REKAPITULASI RENCANA ANGGARAN BIAYA

NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH


A PEKERJAAN PERSIAPAN
1 PENGUKURAN LAHAN 277.5 M² Rp 10,494.00 Rp 2,912,085.00
2 PEMBERSIHAN LAHAN 820 M² Rp 10,494.00 Rp 8,605,080.00
3 PEMASANGAN BOWPLANK 40 LS Rp 54,230.58 Rp 2,169,223.20
C PERHITUNGAN PONDASI
1 PEKERJAAN PASIR URUG 4.8 M³ Rp 176,253.00 Rp 846,014.40
2 PEKERJAAN AANSTAMPING 24 M³ Rp 350,646.78 Rp 8,415,522.72
3 PEKERJAAN BATU KALI 52.8 M³ Rp 821,711.00 Rp 43,386,340.80
D PERHITUNGAN BETON
1 PEKERJAAN SLOOF 15 x 20 2.88 M³ Rp 4,780,824.07 Rp 13,768,773.32
2 PEKERJAAN KOLOM PRAKTIS 13 x 13 2.808 M³ Rp 8,929,009.65 Rp 25,072,659.10
E PEKERJAAN KUSEN
1 KUSEN TYPE P1 (2 BH) 0.1018 M³ Rp 6,353,940.45 Rp 646,576.98
2 KUSEN TYPE P2 (5 BH) 0.2595 M³ Rp 6,353,940.45 Rp 1,648,847.55
3 KUSEN TYPE P3 (2 BH) 0.0979 M³ Rp 6,353,940.45 Rp 622,177.85
4 KUSEN TYPE J1 (1 BH) 0.06 M³ Rp 6,353,940.45 Rp 381,236.43
5 KUSEN TYPE J2 (2 BH) 0.09 M³ Rp 6,353,940.45 Rp 571,854.64
6 KUSEN TYPE J3 (1 BH) 0.043 M³ Rp 6,353,940.45 Rp 273,219.44
7 KUSEN TYPE J4 (2 BH) 0.186 M³ Rp 6,353,940.45 Rp 1,181,832.92
8 KUSEN TYPE J5 (2 BH) 0.254 M³ Rp 6,353,940.45 Rp 1,613,900.87
9 KUSEN TYPE J6 (1 BH) 0.146 M³ Rp 6,353,940.45 Rp 927,675.31
10 KUSEN TYPE J7 (3 BH) 0.069 M³ Rp 6,353,940.45 Rp 438,421.89
11 KUSEN TYPE J8 (1 BH) 0.041 M³ Rp 6,353,940.45 Rp 260,511.56
12 KUSEN TYPE BV (1 BH) 0.016 M³ Rp 6,353,940.45 Rp 101,663.05
13 KUSEN TYPE BV2 (1 BH) 0.022 M³ Rp 6,353,940.45 Rp 139,786.69
F PEKERJAAN DINDING
1 PEKERJAAN DINDING BATU BATA 239.56 M² Rp 119,026.36 Rp 28,513,954.80
2 PEKERJAAN PLESTERAN 479.12 M² Rp 54,825.98 Rp 26,268,223.54
3 PEKERJAAN ACIAN 479.12 M² Rp 34,579.16 Rp 16,567,567.14
G PEKERJAAN PENUTUP LANTAI
1 PEKERJAAN KERAMIK 40x40 72.88 M² Rp 206,135.38 Rp 15,023,146.49
3 PEKERJAAN KERAMIK 20X20 4.16 M² Rp 136,241.38 Rp 566,764.14
H PEKERJAAN PLAFOND
1 PEKERJAAN GYPSUM BOARD 9mm 105.91 M² Rp 47,162.87 Rp 4,995,019.56
2 PEMASANGAN RANGKA PLAFOND 105.91 M² Rp 152,851.61 Rp 16,188,514.02
I PEKERJAAN TANGGA
1 PEMBUATAN BETON BERTULANG 5.341 M³ Rp 747,373.33 Rp 3,991,720.96
J PEKERJAAN ATAP
1 PEKERJAAN PENUTUP ATAP 155.84 M³ Rp 155,773.64 Rp 24,275,764.06
2 PEKERJAAN RANGKA PENUTUP ATAP 155.84 M³ Rp 256,553.00 Rp 39,981,219.52
K PEKERJAAN PENGECETAN
1 PEKERJAAN CAT DINDING 585.85 M² Rp 48,162.33 Rp 28,215,901.03
2 PEKERJAAN CAT PLAFOND 285.51 M² Rp 48,162.33 Rp 13,750,826.84
3 PEKERJAAN CAT LISTPLANK 36.4 M² Rp 58,604.37 Rp 2,133,199.07
4 PEKERJAAN CAT KUSEN TYPE P1 (2 BH) 8.6 M² Rp 58,604.37 Rp 503,997.58
5 PEKERJAAN CAT KUSEN TYPE P2 (5 BH) 19.35 M² Rp 58,604.37 Rp 1,133,994.56
6 PEKERJAAN CAT KUSEN TYPE P3 (2 BH) 6.88 M² Rp 58,604.37 Rp 403,198.07
7 PEKERJAAN CAT KUSEN TYPE J1 (1 BH) 2.62 M² Rp 58,604.37 Rp 153,543.45
8 PEKERJAAN CAT KUSEN TYPE J2 (2 BH) 1.64 M² Rp 58,604.37 Rp 96,111.17
9 PEKERJAAN CAT KUSEN TYPE J3 (1 BH) 0.12 M² Rp 58,604.37 Rp 7,032.52
10 PEKERJAAN CAT KUSEN TYPE J4 (2 BH) 1.52 M² Rp 58,604.37 Rp 89,078.64
11 PEKERJAAN CAT KUSEN TYPE J5 (2 BH) 0.15 M² Rp 58,604.37 Rp 8,790.66
12 PEKERJAAN CAT KUSEN TYPE J6 (1 BH) 2.69 M² Rp 58,604.37 Rp 157,645.76
13 PEKERJAAN CAT KUSEN TYPE J7 (3 BH) 1.335 M² Rp 58,604.37 Rp 78,236.83
14 PEKERJAAN CAT KUSEN TYPE J8 (1 BH) 0.66 M² Rp 58,604.37 Rp 38,678.88
15 PEKERJAAN CAT KUSEN TYPE BV (1 BH) 0.39 M² Rp 58,604.37 Rp 22,855.70
16 PEKERJAAN CAT KUSEN TYPE BV2 (1 BH) 0.33 M² Rp 58,604.37 Rp 19,339.44
L PEKERJAAN MEKANIKAL, ELEKTRIKAL, DAN PLUMBING
1 PEKERJAAN SAKLAR TUNGGAL 6 BH Rp 15,131.05 Rp 90,786.30
2 PEKERJAAN SAKLAR GANDA 5 BH Rp 25,361.05 Rp 126,805.25
3 PEKERJAAN LAMPU 14 BH Rp 183,217.93 Rp 2,565,051.02
5 PEKERJAAN STOP KONTAK 7 BH Rp 201,246.32 Rp 1,408,724.24
9 PEKERJAAN PIPA PVC AIR BERSIH 3/4" 14.6 M Rp 102,597.05 Rp 1,497,916.93
10 PEKERJAAN PIPA PVC AIR BERSIH 1/2" 13 M Rp 43,333.81 Rp 563,339.53
11 PEKERJAAN PIPA PVC AIR HUJAN 3" 25.25 M Rp 266,382.99 Rp 6,726,170.50
12 PEKERJAAN PIPA PVC AIR KOTOR 4" 15.35 M Rp 369,262.91 Rp 5,668,185.67
13 PEKERJAAN PIPA PVC AIR KOTOR 3" 16.9 M Rp 266,382.99 Rp 4,501,872.53
14 PEKERJAAN KERAN AIR 5 BH Rp 632,006.38 Rp 3,160,031.90
15 PEKERJAAN FLOOR DRAIN 3 BH Rp 761,827.00 Rp 2,285,481.00
16 PEKERJAAN WASTAFEL 1 BH Rp 520,088.80 Rp 520,088.80
17 PEKERJAAN KLOSET DUDUK 2 BH Rp 2,051,434.00 Rp 4,102,868.00
M PEKERJAAN AKSESORIS
1 Engsel Pintu 9 SET Rp 91,121.80 Rp 820,096.20
2 Engsel Jendela 18 SET Rp 63,681.20 Rp 1,146,261.60
3 Kaca Jendela J1 0.84 M² Rp 183,329.30 Rp 153,996.61
4 Kaca Jendela J2 1.24 M² Rp 183,329.30 Rp 227,328.33
5 Kaca Jendela J3 0.63 M² Rp 183,329.30 Rp 115,497.46
6 Kaca Jendela J4 2.852 M² Rp 183,329.30 Rp 522,855.16
7 Kaca Jendela J5 5.94 M² Rp 183,329.30 Rp 1,088,976.04
8 Kaca Jendela J6 3.4425 M² Rp 183,329.30 Rp 631,111.12
9 Kaca Jendela J7 0.75 M² Rp 183,329.30 Rp 137,496.97
10 Kaca Jendela J8 0.27 M² Rp 183,329.30 Rp 49,498.91
11 Kaca BV 0.09 M² Rp 183,329.30 Rp 16,499.64
12 Kaca BV2 0.2 M² Rp 183,329.30 Rp 36,665.86
JUMLAH Rp 375,331,333.71
PPN 11,3% Rp33,215,162
TOTAL Rp408,546,496
DIBULATKAN Rp455,000,000
ANALISIS HARGA SATUAN

