03_RMPlan_1.0
03_RMPlan_1.0
03_RMPlan_1.0
Date: 17-May-07
Copyright Notice
This document contains proprietary information of HCL Technologies Ltd. No part of this document may
be reproduced, stored, copied, or transmitted in any form or by means of electronic, mechanical,
photocopying or otherwise, without the express consent of HCL Technologies. This document is
intended for internal circulation only and not meant for external distribution.
Risk Management Plan
Revision History
Table of Contents
1 Risk Identification.....................................................................................4
2.1 Impact................................................................................................................................. 7
2.2 Probability........................................................................................................................... 7
3 Mitigation Plan.......................................................................................11
4 Contingency Plan............................................................................................................14
1 Risk Identification
One of the primary tasks of project management is risk management and containment. The
major risks associated with the project will be identified, and relevant interventions will be made
to contain them. The risk items shall be prioritized and monitored accordingly on a continual
basis, and corrective action will be taken, when necessary.
HCL is aware of the various risk factors associated with the assignment, the impact of the risk
factors on the project schedules and the quality and the measures to control and manage the
risk factors identified. The objective of the planning shall be to highlight the risk factors,
analyze the impact of the risks on project execution and identify strategies to control and
minimize the impact of the risk items.
Assessing the risk at project startup will be the first step in identifying and gaining control of
risk factors during project execution. The risk management process is as follows:
Risk Identification
Risk Analysis
Risk Prioritization
Risk Planning
Risk Monitoring
Risk Identification
At the beginning of the planning phase, identification of other risks and a detailed analysis
of the risks associated with the project is done and documented.
These risks are reviewed both periodically and on event driven basis throughout the project
lifecycle and the status will be updated to UTi in the Project Status Report.
New risks identified in the tracking stages are analyzed, documented and monitored from
then on.
Risks List:
Based on HCL’s Risk Database, the following risks are identified as potential ones for this
engagement:
2.1 Impact
For the risks identified in the earlier section, the Risk impact is measured based on the
following Criteria:
Impact
Rating Cost Schedule Scope Quality
Insignificant
Cost Insignificant Scope changes Quality degradation
1 Increase Schedule slippage barely noticeable barely noticeable
Quality reduction
<5 % cost Schedule slippage Minor areas of scope only on certain
3 increase <5% are affected areas
5-10% cost Overall project Major areas of scope Significant Quality
5 increase slippage 5 to 10% are affected Reduction
Both Minor and Major
10-20% cost Overall project areas of scope are High Quality
7 increase slippage 10 to 20% affected Reduction
>20% Cost Overall project Scope changes to a Greatest impact on
9 Increase slippage slips > 20% greater extent Quality
2.2 Probability
For all the 28 risks identified, Risk Analysis is done based on the Probability and Impact Scales
discussed above
From the Probability and Normalized Impact, Risk Index is calculated as shown below:
Probability
0.1 0.3 0.5 0.7 0.9
1 0.1 0.5
1.5 0.15 0.45
2 0.2 0.6 1
2.5
Normalized Impact
3 0.9 2.1
3.5 0.35 1.05
4 0.4 2.8
4.5
5 0.5 1.5 2.5 3.5
5.5 2.75 3.85
6 1.8
6.5
7
7.5 3.75
8
8.5
9
Higher the impact and probability of occurrence, higher is the risk priority and the need for
action.
The need for action required (with regard to each risk index) is as follows:
Extreme: This risk requires immediate attention, and both contingency and mitigation
planning must be planned and implemented.
Medium: If the risk is realized, related risk management techniques would be implemented.
3 Mitigation Plan
The following table lists the various Risks earlier identified and the mitigation plan that will be
adopted by HCL-UTi Team.
Sl. No. Risk description Risk category Mitigation plan
1 Communication andCommunication Joint reviews by HCL and UTi at regular
reporting intervals as per plan
2 SA Specific Security General Safe & Secured Residential Location for
Risk HCL Project Team will be found out and
other necessary actions will be taken by
HCL engagement Manger at SA.
3 Security andIT Related Periodic security audits by both UTi and
Infrastructure related HCL to ensure compliance with security
issues norms
4 System/Network IT Related ISMS will ensure the restoration of System /
connectivity Failure Network as per the Std SLA norms
5 On time Hardware /IT Related Proper plan for procurement of HW/SW are
Software Availability in place and adequate lead time for
erection & installation is planned.
6 MSA / SOW Delay Management HCL & UTi Senior Management should
review and sort out the ambiguities in the
MSA / SOW document
4 Contingency Plan
The following table lists the some of the High Sensitive Risks and their Contingency plan that
will be adopted by HCL-UTi Team.