PPD Complete
PPD Complete
ÿ2542584725ÿ2ÿ74587ÿ994459
9 4ÿ2ÿ994459ÿ
0
Energy Resources and Technologies
Energy exists freely in nature as the gift to mankind. Energy is the need for all kinds of work done by
human beings and nature. Energy is also defined as the ability or the capacity to do work. Human
transforms the food into energy to do work. Similarly, various machineries also transform energy into
work. Work means moving or lifting something, warming or lighting something. There are many sources
of energy that help to run different machines. Some of them exist infinitely (never run out), are called
Renwable Energy sources. The rest that are available in finite amounts and they took millions of years
to form where as possible to run out one day, are called Non-renewable Energy Sources.
Non-renewable energy is energy from fossil fuels such as coal, crude oil, natural gas and uranium. Fossil
fuels are mainly made up of Carbon. The good thing about fossil fuels is that unlike many renewable
sources of energy, fossil fuels are relatively less expensive to produce. But, fossil fuels when they are
burned (used) they produce a lot of carbon compounds (carbon dioxide and other greenhouse gases) that
hurt the environment in many ways. Air, water and land pollution are all consequences of using fossil
fuels.
Energy sources are also categorized as Conventional and Alternative Sources of Energy. The
conventional sources are basically non-renewable such as coal, petroleum, natural gas etc. Alternative
sources are mainly renewables e.g. wind, solar, geothermal, biomass, tidal and hydro (small hydro).
Nuclear and large hydro power are not considered renewable because of various environmental hazards
even though they do not pollute the air. Renewable energy sources are essentially flows of energy,
whereas the fossil fuels are in essence stocks of energy. Sun is the main source of all types of energy.
The world energy scenario is a major concern in the present time. The adverse effects on environment
caused by the production and consumption of energy have resulted in severe environmental impacts
across the globe. Energy consumption is high in most developed countries. On the other hand, developing
countries need to consume more energy to ensure economic growth.
Major energy sources in the world are coal, natural gas, oil, hydro and nuclear energy. Contribution of
renewable sources has been significantly increasing because of improved technological growth and
1
reduced cost of generation. In 2011, renewable contributed 2.4% in total power generation scenario of the
world whereas it was only 0.52% in 2002. Germany has become so far the top renewable power producer
in the world.
Nepal relies heavily on traditional biomass. Commercial energy need is mainly contributed from
petroleum product apparently in urban areas. Electricity supply accounts below 2% of total energy
consumption. Still above 50% of the people has no electricity supply.
Hydropower
The basic principle of hydropower is that if water can be piped from a certain level to a lower level, the
resulting water pressure can be used to move a mechanical component that converts potential energy of
the water into mechanical energy. In concrete form, hydro turbines convert water pressure into
mechanical shaft power, which can be used to drive an electricity generator. Below 20% of today’s
electricity need of the world is from hydropower. Nepal’s electricity is almost all from hydropower except
diesel generator occasionally used during peak time of the day.
∝ .
That means, electric power output is proportional to flow of water and the available head from where the
water can be dropped down. More the discharge and higher the head, more power is obtained. E
2
However, a project with high head but smaller discharge is economical than the same with lower head and
higher discharge.
Hydroelectric power generation is by far the most efficient method of large scale electric power
generation. The conversion efficiency (η) depends mainly on the type of water turbine employed and can
be as high as 95% for large installations. Smaller plants with output power less than 5 MW may have
efficiencies between 80 and 85 %.
Hydroelectric power plant requires various components for generating electrical power. Some of the
major components in hydroelectric power plants are: Reservoirs, Dam, Trash Rack, Forebay, Surge Tank,
Penstock, Spillway, Prime Mover, Generator, Draft Tube and so on.
The reservoir is built by constructing a dam across the river. The water from the reservoir is drawn by the
forebay through an open canal or tunnel. Forebay acts as regulating reservoir to temporarily store water
during change of electric load. The water intake from the dam or from the forebay are provided with trash
rack that prevents the entry of any debris. The water from the forebay is supplied to the water prime
mover through the penstock which is located at the much lower level than the height of the water in the
reservoir. Thus potential energy of water stored in reservoir is converted into kinetic energy and made to
3
rotate the turbine. Turbine shaft is connected to synchronous generator or alternator for generating
electricity. This generated power is stepped up using step-up transformer and delivered to load centers or
grid. The regulation of water flow to the turbine depending on the electrical load demand is carried out by
the governor system.
Besides, surge tank reduces the water hammering effect during water surges caused in the penstok due to
sudden loading and unloading of the generator. The function of spillway is to provide safety of the dam
by discharging major floods without damage to the dam. The draft tube is a part of the reaction turbine.
The tube is a diverging discharge passage connecting the running with tailrace. It is shaped to decelerate
the flow with a minimum loss so that the remaining kinetic energy of the water coming out of the runner
is efficiently regained by converting into suction head thereby increasing the total pressure difference on
the runner.
Advantages of hydropower
Disadvantages
Thermal Power
Thermal power station utilizes the calorific values of fuels as the source of energy. The conversion of
such energy is carried out by turbo-generator. Turbo generator is run by steam turbines. The steam is
obtained from high pressure boiler. The fuel burnt in the boiler can be either solid (e.g. coal), liquid (e.g
petroleum) and gaseous (natural gas) as well. Conventionally, the thermal generation means steam power
plant using coal as fuel. The diagram of a Thermal Plant is shown below.
4
Fig. Schematic Diagram of Thermal Power Plant
In the boiler, the fuel (coal) is burnt and the water is converted into high pressure steam which is further
superheated in a super heater. Inside the boiler there are various heat exchangers: Economiser,
‘Evaporator, Super Heater’ and so on. In Economiser, the feed water has been heated to considerable
amount by the remaining heat of flue gas. The superheated steam is passed in the turbine to rotate the
turbine blades, thus it converts the heat energy to mechanical energy. The pressure of steam decreases and
its volume increases, after imparting energy to the turbine rotor. The low pressure steam passes into
condenser. This condensed water is then further supplied to low pressure water heater where the low
pressure steam increases the temperature of feed water. Thermal power technology also requires
tremendous amount of water for steam generation as well as for cooling purpose.
The turbine actually is the prime mover of an alternator that generates electricity. The alternator is
connected to bus bar then to grid via transformers and protection devices. The overall efficiency of the
thermal power plant using coal as fuel is in the range 20% to 26% depending upon the capacity of the
plant. Higher the capacity, relatively higher will be the efficiency.
Thermal generation covers a massive and greatest portion of total energy consumption of the world. As a
result, environmental problems are being the challenges. Over 90% of greenhouse gas production is due
to fossil fuels basically to meet the energy need of the today’s industrialized and commercialized world.
Advantages:
Economical for low initial cost than any other generating plant.
Land required is less than hydro power plant.
5
Since coal is main fuel & its cost is quite cheap than petrol/diesel so generation cost is relatively
economical.
Maintenance is easier.
Thermal power plant can be installed in any location suitable according to load center (only fuel
transportation facility & bulk of water need to be available).
Disadvantages:
The running cost for a thermal power station is comparatively high due to fuel cost, maintenance
cost etc.
Large amount of smoke causes air pollution. The thermal power station is responsible for Global
warming.
The heated water that comes from thermal power plant has an adverse effect on the lives in the
water and disturbs the ecology.
Overall efficiency of thermal power plant is low i.e. less 30%.
Diesel Power
A diesel engine acts as prime mover that obtains its energy from a liquid fuel (diesel oil) and converts that
into mechanical work. An alternator or DC generator mechanically coupled to it converts the mechanical
energy into electrical energy. The major difference between a steam turbine and diesel engine is that in
diesel engine the chemical energy of combustion of fuel is released inside a cylinder but in steam turbine
the energy developed during combustion of fuel is first transformed into steam and this in turn develops
mechanical power.
The diesel engines are most popular with small generating stations and with consumers who would like to
have their own power supply for emergency reasons. They are also used in medium sized installations for
peaking loads for a utility. The efficiency of diesel generator ranges from 30% to 40%. Electricity cost is
quite costlier and it pollutes the atmosphere massively.
6
As mentioned already, the cost of diesel is very high compared to coal. This is the main reason for which
a diesel power plant is not getting popularity over other means of generating power. The plant is generally
used to produce small power requirement. Cost of lubricants is high. Maintenance is quite complex and
costs high. They emit significant pollutants such as greenhouse gases.
The basic principle of nuclear power station is same as steam power station. Only difference is that,
instead of using coal, heat is generated due to nuclear fission for producing steam from water in the
boiler. This steam is used to drive a steam turbine, actually the prime mover of the alternator. Although,
the availability of nuclear fuel is not plenty but very less amount of nuclear fuel can generate huge
amount of heat energy. This is the unique feature of a nuclear power plant. One kg of uranium is
equivalent to 4500 metric tons of high grade coal. This is why, although nuclear fuel is much costlier, but
nuclear fuel cost per unit electrical energy is still lower than that of coal.
In fission process, the nuclei of heavy radioactive atoms such as Uranium (U235) or Thorium (Th232) are
broken into parts. During this breaking of nuclei, huge quantity of energy is released. This release of
energy is due to mass defect. That means, the total mass of initial product would be reduced during
fission. This loss of mass during fission is converted into heat energy as per famous equation E = mc2,
established by Albert Einstein. Efficiency of conventional nuclear plant is around 33%.
No GHG is emitted.
Quite low amount of fuel requirement in comparison to other fuel based power generation
method.