NO URAIAN PEKERJAAN KOEF SAT HARGA SATUAN JUMLAH HARGA


A PEKERJAAN PERSIAPAN
PENGUKURAN LAHAN
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
1 PEKERJA 0.1 OH Rp 85,500.00 Rp 8,550.00
JUMLAH Rp 9,540.00
KEUNTUNGAN (10%) Rp 954.00
HARGA SATUAN PEKERJAAN Rp 10,494.00
PEMBERSIHAN LAHAN
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
2 PEKERJA 0.1 OH Rp 85,500.00 Rp 8,550.00
JUMLAH Rp 9,540.00
KEUNTUNGAN (10%) Rp 954.00
HARGA SATUAN PEKERJAAN Rp 10,494.00
PEMASANGAN BOWPLANK
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
PEKERJA 0.1 OH Rp 85,500.00 Rp 8,550.00
KEPALA TUKANG KAYU 0.01 OH Rp 136,800.00 Rp 1,368.00
TUKANG KAYU 0.1 OH Rp 107,400.00 Rp 10,740.00
3 BAHAN
PAPAN KAYU ALBASIA 3/20 0.007 M³ Rp 2,005,570.00 Rp 14,038.99
BALOK KAYU ALBASIA 5/7 0.007 M³ Rp 1,884,020.00 Rp 13,188.14
PAKU 1"-3" 0.02 KG Rp 21,270.00 Rp 425.40
JUMLAH Rp 49,300.53
KEUNTUNGAN (10%) Rp 4,930.05
HARGA SATUAN PEKERJAAN Rp 54,230.58
PEMASANGAN DIREKSI KEET
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
PEKERJA 0.1 OH Rp 85,500.00 Rp 8,550.00
KEPALA TUKANG KAYU 0.01 OH Rp 136,800.00 Rp 1,368.00
TUKANG KAYU 0.1 OH Rp 107,400.00 Rp 10,740.00
BAHAN
BATA MERAH KELAS II 70 BH Rp 720.00 Rp 50,400.00
4 PASIR PASANG 0.25 M³ Rp 149,000.00 Rp 37,250.00
SEMEN TIGA RODA 0.1 KG Rp 1,440.00 Rp 144.00
KAYU ALBASIA 0.1 M³ Rp 2,005,570.00 Rp 200,557.00
TRIPLEKS 3MM 0.5 LBR Rp 52,260.00 Rp 26,130.00
SENG GELOMBANG BJLS 30 1.1 LBR Rp 58,830.00 Rp 64,713.00
PAKU 4"-7" 0.25 KG Rp 19,010.00 Rp 4,752.50
JUMLAH Rp 405,594.50
KEUNTUNGAN (10%) Rp 40,559.45
HARGA SATUAN PEKERJAAN Rp 446,153.95
PEMBUATAN GUDANG
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
KEPALA TUKANG KAYU 0.01 OH Rp 136,800.00 Rp 1,368.00
TUKANG KAYU 0.1 OH Rp 107,400.00 Rp 10,740.00
BAHAN
KAYU ALBASIA 0.1 M³ Rp 1,884,020.00 Rp 188,402.00
5
TRIPLEKS 3MM 0.5 LBR Rp 52,260.00 Rp 26,130.00
SENG GELOMBANG BJLS 30 1.1 LBR Rp 58,830.00 Rp 64,713.00
SEMEN TIGA RODA 0.1 KG Rp 1,440.00 Rp 144.00
PAKU 4"-7" 0.25 KG Rp 19,010.00 Rp 4,752.50
JUMLAH Rp 297,239.50
KEUNTUNGAN (10%) Rp 29,723.95
HARGA SATUAN PEKERJAAN Rp 326,963.45
PEMBUATAN LOS KERJA
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
KEPALA TUKANG KAYU 0.01 OH Rp 136,800.00 Rp 1,368.00
TUKANG KAYU 0.1 OH Rp 107,400.00 Rp 10,740.00
BAHAN
KAYU ALBASIA 0.1 M³ Rp 1,884,020.00 Rp 188,402.00
6
TRIPLEKS 3MM 0.5 LBR Rp 52,260.00 Rp 26,130.00
SENG GELOMBANG BJLS 30 1.1 LBR Rp 58,830.00 Rp 64,713.00
SEMEN TIGA RODA 0.1 KG Rp 1,440.00 Rp 144.00
PAKU 4"-7" 0.25 KG Rp 19,010.00 Rp 4,752.50
JUMLAH Rp 297,239.50
KEUNTUNGAN (10%) Rp 29,723.95
HARGA SATUAN PEKERJAAN Rp 326,963.45
B PEKERJAAN TANAH
GALIAN TANAH PONDASI MENERUS
TENAGA
MANDOR 0.025 OH Rp 198,000.00 Rp 4,950.00
1 PEKERJA 0.75 OH Rp 85,500.00 Rp 64,125.00
JUMLAH Rp 69,075.00
KEUNTUNGAN (10%) Rp 6,907.50
HARGA SATUAN PEKERJAAN Rp 75,982.50
GALIAN TANAH PONDASI SETEMPAT
TENAGA
MANDOR 0.067 OH Rp 198,000.00 Rp 13,266.00
2 PEKERJA 1.05 OH Rp 85,500.00 Rp 89,775.00
JUMLAH Rp 103,041.00
KEUNTUNGAN (10%) Rp 10,304.10
HARGA SATUAN PEKERJAAN Rp 113,345.10
GALIAN TANAH PONDASI ROLLAG
TENAGA
MANDOR 0.025 OH Rp 198,000.00 Rp 4,950.00
3 PEKERJA 0.75 OH Rp 85,500.00 Rp 64,125.00
JUMLAH Rp 69,075.00
KEUNTUNGAN (10%) Rp 6,907.50
HARGA SATUAN PEKERJAAN Rp 75,982.50
URUGAN KEMBALI PONDASI
TENAGA
MANDOR 0.0083 OH Rp 198,000.00 Rp 1,643.40
4 PEKERJA 0.192 OH Rp 85,500.00 Rp 16,416.00
JUMLAH Rp 18,059.40
KEUNTUNGAN (10%) Rp 1,805.94
HARGA SATUAN PEKERJAAN Rp 19,865.34
URUGAN KEMBALI RUANGAN
TENAGA
MANDOR 0.025 OH Rp 198,000.00 Rp 4,950.00
PEKERJA 0.25 OH Rp 85,500.00 Rp 21,375.00
5 BAHAN
TANAH URUG 1 M³ Rp 106,420.00 Rp 106,420.00
JUMLAH Rp 132,745.00
KEUNTUNGAN (10%) Rp 13,274.50
HARGA SATUAN PEKERJAAN Rp 146,019.50
C PERHITUNGAN PONDASI
PEKERJAAN PASIR URUG
TENAGA
MANDOR 0.01 OH Rp 198,000.00 Rp 1,980.00
PEKERJA 0.3 OH Rp 85,500.00 Rp 25,650.00
1 BAHAN
PASIR URUG 1.2 M³ Rp 110,500.00 Rp 132,600.00
JUMLAH Rp 160,230.00
KEUNTUNGAN (10%) Rp 16,023.00
HARGA SATUAN PEKERJAAN Rp 176,253.00
PEKERJAAN AANSTAMPING
TENAGA

