51274-001 -eia-en_10
51274-001 -eia-en_10
51274-001 -eia-en_10
The environmental impact assessemnt is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,
and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of
this website.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
status of any territory or area.
CHAPTER 3
PROJECT DESCRIPTION
CHAPTER 3
PROJECT DESCRIPTION
Pink Line Mass Rapid Transit Project, Khae Rai-Min Buri section, with 34.5 km
in total length, has been defined as a minor mass transit system in the form of elevated
straddle monorail. The alignment of Pink Line Mass Rapid Transit (MRT) Project starts on
Rattanathibet Road in front of Nonthaburi Government Center where the Pink Line will
connect to the Purple Line, Bang Yai-Bang Sue section. Then the Line turns left at Khae Rai
intersection onto Tiwanon Road and goes along Tiwanon Road. It will pass Central Chest
Institute of Thailand, Sanambin Nam intersection and Wat Chonlaprathanrangsarit until
reaching Pak Kret intersection. The Line then turns right onto Chaeng Watthana Road,
passing Impact Arena, Muang Thong Thani, the 2nd stage expressway (Si Rat), Bangkok
Government Complex, and Laksi intersection where it will connect to the Red Line, Bang
Sue-Rangsit section. The Pink Line crosses under Uttraphimuk Tollway (formerly Don
Muang Tollway) and passes Phithak Ratthathammanun Monument Circle where another
interchange station-Wat Phra Si Maha That station-is located. At this interchange, the Pink
Line passengers can connect to the Dark Green Line, Mo Chit-Saphan Mai section, which
was approved by the National Environment Board (NEB) on 31 October 2012. After that, the
Line follows Ram Inthra Road, crosses over Chalong Rat expressway at Watcharaphon
intersection, and runs further until Min Buri intersection. The route alignment continues
toward Min Buri town along Sihaburanukit Road, goes across Khlong Sam Wa and then
turns right to cross over Khlong Saen Saep, passing vacant land. The Line then turns onto
Ramkhamhaeng Road (Sukhaphiban 3) and finally ends at Rom Klao intersection near Soi
Ramkhamhaeng 192 where there is an interchange station linking to the Orange Line, Bang
Kapi-Min Buri section. The project components include:
30 stations,
1 depot and park & ride building.
than other comparable elevated conventional rail lines. Monorail systems are also quieter as
rubber tires are used, creating less noise compared with other steel–wheeled trains running
on steel rails. At present, there are two types of monorail: straddle monorail, as shown in
Figure 3.2-1, and suspension monorail, as presented in Figure 3.2-2.
of guideway beam must be consistent with the car size, taking into account the difference in
car size of each manufacturer.
Generally, monorail train is composed of motor-car (Mc) and passenger–car (M).
A train set has between 2 and 8 cars depending on the passenger demand. Figure 3.2-3
illustrates the various train formations.
Monorail system has a maximum design speed of 80 kilometers per hour and a
maximum service speed of 70 kilometers per hour while the average speed is 35
kilometers per hour. The monorail’s maximum gradient shall not exceed 6% and the
minimum horizontal radius shall be not less than 45-70 meters (40 meters for the depot).
Because of its rubber tires, the monorail’s acceleration and deceleration rates are better
than steel-tired systems. However, the comfort of passengers, particularly standees, must
be considered as well.
Monorail has two-or four-axle bogies, driven by 750 Vdc and 1,500 Vdc traction
power supplied from the power rail system.
The monorail track beam is normally I-beam placed upon the pier with a span
length of about 20-30 meters. The column is on the pile cap, with a diameter of 1.5-1.8
meters, or Barette pile. The horizontal clearance from the track centerline to the support
column should be about 3.70 meters in the straight line section while the clearance should
increase in the curve line section.
The monorail capacity depends on the number of cars per trainset and frequency.
A monorail car can serve 16-26 seated passengers and has 17-29.6 m2 of standing area, thus
carrying a total of 122-200 passengers per car (at a standing passenger density of 6 pp/m2).
As Pink Line MRT System, Min Buri-Khae Rai section, will serve urban areas
throughout its total length of 34.5 kilometers, monorail is ideal for urban transit services.
Nowadays, there are a broad range of straddle monorail manufacturers, with carrying
capacity ranging from 3,000 to 30,000 passengers per hour per direction (pphpd).
When considering the forecast of medium-high ridership level, the Pink Line
requires a large-type monorail system with a passenger load capacity of over 30,000 pphpd.
At present, there are three manufacturers offering large straddle monorail system with a
proven track record widely recognized in many countries, namely Hitachi Ltd., Scomi
Group Bhd, and Bombardier Incorporation. The characteristics of large-type straddle
monorail are summarized in Table 3.2-1.
Size
Motor Car Length (m.) 15.10 10.4 13.03
Middle Car Length (m.) 13.80 9.50 11.84
Coupler (m.) 0.70 1.30 0.36
Width (m.) 2.98 3.00 3.14
Height (m.) 5.20 4.30 3.40
Door Width (m.) 1.27 1.50 1.63
Door Height (m.) 2.03 1.90 1.93
Max. Gross Axle Load (t.) 11 10 10
Tare Weight of Car (Metric ton) 11 10
Performance
Min. Curve Radius (m.) 70 (40 depot) 50 (40 depot) 45
Max. Gradient (%) 6 6 10
Max. Design Speed (km/hr) 90 90 85
Max. Operate Speed (km/hr) 80 80 75
Normal Accel. Rates (m/s2) 0.97 1.1 1.0
Normal Decel. Rates (m/s2) 1.1 1.1 1.0
Emerg. Decel. Rates (m/s2) 1.25 1.3 1.3
Technical
Bogie Placement Under Center Seat Under Center Seat End of Cars
Axles per Car 4 2 2
Power (VDC) 750/1500 750/1500 750/1500
Walk through Yes Yes Yes
Structure
Guideway beam width (m.) 0.85 0.80 0.66
Guideway beam height (m.) 1.50 1.6 (mid)/ 2.2 (end arch) 1.5 (mid)/ 2.1 (end arch)
Crosshead width (m.) 5.15 5.10 5.10
Typical Column Base (m. × m.) 1.2 × 1.6 0.81 × 1.42
Span Length (m.) 25 30 30
Capacity
Motor Car-Seat (seat) 26 22 16
Middle Car-Seat (seat) 24 20 16
Motor Car-Standing Space (m2) 29.00 17.00 18.58
Middle Car-Standing Space (m2) 29.68 17.00 18.58
Train-Capacity @ 4 cars-train; 569 356 361
4 pp/m2 (pp)
Train-Capacity @ 4 cars-train; 804 492 509
6 pp/m2 (pp)
Train-Capacity @ 4 cars-train; 921 560 584
7 pp/m2 (pp)
Ave. capacity per car (pp) 178 123 127
Emergency Walkway
An emergency walkway will be installed on a
track side or between two track beams, with
guard rails between tracks and walkway. In case
of an emergency, passengers will be evacuated
via this emergency walkway and then walk to the
nearest station, as depicted in Figure 3.2-4.
Train to Train Evacuation
An evacuation train may run from the same or in
opposite direction to the train in trouble.
Train to Ground Evacuation
Passengers may be evacuated from train to ground
by using crane truck, rope, or spiral chute.
The station design shall be consistent with MRT operation system. Design
considerations include interconnection with both present and future mass rapid transit
systems, convenient and safe access to and egress from station for passengers as well as
station entrance-exit facilities. This will facilitate passengers’ travel to their destinations.
The design of station elements is in compliance with NFPA 130: Standard for
Fixed Guideway Transit and Passenger Rail Systems regarding fire prevention, NFPA
101: Life Safety Code regarding passenger evacuation, and Thailand’s relevant
ministerial regulations.
The Pink Line is an elevated monorail system, with an average distance between
stations of approximately 1,200 meters, which will offer traffic convenience to residents
along Tiwanon, Chaeng Watthana and Ram Inthra roads until Min Buri intersection. At
present, traffic congestions are quite prominent in those areas. Consequently, the locations
of Pink Line stations were determined, taking into account densely-populated areas with
high travel demand. Table 3.3-1 presents the distance between stations.
With the adjustment of the originally-planned station locations and an increase in
the number of stations, the Consultant conducted field surveys of environmentally sensitive
areas within a radius of 500 meters from the centerline of project route, with details given in
Table 3.3-2.