Occupies much smaller space compared to other conventional power station of same capacity.
Relatively less water amount is required.
7
Fuel transportation is not a problem since the amount of fuel is quite small.
Wind Technology
Wind is air in motion. It is produced due to uneven heating of the earth’s surface by the sun. Since earth’s
surface is made of various land and water formations, it absorbs the sun’s radiation unevenly. During day
time, the air above the land heats up more quickly than the air above water. The warm air above the land
expands and rises and the heavier cooler air over the water moves into take its place, creating local winds.
At night, the process is reverse.
The kinetic energy of the wind is used for electricity generation by wind machines. The wind flows over
airfoil-shaped blades causing them to turn. The blades are connected to a shaft that drives the generator to
produce electricity. For wind mill to be economical there must be winds that blow consistently above 10-
14 miles/hour.
Wind machines were used in Persia as early as 200 BC. First practical windmills were built is Sistan, a
region between Afghanistan and Iran from the 7th century, which were vertical axle windmills, basically
used to grind corn and draw up water. The first electricity generating windmill operated was a battery
charging machine installed in Scotland by James Blyth (1887). The first electricity generating windmill in
United States was built in Cleveland in 1888. A forerunner of modern horizontal-axis wind generators
was in service at Yalta, USSR in 1931, which was of 100kW and connected to 6.3kV distribution system.
The first utility grid-connected wind turbine operated in UK was built in Orkney Island in 1954. It has an
18m diameter, three-bladed rotor and a rated output of 100kW.
Wind turbines work by converting the kinetic energy in the wind first into rotational kinetic energy in the
turbine and then electrical energy that can be supplied for any purpose. The energy available for
conversion mainly depends on the wind speed and the swept area of the turbine. When planning a wind
farm it is important to know the expected power and energy output of each wind turbine to be able to
calculate its economic viability.
8
With the knowledge that it is of critical economic importance to know the power and therefore energy
produced by different types of wind turbine in different conditions, rotational kinetic power produced in a
wind turbine at its rated wind speed is calculated. This is the minimum wind speed at which a wind
turbine produces its rated power.
Let
dm/dt = Mass flow rate (kg/s) dE/dt = Energy Flow Rate (J/s)
The kinetic energy of an object having mass ‘m’ and velocity ‘v’
E = ½ mv2
So, P = ½ ρAv3
A German physicist Albert Betz concluded in 1919 that no wind turbine can convert more than 16/27
(59.3%) of the kinetic energy of the wind into mechanical energy turning a rotor. To this day, this is
known as the Betz Limit or Betz' Law. The theoretical maximum power efficiency of any design of wind
turbine is 0.59 (i.e. no more than 59% of the energy carried by the wind can be extracted by a wind
turbine). This is called the “power coefficient”. Also, wind turbines cannot operate at this maximum
limit. The coefficient is unique to each turbine type and is a function of wind speed that the turbine is
operating in. Once we incorporate various engineering requirements of a wind turbine - strength and
durability in particular - the real world limit is well below the Betz Limit with values of 0.35-0.45
common even in the best designed wind turbines. By the time we take into account the other factors in a
complete wind turbine system - e.g. the gearbox, bearings, generator and so on - only 10-30% of the
power of the wind is ever actually converted into usable electricity. Hence, the extractable power from the
wind is given by:
Pavailabe = ½ ρ Av3 Cp
The swept area of the turbine can be calculated from the length of the
turbine blades using the equation for the area of a circle:
A = πr2
Where, the radius is equal to the blade length as shown in the figure.
9
Example: Given that: Blade length, l = 52 m Wind speed, v = 12 m/sec Air density, ρ = 1.23 kg/m3 Power
Coefficient, Cp = 0.4
A = π * 522 = 8495 m2
P = ½ *1.23*8495*123*0.4 = 3.6 MW
The wind is free and with modern technology it can be captured efficiently.
It does not produce green house gases or other pollutants.
Although wind turbines can be very tall each takes up only a small plot of land. This means that
the land below can still be used. This is especially the case in agricultural areas as farming can
still continue.
Remote areas that are not connected to the electricity power grid can use wind turbines to produce
their own supply.
Wind turbines are available in a range of sizes which means a vast range of people and businesses
can use them. Single households to small towns and villages can make good use of range of wind
turbines available today.
Disadvantages
Power output depends on wind speed which is very unpredictable.
Wind turbines are very noisy.
There occurs pollution during manufacture of wind turbines.
A large wind farm is needed even to feed power to a small community.
Can affect life of birds or insects.
Sun radiates continuously an enormous amount of energy. Only a tiny portion of radiant energy comes to
strike the earth. Yet this amount is enough to meet the world’s needs, if it could be harnessed. The radiant
light and heat from the sun has been harnessed by human since ancient times using a range of over-
evolving technologies. Solar radiation along with secondary solar-powered resources such as wind and
wave-power, hydroelectricity and biomass accounts for most of the available energy on earth. Only a
minuscule fraction of the available solar energy is used so far.
Solar radiant energy application include day lighting, solar hot water system, solar cooking, space heating
and cooling through solar architecture, high temperature process heat for industrial purposes and
electricity generation. Solar powered electricity generation relies either on heat engines (solar thermal
technology) or photovoltaic technology.
10
A solar thermal collector collects heat by absorbing sunlight. A collector is a device for capturing solar
radiation. Solar radiation is energy in the form of electromagnetic radiation from the infrared (long) to the
ultraviolet (short) wavelengths. The quantity of solar energy striking the Earth's surface averages about
1,000 watts per square meter under clear skies, depending upon weather conditions, location and
orientation.
The term "solar collector" commonly refers to solar hot water panels, but may refer to installations such
as solar parabolic troughs and solar towers; or basic installations such as solar air heaters. Solar power
plants usually use the more complex collectors to generate electricity by heating a fluid to drive a turbine
connected to an electrical generator. Simple collectors are typically used in residential and commercial
buildings for space heating.
Parabolic Trough
This type of collector is generally used in solar power plants. A trough-shaped parabolic
reflector is used to concentrate sunlight on an insulated tube (Dewar tube) or heat pipe,
placed at the focal point, containing coolant which transfers heat from the collectors to the
boilers in the power station.
Parabolic dish
With a parabolic dish collector, one or more parabolic dishes concentrate solar energy at a single focal
point, similar to a dish antenna focuses radio waves. This geometry may be used in solar furnaces and
solar power plants. Dish/engine system captures large amount of heat from sun and heats up the working
gases (helium or hydrogen) that drives the piston of external combustion engine which ultimately runs the
generator.
Power Tower
A power tower is a large tower surrounded by tracking mirrors called heliostats. These mirrors align
themselves and focus sunlight on the receiver at the top of tower, collected heat is transferred to a power
11
station below. This design reaches very high temperatures. High temperatures are suitable for electricity
generation using conventional methods like steam turbine or a direct high temperature chemical reaction
such as liquid salt. By concentrating sunlight current systems can get better efficiency than simple solar
cells. A larger area can be covered by using relatively inexpensive mirrors rather than using expensive
solar cells. Heat storage for power production during cloudy and overnight conditions can be
accomplished, often by underground tank storage of heated fluids.
2. Photovoltaic Technology
Photovoltaic comes from the words photo (light) and volt, a measurement of electricity. Photovoltaic cells
are also called PV cells or solar cells. PV cell is made of two thin pieces of silicon, the substance that
gives it a tendency to attract electrons. The other piece of silicon has a small amount of phosphorous to it,
giving it an excess of free electrons. When two pieces of silicon are placed together, an electric field
forms between the layers. When PV cell is placed in the sun, the radiant energy energizes the free
electrons. If a circuit is made, electron flows from n-layer to p-layer, producing electricity.
Typical power output form a cell is in a range a watt. Individual cells are connected together to form a
solar panel or module. Panel can be connected in series or parallel to form solar arrays according to its
purpose. Photovoltaic systems are designed for many applications varying in size and complexity. Some
are isolated from ac power lines. Remote systems include navigational aids along coastlines, remote
homes, isolated villages in developing countries and so on. Some photovoltaic systems have ac power
designed for water pumping stations, for supplying power to TV and communication equipment, village
power, auxiliary power for heating and cooling private homes and industrial applications.
PV tracking system is an alternative to fixed, stationary PV panels. The tracking mechanism orients PV
panel to follow the sun as it moves through the sky. The tracking mechanism runs entirely on its own
power and can increase output by 40%. Battery backup provides power of sunny day on night or in
cloudy days.
12
Efficiency of the PV system is less than 10% as estimated below in diagram.
Let us use 5 hrs of Peak Sunshine. The weather conditions of the area affect the size of the panel or array.
Required solar panel input = (892.8 Wh / 5h) = 178.5W. We need solar panels that will generate 178.5
watts..
Select the solar panels to provide a minimum of 178.5 or 200W. Always round to the nearest 10.
Any combination of solar panels can be used to provide the required 200W
13
Battery input = 1115/0.8 = 1395 Wh
Geothermal energy is the earth’s natural heat available inside the earth. Deep below the Earth’s crust lies
a layer of molten rock called magma where heat is continually produced. This heat can be used as an
energy source in a large complex power station or a smaller pumping station. Geothermal power has been
used for thousands of years in both heating baths and cooking food, and is still used today.
By 2010, United States, the world leader for geothermal electricity generation had installed capacity 3086
MW. The Philippines was the second highest producer, with 1904MW of capacity.