2
MANDOR 0.039 OH Rp 198,000.00 Rp 7,722.00
PEKERJA 0.78 OH Rp 85,500.00 Rp 66,690.00
KEPALA TUKANG BATU 0.039 OH Rp 133,200.00 Rp 5,194.80
TUKANG BATU 0.39 OH Rp 109,300.00 Rp 42,627.00
2
BAHAN
BATU BELAH 1.2 Rp 124,000.00 Rp 148,800.00
PASIR URUG 0.43 M³ Rp 110,500.00 Rp 47,515.00
JUMLAH Rp 318,769.80
KEUNTUNGAN (10%) Rp 31,876.98
HARGA SATUAN PEKERJAAN Rp 350,646.78
PEKERJAAN BATU KALI
TENAGA
MANDOR 0.075 OH Rp 198,000.00 Rp 14,850.00
PEKERJA 1.5 OH Rp 85,500.00 Rp 128,250.00
KEPALA TUKANG BATU 0.075 OH Rp 133,200.00 Rp 9,990.00
TUKANG BATU 0.75 OH Rp 109,300.00 Rp 81,975.00
3 BAHAN
BATU BELAH 1.2 Rp 124,000.00 Rp 148,800.00
PASIR PASANG 0.485 M³ Rp 149,000.00 Rp 72,265.00
SEMEN TIGA RODA 202 KG Rp 1,440.00 Rp 290,880.00
JUMLAH Rp 747,010.00
KEUNTUNGAN (10%) Rp 74,701.00
HARGA SATUAN PEKERJAAN Rp 821,711.00
PEKERJAAN FOOTPLAT
TENAGA
MANDOR 0.262 OH Rp 198,000.00 Rp 51,876.00
PEKERJA 5.3 OH Rp 85,500.00 Rp 453,150.00
KEPALA TUKANG BETON 0.262 OH Rp 133,200.00 Rp 34,898.40
TUKANG BESI BETON 0.275 OH Rp 105,500.00 Rp 29,012.50
TUKANG KAYU 1.3 OH Rp 107,400.00 Rp 139,620.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.2 M³ Rp 1,884,020.00 Rp 376,804.00
4
PAKU 8CM-12CM 1.5 KG Rp 19,010.00 Rp 28,515.00
KAWAT BETON 2.25 KG Rp 20,520.00 Rp 46,170.00
BESI BETON U-24 157.5 KG Rp 12,100.00 Rp 1,905,750.00
MINYAK BEKISTING 0.4 LTR Rp 18,230.00 Rp 7,292.00
SEMEN TIGA RODA 336 KG Rp 1,440.00 Rp 483,840.00
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
KORAL BETON 0.81 M³ Rp 163,650.00 Rp 132,556.50
JUMLAH Rp 3,827,201.30
KEUNTUNGAN (10%) Rp 382,720.13
HARGA SATUAN PEKERJAAN Rp 4,209,921.43
PEKERJAAN PEDESTAL
TENAGA
MANDOR 0.262 OH Rp 198,000.00 Rp 51,876.00
PEKERJA 5.3 OH Rp 85,500.00 Rp 453,150.00
KEPALA TUKANG BETON 0.262 OH Rp 133,200.00 Rp 34,898.40
TUKANG BESI BETON 0.275 OH Rp 105,500.00 Rp 29,012.50
TUKANG KAYU 1.3 OH Rp 107,400.00 Rp 139,620.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.2 M³ Rp 1,884,020.00 Rp 376,804.00
5
PAKU 8CM-12CM 1.5 KG Rp 19,010.00 Rp 28,515.00
KAWAT BETON 2.25 KG Rp 20,520.00 Rp 46,170.00
BESI BETON U-24 157.5 KG Rp 12,100.00 Rp 1,905,750.00
MINYAK BEKISTING 0.4 LTR Rp 18,230.00 Rp 7,292.00
SEMEN TIGA RODA 336 KG Rp 1,440.00 Rp 483,840.00
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
KORAL BETON 0.81 M³ Rp 163,650.00 Rp 132,556.50
JUMLAH Rp 3,827,201.30
KEUNTUNGAN (10%) Rp 382,720.13
HARGA SATUAN PEKERJAAN Rp 4,209,921.43
D PERHITUNGAN BETON
PEKERJAAN SLOOF BETON BERTULANG
TENAGA
MANDOR 0.283 OH Rp 198,000.00 Rp 56,034.00
PEKERJA 5.65 OH Rp 85,500.00 Rp 483,075.00
KEPALA TUKANG BETON 0.323 OH Rp 133,200.00 Rp 43,023.60
TUKANG BESI BETON 1.4 OH Rp 105,500.00 Rp 147,700.00
TUKANG KAYU 1.56 OH Rp 107,400.00 Rp 167,544.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.27 M³ Rp 1,884,020.00 Rp 508,685.40
1
PAKU 8CM-12CM 2 KG Rp 19,010.00 Rp 38,020.00
KAWAT BETON 3 KG Rp 20,520.00 Rp 61,560.00
BESI BETON U-24 210 KG Rp 12,100.00 Rp 2,541,000.00
MINYAK BEKISTING 0.6 LTR Rp 18,230.00 Rp 10,938.00
SEMEN TIGA RODA 6.72 ZAK Rp 1,440.00 Rp 9,676.80
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
KORAL BETON 0.81 M³ Rp 163,650.00 Rp 132,556.50
JUMLAH Rp 4,346,203.70
KEUNTUNGAN (10%) Rp 434,620.37
HARGA SATUAN PEKERJAAN Rp 4,780,824.07
PEKERJAAN KOLOM BETON BERTULANG
TENAGA
MANDOR 0.353 OH Rp 198,000.00 Rp 69,894.00
PEKERJA 7.05 OH Rp 85,500.00 Rp 602,775.00
KEPALA TUKANG BETON 0.403 OH Rp 133,200.00 Rp 53,679.60
TUKANG BESI BETON 2.1 OH Rp 105,500.00 Rp 221,550.00
TUKANG KAYU 1.65 OH Rp 107,400.00 Rp 177,210.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.4 M³ Rp 1,884,020.00 Rp 753,608.00
PAKU 8CM-12CM 4 KG Rp 19,010.00 Rp 76,040.00
2
KAWAT BETON 4.5 KG Rp 20,520.00 Rp 92,340.00
BESI BETON U-24 315 KG Rp 12,100.00 Rp 3,811,500.00
MINYAK BEKISTING 2 LTR Rp 18,230.00 Rp 36,460.00
PORTLAND CEMENT 6.72 ZAK Rp 1,440.00 Rp 9,676.80
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
KORAL BETON 0.81 M³ Rp 163,650.00 Rp 132,556.50
MULTIPLEKS 9MM 120X240 3.5 LBR Rp 151,930.00 Rp 531,755.00
DOLKEN 8-10 20 BTG Rp 32,700.00 Rp 654,000.00
JUMLAH Rp 8,117,281.50
KEUNTUNGAN (10%) Rp 811,728.15
HARGA SATUAN PEKERJAAN Rp 8,929,009.65
PEKERJAAN BALOK BETON BERTULANG
TENAGA
MANDOR 0.318 OH Rp 198,000.00 Rp 62,964.00
PEKERJA 6.35 OH Rp 85,500.00 Rp 542,925.00
KEPALA TUKANG BETON 0.333 OH Rp 133,200.00 Rp 44,355.60
TUKANG BESI BETON 1.4 OH Rp 105,500.00 Rp 147,700.00
TUKANG KAYU 1.65 OH Rp 107,400.00 Rp 177,210.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.32 M³ Rp 1,884,020.00 Rp 602,886.40
PAKU 8CM-12CM 3.2 KG Rp 19,010.00 Rp 60,832.00
3 KAWAT BETON 3 KG Rp 20,520.00 Rp 61,560.00
BESI BETON U-24 210 KG Rp 12,100.00 Rp 2,541,000.00
MINYAK BEKISTING 1.6 LTR Rp 18,230.00 Rp 29,168.00
PORTLAND CEMENT 6.72 ZAK Rp 1,440.00 Rp 9,676.80
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
BATU PECAH MESIN 2/3 0.81 M³ Rp 215,000.00 Rp 174,150.00
KAYU BALOK BORNEO SUPER 0.14 M³ Rp 4,922,770.00 Rp 689,187.80
MULTIPLEKS 9MM 120X240 3.5 LBR Rp 151,930.00 Rp 531,755.00
DOLKEN 8-10 20 BTG Rp 32,700.00 Rp 654,000.00
JUMLAH Rp 6,247,956.70
KEUNTUNGAN (10%) Rp 624,795.67
HARGA SATUAN PEKERJAAN Rp 6,872,752.37
PEKERJAAN PLAT BETON BERTULANG
TENAGA
MANDOR 0.265 OH Rp 198,000.00 Rp 52,470.00
PEKERJA 5.3 OH Rp 85,500.00 Rp 453,150.00
KEPALA TUKANG BETON 0.265 OH Rp 133,200.00 Rp 35,298.00
TUKANG BESI BETON 1.05 OH Rp 105,500.00 Rp 110,775.00
TUKANG KAYU 1.3 OH Rp 107,400.00 Rp 139,620.00
TUKANG BATU 0.275 OH Rp 109,300.00 Rp 30,057.50
BAHAN
KAYU ALBASIA 0.32 M³ Rp 1,884,020.00 Rp 602,886.40
PAKU 8CM-12CM 3.2 KG Rp 19,010.00 Rp 60,832.00
4 KAWAT BETON 2.25 KG Rp 20,520.00 Rp 46,170.00
BESI BETON U-24 157.5 KG Rp 12,100.00 Rp 1,905,750.00
MINYAK BEKISTING 1.6 LTR Rp 18,230.00 Rp 29,168.00
PORTLAND CEMENT 6.72 ZAK Rp 1,440.00 Rp 9,676.80
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
BATU PECAH MESIN 2/3 0.81 M³ Rp 215,000.00 Rp 174,150.00
KAYU BALOK BORNEO SUPER 0.12 M³ Rp 4,922,770.00 Rp 590,732.40
MULTIPLEKS 9MM 120X240 2.8 LBR Rp 151,930.00 Rp 425,404.00
DOLKEN 8-10 32 BTG Rp 32,700.00 Rp 1,046,400.00
JUMLAH Rp 5,838,138.10
KEUNTUNGAN (10%) Rp 583,813.81
HARGA SATUAN PEKERJAAN Rp 6,421,951.91
PEKERJAAN RINGBALK BERTULANG
TENAGA
MANDOR 0.015 OH Rp 198,000.00 Rp 2,970.00
PEKERJA 0.297 OH Rp 85,500.00 Rp 25,393.50
KEPALA TUKANG BETON 0.01 OH Rp 105,500.00 Rp 1,055.00
TUKANG BESI BETON 0.033 OH Rp 105,500.00 Rp 3,481.50
TUKANG KAYU 0.033 OH Rp 107,400.00 Rp 3,544.20
TUKANG BATU 0.033 OH Rp 109,300.00 Rp 3,606.90
BAHAN
5 KAYU ALBASIA 0.003 M³ Rp 1,884,020.00 Rp 5,652.06
PAKU 4CM-7CM 0.02 KG Rp 19,010.00 Rp 380.20
KAWAT BETON 0.05 KG Rp 20,520.00 Rp 1,026.00
BESI BETON U-24 3.6 KG Rp 12,100.00 Rp 43,560.00
SEMEN PC TIGA RODA 0.11 ZAK Rp 1,440.00 Rp 158.40
PASIR BETON 0.009 M³ Rp 232,000.00 Rp 2,088.00
BATU PECAH MESIN 2/3 0.015 M³ Rp 215,000.00 Rp 3,225.00
JUMLAH Rp 96,140.76
KEUNTUNGAN (10%) Rp 9,614.08
HARGA SATUAN PEKERJAAN Rp 105,754.84
E PEKERJAAN KUSEN
PEMBUATAN DAN PEMASANGAN KUSEN PINTU DAN JENDELA
TENAGA
MANDOR 0.04 OH Rp 198,000.00 Rp 7,920.00
PEKERJA 0.8 OH Rp 85,500.00 Rp 68,400.00
TUKANG KAYU 2 OH Rp 107,400.00 Rp 214,800.00
KEPALA TUKANG KAYU 0.2 OH Rp 136,800.00 Rp 27,360.00
1 BAHAN
BALOK KAYU 1.1 OH Rp 4,922,770.00 Rp 5,415,047.00
PAKU 10 CM 1.25 M³ Rp 17,210.00 Rp 21,512.50
LEM KAYU 1 M³ Rp 21,270.00 Rp 21,270.00
JUMLAH Rp 5,776,309.00
KEUNTUNGAN (10%) Rp 577,630.95
HARGA SATUAN PEKERJAAN Rp 6,353,940.45
PEMBUATAN DAN PEMASANGAN DAUN PINTU DAN JENDELA
TENAGA
MANDOR 0.05 OH Rp 198,000.00 Rp 9,900.00
PEKERJA 1 OH Rp 85,500.00 Rp 85,500.00

