: PWA-RPD-QM-FM-028
Comment Category
Section Reference Reviewer Position Comment Response Responder Position
No. (R/S)
This submission is REJECTED since the
contractor had developed the CEMP by
themselves. Rev: 00
As per the MME Environmental Permit Noted & TriConstruct
(2017/29368 – Renewed under Ref assigned Qatar
(2018/29930)), clause 24, the CEMP should be Design Consortium
developed by an Environmental Consultant. (QDC) to prepare
Environmental Therefore, this submission is REJECTED. CEMP. HSE
1 General MK R AM
Specialist Manager
DN099-P05 - CEMP
Prepared by Qatar
Design Consortium
(QDC) Submitting for
Approval.
Rev01 Comments
Contractor to undertake a QA/QC check on the QA/QC has been
Environmental HSE
2 General MK whole document. Different sections showing R check done and AM
Specialist Manager
Error Reference Source not found. corrections made.
Rev 02:
Contractor to Proceed ASAP with
submission of Environmental Permit
Requests. Note on Appendix F, Dewatering
permit is required for the project. Appendix
F to be amended in the final copy of the
CEMP.
Table 2-3 is showing the estimated Permit application
will be submitted by
Section 2.4 quantities for the excavated material.
Environmental the Contractor. HSE
4 (construction MK Contractor to confirm the plan for the R AM
Specialist Amended accordingly Manager
activities) storage of the material. Currently, the in Section 2.4. The
contractor has not applied for any storage laydown area for
Circular (2019/67).
Hazardous waste will
not be stored at site
Contractor to request for the hazardous waste for longer duration.
Environmental HSE
17 General MK storage permit. This needs to be done ASAP R Will be removed on AM
Specialist Manager
prior to storage of any hazardous waste onsite. weekly basis by
approved waste
handler
Contractor to confirm full compliance against
item 3 stating "Times of construction activity
Environmental will be restricted to the agreed and approved Will be Complied by HSE
18 Table7-8 MK R AM
Specialist operational hours 6 am – 5 pm Saturday to the Contractor. Manager
Thursday. Construction work on a Friday to be
approved by the Supervision Consultant "
The baseline test
results (EIA) did not
observe any
contaminations as
Contractor to confirm and link this section with
Environmental per the Dutch Stds. HSE
19 Section 7-4 MK the findings of the baseline. Additional baseline R AM
Specialist However, fresh Manager
will be required.
baseline has been
recommended before
start of the
construction.
Frequency against the sampling of sediments,
Environmental HSE
20 Section 7-5 MK soil quantity and slurry to be provided and R Amended accordingly AM
Specialist Manager
linked with table 7-12.
Frequency against the sampling of soil from Frequency and
stockpile to be provided and linked with table 7- number of samples
Environmental 12. The location planned for the stockpile needs are furnished in Table HSE
21 Section 7-7 MK R AM
Specialist to be provided in the following CEMP 7-13. The Stockpile Manager
submission. locations is 6.5 kms
away from the
Specialist baseline groundwater quality from the EIA and The groundwater Manager
discuss the potential contamination as per the baseline conditions
EIA provided details. The latest water quality are discussed in
data for the deep well must be added to the section 5.4 of this
report and discussed in details. CEMP. However, the
contractor will
conduct (before the
start of dewatering
activity) and furnish
the latest
groundwater quality
of the deep well .
This section MUST discuss the rainy season
Rainy season
management and he set of measures taken by
management plan
the contractor in this regards.
Environmental provided in Appendix HSE
26 Section 7-10 MK R AM
Specialist W, the same has Manager
Rev 02:
been mentioned in
The paragraph related to Rain Season Plan is not
brief in section 7.9
complete in Page 141. Contractor to amend.
Contractor to conduct baseline monitoring
The contractor will
for Air, Noise , Ecology , Soil and conduct a basline for
Groundwater following the EIA sensitive Air, Noise, Ecology,
Receptors and update the table accordingly. Soil and Groundwater
Clear dates to be provided based on the in the sensitive
Environmental construction work and project schedule receptors identified HSE
27 Table 8-1 MK R AM
Specialist near sensitive Receptors. in the EIA. The dates Manager
of the construction
Rev 02: work and the
The baseline monitoring results must be sensitive receptors
are furnished in
submitted in the first environmental
Figure 5-8
monthly report.
28 Table 8-1 MK Environmental The monitoring equipment for each aspect R Furnished accordingly AM HSE
Rev 02:
Contractor to Check comment number 14
and comply accordingly.