The schematic of a single-flash geothermal power plant is shown in Figure. The geothermal liquid is
withdrawn from the production well and is flashed (steam released). The resulting vapor is separated from
the liquid in a separator and directed to the turbine. The low pressure steam or hot water from the turbine
is condensed and routed to a reinjection well along with liquid coming off separator.
14
1. Geothermal power is a renewable source that requires no fuel (except for pumps) but capital costs are
highly significant.
2. Exploration and drilling remains expensive and risky.
3. The plant must be situated near by the reservoir or any other source of water. It is not practical to
transport steam or hot water.
4. Harmful gases can escape from deep within the earth. Possible gases e.g. CO2, H2S, CH4 and NH3
are prone to global warming or acid rain.
5. The hot water from geothermal supply may hold in some toxic chemicals e.g. Hg, B etc. and they
may precipitate as the water cools and can cause environmental damage if released.
Tidal Energy
Tides rise and fall in eternal cycles. Tides are changes in the level of the oceans caused by the
gravitational pull of the moon and sun and the rotation of the earth. Tidal power is a form of hydropower
i.e. the generation of electricity from tides is similar to hydroelectric generation, except that tidal water
flows in two directions. The simplest generating system for tidal plant involves a dam, known as barrage,
across an inlet. Sluice gates on the barrage allow the tidal basin to fill on the incoming high tides and to
empty through the turbine system on the outgoing tide, known as the ebb tide. Flood generating system
that generate power from the incoming tide are possible but are less favored than ebb generating systems.
Two way generation systems which generate electricity on both the incoming and ebb tides are also
possible.
In ebb generation, the basin is filled through the sluices until tide. Then the sluice gates are closed (at this
stage there may be pumping to raise the level further). The turbine gates are kept closed until the sea level
falls to create sufficient head across the barrage, and then are opened so that the turbines generate until
the head is again low. Now the sluices are opened, turbines disconnected and the basin is filled again. The
cycle repeats itself.
In flood generation, the basin is filled through the turbines, which generates at tide flood. This is less
efficient than ebb generation.
Another configuration is Two Basin Schemes. One is filled at high tide and the other is emptied at low
tide. Turbines are placed between the basins. Such scheme may generate power more continuously but
expensive to construct dual basins due to extra length of barrage.
Tidal fences can also harness the energy in the tides. A tidal fence has a vertical axis turbine mounted
within a fence structure called a caisson that completely blocks a channel, forcing all of the water through
it.
Energy available from a barrage is dependent on the volume of water. The potential energy contained in a
volume of water is = ℎ
15
g = acceleration due to gravity
Because the available power varies with square of the tidal range, a barrage is best placed in a location
with very high amplitude tides.
Example: Estimate the power output from a tidal project that has tidal range of approximately 10m. The
surface area of tidal harnessing plant is 3 km x 3 km. Consider that there are two high tides every day.
Assume power conversion efficiency as 30%.
∗
Mean power potential = / s = 104
∗ ∗
France is the country that has significantly harnessed tidal energy. Due to environmental impact, there is
reluctant on such technology. The placement of barrage into an estuary has a considerable effect on water
and on ecosystem. Economically, tidal power schemes have a huge capital cost and very low running
cost. It is obviously an excellent renewable energy resource.
Cogeneration
Cogeneration or combined heat and power (CHP) is the use of a thermal power station to simultaneously
generate electricity and useful heat. This is the technique for thermodynamically efficient use of fuel. In
separate production of electricity, some energy must be discarded as waste heat such as condensation loss
of cooling tower, heat associated with flue gas or by other means. But in cogeneration this thermal energy
is put to use usually for heating purposes e.g. in process industries or in district heating system.
16
Process industries such as Pulp and Paper industry or other forest based industries, sugar mills etc. those
using raw material as bio-products e.g. wood, straw or sugarcanes, usually use their byproduct, which is a
form of biomass, as a source of energy. Pulp and paper industry uses black-liquor for heat and power
burning the liquor in recovery boiler. Bagasse is good energy biomass in sugar industry. Further bagasse
is a good fuel of pulp as well.
In case of combined cycle usually when the fuel used is natural gas, the first will be the gas turbine.
Rather than wasting the flue gases from the gas turbine, the flue gases are directed into boiler again
generating steam to run steam turbine, hence increases the thermal efficiency.
17
123456ÿ89 43
0
12
345657894
1 ÿÿÿ ÿÿÿ ÿÿÿÿ 44 ÿ!ÿÿ
ÿ"ÿ#ÿ ÿ$$ÿÿ ÿ#ÿ ÿ ÿ%#ÿ ÿ &ÿ'()*+',-
0
1234526789ÿ2 26
0
Power System Expansion Planning
Electricity is so basic to the world economy that certain electricity indices are used to express a
country's economic standing (e.g. consumption or production of electricity per capita).
Moreover, electricity supply has special characteristics which make the service unique as
compared to other types of industry. The end product has to be delivered instantaneously and
automatically upon the consumer's demand (exceptions are ‘pumped storage plants’ and ‘electric
batteries’). No technologies have been developed that can
produce electricity economically at uniform rates,
hold electricity in storage in large quantities, and
deliver electricity under convenient schedules;
Insufficient capacity (shortage) or excessive capacity (idle capacity) has negative effects on the
economy. The close interrelation with economic and social factors imposes labor, environmental,
financial and other constraints on the problem. Careful planning of the electric sector is therefore
of great importance since the decisions to be taken involves the commitment of a huge resources,
with potentially serious economic risks for the electrical utility and the economy of the country
as a whole.
Power system planning is part of a more general problem, that of energy and economic
development planning. Its objective is therefore to determine a minimum cost strategy for long-
range expansion of the generation, transmission and distribution systems adequate to supply the
load forecast within a set of technical, economic and political constraints.
Traditionally, power system planning has been mainly related to generation expansion planning.
This is due mainly to the fact that investment in transmission lines is a relatively small fraction
of the investment in the construction of power stations. Furthermore, the investment in the
distribution of electric energy to customers, although sizeable, is to a large extent independent of
the generation and transmission system.
In early years of electricity industry, transmission planning was the responsibility of vertically
integrated utilities that met their native loads from their own generation. The planning process in
deregulated utility structure is significantly more difficult than traditional vertically integrated
utilities because decisions about the installation of new generators are the result of market forces
rather than centralized planning.
The primary purpose of Transmission expansion planning (TEP) is to determine, on the least-
cost basis, the best transmission additions to provide the load with sufficient energy and facilitate
wholesale power marketing with a given criteria. Most new lines can help improve local voltage
quality and improve system reliability, as well as enabling new generation units to served area
load and increasing capability for longer-distance transaction. The benefits of a transmission
upgrade changes over time as the result of the changes of loads, generation and grid topology. In
the regulated environment, the vertically integrated utilities operate the whole electric system
and make investment decision for both generation and transmission additions. Transmission
expansions can be justified if there is a need to build new lines to connect cheaper generators to
meet the current and forecasted demand or new additions are required to enhance the system
reliability so some reliability criteria can be fulfilled, or both.
In the traditional transmission planning model, the capital investments are often justified by
fulfilling the reliability requirements to serve the current and forecasted load. As costs is often
used as a criterion to select the alternative investment plan and various reliability criteria are
used to constrain the decision making problem, the traditional transmission planning problem
normally formulated as cost minimization problem with reliability as constraint.
Distribution Planning
Distribution network expansion planning is one of the important activities in distribution control
centers. Mainly the planning is focused to allocation of substations and feeders.Several
evaluation items such as new equipment installation cost, equipment utilization rate, reliability of
the target distribution system, and loss minimization should be evaluated considering increase of
network loads and newly installed large customer loads when planning.
Electric Load Forecasting
The objective of power system planning is to determine an economical expansion of the
equipment and facilities to meet the customers' future electric demand with an acceptable level of
reliability and power quality. Accurate demand forecasting plays an essential role foe electric
power system planning. . An expensive overestimation of load demand will result in substantial
investment for the construction of excess power facilities, while underestimation will result in
customer discontentment. Accurate forecasts lead to substantial savings in operating and
maintenance costs, increased reliability of power supply and delivery system, and correct
decisions for future development. Electricity as a product has very different characteristics
compared to a material product. For instance, electricity energy cannot be stored as it should be
generated as soon as it is demanded. Unfortunately, it is difficult to forecast load demand
accurately over a planning period of several years. This fact is due to the uncertain nature of the
forecasting process. There are a large number of influential that characterize and directly or
indirectly affect the underlying forecasting process; all of them uncertain and uncontrollable.
Electric Power Load Forecasting (EPLF) is a vital process in the planning of electricity industry
and the operation of electric power systems. The EPLF is classified in terms of the planning
horizon’s duration as follows.
Short-term forecasting
It corresponds to the forecasting duration up to 1 day to a week ahead. Short-term forecasts are
used to schedule the generation and transmission of electricity.
It corresponds to forecasting duration from a week to a year. Medium-term forecasts are used to
schedule the fuel purchases.
It extends the forecasting duration more than 1 year ahead. Long-term forecasts are used to
develop the power supply and delivery system (generation units, transmission system, and
distribution system) i.e. system expansion planning.
Longer the time horizon, more the inaccuracy in forecasting. Any long term load forecasting by
nature is inaccurate because
Peak demand is very dependent on temperature
The economic and weather data may not be available
It is almost impossible to store electric power
Power generation and transmission projects require a great amount of investment and
take several years to construct.
Generally, long-term load demand forecasting methods can be classified in to two broad
categories: Parametric methods & Artificial intelligence based methods.