2
TUKANG KAYU 3 OH Rp 107,400.00 Rp 322,200.00
KEPALA TUKANG KAYU 0.3 OH Rp 136,800.00 Rp 41,040.00
2
BAHAN
PAPAN KAYU 0.04 OH Rp 5,687,430.00 Rp 227,497.20
LEM KAYU 0.5 M³ Rp 21,270.00 Rp 10,635.00
JUMLAH Rp 696,772.20
KEUNTUNGAN (10%) Rp 69,677.22
HARGA SATUAN PEKERJAAN Rp 766,449.42
F PEKERJAAN DINDING
PEMASANGAN DINDING BATA MERAH
TENAGA
MANDOR 0.01 OH Rp 198,000.00 Rp 1,980.00
PEKERJA 0.3 OH Rp 85,500.00 Rp 25,650.00
TUKANG BATU 0.2 OH Rp 109,300.00 Rp 21,860.00
KEPALA TUKANG 0.01 OH Rp 133,200.00 Rp 1,332.00
1 BAHAN
BATA MERAH 0.04 OH Rp 5,687,430.00 Rp 227,497.20
PORTLAND CEMENT 0.1936 ZAK Rp 1,440.00 Rp 278.78
PASIR PASANG 0.045 M³ Rp 149,000.00 Rp 6,705.00
JUMLAH Rp 108,205.78
KEUNTUNGAN (10%) Rp 108,205.78
HARGA SATUAN PEKERJAAN Rp 119,026.36
PEMASANGAN PLESTERAN
TENAGA
MANDOR 0.01 OH Rp 198,000.00 Rp 1,980.00
PEKERJA 0.3 OH Rp 85,500.00 Rp 25,650.00
TUKANG BATU 0.15 OH Rp 109,300.00 Rp 16,395.00
KEPALA TUKANG 0.01 OH Rp 133,200.00 Rp 1,332.00
2
BAHAN
PORTLAND CEMENT 0.12 ZAK Rp 1,440.00 Rp 172.80
PASIR PASANG 0.02 M³ Rp 149,000.00 Rp 2,980.00
JUMLAH Rp 49,841.80
KEUNTUNGAN (10%) Rp 4,984.18
HARGA SATUAN PEKERJAAN Rp 54,825.98
PEMASANGAN ACIAN
TENAGA
MANDOR 0.01 OH Rp 198,000.00 Rp 1,980.00
PEKERJA 0.2 OH Rp 85,500.00 Rp 17,100.00
TUKANG BATU 0.1 OH Rp 109,300.00 Rp 10,930.00
3 KEPALA TUKANG 0.01 OH Rp 133,200.00 Rp 1,332.00
BAHAN
PORTLAND CEMENT 0.065 ZAK Rp 1,440.00 Rp 93.60
JUMLAH Rp 31,435.60
KEUNTUNGAN (10%) Rp 3,143.56
HARGA SATUAN PEKERJAAN Rp 34,579.16
G PEKERJAAN PENUTUP LANTAI
PEMASANGAN KERAMIK 40X40
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
PEKERJA 0.09 OH Rp 85,500.00 Rp 7,695.00
TUKANG BATU 0.09 OH Rp 109,300.00 Rp 9,837.00
1 KEPALA TUKANG 0.009 OH Rp 133,200.00 Rp 1,198.80
BAHAN
KERAMIK 40X40 HALUS 3.53 M³ Rp 47,500.00 Rp 167,675.00
JUMLAH Rp 187,395.80
KEUNTUNGAN (10%) Rp 18,739.58
HARGA SATUAN PEKERJAAN Rp 206,135.38
PEKERJAAN KERAMIK 20X20
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
PEKERJA 0.09 OH Rp 85,500.00 Rp 7,695.00
TUKANG BATU 0.09 OH Rp 109,300.00 Rp 9,837.00
2
2 KEPALA TUKANG 0.009 OH Rp 133,200.00 Rp 1,198.80
BAHAN
KERAMIK 20X20 3.53 M³ Rp 29,500.00 Rp 104,135.00
JUMLAH Rp 123,855.80
KEUNTUNGAN (10%) Rp 12,385.58
HARGA SATUAN PEKERJAAN Rp 136,241.38
H PEKERJAAN PLAFOND
PEMASANGAN RANGKA PLAFOND
TENAGA
MANDOR 0.0135 OH Rp 198,000.00 Rp 2,673.00
PEKERJA 0.27 OH Rp 85,500.00 Rp 23,085.00
TUKANG KAYU 0.13 OH Rp 107,400.00 Rp 13,962.00
KEPALA TUKANG 0.013 OH Rp 136,800.00 Rp 1,778.40
1
BAHAN
PAKU 7-10 0.25 KG 19010 Rp 4,752.50
KASO-KASO 0.0163 M³ Rp 5,687,430.00 Rp 92,705.11
JUMLAH Rp 138,956.01
KEUNTUNGAN (10%) Rp 13,895.60
HARGA SATUAN PEKERJAAN Rp 152,851.61
PEMASANGAN LANGIT-LANGIT GYPSUM BOARD
TENAGA
MANDOR 0.005 OH Rp 198,000.00 Rp 990.00
PEKERJA 0.1 OH Rp 85,500.00 Rp 8,550.00
TUKANG KAYU 0.05 OH Rp 107,400.00 Rp 5,370.00
KEPALA TUKANG 0.005 OH Rp 136,800.00 Rp 684.00
2
BAHAN
GYPSUM UK 120 X 240 0.364 LBR Rp 70,860.00 Rp 25,793.04
PAKU SEKRUP 0.11 BOX Rp 13,530.00 Rp 1,488.30
JUMLAH Rp 42,875.34
KEUNTUNGAN (10%) Rp 4,287.53
HARGA SATUAN PEKERJAAN Rp 47,162.87
I PEKERJAAN TANGGA
PEMBUATAN BETON BERTULANG
TENAGA
MANDOR 1 OH Rp 198,000.00 Rp 198,000.00
PEKERJA 2 OH Rp 85,500.00 Rp 171,000.00
TUKANG BATU 0.35 OH Rp 109,300.00 Rp 38,255.00
KEPALA TUKANG 0.035 OH Rp 133,200.00 Rp 4,662.00
1 BAHAN
PASIR BETON 0.54 M³ Rp 232,000.00 Rp 125,280.00
PORTLAND CEMENT 6.72 ZAK Rp 1,440.00 Rp 9,676.80
KORAL BETON 0.81 M³ Rp 163,650.00 Rp 132,556.50
JUMLAH Rp 679,430.30
KEUNTUNGAN (10%) Rp 67,943.03
HARGA SATUAN PEKERJAAN Rp 747,373.33
J PEKERJAAN ATAP
PEKERJAAN PENUTUP ATAP
TENAGA
MANDOR 0.001 OH Rp 198,000.00 Rp 198.00
PEKERJA 0.104 OH Rp 85,500.00 Rp 8,892.00
TUKANG KAYU 0.092 OH Rp 107,400.00 Rp 9,880.80
1 KEPALA TUKANG 0.012 OH Rp 136,800.00 Rp 1,641.60
BAHAN
GENTING METAL 1 M³ Rp 121,000.00 Rp 121,000.00
JUMLAH Rp 141,612.40
KEUNTUNGAN (10%) Rp 14,161.24
HARGA SATUAN PEKERJAAN Rp 155,773.64
PEKERJAAN RANGKA PENUTUP ATAP
BAHAN
KUDA-KUDA 1 M³ Rp 226,980.00 Rp 226,980.00
TENAGA
2
UPAH PASANG 1.25 OH Rp 5,000.00 Rp 6,250.00
2