Land use survey was carried out within a 500-m radius from the centerline of
project alignment of Pink Line MRT Project, Khae Rai-Min Buri section, at the sites of 30
stations, depot and park & ride building at Romklao intersection. The total distance is 34.5
kilometers. Field surveys were conducted in July 2013, with the results summarized as
follows:
Land use within a 500-m radius mainly consists of urban and built-up areas as
the project alignment is located in urban areas. Land use types comprise about 18,848.14
rai of urban land or 79.24% of the study areas, followed by 4,746.26 rai of other land use
types or 19.94%, and 196.26 rai of agricultural land which is equivalent to 0.82%. The
details of land use types are presented in Figure 3.3-1 and Table 3.3-3.
Table 3.3-3 Land Use within 500-m Radius in the Project Study Areas
Study Areas
Land Use Symbol
Sq.km. rai %
Urban and Built-Up Areas
Commercial areas U1 5.51 3,441.25 14.47
Residential areas U2 16.37 10,231.25 43.01
Government/state enterprise areas U3 5.06 3,160.63 13.29
Educational institutes U4 0.90 563.75 2.38
Religious/archaeological and historical places U5 0.41 255.63 1.07
Medical facilities U6 0.31 196.25 0.82
Industrial plants U7 1.17 733.13 3.08
Public parks/golf driving ranges/sports ground/ amusement parks U8 0.41 256.25 1.08
Abandoned factories U9 0.02 10.00 0.04
Total - 30.16 18,848.14 79.24
Agricultural Lands
Paddy fields A1 0.17 105.63 0.44
Grass farms A2 0.08 52.50 0.22
Mixed fruit orchards A4 0.01 8.13 0.03
Vegetable gardens A5 0.04 22.50 0.10
Fish ponds A6 0.01 7.50 0.03
Total - 0.31 196.26 0.82
Other Land Uses
Abandoned land M1 5.50 3,438.13 14.45
Water sources W1 0.37 229.38 0.96
Roadways - 1.73 1,078.75 4.53
Total - 7.59 4,746.6 19.94
Grand Total - 38.07 23,790.66 100.00
Source: TEAM Consulting Engineering and Management Co., Ltd., July 2013
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1: Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Figure 3.3-1 : Land Use within 500 m from the Centerline of Project Alignment (Cont’d)
Urban and Built-Up Land: This is the major land use type in the study areas,
occupying 18,848.14 rai or 79.24% of the total land. The land uses comprise 10,231.25 rai of
residential area or 43.01%, followed by 3,441.25 rai of commercial areas or equivalent to
14.47%, 3,160.63 rai of government/state enterprise land or 13.29%, 733.13 rai of industrial
plants or 3.08%, 563.75 rai of educational institutes or 2.38%, 256.25 rai of public parks/golf
courses/sports ground/amusement parks or 1.08%, 255.63 rai of religious/archaeological
places or 1.07%, 196.25 rai of medical facilities or 0.82%, and 10.00 rai of abandoned
factories or 0.04%.
Agricultural Land: This land use type occupies the smallest portion of land,
covering 196.26 rai or 0.82% of the total land. Agricultural lands include 105.63 rai of paddy
fields or 0.44%, 52.50 rai of grass farms or 0.22%, 22.50 rai of vegetable gardens or 0.10%,
and 8.13 rai of mixed fruit orchards or 0.03 as well as 7.50 rai of fish ponds or 0.03%.
Other Land Uses: This type is second largest after the urban and built-up
land, with 4,746.6 rai or equivalent to 19.94% of the total. These lands consist of 3,438.13
rai of abandoned land or 14.45%, 1,078.75 rai of roadways or 4.53%, and 229.38 of water
sources or 0.96%.
In addition, drainage conditions along Chaeng Watthana and Ram Inthra roads
were studied, taking into account the 2011 flood, for the design of the Pink Line stations
and elevated structures, as depicted in Figure 3.3-2. The study was aimed at avoiding the
obstruction of road drainage along the Pink Line alignment, with the following results.
For the construction of the Pink Line elevated stations along Ram Inthra
road, no station overlaps with the alignment of canals that were used to drain floodwaters in
2011. Moreover, no station structure will be built in drainage canals.
It is therefore concluded that the station structures of Pink Line MRT
Project, Khae Rai-Min Buri section, will not impede drainage of water from the areas north
of Ram Inthra road in case of inundation similar to the 2011 flood.
(2) Drainage from the Areas North of Chaeng Watthana Road
During the 2011 flood period, the areas north of Chaeng Watthana road
were submerged by the overflows from Rangsit siphon via Khlong Prapa in combination
with water overtopping the Khlong Rangsit flood dike. Floodwaters had to be drained
mainly via Khong Prem Prachakon into Khlong Bang Khen and Khlong Bang Sue while
part of the flood was pumped into Khlong Ban Mai to discharge into the Chao Phraya
River. Generally, when the water level in the Chao Phraya River drops, some water will
flow back into Khlong Rangsit and will be then pumped into the Chao Phraya River.
Floodwaters in Chaeng Watthana Road will be drained into Khong Prem Prachakon mainly
via drains on both sides of the road as well as pumping into Khong Prem Prachakon.
For the construction of the Pink Line elevated stations along Chaeng
Watthana road, there is no station overlying the alignment of canals that were used to drain
floodwaters in 2011. Besides, no station structure will be built in drainage canals.
Consequently, it is concluded that the station structures of Pink Line MRT
Project, Khae Rai-Min Buri section, will not hamper drainage of water from the areas north
of Chaeng Watthana road in case of inundation similar to the 2011 flood.
Figure 3.4-1 : Cross Section and Longitudinal Section of Station Building Type 1 with 15-m Height
Figure 3.4-2 : At Grade Floor of Station Building Type 1 with 15-m Platform Height
Figure 3.4-3 : Concourse Level of Station Building Type 1 with 15-m Platform Height
Figure 3.4-4 : Platform Level of Station Building Type 1 with 15-m Platform Height
Figure 3.4-5 : Roof Plan of Station Building Type 1 with 15-m Platform Height
Figure 3.4-6 : Cross Section and Longitudinal Section of Station Building Type 1 with 14-m Platform Height
Figure 3.4-7 : At Grade Floor of Station Building Type 1 with 14-m Platform Height
Figure 3.4-8 : Concourse Level of Station Building Type 1 with 14-m Platform Height
Figure 3.4-9 : Platform Level of Station Building Type 1 with 14-m Platform Height
Figure 3.4-10 : Roof Plan of Station Building Type 1 with 14-m Platform Height
Station Size: 3rd floor is platform level, 24.6 m wide and 110 m
long
2nd floor is concourse level, 24.6 m wide and 116 m long
1) PK01 Nonthaburi Government Center
station
2) PK02 Khae Rai station
3) PK03 Sanambin Nam station
4) PK04 Samakkhi station
5) PK05 Royal Irrigation Department station
6) PK06 Pak Kret station
7) PK07 Pak Kret Bypass station
8) PK08 Chaeng Watthana-Pak Kret 28
station
9) PK11 Chaeng Watthana 14 station
10) PK12 Bangkok Government Complex
station
11) PK18 Lat Pla Khao station
12) PK19 Ram Inthra 31 station
13) PK20 Maiyalap station
14) PK21 Watcharaphon station
15) PK22 Ram Inthra 40 station
16) PK23 Khu Bon station
17) PK24 Ram Inthra 83 station
18) PK25 East Outer Ring Road station
Number of Stations: 15-m height, totaling 22 stations:
19) PK26 Nopparat Rajathanee station
20) PK27 Bang Chan station
21) PK28 Setthabutbamphen station
22) PK29 Min Buri Market station
14-m height, totaling 4 stations:
1) PK10 Si Rat station
2) PK13 TOT station
3) PK15 Phranakhon Rajabhat University
station
4) PK17 Ram Inthra 3 station
(b) Type 2
Station Design: This is a two-level elevated station, consisting of at
grade floor which is concourse level, and the 2nd floor
which is platform level. Train operation and building
systems are located in a separate building (2 stories)
adjacent to station building, as illustrated in Figures
3.4-11 to 3.4-14.
Station Size: 2nd floor is platform level, 19 m wide and 110 m
long
At grade floor is concourse level, 12 m wide and 143.5 m long
Number of Stations: 1 station: PK09 Muang Thong Thani station
Figure 3.4-11 : Cross Section and Longitudinal Section of Station Building Type 2 with 9-m Platform Height
Figure 3.4-12 : At Grade Floor of Station Building Type 2 with 9-m Platform Height
Figure 3.4-13 : Platform Level of Station Building Type 2 with 9-m Platform Height
Figure 3.4-14 : Roof Plan of Station Building Type 2 with 9-m Platform Height
(c) Type 3
Station Design: This is a two-level elevated station, consisting of at
grade floor which is concourse level, and the 2nd floor
which is platform level. The station is located parallel
to the existing road, as shown in Figures 3.4-15 to
3.4-18.
