PSM1 Test1
PSM1 Test1
True or False: The Sprint for all the Scrum Teams working on the
same product must start and end on the same date.
Your answer is correct
False
True
Overall explanation
Scrum does not require having aligned Sprints for multiple
teams. The Scrum Teams self-manage and define the best option for
them.
Question 2Correct
What is Scrum?(choose the best answer)
1}. A complete process to deliver complex products.
Your answer is correct
2}. Scrum is a lightweight framework that helps people, teams, and
organizations generate value through adaptive solutions for
complex problems.
3}. A software development cookbook including the best agile
practices.
Overall explanation
Scrum is a lightweight framework that helps people, teams and
organizations generate
value through adaptive solutions for complex problems.
Question 3Incorrect
What can Scrum be used for?(choose all that apply)
Your selection is correct
Develop products and enhancements.
Your selection is correct
Sustain and renew products.
Correct selection
1
Research and identify viable markets, technologies, and product
capabilities.
Correct selection
Release products and enhancements, as frequently as many times
per day.
Correct selection
Develop and sustain Cloud (online, secure, on-demand) and other
operational environments for product use
Overall explanation
Scrum was initially developed for managing and developing products.
Starting in the early 1990s, Scrum has been used extensively,
worldwide, to:
1. Research and identify viable markets, technologies, and product
capabilities;
2. Develop products and enhancements;
3. Release products and enhancements, as frequently as many times
per day;
4. Develop and sustain Cloud (online, secure, on-demand) and other
operational environments for product use; and,
5. Sustain and renew products.
Scrum has been used to develop software, hardware, embedded
software, networks of interacting function, autonomous vehicles,
schools, government, marketing, managing the operation of
organizations and almost everything we use in our daily lives, as
individuals and societies.
Question 4Correct
Who participates in Sprint Planning?(choose all that apply)
Your selection is correct
The Developers
Your selection is correct
The Product Owner
Your selection is correct
Invited people
Your selection is correct
2
The Scrum Master
Overall explanation
The Scrum Team may also invite other people to attend Sprint
Planning to provide advice.
Question 5Correct
What is the Sprint Retrospective?(choose the best answer)
It is the meeting that occurs at the end of the project to identify its
lessons learned.
It is a meeting where the Development Team plans work for the
next 24 hours.
Your answer is correct
It is an opportunity for the Scrum Team to plan ways to increase
quality and effectiveness.
It is a meeting to inspect the Increment and adapt the Product
Backlog if needed.
Overall explanation
The purpose of the Sprint Retrospective is to plan ways to increase
quality and effectiveness.
Question 6Correct
In which Scrum event do key stakeholders collaborate with the
Scrum Team about the outcome of the Sprint and future
adaptations?(choose the best answer)
The Daily Scrum
Your answer is correct
The Sprint Review
The Sprint Retrospective
The Sprint Planning
Overall explanation
Question 7Correct
3
What should the Scrum Team do when during the Sprint
Retrospective meeting, they identified some improvements that can
be done?(choose the best answer)
Assign a responsible team member for at least one improvement.
Check the progress at the next Retrospective.
Make sure the Sprint Backlog for the next Sprint includes all the
improvements.
Your answer is correct
The most impactful improvements are addressed as soon as
possible. They may even be added to the Sprint Backlog for the
next Sprint.
Assign responsible team members for every improvement. Check
the progress at the next Retrospective.
They should not talk about improvements because it could harm
the company.
Overall explanation
During Sprint Retrospective, the Scrum Team identifies the most
helpful changes to improve its effectiveness. The most impactful
improvements are addressed as soon as possible. They may even be
added to the Sprint Backlog for the next Sprint.
Question 8Correct
Select the three most applicable items that Product Backlog
management includes:(choose the best three answers)
Your selection is correct
Ordering Product Backlog items
Your selection is correct
Ensuring that the Product Backlog is transparent, visible, and
understood
Presenting Product Backlog items to the Key Stakeholders
Moving Product Backlog items into the Sprint Backlog
Your selection is correct
Developing and explicitly communicating the Product Goal
Overall explanation
4
Product Backlog management includes:
- Developing and explicitly communicating the Product Goal;
- Creating and clearly communicating Product Backlog items;
- Ordering Product Backlog items; and,
- Ensuring that the Product Backlog is transparent, visible, and
understood.
Question 9Correct
Select which are not part of the pillars that uphold Scrum?
(choose all that apply)
Adaptation
Your selection is correct
Agility
Your selection is correct
Cross-functionality
Inspection
Transparency
Your selection is correct
Teamwork
Your selection is correct
Self-organization
Overall explanation
Scrum is founded on empiricism and lean thinking. Empiricism
asserts that knowledge comes from experience and making decisions
based on what is observed. Lean thinking reduces waste and focuses
on the essentials.