JUMLAH Rp 233,230.00
KEUNTUNGAN (10%) Rp 23,323.00
HARGA SATUAN PEKERJAAN Rp 256,553.00
K PEKERJAAN PENGECETAN
PEKERJAAN CAT DINDING
TENAGA
MANDOR 0.0025 OH Rp 198,000.00 Rp 495.00
PEKERJA 0.02 OH Rp 85,500.00 Rp 1,710.00
TUKANG CAT 0.063 OH Rp 76,300.00 Rp 4,806.90
KEPALA TUKANG 0.0063 OH Rp 130,800.00 Rp 824.04
1 BAHAN
CAT DASAR 1 M³ Rp 121,000.00 Rp 121,000.00
CAT PENUTUP 0.35 KG Rp 55,250.00 Rp 19,337.50
PLAMIR 0.1 KG Rp 16,570.00 Rp 1,657.00
JUMLAH Rp 43,783.94
KEUNTUNGAN (10%) Rp 4,378.39
HARGA SATUAN PEKERJAAN Rp 48,162.33
PEKERJAAN CAT KAYU
TENAGA
MANDOR 0.0025 OH Rp 198,000.00 Rp 495.00
PEKERJA 0.07 OH Rp 85,500.00 Rp 5,985.00
TUKANG CAT 0.105 OH Rp 76,300.00 Rp 8,011.50
KEPALA TUKANG 0.004 OH Rp 130,800.00 Rp 523.20
BAHAN
2
CAT DASAR 0.17 KG Rp 121,000.00 Rp 20,570.00
CAT MENI 0.2 KG Rp 68,000.00 Rp 13,600.00
CAT PENUTUP 0.35 KG Rp 55,250.00 Rp 19,337.50
PLAMIR 0.15 KG Rp 16,570.00 Rp 2,485.50
JUMLAH Rp 53,276.67
KEUNTUNGAN (10%) Rp 5,327.67
HARGA SATUAN PEKERJAAN Rp 58,604.37
L PEKERJAAN MEP
PEKERJAAN INSTALASI LAMPU
TENAGA
PEKERJA 0.03 OH Rp 85,500.00 Rp 2,565.00
TUKANG LISTRIK 0.3 OH Rp 73,500.00 Rp 22,050.00
BAHAN
NYM 3x2,5 8.931 M³ Rp 11,550.00 Rp 103,153.05
1 SOLATIF 0.333 ROLL Rp 18,900.00 Rp 6,293.70
PIPA KABEL 1.5 BTG Rp 11,000.00 Rp 16,500.00
T-DOOS 1 BH Rp 12,500.00 Rp 12,500.00
INBOW-DOOS 1 BH Rp 3,500.00 Rp 3,500.00
JUMLAH Rp 166,561.75
KEUNTUNGAN (10%) Rp 16,656.18
HARGA SATUAN PEKERJAAN Rp 183,217.93
MEMASANG INSTALASI STOP KONTAK
TENAGA
PEKERJA 0.03 OH Rp 85,500.00 Rp 2,565.00
TUKANG LISTRIK 0.3 OH Rp 73,500.00 Rp 22,050.00
BAHAN
NYM 3x2,5 10.35 M³ Rp 11,550.00 Rp 119,542.50
2 SOLATIF 0.333 ROLL Rp 18,900.00 Rp 6,293.70
PIPA KABEL 1.5 BTG Rp 11,000.00 Rp 16,500.00
T-DOOS 1 BH Rp 12,500.00 Rp 12,500.00
INBOW-DOOS 1 BH Rp 3,500.00 Rp 3,500.00
JUMLAH Rp 182,951.20
KEUNTUNGAN (10%) Rp 18,295.12
HARGA SATUAN PEKERJAAN Rp 201,246.32
MEMASANG INSTALASI SAKLAR TUNGGAL
TENAGA
PEKERJA 0.001 OH Rp 85,500.00 Rp 85.50
TUKANG LISTRIK 0.02 OH Rp 73,500.00 Rp 1,470.00
3
BAHAN
3
SAKLAR TUNGGAL 1 BH Rp 11,700.00 Rp 11,700.00
PERLENGKAPAN 0.1 LS Rp 5,000.00 Rp 500.00
JUMLAH Rp 13,755.50
KEUNTUNGAN (10%) Rp 1,375.55
HARGA SATUAN PEKERJAAN Rp 15,131.05
MEMASANG INSTALASI SAKLAR GANDA
TENAGA
PEKERJA 0.001 OH Rp 85,500.00 Rp 85.50
TUKANG LISTRIK 0.02 OH Rp 73,500.00 Rp 1,470.00
BAHAN
4
SAKLAR GANDA 1 BH Rp 21,000.00 Rp 21,000.00
PERLENGKAPAN 0.1 LS Rp 5,000.00 Rp 500.00
JUMLAH Rp 23,055.50
KEUNTUNGAN (10%) Rp 2,305.55
HARGA SATUAN PEKERJAAN Rp 25,361.05
PEKERJAAN INSTALASI KLOSET DUDUK
TENAGA
PEKERJA 1 OH Rp 85,500.00 Rp 85,500.00
MANDOR 0.16 OH Rp 198,000.00 Rp 31,680.00
KEPALA TUKANG 1.5 OH Rp 133,200.00 Rp 199,800.00
TUKANG PIPA 1.5 OH Rp 109,300.00 Rp 163,950.00
5 BAHAN
KLOSET DUDUK 1 BH Rp 1,373,880.00 Rp 1,373,880.00
PORTLAND CEMENT 6 KG Rp 1,440.00 Rp 8,640.00
PASIR PASANG 0.01 M³ Rp 149,000.00 Rp 1,490.00
JUMLAH Rp 1,864,940.00
KEUNTUNGAN (10%) Rp 186,494.00
HARGA SATUAN PEKERJAAN Rp 2,051,434.00
PEKERJAAN INSTALASI KERAN AIR
TENAGA
PEKERJA 1 OH Rp 85,500.00 Rp 85,500.00
MANDOR 0.16 OH Rp 198,000.00 Rp 31,680.00
KEPALA TUKANG 1.5 OH Rp 133,200.00 Rp 199,800.00
TUKANG PIPA 1.5 OH Rp 109,300.00 Rp 163,950.00
5
BAHAN
KERAN AIR 1 BH Rp 93,590.00 Rp 93,590.00
SEAL TAPE 0.025 BH Rp 1,250.00 Rp 31.25
JUMLAH Rp 574,551.25
KEUNTUNGAN (10%) Rp 57,455.13
HARGA SATUAN PEKERJAAN Rp 632,006.38
PEKERJAAN INSTALASI FLOOR DRAIN
TENAGA
PEKERJA 1 OH Rp 85,500.00 Rp 85,500.00
MANDOR 0.16 OH Rp 198,000.00 Rp 31,680.00
KEPALA TUKANG 1.5 OH Rp 133,200.00 Rp 199,800.00
TUKANG PIPA 1.5 OH Rp 109,300.00 Rp 163,950.00
5 BAHAN
FLOOR DRAIN 1 BH Rp 218,790.00 Rp 218,790.00
PORTLAND CEMENT 6 ZAK Rp 1,440.00 Rp 8,640.00
PASIR PASANG 0.01 M³ Rp 149,000.00 Rp 1,490.00
JUMLAH Rp 692,570.00
KEUNTUNGAN (10%) Rp 69,257.00
HARGA SATUAN PEKERJAAN Rp 761,827.00
PEKERJAAN INSTALASI PIPA PVC 1/2"
TENAGA
PEKERJA 0.036 OH Rp 85,500.00 Rp 3,078.00
MANDOR 0.0018 OH Rp 198,000.00 Rp 356.40
KEPALA TUKANG 0.006 OH Rp 133,200.00 Rp 799.20
TUKANG PIPA 0.06 OH Rp 109,300.00 Rp 6,558.00
5
BAHAN
PIPA PVC 1.2 M Rp 21,910.00 Rp 26,292.00
5