Station Size: At grade floor is concourse level, 28.5 m wide and
98 m long
2nd floor is platform level, 30 m wide and 110 m long
Number of Stations: 1 station: PK14 Lak Si station
(d) Type 4
Station Design: This is a two-level elevated station, consisting of at
grade floor which is concourse level, and the 2nd
floor which is platform level, with a skywalk connec-
ting to the Orange Line in the future, as depicted in
Figures 3.4-19 to 3.4-22.
Station Size: At grade floor is concourse level, 24.6 m wide and
110 m long
2nd floor is platform level, 24.6 m wide and 110 m long
Number of Stations: 1 station: PK30 Min Buri station
(e) Type 5
Station Design: This elevated station building has two levels. At
grade floor will house concourse level and building
system. The 2nd floor is platform level, as depicted
in Figures 3.4-23 to 3.4-26.
Station Size: At grade floor is concourse level, 132.5 m wide and
184.5 m long
2nd floor is platform level, 132.5 m wide and 184.5 m long
Number of Stations: 1 station: PK16 Wat Phra Si Maha That station
(2) Uniqueness of Stations
To create uniqueness of stations, building elements feature the unique Thai
architecture such as station roof where curved lines will be applied to the station design in
order to create a sense of gracefulness, aesthetics and modernity, as presented in Figures
3.4-27 and 3.4-28.
Figure 3.4-15 : Cross Section and Longitudinal Section of Station Building Type 3 with 9-m Platform Height
Figure 3.4-16 : At Grade Floor of Station Building Type 3 with 9-m Platform Height
Figure 3.4-17 : Platform Level of Station Building Type 3 with 9-m Platform Height
Figure 3.4-18 : Roof Plan of Station Building Type 3 with 9-m Platform Height
Figure 3.4-19 : Cross Section and Longitudinal Section of Station Building Type 4 with 9-m Platform Height
Figure 3.4-20 : At Grade Floor of Station Building Type 4 with 9-m Platform Height
Figure 3.4-21 : Platform Level of Station Building Type 4 with 9-m Platform Height
Figure 3.4-22 : Roof Plan of Station Building Type 4 with 9-m Platform Height
Figure 3.4-23 : Cross Section and Longitudinal Section of Station Building Type 5 with 11.10-m Platform Height
Figure 3.4-24 : At Grade Floor of Station Building Type 5 with 11.10-m Platform Height
Figure 3.4-25 : Concourse/Platform Level of Station Building Type 5 with 11.10-m Platform Height
Figure 3.4-25 : Concourse/Platform Level of Station Building Type 5 with 11.10-m Platform Height
Figure 3.4-26 : Roof Plan of Station Building Type 5 with 11.10-m Platform Height
(4) Signage
(a) Standard Signs in Stations
There are five types of station signage according to the following
communication purposes.
(1) Directional Signs
Directional signs shall direct passengers to their destination inside
and outside of the stations.
Materials: Stainless steel frame, Aluminum Composite surface
or Color Acrylic;
Location: At entrances, exits, junctions, way-up and way-down;
Installation: Hanging from upper structure;
Color: Standard color of the background shall be white, with
black letters.
(2) Identification Signs
Identification signs shall indicate room names, such as function of
rooms/areas, e.g. public telephone, ticketing office; locations of facilities, etc.
Materials: Laminate panel with stainless steel mounting;
Installation: Wall fixing or hanging from upper structure;
Color: White surface with black letters.
(3) Information Signs
Information signs shall provide information to passengers, e.g.
route map, station location map, fare signs etc.
(4) Statutory and Warning Signs
Statutory and warning signs shall be installed in prohibited or
hazardous areas, i.e. No entry signs, Do not enter track area signs, Wait here signs, etc.
(5) Notice Board
Notice board displays public messages to passengers such as
announcement, general standard boards.
The station design of Pink Line MRT Project has taken into consideration
accessibility for the disabled and elderly, with accessible facilities such as ramps, lifts and
toilets as well as accessible parking spaces and toilets at the park & ride building.
Persons with Disabilities Empowerment Act, B.E.2550 defines that “persons
with disabilities/disabled persons” shall mean persons who encounter certain limitations
in performing their daily activities or social participation due to impairment in vision,
hearing, mobility, communication, mind, emotion, behavior, intellect, learning or any
other impairment along with various difficulties, and specifically need some assistance to
perform their daily activities or participate in social activities as ordinary persons.
There are 5 types of disabled persons who are eligible for MRT fare exemption,
namely:
Visual impairment
Hearing or communication impairment
Physical or mobility impairment
Mental or behavioral impairment
Intellectual or learning impairment
Universal Design for Mass Transit System is design for all user groups in the
society, targeted at creating an accessible environment. For the design of mass transit
system : an important public transport mode, accessibility shall be integrated into the
building and facility design. This is to accommodate travel needs of all people including
the elderly, disabled and disadvantaged people who have limitations to use or access to
mass transit services in order to enable equitable use by all people.
(1) Universal Design
Universal Design, as illustrated in Figures 3.4-29, is an environmental
design concept of universally and equitably usable buildings and products for everyone in
the society without any need for adaptation or specialized design for any particular group of
people, whether they be female or male, persons with normal walking ability or requiring
wheelchairs, persons with normal vision or visual impairment, a child or an adult, literate or
illiterate persons, etc. The Universal Design takes into account usability and accessibility
for everyone. Consideration is first given to address how to offer equal opportunity to
people with different abilities to access buildings and facilities, such as the elderly, people
with health problems, expectant mothers, short-statured persons, baby on pushchair,
children, and persons with disabilities, e.g. visual impairment, hearing impairment, physical
impairment, mental impairment, or illiterate persons, etc. Even though these people may
have physical, intellectual or mental limitations, they are part of the society which should
be taken care of so that they can happily live among persons with normal abilities. For
example, ramps should be provided for sidewalks and public buildings to facilitate
wheelchair users or tactile ground surface indicators for visually impaired persons. This
will enable these people to conveniently and safely undertake outdoor activities.
to be conveniently and safely usable by all people. The principles of Universal Design are
presented in Figure 3.4-30.
(b) Accessible telephones, taking into account wheelchair users and the
elderly including people in general.
(d) Accessible ramp design for wheelchair users and the elderly
(e) Accessible toilets for wheelchair users, the elderly and expectant
mothers
Stainless steel bars will be installed in toilets for the elderly and expectant
mothers. At least one accessible toilet will be provided for wheelchair
users in public toilets (this can be used by expectant mothers, persons
with children or baby pushchair, including diaper changing station).
Accessible Toilet Design with Braille Indicators on the Floor for Visually Impaired Persons
(f) Accessible walkway design for visually impaired persons will include
tactile ground surface indicators to guide visually impaired persons to
safe walkways. For example, ramps will be provided at walkway edges
at intersections to facilitate wheelchair users, and tactile indicator tiles
will be installed in the MRT station areas for visually impaired persons.
(g) Tactile floor surface will be designed and installed to provide inter-
connectivity to public facilities around the station, resulting in safe and
barrier-free circulation for visually impaired persons
(h) Accessible lifts will be provided for all people, with installation of call
and control buttons for the disabled and wheelchair users as well as
buttons with Braille marking indicators and tactile blocks for visually
impaired persons
(i) Staircase Design
Height of each step will be reduced and color strips installed to provide
greater visibility. There will be several levels of stair handrails to
facilitate people of different height such as children, adults, the
hunchback elderly, etc.
Since the station length is not very long, landscape at traffic medians and
footpaths shall be designed as hardscape. Two main reasons are low maintenance cost and
convenience for disabled people.
For stations with sufficient space for softscape, such as interchange stations,
plants shall be selected taking into account ease of maintenance. Landscape design shall
emphasize pleasant atmosphere and softened appearance of the station and structures.
The design load of the monorail track beam shall be as shown in Figure 3.5-1.
Figure 3.5-2 : Comparison of Forces of Track Beam for Span Length of 20.0,
22.5, 25.0, 27.5 and 30.0 meters
The selection of such track beam makes it possible for efficient control of
component manufacturing. The superstructure of the monorail is the precast girder. There
are 2 types of beam based on the span length. Pre-stress concrete girder shall be applied
for the guideway beam that does not exceed 25 meter long and steel girder bridge shall be
applied for the guideway beam that is longer than 25 meters.
Type 1 As for the standard span that does not exceed 2 5 meter long, pre-
stress concrete girder shall be applied as shown in Figure 3.5-3.