I. Parametric Methods
The parametric methods are based on relating load demand to its affecting factors by a
mathematical model. The model parameters are estimated using statistical techniques on
historical data of load and it's affecting factors. Parametric load forecasting methods can be
generally categorized under three approaches:
Trend Analysis
Trend analysis extends past rates of electricity demand in to the future, using techniques that
range from hand-drawn straight lines to complex computer- produced curves. These extensions
constitute the forecast. Trend analysis focuses on past changes or movements in electricity
demand and uses them to predict future changes in electricity demand.
The advantage of trend analysis is that, it is simple, quick and inexpensive to perform. The
disadvantage of a trend forecast is that it produces only one result, future electricity demand. It
does not help analyze why electricity demand behaves the way it does, and it provides no means
to accurately measure how changes in energy prices or government polities influence electricity
demand.
End-Use Models
The end-use approach directly estimates energy consumption by using extensive information on
end users, such as applications, the customer use, their age, sizes of houses, and so on. End-use
models focus on the various uses of electricity in the residential, commercial, and industrial
sector. These models are based on the principle that electricity demand is derived from
customer's demand for light, cooling, heating, refrigeration, etc. Thus, end- use models explain
energy demand as a function of the number of applications in the market.
Ideally, this approach is very accurate. However, it is sensitive to the amount and quality of end-
use data. End-use forecast requires less historical data but more information about customers and
their equipments. The disadvantage of end-use analysis is that most end-use models assume a
constant relationship between electricity and end-use (electricity per appliance). This might hold
for over a few years, but over 10 or 20-year period, energy saving technology or energy prices
will undoubtedly change, and the relationships will not remain constant.
Econometric Models
The econometric approach combines economic theory and statistical techniques for forecasting
electricity demand. The approach estimates the relationship between energy consumption
(dependent variables) and factors influencing consumption. The relationships are estimated by
the least-square method or time series methods. One of the options in this framework is to
aggregate the econometric approach, when consumption in different sectors (residential,
commercial, industrial, etc.) is calculated as a function of weather, economic and other variables,
and then estimates are assembled using recent historical data. The advantage of econometrics are
that it provides detailed information on future levels of electricity demand, why future electricity
demand increases, and how electricity demand is affected by all the various factors.
Artificial neural networks (ANNs) have succeeded in several power system problems, such as
planning, control, analysis, protection, design, load forecasting, security analysis, and fault
diagnosis. The last three are the most popular. The ANNs ability in mapping complex non-linear
relationships is responsible for the growing number of its application to load forecasting. Most of
the ANNs have been applied to short- time load forecasting.
To use the ANN in electric load forecast problems, distribution engineers should decide upon a
number of basic variables such as:
Input variable to the ANN (load, temperature…etc)
Number of classes (weekday, weekend, season…etc)
What to forecast: hourly loads, next day peak load, next day total load …etc
Neural network structure (Feedforward, number of hidden layer, number of neuron in the
hidden layer…etc)
Training method and stopping criterion
Activation functions
Size of the training data
Size of the test data
Expert systems
Expert systems are new techniques that have come out as a result of advances in the field of
artificial intelligence (AI) in the last two decades. An expert system is a computer program,
which has the ability to act as an expert.
Expert System
Knowledge Base
Expert (Set of rules)
(Knowledge
I/O Interface
Inference Engine
(Rule Interpreter)
User
Data Base
(Set of facts)
The load forecast model is built using the knowledge about the load forecast domain from an
expert in the field. The "Knowledge Engineer" extracts this knowledge from load forecast
(domain) expert. This knowledge is represented as facts and rules by using the first predicate
logic to represent the facts and IF-THEN production rules. The search for solution or reasoning
about the conclusion drawn by the expert system is performed by the "Inference Engine"
component of the expert system.
Fuzzy logic
It is based on the usual Boolean logic which is used for digital circuit design. In Boolean logic,
the input may be the truth value in the form of “0” and “1”. In case of fuzzy logic, the input is
related to the comparison based on qualities. For example, we can say that a transformer load
may be “low” and “high”. Fuzzy logic allows us to deduce outputs form inputs logically. The
advantage of fuzzy logic is that there is no need of mathematical models for mapping between
inputs and outputs and also there is no need of precise or even noise free inputs. Based on the
general rules, properly designed fuzzy logic systems are very strong for the electrical load
forecasting. There are many situations where we require the precise outputs. After the whole
processing is done using the fuzzy logic, “defuzzification” is done to get the precise outputs.
Fig. Fuzzy Expert System
Genetic Algorithm
Support Vector Machine
Comparison and usefulness of various forecasting methods
The method for short-term forecasting are similar day approach, various regression models, time
series, neural networks, statistical learning algorithms, fuzzy logic, and expert systems. Similar
day approach is based on searching historical data of days of one, two or three years having the
similar characteristics to the day of forecast. Regression is the one of most widely used
statistical techniques.
The methods for long- and medium-term forecasting are trend analysis, end-use and econometric
approach. The advantage of trend analysis is that it is quick, simple and inexpensive to perform
and does not require much previous data.
Power System Security
The Power System needs to be operationally secure, i.e. with minimal probability of blackout
and equipment damage. An important component of power system security is the system’s
ability to withstand the effects of contingencies. A contingency is basically an outage of a
generator, transformer and or line. Its effects are monitored with specified security limits.
The power system operation is said to be normal when the power flows and the bus voltages are
within acceptable limits despite changes in load or available generation. From this perspective,
security is the probability of a power system’s operating point remaining in a viable state of
operation.
System security can be broken down into TWO major functions that are carried out in an
operations control centre:
Security assessment
o It gives the security level of the system operating state.
Security control.
o It determines the appropriate security constrained scheduling required to
optimally attaining the target security level.
The preventive state is actually the normal state. The term ‘preventive’ was used to stress the
‘Security’ aspect of the normal operation. The operation of a power system is usually in a normal
state. Voltages and the frequency of the system are within the normal range and no equipment is
overloaded in this state. The system can also withstand any single contingency without violating
any of the limits.
The system transits into the emergency state if a disturbance occurs. Many system variables are
out of normal range or system frequency starts to decrease . Emergency control actions can
restore the system. Economic considerations become secondary at this stage. The emergency
control actions include fault clearing, excitation control, fast valving, generation tripping etc.The
extreme emergency state is a result of the occurrence of an extreme disturbance or action of
incorrect of ineffective emergency control actions. The power system is in a state where
cascading outages and shutdown of a major part of power system might happen. The system is in
unstable state. The control actions, such as load shedding of the most unimportant loads and
separation of the system into small independent parts, are required.
Restorative state is the condition when some parts (or whole) of the system has lost power. The
control objective in this state is to steer the system to a normal state again by taking appropriate
actions.
Interconnection of Utilities
Electric utilities across regions are many times interconnected to allow for a variety of
advantages.
It is the fact that electric utilities benefits from its nature of being large and
interconnecting utilities allows for economies of scale.
Utilities can draw power from generator reserves from a different region in order to
ensure continuing, reliable power and diversify their loads.
Interconnection also allows regions to have access to cheap bulk energy by receiving
power from different sources. For example, one region may be producing cheap hydro
power during high water seasons, but in low water seasons, another area may be
producing cheaper power through wind, allowing both regions to access cheaper energy
sources from one another during different times of the year. (how about tie up in
between Nepal and India?).
Neighboring utilities also help others to maintain the overall system frequency and also
help manage tie transfers between utility regions.
Reserve Capacity
For reliable operation of power system, reserve capacity is needed. It is an additional installed
capacity than the required demand. More reserve means less efficient expansion planning.
In electricity networks, the operating reserve is the generating capacity available to the system
operator within a short interval of time to meet demand in case a generator goes down or there is
another disruption to the supply. Most power systems are designed so that, under normal
conditions, the operating reserve is always at least the capacity of the largest generator plus a
fraction of the peak load.
The operating reserve is made up of the spinning reserve as well as the non-spinning or
supplemental reserve:
The spinning reserve is the extra generating capacity that is available by increasing the
power output of generators that are already connected to the power system. For most
generators, this increase in power output is achieved by increasing the torque applied to
the turbine's rotor.
The non-spinning reserve or supplemental reserve is the extra generating capacity that is
not currently connected to the system but can be brought online after a short delay. In
isolated power systems, this typically equates to the power available from fast-start
generators. However, in interconnected power systems, this may include the power
available on short notice by importing power from other systems or retracting power that
is currently being exported to other systems.
Short notes PPD
Spinning Reserve
Generation capacity that is online but unloaded and that can respond within 10 minutes to compensate
for generation or transmission outages. Frequency Responsive spinning reserve responds within 10
seconds to maintain system frequency. Spinning reserve are the first type used when shortfalls occur.
Supplemental Reserve
Unlike spinning reserve, supplemental reserves capacity is not synchronized with the grid. They are used
after all spinning reserves are online.
Distributed storage
Electricity storage located in the utility distribution system, at or near the load center.
It is a measure of the reliability of an electrical grid. It is the probability that there is insufficient
generating supply to support electrical demand.
01234ÿ06789ÿ3 8
ÿÿÿ
ÿ!ÿ"ÿ#ÿ
$ÿÿ%ÿÿ
#$ÿ&ÿ'!
01234ÿ06789ÿ3 8
ÿÿÿ
ÿ!ÿ"ÿ#ÿ
$ÿÿ%ÿÿ
#$ÿ&ÿ'!