PERLENGKAPAN 0.35 Rp 7,668.50 Rp 2,683.98


JUMLAH Rp 39,394.38
KEUNTUNGAN (10%) Rp 3,939.44
HARGA SATUAN PEKERJAAN Rp 43,333.81
PEKERJAAN INSTALASI PIPA PVC 3"
TENAGA
PEKERJA 0.081 OH Rp 85,500.00 Rp 6,925.50
MANDOR 0.0041 OH Rp 198,000.00 Rp 811.80
KEPALA TUKANG 0.0135 OH Rp 133,200.00 Rp 1,798.20
TUKANG PIPA 0.135 OH Rp 109,300.00 Rp 14,755.50
5
BAHAN
PIPA PVC 1.2 M Rp 165,380.00 Rp 198,456.00
PERLENGKAPAN 0.35 Rp 57,883.00 Rp 20,259.05
JUMLAH Rp 242,166.35
KEUNTUNGAN (10%) Rp 24,216.64
HARGA SATUAN PEKERJAAN Rp 266,382.99
PEKERJAAN INSTALASI PIPA PVC 4"
TENAGA
PEKERJA 0.081 OH Rp 85,500.00 Rp 6,925.50
MANDOR 0.0041 OH Rp 198,000.00 Rp 811.80
KEPALA TUKANG 0.0135 OH Rp 133,200.00 Rp 1,798.20
TUKANG PIPA 0.135 OH Rp 109,300.00 Rp 14,755.50
5
BAHAN
PIPA PVC 1.2 M Rp 236,100.00 Rp 283,320.00
PERLENGKAPAN 0.35 Rp 57,883.00 Rp 20,259.05
JUMLAH Rp 335,693.55
KEUNTUNGAN (10%) Rp 33,569.36
HARGA SATUAN PEKERJAAN Rp 369,262.91
PEKERJAAN INSTALASI PIPA PVC 3/4"
TENAGA
PEKERJA 0.081 OH Rp 85,500.00 Rp 6,925.50
MANDOR 0.0041 OH Rp 198,000.00 Rp 811.80
KEPALA TUKANG 0.0135 OH Rp 133,200.00 Rp 1,798.20
TUKANG PIPA 0.135 OH Rp 109,300.00 Rp 14,755.50
6
BAHAN
PIPA PVC 1.2 M Rp 40,600.00 Rp 48,720.00
PERLENGKAPAN 0.35 Rp 57,883.00 Rp 20,259.05
JUMLAH Rp 93,270.05
KEUNTUNGAN (10%) Rp 9,327.00
HARGA SATUAN PEKERJAAN Rp 102,597.05
PEKERJAAN INSTALASI WASTAFEL
TENAGA
PEKERJA 0.03 OH Rp 85,500.00 Rp 2,565.00
MANDOR 0.0015 OH Rp 198,000.00 Rp 297.00
KEPALA TUKANG 0.03 OH Rp 133,200.00 Rp 3,996.00
TUKANG PIPA 0.3 OH Rp 109,300.00 Rp 32,790.00
6
BAHAN
WASTAFEL 1 BH Rp 386,750.00 Rp 386,750.00
WATERDRAIN 0.12 BH Rp 386,750.00 Rp 46,410.00
JUMLAH Rp 472,808.00
KEUNTUNGAN (10%) Rp 47,280.80
HARGA SATUAN PEKERJAAN Rp 520,088.80
M PEKERJAAN AKSESORIS
PEMASANGAN ENGSEL PINTU
TENAGA
PEKERJA 0.015 OH Rp 85,500.00 Rp 1,282.50
MANDOR 0.0008 OH Rp 198,000.00 Rp 158.40
KEPALA TUKANG 0.015 OH Rp 130,800.00 Rp 1,962.00
1 TUKANG 0.15 OH Rp 76,300.00 Rp 11,445.00
BAHAN
ENGSEL PINTU 1 BH Rp 68,000.00 Rp 68,000.00
JUMLAH Rp 82,838.00
1