Type 2 Regarding the long span with the span length of more than 25 meters,
steel girder bridge shall be applied as illustrated in Figure 3.5-4.
Pre-stress concrete I-Girder or steel girder bridge with the depth of 1.50 to 2.00
meters and the length of not more than 25 meters shall be used.
It is used when the steel girder bridge is exceptionally long, that is, longer than
25 meters to 8 0 meters. The steel girder is applied in the sections that require long span
like road crossing or canal crossing. It shall also be applied to the highway right-of-way
of 30 meter wide or more as shown in Figure 3.5-4.
3.5.3 Substructure
Figure 3 . 5 -5 and Figure 3 . 5 -6 show the cross section and dimension of the
viaduct. There are 6 structures of pier that support the viaduct.
One track on single pier : Concrete girder or steel girder bridge is used.
One track on eccentric single pier : Concrete girder or steel girder bridge is
used to support the one track monorail. The eccentric single pier is laid to
avoid barriers.
Double track on single pier : Concrete girder or steel girder bridge is used
to support the double track monorail. The distance of the guideway beam
is 4.3 meters.
Double track on eccentric single pier: Concrete girder or steel girder
bridge is used to support the double track monorail. The eccentric single
pier is laid to avoid barriers. The distance of the guideway beam is 4.3
meters.
Portal structure with 2 piers with one track and double track
Portal structure with 3 piers and double track
The applied concrete pier of viaduct shall have the cross section of approx.
2 .0×2.0 meters with approx. span length of 2 5 meters. Pile cap with a single pile of 2.0
meters diameter supports a concrete pier of viaduct as shown in Figure 3.5-5 and Figure
3.5-6.
The civil works of the viaduct that passes over the road beneath start with the
construction of bored pile, foundation, pier and installation of guideway beam, respectively.
As bored pile work and the installation of guideway beam need the cut and cover, it is
unavoidable to use some traffic lanes for the construction of retaining structure and bored
pile. Therefore, some traffic mitigation measures are established.
(1) Coordinating with involved agencies for traffic planning for vicinities of
construction area and suggesting other routes to avoid construction area;
(2) Controlling construction area making it impede the traffic as minimal as
possible, managing lane transition and providing sign of construction area;
(3) Coordinating with all involved parties when traffic diversion is required;
and
(4) Establishing traffic management plan that is consistent with the construction
work plan, construction process and construction method of the track beam. Construction
will be divided into sub-process to minimize impact on traffic flow during construction.
Considerations will be made for important factors like road capacity before and during
construction, soil transfer, construction material transportation, security and safety, etc.
Traffic management plan during construction shall be considered and approved by directly
involved agencies like Traffic and Transportation Department, Bangkok Metropolitan
Administration, Royal Thai Police, etc. prior to starting construction.
A single large bored pile or two bored piles lining up in the same row shall be
used in the Project as shown in Figure 3.5-7. This pattern of bored pile laying makes pile
cap smaller than the width of typical traffic island which is approx. 4 meters. In the areas
of considerable restrictions, barrette piles shall be used. An excavator with the narrow
side of approx. 0.8to1.0 meter shall be operated instead of a drill bit. The advantages of
using barrette piles include capability to work in limited area, horizontally and vertically.
Also, larger size of the piles can be used through more excavation. However, the cost of
barrette pile is more expansive than bored pile. In regard to pier, a single pier is typical as
it is convenient and fast for construction. This is exceptional in some areas where the
track centerline is not in the line of traffic island. In such areas, portal structure will be
used instead of single pier structure. The construction process is detailed below.
The construction of pile, footing and pier for track starts with stripping of approx.
4 meter with the allowance of 2 meters on lateral sides for operation. As a result, the
required construction area is about8meters.The construction area will intrude approx. 2
meters of the rightmost lane; so it remains 4 lanes on the road where the construction
proceeds ( 2 lanes per direction) . The construction in this part will last about 45 days: 28
days for pile work, 5 days for pier, 9 days for 3 viaduct piers(3 days for each pier) and
3surplus days. The construction zone of specific phase will be isolated for not exceed 150
meter long.
As for portal structure, the pier position is in the pavement line. The
construction of footing and piers, which covers the area of approx. 8 meters in width,
requires lane closure on the pavement sides. The construction will be proceeded on the
alternate side to avoid traffic problem. Then piers are constructed and the beam formwork
of portal structure is installed. The installation will be made at nighttime with traffic closure
for 1-2 hours while lifting the beam formwork for safety reason. Then the concrete beam is
cast and pre-stressed, respectively when it has unconfined compressive strength as
designed.
3.5.4.2 Installation of Precast Girder when Track Passes Traffic Island Line
The installation of precast girder for monorail needs the area of approx. 4 meter
wide for safety reason while casting closure joint. In this step, resurfacing work can be
done concurrently. Once the precast girder is installed, road surface return can be done shortly.
3.5.4.3 Construction of Portal Structure when Track does not Passes Traffic Island
Line
Portal structure shall be applied when the track centerline deviates from traffic
island line. In this case, piers and footing shall be laid on the pavement line. The
construction of portal structure needs traffic closure on the pavement side in order to
build footing and piers in the area of approx. 5.0 meter wide. The construction will be
proceeded on the alternate side to avoid traffic problem. Then piers are constructed and
the beam formwork of portal structure is installed. The installation will be made at
nighttime with traffic closure for 1-2 hours while lifting the beam cast for safety reason.
Next, cast and pre-stress concrete beam, respectively when the concrete beam has
unconfined compressive strength as designed as shown in Figure 3.5-8.
Figure 3.5-9 : Drop-off Area, Bicycle Parking and Elevator for Disabled Person at Station
Figure 3.5-10 : Drop-off Area at Min Buri Station (PK30) in Front of Park & Ride
(4) Study an Average Vehicle Occupancy departure and arrival using case study
projects. The resulting outcome will be used to calculate the number of vehicles of any kind
for the whole day and peak hours.
(5) Study the time spent to pick up and drop off passengers of different modes
of travel such as by car, by taxi, by bus, by public carrier, etc. to calculate service
capability.All required data which are obtained are used for calculation of the requirement
for facilities of each station for passengers of the Pink Line Project (Khae Rai-Min Buri
Section). All required data are used for calculation of requirement for facilities of each
station for passengers of the Pink Line Project (Khae Rai-Min Buri Section). These
facilities consist of the stop and parking lot for buses, parking lot for van and minibus, the
stop for public carriers and drop-off area.
It is necessary to design the Park & Ride for passengers of the Pink Line Project
(Khae Rai-Min Buri Section) to reduce use of personal cars. According to this study, one
Park & Ride at Rom Klao Intersection is required. This Park & Rideshares the area with
the depot of the Project.
The 3-storey Park & Ride can accommodate 3 ,0 0 0 cars (1 ,0 0 0 cars/storey).
Apart from this, the Consultants improved the open space of Pak Kret station (PK06) for
use as outdoor car parking which can accommodate about 30 cars.
As not all 30 stations are located near bus stops and the request for additional
bus stops needs to be approved by involved agencies such as Bangkok Metropolitan
Administration (BMA) and Bangkok Mass Transit Authority (BMTA), the Consultants
assigned the drop-off areas beneath 29 stations (PK01-PK29) on both sides of the road, 1
Park & Ride (Min Buri station-PK30) and 1 car parking (Pak Kret station-PK06) for the
convenience of the public.
Figure 3.5-11 : Impact from Differential Settlement at Pier of Viaduct and Road
damage resulting from differential settlement. Owing to the fact that the road in the
project area was constructed and has been used for a very long time, it is implied that the
consolidation settlement of the Bangkok clay because of the weight of the embankment
and the pavement structure no longer occurs. Thus, the potential long-term settlement will
be resulted from groundwater pumping and natural compressibility. This settlement
evaluation refers to land subsidence level in Bangkok Metropolitan due to groundwater
pumping, 2002-2007 as shown in Figure 3.5-12. The study reveals that land subsidence
level along the project alignment will be less than1 centimeter/ year. Considering road
settlement in 50 year-service life prior to resurfacing, it will subside for not more than50
centimeters.
However, soil boring shall be determined in the detailed design.
Furthermore, the data of land subsidence as a result of groundwater pumping shall be
collected for the clear analysis of subsidence.
Project
alignment
Filler
Filler(mater
ial) Coating for reduction in
There are 2 causes of pile settlement: immediate settlement due to load and
consolidation settlement due to land subsidence and constant load. As the end of the pile
is deeper than 50 meters, pile settlement in the long-term will be minimal. Load test will
be conducted for immediate settlement. The service load (pile capacity) shall not make
pile settlement exceed 25 millimeters. That is to say settlement from the service load of
each pier shall not exceed 12.5 millimeters. Combined with consolidation settlement, it
shall not exceed 25 millimeters. Differential settlement throughout the project life shall
100 years of the service life of structure.