12345ÿ1789ÿ4 9
524745ÿ1524ÿ447249
0
01234ÿ06789ÿ3 8
ÿÿ
ÿ
Selection of Optimal Turbine for Hydropower
For the cost effective and efficient project, it is worthy to study the optimal selection of hydro turbine. The turbine
is an assembly consisting of a nozzle or stator, runner, and shaft that collectively convert momentum and pressure
in a water flow into rotational mechanical work. The mechanical work is transferred by the shaft to a generator.
TYPES OF TURBINE
Impulse Turbines
In impulse turbine, pressurized water from the penstock is converted to high-speed water jets that transfer the
kinetic energy of the jet by impacting the turbine blades or cups causing rotation. Examples of impulse turbines
include the Pelton wheel, Turgo wheel, and cross-flow turbines. Turgo wheel has been developed to be a simple
impulse type machine with a higher specific speed than a Pelton. The design therefore allows a larger jet of water
to be directed at an angle onto the runner. Impulse turbines generally operate best with medium or high head
(above 10 m).
Reaction Turbines
Reaction turbines operate under pressure in an internal flow regime. Water passes the stator, which takes the form
of spiral casings or guide vanes, to introduce swirl into the flow. The flow is then redirected by the runner blades.
The angular momentum of the water forces rotation in the runner. In contrast to impulse turbines, the water
pressure drops at the stator and the runner. Examples of reaction turbines include Propeller, Kaplan, and Francis.
Reaction turbines often have complex blade geometries and housings, which make them more difficult to
manufacture at smaller scales. However, reaction turbines can perform well even in the low head range (less than
10 m).
SELECTION OF TURBINE
Hydro power designer has to make a choice on the type of turbine that can be adopted for a particular project. The
capacity of the plant should be fixed as high as possible with adequate care on efficient running and low initial
costs, and available transport and shipping facilities. The size should not be so high so that turbine would run at
low efficiency at the time of lean season.
Thumb Rule
Different types of turbines can be selected to best suit given head and flow conditions. The optimum turbine
selection for a given hydraulic duty and site application is dependent on many parameters. For preliminary
selection, the table below can be used.
(http://www.gilkes.com)
One of the important parameters of a turbine is the Specific Speed. It is the speed in rpm at which a turbine would
operate with unity meter head to give a unit power output. It is denoted by ns. It is given by the following relation
as below.
√
/
Once the specific speed (ns) is determined, the chart given below may be used to determine the type of turbine
that may be adopted for the particular project.
Efficiency
Constructability
Maintenance and serviceability
Portability (manageable for transportation)
Cost
The efficiency of turbine types based on design discharge is shown in the figure below.
3. Generator voltage.
The voltage of large, slow- speed generators should be as high as
the economy of machine design and the availability of switching
equipment permits. Generators manufacturing practices generally
dictate an upper voltage limit of 13.8 kV for machines up to 250
MVA rating.
Larger voltages means less current for the same rating, but it also
means larger voltage difference between turns and with earth
requiring expensive insulation and space. So economic design
should be left to manufacturers, while specifying only the
performances by the Power Plant designer. Based on required
generator reactances, size, and Wk2, a lower generator voltage,
such as 6.9 kV, is proven to be more economical than higher
voltages.
4. Insulation.
5. Short-circuit ratio:
The ratio of the field current required to generate rated voltage on
open circuit required to circulate rated armature current during
short circuit is termed as short circuit ratio (SCR).
Based on open circuit characteristics (OCC) and Short circuit
characteristics (SCC), the ratio is determined as
The short-circuit ratio is also the reciprocal of the per unit value of
the saturated synchronous reactance.
6. Reactance
7. Efficiencies
For a generator of any given speed and power factor rating, design
efficiencies are reduced by the following:
Type: Step-up transformers for use with main units should be of the oil
immersed type for outdoor operation, with a cooling system.
Type of cooling.
Insulation level of high-voltage winding.
Departure from normal design impedance.
Transformer construction:
There are two types of construction used for GSU transformers. These
are the core form type and the shell form type.
Core form transformers generally are supplied by manufacturers
for lower voltage and lower MVA ratings. The core form unit is
adaptable to a wide range of design parameters, is economical to
manufacture, but generally has a low kVA-to- weight ratio. Typical
HV ranges are 230 kV and less and 75 MVA and less.
Shell form transformers have a high kVA-to-weight ratio and find
favor on EHV and high MVA applications. They have better short-
circuit strength characteristics, are less immune to transit
damage, but have a more labor intensive manufacturing process.
Rating:
The full load kVA rating of the step-up transformer should be at least
equal to the maximum kVA rating of the generator or generators with
which they are associated.
Where
SG = rating of generator
Cooling:
Electrical Characteristics
Voltage
High-voltage BIL
Impedance
Impedance of the transformers has a material effect on system
stability, short-circuit currents, and transmission line regulation,
and it is usually desirable to keep the impedance at the lower limit
of normal impedance design values. In fact, the impedance of
transformer is direct function of its transformer rating.
Transformer efficiency
Transformer losses represent a considerable economic loss over
the life of the power plant. A study should be made to select
minimum allowable efficiencies for purposes of bidding.
Vector group
For example,
Other Accessories
Terminals
KVA Rating
Rated Voltage
Number of phases
Rated frequency
Connections (star or delta)
Tappings (if any)
Type of core (core or shell)
Type (Power or Distribution)
Ambient tempr. (usually 400)
Type of Cooling (cooling medium: air, oil or water and circulation
type: natural or forced, simple/mixed cooling)
Temper rise above ambinent tempr (insulation class)
Voltage regulation (at full load and 0.8 pf lag,
impedance/reactance in p.u or %)
No load current (or % of rated current at rated voltage and
frequency)
Efficiency (at full load, half load, ¾ load)
INTRODUCTION TO EXCITATION SYSTEM
It is necessary to provide constancy of the alternator terminal
voltage during normal small and slow changes in the load. For
this purpose the alternators are provided with Automatic
Voltage Regulator (AVR). The exciter is a separate source to
provide DC field current to the alternator. It is one of the
main components in the AVR loop.
It must have adequate power capacity and sufficient speed
of response (rise time less than 0.1 sec.)
Hence, the basic function of an excitation system is to provide
necessary direct current to the field winding of the
synchronous generator. The excitation system must be able
to automatically adjust the field current to maintain the
required terminal voltage.
Fig.1 General Components of Excitation System
1. Exciter: The DC power provider to field of alternator.
2. Regulator: Processes and amplifies input control signal to
level and form appropriate to control exciter.
3. Voltage Transducer: It senses terminal voltage of
alternator, rectifies and filters it to dc quantity and
compares with reference value that denotes desired
terminal voltage.
4. Power System Stabilizer (PSS): It provides an additional
input signal to regulator to damp power system
oscillation.
5. Limiters and Protective Circuits: They include a wide
range of control and protective functions such as not to
exceed the capability limits such as field current limiter,
maximum excitation limiter, volts per Hertz limiter etc.
The excitation systems have taken many forms over the years
of their evolution. The modern trend in interconnected
operation of power systems for the purpose of reliability and
increasing size of generators for the purposes of economy are
mainly responsible for the evolution of new excitation
schemes. The excitation systems practiced so far are the
following.
1. DC excitation systems
2. AC excitation systems
3. Brushless AC excitation systems
4. Static excitation systems
1. DC EXCITATION SYSTEMS
In DC excitation system, the field of the main synchronous
generator is fed from a DC generator, called exciter. Since the
field of the synchronous generator is in the rotor, the
required field current is supplied to it through slip rings and
brushes. The DC generator is driven from the same turbine
shaft as the generator itself. One form of simple DC excitation
system is shown in Fig.1.
Fig. 1 DC Excitation system
DC excitation system has slow response. Normally for 10 MVA
synchronous generator, the exciter power rating should be
nearly 1% of the main generator, for which we require a huge
DC generator. For these reasons, DC excitation systems are
gradually disappearing.
2. AC EXCITATION SYSTEMS
In AC excitation system, the DC generator is replaced by an
alternator of sufficient rating, so that it can supply the
required field current to the field of the main synchronous
generator. In this scheme, three phase alternator voltage is
rectified and the necessary DC supply is obtained. Generally,
two sets of slip rings, one to feed the rotating field of the
alternator and the other to supply the rotating field of the
synchronous generator, are required. Basic blocks of AC
excitation system are shown in Fig. 2.
Generator Grounding
1
2. Solidly grounded
3. Low reactance grounded
4. Resonant (Arc suppression coil) grounding.
5. Low resistance grounded
6. High resistance grounded
1. Ungrounded systems
Advantages:
Low fault current limited by the system’s capacitance to ground.
The system can be operated, at least for a limited period of time, with
one ground fault present if correctly designed, providing high service
continuity.
2
Disadvantages:
In case of fault, voltages on the healthy phases are equal to line-to-
line voltages, thereby affecting the rating of the surge protective
devices.
Danger of very high over voltages with an intermittent fault.
Difficult to achieve selective ground fault protection.
Advantages:
Disadvantages:
Very high and potentially destructive fault currents for internal faults.
May cause voltage gradient problems.
Causes high stress on the equipment for external faults.
3
May cause 3rd harmonic voltage1 circulation problems.
Advantages:
Limits transient and temporary over voltage to values close to those of
a solidly grounded system. Allows the use of lower rated surge
protective equipment.
Lower ground fault current compared to solidly grounded systems.
Disadvantages:
Ground fault current levels, while limited, are still high, with
potentially destructive fault currents.
Low reactance systems may experience circulation of a 3rd harmonic
current.
Resonance conditions might occur. Need of surge protection.