KEUNTUNGAN (10%) Rp 8,283.80


HARGA SATUAN PEKERJAAN Rp 91,121.80
PEMASANGAN ENGSEL JENDELA
TENAGA
PEKERJA 0.01 OH Rp 85,500.00 Rp 855.00
MANDOR 0.0005 OH Rp 198,000.00 Rp 99.00
KEPALA TUKANG 0.01 OH Rp 130,800.00 Rp 1,308.00
2 TUKANG 0.1 OH Rp 76,300.00 Rp 7,630.00
BAHAN
ENGSEL JENDELA 1 BH Rp 48,000.00 Rp 48,000.00
JUMLAH Rp 57,892.00
KEUNTUNGAN (10%) Rp 5,789.20
HARGA SATUAN PEKERJAAN Rp 63,681.20
PEMASANGAN KACA
TENAGA
PEKERJA 0.015 OH Rp 85,500.00 Rp 1,282.50
MANDOR 0.0008 OH Rp 198,000.00 Rp 158.40
KEPALA TUKANG 0.015 OH Rp 136,800.00 Rp 2,052.00
3 TUKANG 0.15 OH Rp 107,400.00 Rp 16,110.00
BAHAN
KACA 1.1 M² Rp 133,700.00 Rp 147,070.00
JUMLAH Rp 166,663.00
KEUNTUNGAN (10%) Rp 16,666.30
HARGA SATUAN PEKERJAAN Rp 183,329.30
PERHITUNGAN PEKERJAAN

GAMBAR URAIAN PEKERJAAN PERHITUNGAN VOL SAT


PEKERJAAN PERSIAPAN
PENGUKURAN LAHAN P x L = 18 x 10 180 M²
PEMBERSIHAN LAHAN P x L = 18 x 10 180 M²
PEMASANGAN BOWPLANK K = 2 (10 + 10) 40 LS
PEMASANGAN PAPAN PROYEK KERTAS A1 1 LBR
PEMBUATAN DIREKSI KEET PXL=4x4 16 M²
PEMBUATAN GUDANG PxL=4x3 12 M²
PEMBUATAN LOS KERJA PxL=4x3 12 M²
AIR KERJA 13 L/hari 390 L
LISTRIK KERJA 15 kwh/hari 450 KWH
PEKERJAAN TANAH
GALIAN TANAH PONDASI
BATU KALI

P1 = (1+0,8)/2 x 0,7 x 8 5.04 M³


P2 = (1,4+0,9)/2 x 0,7 x 38,75 31.2 M³
P3 = (0,9+0,6)/2 0,5 x 48 18 M³
SETEMPAT

P1 = 0,5 x 0,5 x 1,3 x 27 8.7 M³


P2 = 0,7 x 0,7 x 1,3 x 5 3.1 M³
P3 = 1 x 1 x 1,3 x 5 6.5 M³
P4 = 1 x 0,75 x 1,3 0.975 M³

ROLLAG

TERAS = 0,15 x 0,3 x 8 0.36 M³


URUGAN TANAH KEMBALI BATU KALI
P1 = (0,25 x 0,7)/2 x 0,7 x 8 2.38 M³
P2 = (0,3 + 0,7)/2 x 0,7 x 38,75 17.7 M³
P3 = (0,25 + 0,5)/2 x 0,5 x 48 9 M³
RUANGAN
DAPUR = 3 x 1,05 x 0,25 0.78 M³
R. MAKAN = 2 x 4 x 0,25 2 M³
R. KELUARGA = 5 x 2 x 0,25 2.5 M³
R. TAMU = 2 x 3 x 0,25 1.5 M³
R. TIDUR I = 3 x 4 x 0,25 3 M³
R. TIDUR II = 3 x 3 x 0,25 2.25 M³
TERAS = 3 x 1 x 0,23 0.69 M³
WC = 2 x 2 x 0,05 0.2 M³
TAMAN I = 5 x 10 x 0,05 2.5 M³
TAMAN II = 62, 0,05 3.1 M³
PERHITUNGAN PONDASI
PONDASI MENERUS
PONDASI 1 Pasir = 0,05 x 0,8 x 8 0.32 M³
Aanstamping = 0,1 x 0,8 x8 0.64 M³
Batu = (0,25+0,7)/2 x 0,7 x 8 2.66 M³
PONDASI 2 Pasir = 0,05 x 0,9 x 38,75 1.74 M³
Aanstamping = 0,1x0,9x38,75 3.48 M³
Batu = (0,7+0,7)/2 x0,7x38,75 13.5 M³
PONDASI 3 Pasir = 0,05 x 0,6 x 48 1.44 M³
Aanstamping = 0,1x0,9x38,75 3.48 M³
Batu = (0,25+0,5)/2x0,5x48 9 M³
PONDASI TELAPAK
PONDASI 1 Pasir = 0,05 x 0,4 x 0,4 x 27 0.216 M³
Pondasi = 0,14x0,4x0x4x27 0.6 M³
Pedestal = 0,13x0,13x1,16x27 0.52 M³
PONDASI 2 Pasir = 0,05x0,6x0,6x5 0.09 M³
Pondasi = 0,18x0,6x0,6x5 0.32 M³
Pedestal = 0,13x0,25x1,12x5 0.18 M³
PONDASI 3 Pasir = 0,05x0,8x0,8x5 0.16 M³
Pondasi = 0,25x0,8x0,8x5 0.8 M³
Pedestal = 0,13x0,3x1,05x5 0.2 M³
PONDASI 4 Pasir = 0,05x0,8x0,65x1 0.026 M³
Pondasi = 0,25x0,65x0,8x1 0.13 M³
Pedestal = 0,13x0,3x1,05x1 0.04 M³
PEKERJAAN BETON
SLOOF S1 = 0,15 x 0,2 x 46 1.38 M³
S2 = 0,15 x 0,15 x 48 1.08 M³
KOLOM LT 1 KP = 0,15 x 0,15 x 3 x 27 1.82 M³
K1 = 0,15 x 0,3 x 3 x 4 0.54 M³
K2 = 0,3 x 0,3 x 3 x 5 1.35 M³
KOLOM LT 2 KP = 0,15 x 0,15 x 3 x 13 0.87 M³
BALOK 0,15 x 0,2 x 26,5 0.79 M³
PLAT LANTAI 29 x 0,12 3.48 M³
RINGBALK LT 1 = 0,15 x 0,15 x 31 0.69 M³
LT 2 = 0,15 x 0,15 x 24 0.54 M³
AMPIG LT 1 = 0,1 x 0,1 x 6,6 0.06 M³
LT 2 = 0,1 x 0,1 x 8 0.08 M³
PEKERJAAN BUKAAN & KUSEN
PINTU 1 Bukaan = 2,15 x 1 x (2 buah) 4.3 M²
Panjang Kusen (2,15 x 2) + 1 x (2
buah) 10.6 M