3.6.1 Selection of Site and Size of Depot and Park & Ride Building
Figure 3.6-1 Location of Depot and Park & Ride Building at Rom Klao Intersection
Figure 3.6-2 Existing Conditions of Depot and Park & Ride Building Site
at Rom Klao Intersection
to accommodate all trains of the Pink Line, a total of 56 trains, and 3,000 car parking
spaces as well as an increased number of trains resulting from the government’s policy of
20-baht flat fare. A larger building can be built because the existing land uses at Rom
Klao intersection are paddy fields and grass farms. To reduce the operation and
maintenance (O&M) costs arising from the operation of empty morning trains from the
terminal station PK30 Min Buri to the first station PK01 Nonthaburi Government Center,
a stabling area for 4 trains is provided at Nonthaburi Government Center so that trains can
park in the nighttime and start services right away in the morning.
Therefore, there is only one depot and park & ride building at Rom Klao
intersection for Pink Line MRT Project, Khae Rai–Min Buri section. It has potential to
adequately provide services to the Pink Line patrons in the future. In addition, the large
park & ride building that can accommodate 3,000 cars will attract more people to use
MRT services. This will also help reduce the use of private cars and alleviate the current
traffic congestions.
Additionally, the Consultants have arranged a vacant area at PK06 Pak Kret
Station to be car parks for private cars and public cars to cater for MRT passengers. The
parking area for private cars is at grade open area for 30 cars. A parking area is also
provided for public cars such as vans, taxis, etc. Passengers can access the MRT station
through 2 routes: Tiwanon Road and Chaeng Watthana Road. Internal road system in the
station has been designed for passengers’ convenience and safety, with details presented
in Figure 3.6-3.
Entrance
Entrance-Exit
Pink Line MRT Project, Khae Rai-Min Buri Section
Exit
Car parks for private cars
Drop-off Area
3-84
Figure 3.6-3 Car Park and Public Car Park at PK06 Pak Kret Station
Amendment EIA Report 3-85
Chapter 3 Project Description
Pink Line MRT Project, Khae Rai-Min Buri section, is one of the mass
rapid transits incorporated into the Mass Rapid Transit Master Plan in Bangkok
Metropolitan Region (M-MAP) with interconnection with 4 mass rapid transit projects, i.e.
Purple Line, Bang Yai–Bang Sue section; Commuter Train System (Red Line), Bang Sue–
Rangsit section; Green Line, Mo Chit–Saphan Mai section; and Orange Line, Bang Kapi–
Min Buri section. A park & ride building has been designed for each of the 4 lines that
intersect the Pink Line alignment in order to facilitate passengers, with details as follows:
Purple Line, Bang Yai–Bang Sue section, has 2 park & ride buildings. One is
located at Nonthaburi Intersection 1 Station, with 470-car parking capacity. The other is
located at Bang Rak Noi- Tha It Station with 1,244-car capacity. Passengers living around
Rattanathibet Road, Bangkok-Nonthaburi Road and vicinity can park their cars at the two
park & ride buildings to use the Purple Line and then can connect to the Pink Line at PK01
Nonthaburi Government Center Station-the starting station of Pink Line MRT Project,
Khae Rai–Min Buri section.
Commuter Train System (Red Line), Bang Sue–Rangsit section, has 1 park &
ride building, located at Bang Sue Grand Station with 1,000-car capacity. Passengers
living in Bang Sue and vicinity can park their cars to use the Red Line and get on the Pink
Line at PK14 Lak Si Station.
Green Line, Mo Chit–Saphan Mai section, has 2 park & ride buildings, located
at Km. 25 Station with 1,043-car capacity and at Khu Khot Station with 713-car capacity.
Passengers living in Rangsit, Lam Luk Ka, Pathum Thani, and vicinity can park their cars
to board the Green Line and then connect to the Pink Line at PK16 Wat Phra Si Maha
That Station.
Orange Line, Bang Kapi–Min Buri section, has 2 park & ride buildings,
located at Min Buri Station with 3,000-car capacity (a joint facility with the Pink Line),
and at Khlong Ban Ma Station with 1,200-car capacity. Passengers living in
Ramkhamhaeng, Hua Mak, Bang Kapi, Saphan Sung, Bueng Kum and vicinity can park
their cars to connect to the Orange Line and Pink Line at PK30 Min Buri Station.
Therefore, people will be able to park their cars at the park & ride
buildings provided by these four projects, with service area coverage in Bangkok and
Nonthaburi. The parking areas are sufficient to meet the passengers’ need. As a result,
expropriation of additional land and built structures along the alignment of Pink Line
MRT, Khae Rai–Min Buri section, is not required, leading to the reduction of
resettlement and land acquisition impacts.
3.6.2 Design Criteria for Depot and Park & Ride Building
3.6.3 Location and Design Concept of Depot and Operation and Control Center,
and Park & Ride Building
The layout of depot and park & ride building was determined, taking into
account convenient use and functional relationship between buildings and activities, so as
to achieve optimum utilization and continuous flow of functions. Emphasis is also given
to provision of necessary facilities for staff, maximum safety and efficient evacuation in
case of an emergency. The management of the depot and park & ride building is
explained in details as follows:
(2) Layout Arrangement of Depot and Park & Ride Building
The internal management of the depot and park & ride building at Rom
Klao intersection is divided into two main activities: park & ride building and depot, with
details as follows:
Park & ride building is a 3-storey building, located adjacent to Ramkhamhaeng
Road. The total area is about 50.57 rai, with parking capacity of 3,000 cars (1,000
cars/floor).
Depot is located behind the park & ride building, on 178.43 rai of land.
The depot consists of Administration and OCC Building, main workshop, bulk
substation, hazardous building, storm water pump house, wastewater treatment plant,
guard house, stabling yard for 56 trains, and canteen. The details of layout arrangement
are presented in Table 3.6-2, and Figures 3.6-4 to 3.6-13.
Table 3.6-2 Components of Depot and Park & Ride Building
Number of Usable Area Building Size (m)
No. Building/Office
Floors (m2) (W x L)
DE01 Administration and OCC building 5 3,965 13x61
DE02 Main workshop 1 12,782 77x166
DE03 Park & ride building 3 95,064 136x233
DE04 Bulk substation 2 924 21x22
DE05 Hazardous building 1 136 8x17
DE06 Storm water pump house 1 27 5x5.40
DE07 Wastewater treatment plant 2 221 6.50x17
DE08 Guard house 1 8.32 2.60x3.20
DE09 Stabling yard 1 31,240 142x220
DE10 Canteen 1 960 24x40
Source: The Consultants, 2012
Bogie Repair Facility will be used for lifting bogie from the car
body. Monorail bogie will be removed by bogie drop system and then latched on to the main
track beam which can turn up or down as shown in Figure 3.6-17. The engineering
specifications of Bogie Repair Facility for Monorail System are illustrated in Figure 3.6-18.
Figure 3.6-17 Turning and Lifting up-down of Monorail Main Track Beam
Train Washing Plant: Trains will be washed in this building and the tracks
inside the plant are about 150 m long. A 6-car train will slowly move into the train
washing plant, and the washing process will be done by automatic washing machine.
Wastewater from the washing process will be stored in a tank and treated by the
wastewater treatment system installed in the washing plant where oil and mud will be
separated from water. The effluent will be used for watering plants or floor cleaning. The
typical train washing plant is presented in Figure 3.6-24.
Figure 3.6-25 Catchment in Depot and Park & Ride Building at Rom Klao
Intersection
adjacent to Ramkhamhaeng Road. The staff parking lot is provided near Office Building
and Operation Control Center
- Depot and Stabling yard. To access these areas, the trains
have to run on the ramp passing the front door checking point only. The Platform road
connects buildings that need service road for forklift and trucks, Wheel Turning Plant,
Wheel Diagnostic Facility, Hazardous Building, Garbage Storage Building, Train
Washing Plant, Heavy Maintenance Workshop, Light Maintenance Workshop, Material
Storage Building, Permanent Way Workshop Building and Bulk Substation. The road
inside is approximately 6-15 m. in width and used as transportation route of equipment
and machinery, such as trains, power supply, etc. The road can be used before the Project
commencement and when additional equipment and machinery are ordered.