Scrum employs an iterative, incremental approach to optimize
predictability and to control risk. Scrum engages groups of people
who collectively have all the skills and expertise to do the work and
share or acquire such skills as needed.
Scrum combines four formal events for inspection and adaptation
within a containing event, the Sprint. These events work because
they implement the empirical Scrum pillars of transparency,
inspection, and adaptation.
Question 10Correct
5
True or False: The Product Owner and the Scrum Master cannot be a
part of Developers
True
Your answer is correct
False
Overall explanation
Scrum does not prohibit the Product Owner or the Scrum Master do
development work. However, it is not the best practice because it
could create a conflict of interest.
Question 11Correct
Ordinarily, items on the Sprint Backlog tend to be...(choose the best
answer)
Larger than those on the Product Backlog
Your answer is correct
Smaller than those on the Product Backlog
The same size as those on the Product Backlog
Overall explanation
A Sprint Backlog will often be expressed as tasks for implementing a
collection of PBIs that meet an agreed Sprint Goal. There will usually
be multiple tasks associated with realizing a single PBI; therefore,
these tasks tend to be regarded as being "smaller."
Question 12Incorrect
The Scrum framework consists of what?
(choose all that apply)
Your selection is correct
Accountabilities
Correct selection
Rules
Your selection is correct
Artifacts
Your selection is correct
6
Events
Overall explanation
The Scrum framework contains Accountabilities (i.e., Scrum Master,
Product Owner, Developers), Artifacts (i.e., Product Backlog, Sprint
Backlog, Increment), Events (i.e., Sprint, Sprint Planning, Daily Scrum,
Sprint Review, Sprint Retrospective), and rules.
Question 13Incorrect
How does the Scrum Master help the Product Owner?
(choose the best three answers)
Helping establish the project plan
Your selection is correct
Helping find techniques for effective Product Backlog management
Helping find techniques for effective Sprint Goal definition
Your selection is correct
Facilitating stakeholder collaboration as requested or needed
Your selection is incorrect
Leading and coaching the organization in its Scrum adoption.
Correct selection
Helping the Scrum Team understand the need for clear and concise
Product Backlog items
Overall explanation
7
The Scrum Master serves the Product Owner in several ways,
including:
- Helping find techniques for effective Product Goal definition and
Product Backlog management;
- Helping the Scrum Team understand the need for clear and concise
Product Backlog items;
- Helping establish empirical product planning for a complex
environment; and,
- Facilitating stakeholder collaboration as requested or needed.
Question 14Correct
True or False: All Scrum Teams working on the same Product must
use a single Product Backlog.
Your answer is correct
True
False
Overall explanation
If Scrum Teams become too large, they should consider reorganizing
into multiple cohesive Scrum Teams, each focused on the same
product. Therefore, they should share the same Product Goal,
Product Backlog, and Product Owner.
Question 15Incorrect
Who is allowed to update the Product Backlog?
8
The Product Owner may perform activities related to Product
Backlog management or may delegate the responsibility to others.
Regardless, the Product Owner remains accountable.
Question 16Incorrect
What does the Cone of Uncertainty show?
9
Overall explanation
During a Sprint, the Scrum Team turns a selection of the work into an
Increment of value. In other words, for each Sprint, the Scrum Teams
must deliver business functionality. Further, Scrum Teams are cross-
functional, meaning the members have all the skills necessary to
create value for each Sprint.
Question 18Correct
True or False: The Scrum Master does not help those outside the
Scrum Team understand which of their interactions with the Scrum
Team are helpful and which aren’t.
Your answer is correct
False
True
Overall explanation
Scrum Masters are true leaders who serve the Scrum Team and the
larger organization. The Scrum Master helps those outside the Scrum
Team understand which of their interactions with the Scrum Team
are helpful and which aren’t. The Scrum Master helps everyone
change these interactions to maximize the value created by the
Scrum Team.
Question 19Correct
Which of the following is Scrum founded upon?
10
Which of the following are applicable characteristics of the Product
Owner?
12
everyone a shared understanding of what work was completed as
part of the Increment.
Question 24Correct
Which statement is correct about the Sprint Backlog?
13
Goal is in the Product Backlog. The rest of the Product Backlog
emerges to define “what” will fulfill the Product Goal.
The Product Goal is the long-term objective for the Scrum Team.
They must fulfill (or abandon) one objective before taking on the
next.
Question 26Correct
True or False: The Scrum Team can only pursue one Product Goal at
a time.
Your selection is correct
True
False
Overall explanation
The Product Goal is the long-term objective of the Scrum Team. They
must fulfill (or abandon) one objective before taking on the next.