Care should be exercised in rating neutral point equipment
Relatively expensive neutral point equipment.
4. Resonance Grounding
1
The voltage of generators has a low content of 3rd harmonic voltage due to the uneven physical distribution of stator-
windings in the generator, which do not produce a fully sinusoidal voltage. The generators should be designed for
minimized 3rd harmonic voltage content by utilizing a 2/3 winding pitch. On the other hand, this usually means over
sizing of the generator and potentially reduced efficiency.
4
It operates on the principle that if an inductance of appropriate value is
connected in parallel to the capacitance, the fault current can be reduced
significantly if operates at resonance. Hence the inductance required
depends on capacitive current to ground. The arc suppression coil is an iron
core tapped reactor connected to neutral to ground connection. The tap
setting should be such that it should be tuned to system capacitance. To
some extent, it acts same as ungrounded system.
Advantages:
Lower ground fault current compared to solidly grounded systems.
5
Good control of temporary and transient over voltages.
Easy and selective fault detection.
Disadvantages:
Ground fault current are still at a comparably high level to cause
possible damage.
Care should be exercised in the selection of surge protective
equipment. Low impedance systems may experience the circulation of
a 3rd harmonic current.
Relatively expensive neutral point equipment.
6
Fig. 1 Transient Voltage in percent of Rated Peak Line to Ground
Voltage
Advantages:
Limits transient and temporary over voltage to safe values if correctly
designed.
Ground fault currents limited to low values, with lower potential
damage for an earth fault.
High enough resistance to inhibit circulation of a 3rd harmonic
current. Relatively inexpensive neutral point equipment.
Easy and selective fault detection with modern relays.
Disadvantages:
May not be applicable to all systems, as the ground fault current
maybe too low to be detected by older types of relays. The equipment
installed in an existing system (e.g. surge arrestors) may also have
voltage ratings that are too low.
High Resistance Grounding normally takes the form of a low ohmic value
resistor connected to the secondary of a distribution transformer with the
primary winding of the transformer connected from the generator neutral to
ground. The advantage of the distribution transformer resistor combination
is that the resistor used in the secondary of the distribution transformer is of
comparatively low ohmic value and of rugged construction as compared to
obtaining the same result by installing a high ohmic, low current resistor
directly in the generator neutral.
7
Fig. Resistance grounding with Distribution Transformer
Utilities generally prefer solidly grounded systems for voltage levels from
69 kV upwards, for their transmission and sub-transmission systems. This
is primarily due to the control of Transient Over Voltages permitting the
use of lower rated insulation and surge protection. At 3.3-33 kV, practices
differ, even between utilities in the same country. Consideration has to be
given to a variety of factors; economics, loads (three-phase or single phase),
service continuity, control of over voltage, and even environmental
considerations. Industrial systems are often resistance grounded - high or
low resistance, or ungrounded for very critical processes. The primary goal
here is service continuity and equipment damage control.
8
Calculation of Neutral Resistor:
And the Capacitance of Cable from generator terminal to CB, Unit Aux.
Transformer, and Generator Transformers can be neglected since they are
in the range of Pico Farad.
Cg = Co + Cs
= 0.385 µF
Xco = 1/ (2πfCg) = 8267.8 Ω
As Shown in Fig. 1, for the Restriking voltage not to exceed 2.5 times the
rated voltage, Rn should be equal to or greater than Xcg .
Hence,
Rn = Xcg = 2756.0 Ω
9
Rating of Distribution Transformer:
During a sustained ground fault, current will flow in the secondary resistor.
The maximum neutral voltage is assumed to be phase to ground voltage.
Isec max = Vsec max / Rsec = 240/3.94 = 61.0 A
Since the Current rating of the calculated Grounding Resistor is high, it can
be significantly reduced by selecting the voltage ratio of the distribution
transformer high i.e. 11/ 3 : 0.480 kV
During a sustained ground fault, current will flow in the secondary resistor.
The maximum neutral voltage is assumed to be phase to ground voltage.
Isec, max = Vsec max / Rsec = 480/15.74 = 30.5 A
This value is the current through the neutral device during a ground fault
condition. Grounding resistor must be rated to withstand the full thermal
current.
The thermal rating of the transformer is calculated using full transformer
voltage and the following equation:
kVA = Esec rated * Isec max = 14.64 kVA
10
Duration of Overload Multiple of Rated kVA
10 Sec 10.5
60 Sec 4.7
10 min 2.6
20 min 1.9
2 hr 1.4
Now, the thermal rating of the resistor can be calculated with the
assumption:
if a solid fault occurs so Rfault=0, the power dissipated in the grounding
resistor, Pr, will be:
Pr = E2L-N / Rn = (11000/ 3 ) 2 / 2756.0 = 14.64 kW.
11
Generator Lead
The term “generator leads” applies to the circuits between the generator terminals and the low- voltage
terminals of the Generator Step Up (GSU) transformers. The equipment selected depends upon the
distance between the generator and transformer, the capacity of the generator, the type of generator
breakers employed, and the economics of the installation. There are two general classes of generator
leads:
Metal-enclosed buses
Power cables.
Enclosed Bus Ducts are designed for use on circuits whose importance requires greater reliability than
power cables. Cables may be appropriate for some small generators or in installations where the GSU
transformer is located in the plant’s switchyard.
A. Metal-enclosed buses
There are three categories of metal-enclosed bus: nonsegregated-phase, segregated- phase, and isolated-
phase.
All phase conductors are enclosed in a common metal enclosure without barriers, with phase
conductors insulated with molded material and supported on molded material or porcelain insulators.
This bus arrangement is normally used with metal-clad switchgear and is available in ratings up to
4,000 A (6,000 A in 15-kV applications) in medium-voltage switchgear applications.
Adhikari YR
(2) Segregated-phase buses
All phase conductors are enclosed in a common enclosure, but are segregated by metal barriers
between phases. Conductor supports usually are of porcelain. This bus arrangement is available in
the same voltage and current ratings as nonsegregated- phase bus, but finds application where
space limitations prevent the use of isolated-phase bus or where higher momentary current ratings
than those provided by the nonsegregated phase are required.
Each phase conductor is enclosed by an individual metal housing, which is separated from adjacent
conductor housings by an air space. Conductor supports are usually of porcelain. Isolated-phase bus is
available in ratings through 24,000 A and voltage level up to 35 kV.
Cables may be appropriate for some small generators or in installations where the GSU transformer is
located in the plant’s switchyard. In the latter situation, economic and technical evaluations should be
made to determine the most practical and cost-effective method to make the interconnection. Factors
to consider when selecting power cables as generator leads:
Simpler in design
Safer (Due to a high short-circuit rating and minimal combustive energy)
Quicker to install
More flexible for modification and expansion
Adhikari YR
Protection against the ingress of dust
Protection against the ingress of liquids
The description of IP code letters are given below in chart. If a characteristic numerical is not
required to be specified, the letter ‘X’ is used.
Adhikari YR
Circuit Breaker Selection
Type
Rated Voltage
The rated voltage indicates the upper limit of the highest voltage of systems for which the switchgear
and control gear is intended. It is the highest root-mean-square (rms) voltage for which the circuit
breaker is designed and is the upper limit for operation (e.g. 12 kV for 11 kV systems, 145 kV for 132 kV
systems and 72.5 kV for 66 kV systems).
Rated Current
The rms value of the current which the circuit breaker shall be able to carry at rated frequency and at
rated voltage continuously at normal working conditions.
Rated Frequency
The frequency at which it is designed to operate (e.g. 50 Hz for Nepalese power system).
It consists of the prescribed number of unit operations at stated intervals. The operating sequence
denotes the sequence of opening and closing operations which the circuit breaker can perform under
specified conditions.
O– t – CO – t’ – CO
O = opening operation of circuit breaker
CO = closing operation immediately followed by an opening operation without
any intentional time delay.
t = 3 min for circuit-breaker not intended for rapid auto reclosing & t = 0.3 s for
circuit-breaker intended for rapid auto reclosing.
t’ = 3 min
Instead of t’ = 3 min, other values such as t’ = 15s (for rated voltages less than or
equal to 52 kV) and t’ = 1 min are also used for circuit-breaker intended for
rapid auto-reclosing.
Breaking capacity
It is the highest rms value of shot circuit current that the circuit breaker is capable of breaking under
specified conditions of transient recovery voltage and power frequency voltage. Power frequency
withstand voltage and impulse withstand voltage are used to characterize the insulation level of circuit
breaker. Power frequency withstand voltage is designed for a minute duration. Impulse withstand
voltage is designed for only microsecond interval.
Making Capacity
There is always a possibility that the circuit breaker is closed under short-circuit condition. The making
capacity of the circuit breaker depends upon its ability to withstand the effect of electromagnetic forces
which are proportional to the square of the peak of value of the making current.
The rated value of making current = 2.55 * rated short-circuit breaking current.
The current will be the maximum at the instant of occurring of fault, after which current decays. The CB
starts to operate after the initiation of fault. Hence actual current interrupted by CB is less than initial
short-circuit current. For this too small interval of time, CB should be able to hold this large current
without damage, this rms current carrying capability is Short-time current rating. This is expressed in kA
for a period of 1 s or 4 s.
Medium voltage generation voltage level SF6 and Vacuum circuit breaker (VCB) seem suitable as
Generator Circuit Breaker (GCB). But, for 12 kV switchgear system, VCB is generally preferred because
No emission of gases, pollution free and does not need filling of gas or oil.
Non explosive and silent operation.