- Service roads around the Depot-Service roads are provided
for safety reason. These service roads connect Administration and Operation Control
Center Building (OCC), Train Operation Control Staff Dormitory and Office. Service
roads can be in the same level or almost in the same level of to the road outside the
Depot. The two types of service roads are designed for the access of fire engine to all
buildings.
(d) Traffic Management for Depot and Park & Ride
Traffic Management of Depot and Park & Ride
The traffic management of Depot and Park & Ride Building of
Rom Klao Intersection. The Project designed the entrance-exit that passengers can access
the Park & Ride Building through 2 main roads, Ramkhamhaeng Road and Rom Klao
Road.
Traffic Management of Entrance-Exit through 2 main roads
Entrance-Exit No.1: The entrance from Ramkhamhaeng Road
can lead to the Park & Ride Building in 2 ways below:
Directional Ramp: There is the left diversion from Ramkhamhaeng
Road, on Khlong Song Ton Nun bridge for the passengers access to Park & Ride Building
as shown in Figure 3.6-26 and Figure 3.6.27.
Level road: When driving past Suwinthawong Intersection,
passengers can turn left to Depot to enter in to and exit from Park & Ride Building.
Entrance-Exit No.2: Preliminarily, traffic lights are provided for
the entrance from Rom Klao Road as shown in Figure 3.6.28. In the future when the
traffic is more congested, there will be the directional ramp from Depot and Park & Ride
Building to Rom Klao Road for both entry and exit points.
Figure 3.6-30 Layout of Depot and Park & Ride Building at Rom Klao Intersection
For the size of reserved water tank within Depot and Park & Ride
Building at Rom Klao Intersection, 4 tanks of 50 m3, totaling 200 m3/day were replaced
with 4 tanks of 150 m3, totaling 600 m3 for 3 days. In addition, water tank for reserved
water shall be provided for firefighting for at least 30 minutes at Depot and Park & Ride
Building. This matter is added in management of water consumption, safety and security
and fire protection as follows:
The consumable water of Depot and Park & Ride Building at Rom
Klao Intersection is supplied from Metropolitan Waterworks Authority through water
pipes to reserved underground water tank of 4 tanks of 150 m3, totaling 600 M3 .Water is
then pumped to all buildings within the Depot and Park & Ride Building for all activities.
The volume of consumable water of Depot and Park & Ride Building at Rom Klao
Intersection can be divided by types of activities below:-
Administration and Operation Control Center
- The Operation Control Center has approximately 100 staffs
and water use ratio is 70 liters/person/day (according to Design of Wastewater and Storm
Drainage System Guidelines, Engineering Institute of Thailand, under H.M. the King’s
Patronage, B.E.2549), totaling 100 x 70 = 7,000 liters/ day or equivalent to 7.00 m3/ day.
- The Administration has approximately 150 staffs and water
use ratio is 70 liters/person/day (according to Design of Wastewater and Storm Drainage
System Guidelines, Engineering Institute of Thailand, under H.M. the King’s Patronage,
B.E.2549), totaling 150 x 70 = 10,500 liters/day or equivalent to 10.50 m3/day.
- The Depot Platform has 400 staffs at maximum and water
use ratio is 70 liters/ person/day (according to Design of Wastewater and Storm Drainage
System Guidelines, Engineering Institute of Thailand, under H.M. the King’s Patronage,
B.E.2549), totaling 400 x 70 = 28,000 liters/day or equivalent to 28.00 m3/ day.
- Staffs in other buildings and train control staffs who use the
building area are approximately 300 persons and water use ratio is 70 liters/person/day
(according to Design of Wastewater and Storm Drainage System Guidelines, Engineering
Institute of Thailand, under H.M. the King’s Patronage, B.E.2549), totaling 300 x 70 =
21,000 liters/day or equivalent to 21.00 m3/day.
Dormitory is to be used by 60 staffs at maximum and water usage
ratio is 200 liter/1 person/1 day (as per Guidelines for Reporting of Environmental Impact
Assessment of Accommodation for Community Services and Resort Project of Office of
Natural Resources and Environmental Policy and Planning, B.E.2542), totaling 60 x 200 =
12,000 liters/day or equivalent to 12.00 m3/day.
Canteen at the ground floor of OCC Building is to be used by 950
staffs at maximum and water use ratio is 50 liters/person/day (as per Guidelines for
Reporting of Environmental Impact Assessment of Accommodation for Community
Services and Resort Project of Office of Natural Resources and Environmental Policy and
Planning, B.E.2542), totaling 950 x 50 = 47,500 liters/day or equivalent to 47.50 m3/day.
Train Washing Plant will have 56 procured trains (Year 2047) at
maximum and water use ratio will be1,045 m3/day (according to Bangkok Mass Transit,
Extension Project, B.E.2543), totaling 56x 1,045 = 58.52 m3/day.
Therefore, water requirement of Depot and Park & Ride Building will
be equivalent to 184.52 m3/day or approximately 200 m3/day. If water needs to be
reserved for consumption for at least 3 days, it is necessary to use 4 reserved water tanks
of 150 M3/tank, totaling 600 m3.
(j) Wastewater Collection and Treatment Systems
Wastewater of Depot and Park & Ride Building at Rom Klao Intersection
originates from Administration and Operation Control Building, Dormitory, Canteen and
Train Washing Plant and which account for 80% of total used water (as per Guidelines
for Reporting of Environmental Impact Assessment of Accommodation for Community
Services and Resort Project of Office of Natural Resources and Environmental Policy and
Planning, B.E.2542). The wastewater can be divided into 2 types: wastewater from
activities of staffs, and wastewater from maintenance and train washing activities. The
total volume of wastewater from Depot and Park & Ride Building at Rom Klao
Intersection is equivalent to 184.52 x 0.80 = 147.62 m3/day as detailed in Table 3.6-5 and
Figure 3.6-31.
Table 3.6-5 Classification of Buildings within Depot and Park & Ride Building
at Rom Klao Intersection
Types of Buildings Wastewater Volume (m3/ day)
1. Administration and Operation Control Center 53.20
2. Staff dormitory 9.60
3. Canteen 38.00
4. Train washing plant 46.82
Total 147.62
Remark : Guidelines for Reporting of Environmental Impact Assessment of Accommodation for Community Services and Resort
Project of Office of Natural Resources and Environmental Policy and Planning, B.E.2542)
Figure 3.6-31 Summary of Wastewater Volume within Depot and Park &
Ride Building at Rom Klao Intersection
building site shall not block the sunlight and the wind so that it can make use of the
nature, making the area shady, comfortable with energy-saving and beautiful view. Site
planning contributes to the excellence of this project in terms of utilization, esthetics and
energy saving as shown in Figure 3.6-32.
(b) Concept of Architectural Design
The Project buildings are for administration, train operation and
maintenance. Utility space, size and relation of each building, the number of staffs and
organization were determined by specialists. The information is important for planning
inside the building. Regarding planning inside the building, architects create the layout
that meets requirements for optimization of technical utilization. Besides, secondary
utility space is added for operation of staffs and other engineering works. The buildings
should support technical works, and be convenient for building users. Buildings shall be
associated with outside environment and sunlight and wind direction which contribute to
energy saving. Suitable materials shall be selected for the floor, wall, and ceiling for
utility space that needs special care, i.e. special equipment room, operation room, etc. in
order to control the light and the noise. Moreover, the height of utility space is vitally
important. The height of utility space shall be suitable for utilization and the size of the
room. The height of utility space affects the feelings of building users. For example, a
lobby should boost the feelings of relief, joy and relaxation, etc., which contribute to
working efficiency. A canteen should create the feeling of relaxation. A meeting room
should be calm and tranquil with the light, sound and temperature that encourage meeting
environment, creativity and initiatives. Utility space, utilization and the atmosphere inside
buildings will influence the shape of the outside of the building, determination of opaque
wall, fanlight, and the shape of roof. Applied materials of the Project shall be controlled
for suitability and neatness. Although there are a lot of buildings, the buildings, overall,
shall be in harmony. Modern, durable, nice and enduring materials shall be selected.
Figure 3.6-32 Design concepts of Depot and Park & Ride Building at Rom
Klao Intersection
Intersection. The Park& Ride Building is a 3-floor reinforced concrete structure that
accommodates approx. 3,000 cars (1,000 cars/floor) as shown in Figure 3.6-33. It will
serve passengers living around Ramkhamhaeng Road and Rom Klao Road. Moreover, the
Project has provided an additional parking lot at Pak Kret Station (PK06) as shown in
Figure 3.6-34. This outdoor parking lot on the ground level is for approx. 30 cars and
public carriers, such as van, taxi, and others for passengers travelling from Tiwanon Road
and Chaeng Watthana Road.