Question 27Correct
Who is accountable for establishing Scrum?
14
Your answer is incorrect
True
Correct answer
False
Overall explanation
It is not recommended. The Scrum Team delivers Done, usable
Increment Sprint.
Question 29Incorrect
How regularly should Scrum users examine Scrum artifacts and
progress approaching a Sprint Goal?
15
Openness
Lean
Your selection is correct
Commitment
Your selection is correct
Courage
Your selection is correct
Focus
Overall explanation
When the values of commitment, courage, focus, openness and
respect are embodied and lived by the Scrum Team, the Scrum pillars
of transparency, inspection, and adaptation come to life and build
trust for everyone.
Question 31Incorrect
At some point during the product development cycle, a key
stakeholder started using the product and was unhappy with its
quality. Thus, he made his concern very clear to the Product Owner.
According to the key stakeholder, the product’s performance was
below what he expected. Thus, the Product Owner went to talk to
you, the Scrum Master, about this issue. What should you tell her?
17
A Product Backlog could be closed when it contains no items to
include in the next Sprint.
Your selection is correct
It is emergent.
Your selection is correct
It is continuously refined.
Your selection is correct
As long as a product exists, its Product Backlog also exists.
Overall explanation
A Product Backlog is emergent. The earliest development of it only
lays out the initially known and best-understood requirements.
Further, it is refined as the product and the environment in which it
will be used evolves. Finally, it is refined to identify what the product
needs to be appropriate, competitive, and useful. As long as a
product exists, its Product Backlog also exists since it is the single
source of work undertaken by the Scrum Team.
Question 34Incorrect
What happens when a Sprint is canceled?
18
The Scrum Guide is not explicit anymore about what happens.
However, these are the best options following Scrum's mindset.
Independent of the case, if a Product Backlog item does not meet the
Definition of Done, it cannot be released or even presented at the
Sprint Review. Instead, it returns to the Product Backlog for future
consideration.
Question 35Incorrect
During Sprint Planning, the Developers must plan the work for all
days of the Sprint. It is decomposed by the end of this meeting, often
to units of one day or less.
19
progress in the Daily Scrum.. Thus, it is not recommended to attempt
to plan the work for all days of the Sprint during Sprint Planning.
Question 36Correct
Which of the following are correct regarding the Product Goal?
20
Maximum 3 hours
Overall explanation
The timeboxed duration of events is as follows:
Sprint - Maximum 1 month
Daily Scrum - 15 minutes
Sprint Planning - 8 hours in a one-month Sprint, and normally shorter
proportionally for shorter Sprints
Sprint Review - 4 hours in a one-month Sprint, and normally shorter
proportionally for shorter Sprints
Sprint Retrospective - 3 hours in a one-month Sprint, and normally
shorter proportionally for shorter Sprints
21
- Leading, training, and coaching the organization in its Scrum
adoption;
- Planning and advising Scrum implementations within the
organization;
- Helping employees and stakeholders understand and enact an
empirical approach for complex work; and,
- Removing barriers between stakeholders and Scrum Teams.
Question 39Correct
True or False: According to the Scrum framework, the Scrum
components and rules for the project are chosen depending on the
project's specific characteristics.
True
Your answer is correct
False
Overall explanation
While implementing only parts of Scrum is possible, the result is not
Scrum. Scrum exists only in its entirety and functions well as a
container for other techniques, methodologies, and practices.
Question 40Correct
What are the Scrum Artifacts?
22
Question 41Correct
During a Sprint, the CEO asks the Developers to add an urgent item
to the Sprint Backlog. What should the Developers do?
23
You are a Scrum Master and about to begin working with five new
Scrum Teams; all working on the same product. Which of the
following should you strive for?
24
The need for the team to keep delivering value fast
Overall explanation
Scrum Teams are self-managed and cross-functional. Thus, the
Scrum Master should coach the team to be autonomous whenever
possible. However, it is also important for the Scrum Master to
consider the cases in which specialists are really needed and that
problem at hand is too complex for the Developers to figure out on
their own. In these cases, the Scrum Master can work with the
Developers with the possibility of having specialized training or even
having the specialist join the Scrum Team for the period in which
his/her expertise is needed. Whatever the case, keep in mind that
the Scrum Master has to respect the Scrum Team's self-
management, but fulfill his/her accountability for the Scrum Team’s
effectiveness.
Question 44Correct
True or False: The Definition of Done is created during the first Sprint
and remains unchanged until the end of the project.
Your answer is correct
False
True
Overall explanation
During the Sprint Retrospective, the Scrum Team inspects how the
last Sprint went with regards to individuals, interactions, processes,
tools, and their Definition of Done. Thus, the Definition of Done can
be adapted.