Large number of operations on load or short circuit. Suitable for repeated operating duty. Long
life as compared to SF6 circuit breakers.
Suitable for capacitor switching, cable switching, industrial load switching.
As its interrupting medium is vacuum, breaking time is very short.
Oil circuit breaker are possible instead but may have following drawbacks
Air Blast Circuit breaker is suitable for very large current and generally used for outdoor high voltage
applications.
The interrupting rating of circuit breakers should be selected with the help of fault current.
Assignment: Compare VCB and SF6 CB on the basis of their uses and other techno-economic factors.
Damage of the equipments due to overheating and high mechanical forces from short circuit
current.
Fire Hazards.
Low Voltage in other circuits.
Unbalance in network, can cause heating of rotating machines.
System instability.
The short circuit value of bus bar fault gives the maximum current that flows from the system to
the earth through the bus.
The earthing mat designed at the power house and switchyard is purely governed by the
maximum fault level.
The short circuit current rating of overhead line conductor and cable should be such that it
should withstand its respective fault current.
The interrupting rating of circuit breakers should be selected with the help of fault current.
The emfs of all generators are 1<0° per unit. This means that the system voltage is at its nominal
value before fault and load current is ignored.
Shunt elements in the transformer model that account for magnetizing current and core loss are
neglected.
System resistance is neglected and only inductive reactance of the system is taken into account
i.e. X/R ratio is assumed to be high.
Computation of Fault currents for electric systems is carried out in terms of per-unit values
Sketch the Single Line Diagram of the given power system. For example consider a case as below
in figure.
Convert the impedance of generators, transformers, transmission lines etc. to per-unit values on
its respective bases.
To obtain asymmetrical rms fault current, multiply the symmetrical fault current by a factor of
1.6.
Find the appropriate CB from the coordination vales using table given below.
(sub-clause 4.1.1 of IEC Publication 694 for Series I)
Source Feeder
Feeder Source
1
Disadvantages
a.) The supply from the busbar is interrupted during the routine maintenance of the busbar
system and disconnects switches connected to it.
b.) Feeder supply is lost during the repair and maintenance of the feeder, breaker, and the
disconnect switches.
c.) Short circuits in the busbar lead to the loss of supply to all the feeders.
d.) Feeder short circuits in case of circuit breaker failure lead to loss of supply to all feeders.
3
1. Load can be shifted to any bus during maintenance of other bus.
2. Even using the main or transfer bus one at a time, it need not to use the breaker of
bus coupler, i.e. the feeder uses it's own breaker when either bus is in operation.
Disadvantages:
1. The addition of one extra isolator increases the cost of the arrangement.
2. This system is somehow more difficult to arrange i. e. layout in switchyard.
12 11 10 9 8
Bus
CB-5 coupler
3 4 6 7
5
Bus-1
1 2
Load
Source-1 Load Source-2
Suppose power flow is now in direction from source-1 to source-2. In this case bus-1 is charged
through CB-2, DS-1 and DS-4. If fault occurs in line of source -2, it is isolated by opening CB-4
and DS-2. Also in case of maintenance of Bus-1, Bus-2 is charged through bus coupler by
closing DS-5, DS-10 and CB-5 .Both the buses now are at same potential. Source-1 can supply
Bus-2 through DS-11 and also the load can be connected to bus-2 through DS-12 safely. Now
DS-3, DS-4, DS-5 and CB-5 can be opened. Similar operations can be performed at source-2
side. And hence maintenance at Bus-1 can be performed safely.
The main features of this scheme are as follows:
4
Advantages
1. Flexible operation.
2. Possibility of maintaining a busbar at a time without the loss of supply.
3. Breaker or line relays can be taken out of service at any time with only slight
modification of line protection.
4. Either main bus may be isolated for maintenance.
5. Has high availability.
Disadvantages
1. An extra breaker is required for the bus tie.
2. Fault in the tiebreaker disables both busbars
3. Complicated switching required when removing a breaker for maintenance.
4. Bus tie breaker relaying complicated since it must be able to spare any breaker.
5. Requires separate complicated bus protective scheme.
6. Has greatest exposure to bus faults.
7. Line breaker failure takes half of substation out of service.
8. Bus tie breaker failure takes entire station out of service.
9. Not convenient for Supervising Control & Data Acquisition (SCADA) control.
10. High cost.
11. Loss of supply of corresponding feeder during maintenance of that feeder.
A double bus bar scheme with addition of bypass isolator in circuit breaker is more reliable. It
resumes continuity of supply even during maintenance of breaker through the bypass isolator.
This system is as shown in figure below:
As shown in figure 5, it requires two additional isolators than that in simple Double bus single
breaker arrangement. The increased reliability will cause higher cost of the system. Its cost index
is 1.8.
5
Bus-2
Bus-1
Bypass Isolator
6
3. Any individual breaker can be taken out of service at any time
4. No complicated bus differential relaying scheme required
5. Breaker failure operation removes two circuits from service under normal operation
6. No main bus required
7. All switching is done by breakers
8. Cost Index 1.04
Disadvantages:
1. If a fault occurs during breaker maintenance, the system may be separated into two
sections
2. Automatic Reclosing is complicated
3. If single relay set used circuit must be taken out of service to maintain relay
4. since there is no definite potential point, potential devices must be provided on all circuits
5. Tripping matrix becomes complicated and may not be easy to understand.
7
Station Service System
A complete station service supply and distribution system should be provided to furnish power for station,
dam auxiliaries, lighting, and other adjacent features of the project.
“Black start” capability is desirable at hydro plants. “Black start” capability is defined as the ability of the
plant, without an external source of power, to maintain itself internally and start generating units. The
plant must then resynchronize to the grid. At least one emergency power source from an automatic start-
engine-driven generator should be provided for operating governor oil pumps and re-establishing
generation after losing normal station service power. Figure below would be a scheme for station power
supply.
In case of large size power plant, two station service transformers (as shown below) with buses and
switching arrangement can be used. Now either of the transformers can be supplied from either the main
generators or the transmission system. Each transformer is supposed to be capable of supplying the total
station load.
The station service switchgear should have a sectionalized bus, with one section for each normal station
service source. Switching to connect emergency source power to one of the buses, or selectively, to either
bus should be provided. Three-phase, 480 V station service systems using an ungrounded-delta systems
are still preferred in hydro stations.
The main distribution board supplies power to sub distribution boards and to some feeders directly. It may
consist of four incomers, incomer 1 and incomer 2 from station transformers, incomer 3 from DG and
incomer 4 from emergency transformer situated outside the power house. Each feeder panel is protected
by appropriately rated MCCB and necessary auxiliary devices like indicator lamps, selector switches,
push buttons etc. For important feeders like unit sub distribution board, cooling waters, battery charger
etc. two feeder panels are located, one from each bus, for the reliability and uninterruptible supply to the
feeders.
Important consumers such as Unit Control Board, governor, excitation panel etc. have feeder control
crucible from both the LV buses. There should be provision for Main and Stand by selection. This ensures
operation of only one feeder at the time of supply resumption. It also helps in the load balancing of both
the station transformer. When the feeder designated as main fails, the standby feeder is operated
automatically.
Most of the loads of the power plant are motor loads which may be in the form of Cooling water pumps,
governor oil pumps, ventilation motors etc. Majority of the motors used are of induction type. Depending
upon their size and their operation requirement they need different types of starters and protection system.
The maximum demand that is expected on the station service system is the basis for developing station
service transformer ratings. The expected demand may be determined from a total of the feeder loads with
an appropriate diversity factor, or by listing all connected loads and corresponding demand loads in kVA.
A diversity factor smaller than 0.75 should not be used. Demand factors used for developing station
service equipment capacities can vary widely due to the type of plant. For instance, the governor oil pump
demand for a Kaplan turbine will be greater than that for the governor oil pump demand for a Francis
turbine of the same output rating because of the additional hydraulic capacity needed to operate the
Kaplan turbine blades. If the plant is base loaded, governor oil pumps will not cycle as often as governor
oil pumps in a similar plant used for automatic generation control or peaking service. Station service
systems should be designed also to anticipate load growth.
• Generator cooling (stator, bearing), turbine bearing cooling, transformer cooling (OFWF)
• Governor pumps- actuator control of Guide vane/Nozzle. Inlet valve, bypass valve etc
• service air for repair jobs and compressed air for pressurized oil tank
Lubricating system
DC distribution supply
Ancillaries
Ventilation System
Elevator
Diesel Generator
Experiences indicate that the station power consumption for hydropower station is below 1% of its
installed capacity. An example case for estimating total auxiliary load demand and hence the selection of
capacity of station transformer is shown below.
Connected load
Function KVA Demand KVA
Unit auxillaries for 2 units
pump#3bus#1 1@25hp 25 25
pump#4bus#2 1@25hp 25
bus #1 4@13kw 52 52
bus #2 4@13kw 52
bus #1 2@2hp 4 4
bus #2 2@2hp 4
bus #1 3@2hp 6 6
bus #2 3@2hp 6
bus #1 1@5hp 5 5
bus #2
Fire pump 25 25
Elevator 25 25
Water heater 5 2
Switchyard
Power outlets 5
Lighting 38 30
Air compressors 2
Machine Shop
Largest Machine 15
Total less heating 1465 618
(Table above assumes 1 hp as the equivalent of 1 kVA and on lights and heaters uses the kW rating as the
kVA equivalent.)
DC Supply System
Different rated values of dc voltage have been used in power plant depending upon types of equipments
and their power requirements. The rated dc voltage for auxiliary equipments as per IEC 60694_2002 is
shown.