(e) Usage of Park & Ride Building with other Mass Rapid Transit Projects
The Pink Line MRT Project, Khae Rai–Min Buri section is one of the
Mass Rapid Transit Master Plan in Bangkok Metropolitan Region that links other four (4)
projects such as Mass Rapid Transit Purple Line, Bang Yai-Bang Sue section, Commuter
Train Project (Red Line), Bang Sue-Rangsit section, Mass Rapid Transit Green Line,
Moe Chit-Saphan Mai section and Mass Rapid Transit Orange Line, Bang Ka Pi-Min
Buri section. The Park & Ride Building is designed for all projects for the convenience of
passengers with the following details:
Commuter Train System Project (Red Line), Bang Sue-Rangsit
section: One (1)
Park & Ride Building at Bang Sue Grand Station is provided for
1,000 cars for passengers living around Bang Sue and nearby areas to park their cars
before traveling by Commuter Train (Red Line) which links to Pink Line MRT Project at
Lak Si Station (PK14).
Figure 3.6-33 Location of Depot and Park & Ride Building at Rom Klao Intersection
Figure 3.6-34 Parking Lot for Cars and Public Carriers at Pak Kret Station (PK06)
Mass Rapid Transit Green Line, Moe Chit-Ku Kot section: Two (2)
Park & Ride Buildings are provided at Kor. Mor. 25 Station for 1,043 cars and at Ku Kot
Station for 713 cars. Therefore, passengers living around Rangsit, Lum Look Ka,
Pathumthani, and nearby areas are able to park their cars at both Park & Ride Buildings
before traveling by Mass Rapid Transit Green Line which links to Mass Rapid Transit
Pink Line at Wat Phra Si Maha That Station (PK16).
Mass Rapid Transit Orange Line, Bang Kapi-Min Buri section: Two
(2) Park & Ride Buildings are provided at Min Buri Station for 3,000 cars (shared with
Pink Line MRT Project, Khae Rai–Min Buri section) and at Klong Ban Ma Station for
1,200 cars. Therefore, passengers living around Ramkhamhaeng, Hua Mak, Bang Kapi,
Saphan Sung, Bung Kum, and nearby areas are able to park their cars at both Park & Ride
Buildings before traveling by Mass Rapid Transit Orange Line and Pink Line at Min Buri
Station (PK30).
As passengers can park their personal cars at Park & Ride Buildings
provided by all 4 Mass Rapid Transit Projects, which cover Bangkok and Nonthaburi and
as Park & Ride Buildings are sufficient for their needs, land acquisition and removal of
buildings of people living around Pink Line MRT Project, Khae Rai–Min Buri section are
not required. Therefore, it alleviates impacts from land acquisition and relocation.
For more convenience of train passengers who access the rail station
by bus, van, and taxi, etc., the Pink Line MRT Project, Khae Rai-Min Buri section, has
provided intermodal passenger transportation facilities. At PK01-PK29 stations, the
Consultants assigned Drop-off areas under the stations on both sides of the road. Rail
passengers will be picked up and drop off in these areas by personal cars, vans and taxis
in order to travel to the destination. Moreover, at Min Buri station (PK30), which is the
terminal station, the Park & Ride Building is designed for approx. 3,000 cars. At Pak Kret
station (PK06), the outdoor parking lot is provided for approx. 30 cars. Vans, taxis and
other public carriers can be parked inside the station.
Based on the forecast that the Pink Line (Khae Rai–Min Buri Section) Project
will require about 200 workers, estimation of water consumption, wastewater and solid
waste is described follows.
Water Consumption
Number of workers = 200 persons
Water consumption = 200 liters/person/day (Kriangsak, 1996)
Or = 40 m3/day
Wastewater
Based on the estimate that water consumption will be 200/liters/person/day
(Kriangsak, 1996), wastewater from toilets and other activities will be 80% of the daily
water usage (Kriangsak, 1996).
Wastewater = 32 m3/day
Regarding management of wastewater and solid waste during the construction
and operation periods, the proper wastewater treatment system was designed for the
project. Treated wastewater will be released into the sump provided in the project area
before being discharged into the public sump.
Since the project construction will take about 4 years, the Engineering Institute
of Thailand’s Standards (EIT Standard 1010-30) about temporary buildings for
construction workers have been applied to design the layout of the project’s worker
campsite. This is to ensure it will be arranged in an orderly fashion without causing any
impact to local communities in the project’s environs. Each campsite will cover an area of
1 rai and accommodate about 200 workers as illustrated in Figure 3.7–1. Details of the
worker campsite are as follows.
There are five 1-floor row house buildings. Each consists of 20 rooms (10
rooms in the front row and another 10 on the back row). Each room is for 2
persons. Therefore, each building can house 40 persons.
There are 20 toilets built in accordance with the relevant standards. 1
sanitary toilet is for 10 workers.
Two common bathing and washing areas and four water storage tanks, each
with a 4.8 m3 capacity, are provided.
Temporary ditches are provided around the campsite. There are also
sediment traps.
Refuse containers should be sufficiently provided at workers’ houses.
There is also a waste collection site for the responsible agency to collect for
further disposal.
Eight dry chemical fire extinguishers (15 lbs) are arranged for each
building.
Guardhouses are located at the campsite.
Sufficient public utilities, e.g. electricity, water supply, etc., are provided.
Solid Waste
Solid waste in the project site is divided into two major types: refuse and
construction waste.
Refuse consists of food scraps, wastepaper, plastic scraps, etc. Considering the
workers’ consumption activities, the waste generation rate was estimated at about 0.5
kg/person/day. Therefore, the amount of solid waste was computed as follows.
Number of workers = 200 persons
Waste generation rate = 0.5 kg/person/day
Amount of solid waste = 100 kg/day
Construction waste comprises rubble, including pieces of bricks, concrete,
wood, cement bags, and scarp metal. The generation rate of this waste is not certain.
Some materials can be reused (e.g. formworks) and some can be sold for recycling.
All solid waste generated in the project site will be collected and disposed of at
the sites specified by the Bangkok Metropolitan Administration (BMA) or the project
staff will contact BMA to collect solid waste from the project site for proper disposal.
According to the statistics on solid waste collection during 2012-2013, the quantities of
solid waste in Lak Si, Bang Khen, Bueng Kum, Khan Na Yao, and Min Buri districts
were 159.86-156.39 tons/day, 248.33-252.73 tons/day, 175.51-187.60 tons/day, 125.03-
128.01 tons/day, and 178.80-186.76 tons/day respectively (Environment Department,
BMA). Domestic waste in Bangkok are collected and transferred to 3 solid waste transfer
stations in Sai Mai, Nong Khaem, and On Nut districts as shown in Figure 3.7-3. Refuse
is normally conveyed to the landfills in Kamphaeng Saen district, Nakhon Pathom
province, and in Phanom Sarakham district, Chachoengsao province. Organic waste is
used to make compost at fertilizer plan in On Nut. As for infectious waste and hazardous
waste, BMA has assigned private companies to transfer and dispose of by using specific
method.
Upon commencement of construction activities for the Pink Line (Khae Rai-
Min Buri Section) Project, about 100 kg/day of solid waste will be generated. This
amount is considered slight when compared to the total waste in the aforementioned
districts. The responsible agency will be contacted to collect solid waste for proper
disposal.
Pursuant to Clause 4 in the Ministerial Regulations Prescribing the Standards
for Administration and Management of Occupational Safety, Health, and Environment in
Relation to Fire Prevention and Control, B.E.2555, in the workplace having ten
employees or more, the employer shall prepare the fire prevention and control plan,
Duties of Operators in Firefighting Team Structure in Case of Severe Fire (if any)
Operators Duties
Firefighting Director 1. Listen to the reports on the situation and order implementation of firefighting plan.
2. Request for assistance from related organizations.
3. Report the firefighting result to the superior
4. Provide information on fire event to mass media.
Electrical Department 1. In case of fire, rush to the scene and receive order to cut electricity from the Operations
Department.
2. Receive instructions from the Firefighting Director.
Operations Head of Operations Department must perform the following.
Department 1. In case of fire, the Head of Operations Department must divide his staff into two groups:
Machine Control Group and Firefighting Group.
a. Machine Control Group: In case of fire, the group must continue machine operations
until the Head of Operations Department orders to stop. In case of obtaining order to
stop machine operations or inability to operate machines, the group will join the
Firefighting Group.
b. Firefighting Group: In case of fire whether slight or severe, this group will leave the
machines without stopping them and rush to immediately extinguish fire. They will
follow the instructions of the Head of Operations Department. In case assistance
from other units is needed, the Head of Operations Department will have to order
first.