Question 45Correct
Who attends the Sprint Review?
28
The sum of all the Product Backlog items completed during the
Sprint, excluding the value of the increments of all previous Sprints
Overall explanation
Each Increment is additive to all prior Increments and thoroughly
verified, ensuring that all Increments work together.
Question 51Incorrect
What is a possible result of the Sprint Review?
29
The Development Team
The Scrum Master
The Key Stakeholders
The Product Owner
Overall explanation
The whole Scrum Team then collaborates to define a Sprint Goal that
communicates why the Sprint is valuable to stakeholders.
Question 53Correct
Who has the authority to cancel the Sprint?
30
Facilitate the process of having the Scrum Team improve its skills,
tools, and environment over time and adjust the Definition of Done
as needed
Tell them that, in this case, it is acceptable to have the partially
Done Increment accepted during Sprint Reviews
Overall explanation
The Definition of Done is a formal description of the state of the
Increment when it meets the quality measures required for the
product. However, as with any goal, it must be attainable. Thus, to
keep the team motivated, but aware that the Definition of Done
must be met, the best solution is to work with the Definition of
Done. Notice that, in this case, the Scrum Team must recognize that,
whenever the Definition of Done becomes more stringent in the
future, technical debt will need to be paid off.
Question 55Correct
Refinement usually consumes how much of part of the capacity of
the Scrum Team?
31
The Increment commits to the Definition of Ready
The Product Backlog commits to the Product Vision
Overall explanation
Each artifact contains a commitment to ensure it provides
information that enhances transparency and focus against which
progress can be measured:
- For the Product Backlog it is the Product Goal.
- For the Sprint Backlog it is the Sprint Goal.
- For the Increment it is the Definition of Done.
These commitments exist to reinforce empiricism and the Scrum
values for the Scrum Team and their stakeholders.
Question 57Incorrect
Which of the following ways of forming Scrum Teams meet Scrum´s
values?
33
The Developers.
Correct answer
A small team of people.
The Learning process.
The Scrum Guide's rules.
Overall explanation
The fundamental unit of Scrum is a small team of people, a Scrum
Team.
Question 61Correct
Which of the following is NOT correct about the Developers?
b. It's up to the Developers to see how many items they can develop
during the Sprint, and no one can force them to pick more (or fewer)
items. (correct)
34
(choose the best two answers)
Your selection is correct
They should be placed on the Product Backlog
Your selection is correct
They must not be included as part of the Increment
The items should be demonstrated during the Sprint Review, the
Sprint’s velocity should consider the part of the items that were
Done during the Sprint, and the remaining work should be
considered as a new Product Backlog item
If the Product Owner is satisfied with the work, he can accept them
and release them
Overall explanation
The Definition of Done creates transparency by providing everyone a
shared understanding of what work was completed as part of the
Increment. If a Product Backlog item does not meet the Definition of
Done, it cannot be released or even presented at the Sprint Review.
Instead, it returns to the Product Backlog for future consideration.
Question 63Incorrect
What should be the length of a Sprint?
35
True or False: The Product Owner is the main person responsible for
engaging the stakeholders
True
Your answer is correct
False
Overall explanation
The Scrum Guide reads: "The Scrum Team is responsible for all
product-related activities from stakeholder collaboration,
verification, maintenance, operation, experimentation, research and
development, and anything else that might be required."
37
(choose the best answer)
The Product Owner.
39
Overall explanation
When the words “develop” and “development” are used in the
Scrum Guide, they refer to complex work including software and
hardware development, development and releasing of products and
enhancements, development and sustaining product operational
environments, research and identifying of viable markets and
technologies, and even more.
Question 72Correct
Who is allowed to change the actionable plan for delivering the
Increment?
No one else tells them how to turn Product Backlog items into
Increments of value.
Question 73Correct
Which of the following is false with regards to what happens during
the Sprint?
b. They can still miss something. On the other hand, if the test is
focused on the unit, what about testing the integrated solution? It
may break something.
c. It doesn't guarantee that we're absolutely Done with the item and
that it satisfies the customer and user.
A Product Backlog item that you have in the Sprint Backlog is Done
when it satisfies the Definition of Done.
Question 76Correct
Which of the following are commitments of Scrum Artifacts.
43
Ask the development managers to introduce their departments and
capabilities
Your selection is correct
Ask the Developers to discuss and identify the way they are going
to develop the product.
Ensure that a bonus system is in place for the top performance of
individuals.
Overall explanation
Product Backlog is never complete. It has to be about the project
and people internal to it, not the external departments. Remember
that the team is cross-functional and does everything needed for the
project, without outside help. Having a reward system is harmful to
the unity of the team.
Question 79Correct
What is the single source of requirements for any changes to be
made to the product?
45