG99), 11 & 12th May, 1999, Kuala Lumpur.
Raj, J.K. & Singh, M. (1990) “Unconsolidated Holocene Sediments along the North-South
Expressway”. Proc. of the Seminar on Geotechnical Aspects of the North-South
Expressway, Kuala Lumpur, pp.159-166.
O’Riordan, N.J. & Seaman, J.W. (1993) “Highway Embankments over Soft Compressible
Alluvial Deposits : Guidelines for Design and Construction”. Contractor Report 341,
Transport Research Laboratory, Department of Transport, U.K.
Osterberg, J.O. (1957) “Influence Values for Vertical Stresses in a Semi-infinite Mass due to
an Embankment Loading”. Proc. 4th ISMFE, pp.393-394.
Poulos, H.G. & Davis. E.H. (1974) “Elastic Solutions for Soil and Rock Mechanics”. Wiley,
New York.
Sarma, S.K. (1979) “Stability Analysis of Embankments and Slopes”. ASCE, JGED,
Vol.105, pp1511-1524.
Skempton, A.W. (1957) “Discussion : The Planning and Design of the New Hong Kong
Airport”. Proc. ICE, Vol.7, pp.305-307.
Stauffer, P.H. (1973) Cenozoic. In Gobbett, D.J. & Hutchison, C.S. (Eds.) “Geology of the
Malay Peninsular West Malaysia and Singapore”. John Wiley Interscience, New York,
pp.143-176.
Tan, Y.C. (1999) ”Piezocone Tests and Interpretation”. Short Course on Soil Investigation and
Design for Slope (SCOFG99), 11 & 12th May, 1999, Kuala Lumpur.
Tan, Y.C. (1994) “Analysis of Trial Embankments at the Muar Flat Site, Malaysia”. Master
Thesis, Asian Institute of Technology, Bangkok, Thailand.
Tan, S. A. (1995) “Validation of Hyperbolic Method for Settlements in Clays with Vertical
Drains”. Soils and Foundations, Vol35(1), pp.101-113.
Tan, S. B. (1971) “An Empirical Method for Estimating Secondary and Total Settlement”.
Proc. 4th Asian Regional Conf. on Soil Mech. & Found., Bangkok, pp147-151.
Page 21