• 110V DC System:
– The rated 110V dc system is extensively used in Nepalese power plants for various
purposes such as switchgear operations, emergency lighting, generator field flashing,
relay panels, inverter supply, solenoids, annunciations, control and so on.
• 48V DC System:
– 48V dc system is another preferred value for electronic auxiliary equipments as per IEC
standard, usually used for communication system and PLC.
• 24V DC System:
– The rated 24V dc system is being used in electronic equipments which functions as
control units. It is extensively used in microprocessor based control units as its power
requirement and voltage level is low. It is also used in LED indicators, SCADA
equipments, solenoids control circuits etc.
Batteries
Components of Battery
Cell
– It is the basic unit of battery consisting negative and positive plate.
Electrodes
– They are Metallic Plates made of active material e.g. Pb.
Electrolytes
– They are the conducting medium in battery cell e.g. H2SO4
Separator
– Porous insulating divider between plates that prevents electrical contact
between them
Cell Vent
– It allows escaping of gases produced in battery.
Case
– It is the outer body or frame that covers entire components of battery.
Charge modes
• Nomimal Charge – First charge including the dead cell charge which can not be
recovered (Constant current charging).
• Float / Trickle charge – After near to full charge, the maintaining charge – low current&
constant voltage
• Boost / Equalizing charge – After discharge, fast recharge is necessary, high and constant
current initially, and later constant voltage reducing current, switching over to Trickle
charge
Sulfation: It is a normal slow process in Lead Acid batteries operating in a partial charge state
due to growth of Lead sulphate crystals in the plates and that will reduce the active area and
capacity. So, the batteries should be charged to full when leaving for long duration.
Stratification: Electrolyte density is changing from bottom to top due to undercharging and lack
of agitation. This causes lower plate to deplete and reduce capacity while top portion is still
active. During charging, Equalizing charge or Boost charge should be done so the electrolyte is
agitated.
Ampere-hour or Capacity or Ampacity: 1Ah means1 Amp of current over a period of 1 hour.
Slower the discharge rate, higher the capacity. Energy-out depends upon depth of discharge, cut-
off voltage, temperature, and discharge rate (Ampere drawn out).
Temperature Correction: Lower Temperature lowers the capacity. Below 200c, a correction
factor has to be applied to maintain the capacity.
Battery Selection
• For energy storage from renewables as solar or wind, efficiency is more critical.
• For vehicles, energy density and DOD is more important for easy transport and limited space.
• For fixed travel vehicles, locomotives, energy efficiency may be more important (safa tempo)
• Operational pollution
• Cost
• Maintenance requirement etc.
Firstly the battery duty cycle is observed according to load requirement. Consider a duty cycle as
in figure as an example case.
• Battery reserve time: 8 hours
• For higher reliability and segregation of faults, the battery bank is constructed with two battery
bank with half the capacity i.e. 200 Ah each. However, considering the future load growth,
capacity factor and compensation for age of battery, each battery bank of 250 Ah is chosen.
• Battery capacity of 500 Ah is used in Kali Gandaki ‘A’ HPP (144 MW)
Battery Charger
• It should be sufficient for supplying the continuous DC load while recharging the station battery
at the normal rate.
Charging System
• Constant Current System - charging current is kept constant by varying the supply voltage.
Charging current is controlled by varying the rheostat or by controlling the firing angle of
thyristors. Takes longer time for charging.
• Constant Voltage System - voltage is kept constant but it results in very large charging current
in the beginning. Charging time is almost reduced to half. It may not be applicable for Ni-Cd
battery system, whose voltage level does not decrease appreciable.
350+0.2*350=420Ah.
For greater reliability and segregation of faults we use two battery banks 210Ah.
Number of cell
Voltage regulation method, for the instance consider ‘Diode voltage regulation’
But final cell voltage at full discharge=1.8 V for 10 hours discharging (according to supplier)
Therefore we require 66 numbers of cells voltage ranging from 2.0 V at fully charged to 1.8 V as end of
discharger voltage at maximum discharge.
In order to safely put battery, better to provide one separate room or as compromise we can use area
enclosed with fence for protection against accident contact. Area should be well ventilated so that exhaust
air from the room does to enter any other room in the power plant. Rating of battery decrease with
temperature should be multiplied by correction factor below certain definite temperature. So, adequate
heat must be provided for full rated performance out of the cells. Battery charging equipments, contactors
and arc producing device and control are not in battery room. Thermostat for heater should be sealed. The
cells should be mounted in rows on racks.
Fig. Battery Bank
For 110V battery system ( i.e. Two battery banks of 210Ah capacity and 66 cells:)
Size of 110 V system having 960mm gap between the two banks=1661mm*(1020*2+960)
Length*Width=2m*3m
Battery Chargers
For backups there is battery chargers in the power plant. Battery chargers are used to convert ac to dc to
charge station batteries which helps in supplying power to dc loads during normal operation. Two sets are
generally preferred one for normal use while other for backup. The charger capacity should be sufficient
for supplying the continuous DC load normally carried while recharging the station battery at the normal
rate. The chargers should be of the “battery eliminator” type (additional filtering) allowing them to carry
station DC loads while the battery is disconnected for service.
Charger output current is estimated on the basis of continuous and non continuous DC load current.
Considering duty cycle as above in example case
I2 = the minimum charger output (in amperes) that will supply the maximum operational load.
I3 = the recommended charger rated output (in amperes); i.e., the larger of I1 or I2.
ILC = the continuous dc load (in amperes), including future load growth.
I2 = ILC + ILN
= 80 + 0 = 80 A
The maximum value of short circuit due the battery charger is limited by the current limiting circuit of the
charger to 1.5 times the output current
For our example, fault current of battery charger = 1.5 * 120 = 180 A
For the DC system as below in figure (a case of MBKHP), the dc fault current is
1. System Earthing:
Earthing of the neutral of generators, generator, etc. are known as system earthing. It is
employed to restrict the voltage of live conductors with respect to the potential of general mass
of the earth to a value consistent with the insulation level.
2. Body earthing:
It refers to the earthing of non-current carrying conductive part of electrical equipment.
Fig. Body earthing
Purposes of earthing:
1. Earthing provides protection to the personnel and equipment by ensuring the operation of
protective device to isolate the faulty circuit in the following cases:
i. Insulation failure
ii. Accidental contact between HV and LV lines.
iii. Breakdown of insulation between HV winding and LV winding of a transformer.
iv. Lightning strokes.
2. To ensure safe value of step potential and touch potential in the substation yard during
the fault period.
A threshold current of Ventricular fibrillation is100 mA for 3 seconds however, more higher
current can be tolerated without Ventricular fibrillation, if the duration of current flow is very
short. The safe value of current through a human body is given by:
.
=
√
The operation of C.B. is expected in less than 3 sec. For sustained fault, Ik is taken as 9mA.
(tolerable) = (1000+6∗ )*0.009
&
(tolerable) = (1000+ 1.5 ∗ )* ∗ 0.009
Clay 50 ohm-mm-m
Sandy clay 100 ohm-m
Sand 2000 ohm-m
Rock 10,000 ohm-m
Megger is used to determine soil resistance and soil resistivity is calculated as
ρ = 2.π.S.Rg
Where S = separation between electrode (see figure below)
Rg = soil resistance measured from Megger.
2. Choose fault clearing time:
The fault clearing time is determined from the system stability consideration and it depends upon
the type of circuit breaker. The circuit breakers are usually specified by their operating time in
terms of number of cycles. For e.g. two cycles C.B., 4 cycle C.B. etc. in order to increase the
safety, the fault clearing time shall be taken as 3 second for grounding system design.
3. Calculation of tolerable step potential and touch potential. E.g. assuming an average soil
resistance as 3000Ω,
(tolerable) =(1000+6*3000)*0.165/√3
=1810 V
=K* *√
Where
= fault current in KA
Eg. = 5 KA = 5000 A
5000
∴ = = 10.
500
∗ 1 1
= +
2ℎ ( − 1) + ℎ
∴ at site = *S
= Ks* ∗ I
Where, Ks = *[ +∑ ( )
]
= step factor
h = depth at which the grounding mat is buried below the ground level
D = distance between two main conductors
Taking irregularity factor into consideration,
Estep (at site) = Ki*Ks* ∗ I
Where,
Ki= irregularity factor = 0.657+0.172n (for n≤ 10)
= 0.2+0.22n (for n> 10)
Touch potential at site is given by :-
∗ ∗
∴ (site)= *log + ∗ log ∑ [ ]
∗ ∗ ∗ ( )
∴ (site)= ∗ ∗
Where,
= *log + ∗ log ∑ [ ]
∗ ∗ ∗ ( )
(site)= ∗ ∗ ∗
(site)≤ (tolerable)
(site)≤ (tolerable)
If the length of the grounding conductor is less than Lmin, then layout shall be modified and
closer mesh should be adopted to achieve the safe potential gradient.
The grounding resistance of mat is calculated as:
= +
Where,
r=radius of the circle having same area as the area of the s/s yard
L=total length of conductors
Maximum Grid Potential = If × Rmat
123454666ÿ381291 9ÿ96 46ÿ
2 6 3
421!"
!!!#"$%!!!
$
92#"&#!"!'
0$ 6
($ 89
)$ *4*
+$
,$ 39
-$ 3 #*
.$ 1! #*
0
1234564738
9 5852432ÿ1234564738
9 283252ÿ234564738
9785ÿ1234564738
900ÿÿÿ3ÿ345ÿ74274738ÿ234564738
0