PINTU 2 Bukaan = 2,15 x 0,9 x (5 buah) 9.675 M²


Panjang Kusen (2,15 x 2) + 0,9 x (5
buah) 27.04 M

PINTU 3 Bukaan 2,15 x 0,8 x 2 (buah) 3.44 M²


Panjang Kusen = (2,15 x 2) + 0,8 x
(2 buah) 10.2 M

JENDELA 1 Bukaan = 1,15 x 1 1.15 M²


Panjang Kusen = (1,15 x 2) + (1 x
4) 6.3 M
JENDELA 2 Bukaan = 1,75 x 0,6 x 2 (buah) 2.1 M²
Panjang Kusen = (1,75x2) + (0,6x2)
x 2 (buah) 9.4 M

JENDELA 3 Bukaan = 0,5 x 1,5 0.75 M²


Panjang Kusen = (0,5 x 3) +1,5x2)
4.5 M

JENDELA 4 Bukaan = 1,75 x 1,35 x 2(buah) 4.72 M²


Panjang Kusen = (1,75x4) +
(1,35x2) x 2(buah) 19.4 M

JENDELA 5 Bukaan = 2,35 x 1,55 x 2 (buah) 7.28 M²


Panjang Kusen (2,35x3) + (1,55x4)
x 2(buah) 26.5 M

JENDELA 6 Bukaan = 2,65 x 1,55 4.1 M²


Panjang Kusen = (2,65 x 4) + (1,55
x 3)
15.25 M

JENDELA 7 Bukaan = 0,6 x 0,6 x 3 (buah) 1.08 M²


Panjang Kusen = 0,6 x 4 x 3(buah)
7.2 M

JENDELA 8 Bukaan = 0,3 x 1,55 0.465 M²


Panjang Kusen = (0,3x4) + (1,55x2)
4.3 M

BV1 Bukaan = 0,3 x 0,55 0.165 M²

1.7 M
Panjang Kusen = (0,3x2) + (0,55x2)
BV2 Bukaan = 0,6 x 0,55 0.33 M²

2.3 M
Panjang Kusen = (0,6x2) + (0,55x2)
PEKERJAAN DINDING
DINDING LT.1 PxL
50,75 x 3,3 = 167,475
239.56 M
DINDING LT.2 PxL
32,5 x 3,3 = 107,25
PEKERJAAN PLAFOND
GYPSUM BOARD 9mm 105.91 M²
GRC 3mm 6.7 M²
LIST PLAFOND
172.9 M
PEKERJAAN LANTAI
KERAMIK 40x40 (HALUS) 66.48 M²
KERAMIK 40x40 (KASAR) 6.4 M²
KERAMIK 20X20 (KASAR) 4.16 M²
PEARLSTONE 3.1 M²
PEKERJAAN TANGGA
Panjang Anak Tangga
Anak Tangga
Lebar Pijak x Tinggi x Jumlah Anak
Tangga 9.18 M²
(0,3+0,21) x 18
Bordes
Panjang Bordes x (Lebar Bordes +
tinggi bordes dari satu anak M²
tangga sebelumnya)
2 x (1,1 + 0,21) 2.62
Total Panjang Anak Tangga 9,18 + 2,62 11.8 M²
Volume Anak Tangga (1/2 x (Lebar Pijakan Tangga +
tinggi anak tangga) x jumlah anak
tangga 4.59 M³

(1/2 x (0,3 + 2,1) x 18


Volume Plat Tangga
Lebar anak tangga x panjang anak
tangga x lebar plat 0.751 M³
0,9 x 6,96 x 0,12
PEKERJAAN ATAP
Penutup Atap
Penutup Atap Lt.1 29.6 M²
Penutup Atap Lt.2 64.68 M²
Bubungan Atap 10.48 M
155.84
Papan Ruiter 10.48 M
Talang Air Tengah 4.2 M
LIstplank 36.4 M
Rangka Atap 155.84 155.84 M²
Kuda-Kuda Atap
Tiang kuda-kuda 0,12 x 0,08 x 1,84 x 2 0.0353
0,12 x 0,08 x 1,44 x 3 0.0415
Balok kuda-kuda 0,12 x 0,8 x 2,85 x 4 0.1094
0,12 x 0,08 x 2 x 5 0.096
Balok sokong tegak 0,12 x 0,08 x 0,75 x 4 0.0288
0,12 x 0,08 x 0,56 x 5 0.0108
Balok sokong miring 0,12 x 0,08 x 1,2 x 4 0.023
0,12 x 0,08 x 0,8 x 5 0.0461
Balok Tarik 0,12 x 0,08 x 5,14 x 2 0.0987
0,12 x 0,08 x 4 x 2 0.0768

0,12 x 0,08 x 2 x 1 0.0192
Balok Kunci 0,12 x 0,08 x 1,5 x 4 0.0288
Balok Gording 0,12 x 0,08 x 7,9 x 6 0.455
0,12 x 0,08 x 2,9 x 2 0.0557
0,12 x 0,08 x 6,9 x 1 0.0662
0,12 x 0,08 x 5,9 x 1 0.0566
0,12 x 0,08 x 4 x 1 0.0384
Balok Nok 0,12 x 0,08 x 7,9 x 1 0.0758
0,12 x 0,08 x 2,9 x 1 0.0278
0,12 x 0,08 x 3,9 x 1 0.0378
PEKERJAAN PENGECETAN
Dinding 274x725 x 2 585.85
Plafond 112.61
Profile gypsum 172.9 285.51
Listplank 36.4 36.4
Pintu dan jendela P1 = 2,15 x 1 x 2 x 2(buah) 8.6
P2 = 2,15 x 0,9 x 2 x 5 (buah) 19.35
P3 = 0,8 x 2,15 x 2 x 2 (buah) 6.88
J1 = ((1x1,55)-(0,35x0,8x3) x 2 2.62
J2 = ((0,6x1,75)-(1,55x0,4) x 2 x 2
(buah)
1.64
J3 = ((0,1x1,5)+(0,15x0,4)) x 2 0.12
J4 = ((1,75x1,35)-(0,6x1,65x2)) x 2 M²
x 2 (buah)
1.52
BV = ((0,55x0,3)-0,45x0,2)) x 2 0.15
J5 = ((1,55x2,35)-(0,45x0,8x3)-
(0,45x1,4x3)) x 2 x 2 (buah)
2.69
J6 = ((1,55x2,65)-(0,45x0,8x3)-
(0,45x1,75x3)) x 2
1.335
J7 = ((0,6x0,6)-(0,5x0,5)) x 2 x 3
(buah)
0.66
J8 = ((1,55x0,3)-(0,2x1,35)) x 2 0.39
BV 2 = ((0,65x0,6)-(0,5x0,45))x2
0.33
PEKERJAAN MEP
Pekerjaan MEP
Saklar Tunggal 6
Saklar Ganda 3
Lampu 14
Saklar Hotel 2 BH
Stop Kontak 7
Outlet Antena 2
Outlet Telepon 1
Kabel 53.9 53.9 M
Pekerjaan Plumbing
Pipa PVC Air Bersih 3/4" 14.6
Pipa PVC Air Bersih 1/2" 13
Pipa PVC Air Hujan 3" 25.25 85.1 M
Pipa PVC Air Kotor 4" 15.35
Pipa PVC Air Kotor 3" 16.9
Keran Air 5 BH
Floor Drain 3 BH
Wastafel 1 BH
Kloset Duduk 2 BH
Septic Tank 1 BH
Sumur Resapan 1 BH
PEKERJAAN AKSESORIS
Engsel Pintu 9 9 SET
Engsel Jendela 18 18 SET
Kaca Jendela J1 0,28 x 3

0.84 M²

Kaca Jendela J2 0,62 x 2 (buah)

1.24 M²

Kaca Jendela J3 0.63

0.63 M²

Kaca Jendela J4 0,713 x 2 x 2 (buah)

2.852 M²

Kaca Jendela J5 0,99 x 3 x 2 (buah)

5.94 M²

Kaca Jendela J6 1,1475 x 3

3.4425 M²

Kaca Jendela J7 0,5 x 0,5 x 3

0.75 M²

Kaca Jendela J8 0,09 x 3

0.27 M²

Kaca BV `

0.09 M²

Kaca BV2 0,4 x 0,5

0.2 M²