2. Upon being notified of fire, immediately contact safety officers, the Firefighting
Director, and the Press Center to inform of the emergency.
Communications and 1. Provide assistance and coordination with related persons.
Coordination 2. Receive instructions from the Firefighting Director and contact the Press Center.
Department 3. Give instructions on behalf of the Firefighting Director if assigned.
Firefighting 1. Provide assistance and coordination between the Firefighting Director, security guards,
Procurement and and related parties.
Support Unit 2. Receive instructions from the Firefighting Director and contact the Press Center.
- Coordinator 3. Give instructions on behalf of the Firefighting Director if assigned.
- Security Guards 1. Rush to the scene, and receive instructions from the Firefighting Director and the Head
of Communications and Coordination Department.
2. Prevent unauthorized persons from entering the place.
3. Safeguard the assets and materials moved by the Internal-External Transfer Department.
Internal-External 1. Responsible for identifying the safe places for keeping materials and assets.
Transfer Department 2. Provide convenience for transfer of materials and assets.
3. Provide vehicles and equipment for transfer of materials and assets.
Operations Support 1. Send safety order system (SOS) message.
Department 2. Employees who wish to help extinguish the fire have to report to the Firefighting
- Unit Responsible for Director who will assign them to the Operations Support Department.
Contacting other 3. In case of fire near machines, the firefighting team members should be those who
Fire Stations normally work in the area. Others should assist in conveying firefighting equipment.
4. Be around the scene of fire, waiting for orders from the Firefighting Director.
- Fire Pump 1. Start the fire pump immediately upon being informed of the fire occurrence.
Operation Unit 2. Control the fire pump during firefighting procedures.
3. In normal situation, regularly perform maintenance of firefighting equipment in
accordance with maintenance schedule.
Press/Communications 1. Upon being notified of fire, check whether the news is true.
Center 2. Inform of fire event.
3. Regularly follow up and update the event.
4. Request for help from related organizations.
5. Inform of the result after fire suppression.
The construction company shall coordinate with the responsible agency in the area such as
Environment Department, Bangkok Metropolitan Administration, Regional Environment
Office 6 ( Nonthaburi) , etc. to select suitable trees for planting. The landscape architecture
concept is shown in Figure3.8-1.The example of tree planting at the piers of track beam
along the rail alignment as illustrated in Figure 3.8-2.
The train operation plans of the Pink Line Project (Khae Rai-Min Buri Section)
are designed to accommodate the ridership along the routes and they are consistent with
the train capacity to accommodate the ridership. The train speed and frequency of service
meet international standards. The detailed train operation plans are given below.
Central Train Capacity (Normal) *1 Persons/Train c1 460 581 702 702 702 702
Section Congestion Ratio % d1 155% 161% 160% 156% 161% 168%
Figure 3.9-1 Calculation Method of Required Rolling Stocks during Peak Hours
Remark: In 2570 (2027), (1) 19 Trains of 4 cars/train and (2) 18 Trains of 6 cars/train shall apply.
Source : Consultants, 2012
Peak
8,569 4,029 16,820 6,526 20,275 7,797 21,844 9,397 27,060 11,516 32,989 14,040
Demand
Congestion
Ratio 155% 146% 183% 142% 174% 134% 156% 134% 161% 137% 168% 143%
Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay Frequency Headw ay
Time /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min) /direction (min)
5-6 4 15 3 20 5 12 4 15 5 12 4 15 5 12 4 15 5 12 4 15 6 10 4 15
6-7 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
7-8 10 6 5 12 15 4 8 7.5 15 4 8 7.5 15 4 8 7.5 18 3.33 9 6.67 21 2.86 11 5.45
8-9 12 5 6 10 20 3 10 6 20 3 10 6 20 3 10 6 24 2.5 12 5 28 2.14 14 4.29
9-10 10 6 5 12 15 4 8 7.5 15 4 8 7.5 15 4 8 7.5 18 3.33 9 6.67 21 2.86 11 5.45
10-11 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
11-12 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
12-13 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
13-14 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
14-15 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
15-16 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
16-17 9 6.67 5 12 12 5 6 10 12 5 6 10 12 5 6 10 15 4 8 7.5 18 3.33 9 6.67
17-18 10 6 5 12 15 4 8 7.5 15 4 8 7.5 15 4 8 7.5 18 3.33 9 6.67 21 2.86 11 5.45
18-19 10 6 5 12 15 4 8 7.5 15 4 8 7.5 15 4 8 7.5 18 3.33 9 6.67 21 2.86 11 5.45
19-20 9 6.67 5 12 12 5 6 10 12 5 6 10 12 5 6 10 15 4 8 7.5 18 3.33 9 6.67
20-21 9 6.67 5 12 12 5 6 10 12 5 6 10 12 5 6 10 15 4 8 7.5 18 3.33 9 6.67
21-22 8 7.5 4 15 10 6 5 12 10 6 5 12 10 6 5 12 12 5 6 10 15 4 8 7.5
22-23 6 10 4 15 8 7.5 5 12 8 7.5 5 12 8 7.5 5 12 8 7.5 5 12 10 6 6 10
23-24 4 15 3 20 5 12 4 15 5 12 4 15 5 12 4 15 5 12 4 15 6 10 4 15
TOTAL 157 83 214 113 214 113 214 113 255 133 308 163
Remark : Assumption for calculation method of operation distance: Operation distance on weekend accounts for 9 0 % of operation
distance on weekday.
Move passengers from one train to another train which may be on the
same track or on the track on the opposite side.
Move passengers from the train to the ground using ground service
vehicle, slow down rope, spiral chute and an emergency walkway.
Regarding the maintenance policy of the monorail of the Pink Line Project
(Khae Rai-Min Buri Section), the Time Base Maintenance: TBM shall apply for
inspection. The real operation time obtained from the monorail operator will be taken into
account.
Due to the unique characteristics of the monorail structure, track maintenance
needs specially designed maintenance vehicles. These maintenance vehicles are self-
operable by battery or diesel engine as maintenance work will be conducted at nighttime
when the track has no driving power.
These maintenance vehicles will be kept in the stabling yard for “deployment-
site works-pullout” process for approx. 5 maintenance hours, which are between the last
train of the day and the first train of the following day.
The Pink Line Project (Khae Rai-Min Buri Section) can be connected to other
4 mass rapid transit projects that pass through the project alignment.
- The Purple Line Project (Bang Yai-Bang Sue Section) ( at Nonthaburi
Government Center station)
- The Red Line Mass Transit Project(Bang Sue-Rangsit Section) including
Bang Sue Grand Station (at Lak Si station)
- The Green Line Project(Mo Chit-Saphan Mai Section) ( at Wat Phra Si
Maha That Station)
- The Orange Line Project (Bang Kapi-Min Buri section) ( at Min Buri
station)
The Pink Line Project (Khae Rai-Min Buri Section) has 4 interchange stations
below.
(1) Interchange with the Purple Line Project (Bang Yai-Bang Sue Section)
:Passengers can be connected to the Purple Line Project (Bang Yai-Bang Sue Section) at
Nonthaburi Government Center Station, which is the starting station of the Pink Line
Project (Khae Rai-Min Buri Section), on the 2nd floor (concourse level) through skywalk for
the distance of approx.30 meters as illustrated in Figure 3.9-2 and Figure 3.9-3.
(2) Interchange with the Red Line Mass Transit Project (Bang Sue-
Rangsit Section) including Bang Sue Grand Station : Passengers can be connected to
the Red Line Mass Transit Project(Bang Sue-Rangsit Section) including Bang Sue Grand
Stationat Lak Si station through the approx. 60 meter long sky walk on Vibhavadi-Rangsit
Road at the platform level as illustrated in Figure 3.9-4 and Figure 3.9-5.
3-162
Figure 3.9-2 : Illustration of Connectivity to the Purple Line Project (Bang Yai-Bang Sue Section) at Nonthaburi Government Center
VPK/ENV/RT1203/P1988/RE128
Figure 3.9-3 : Connectivity to the Purple Line Project (Bang Yai-Bang Sue Section)
3-163
VPK/ENV/RT1203/P1988/RE128
Figure 3.9-4 : Illustration of Connectivity to the Red Line Mass Transit Project (Bang Sue-Rangsit Section)
including Bang Sue Grand Station at Lak Si Station
3-164
Amendment EIA Report 3-165
Chapter 3 Project Description
Figure 3.9-5 : Connectivity to the Red Line Mass Transit Project (Bang Sue-Rangsit Section) including Bang Sue Grand Station
(3) Interchange with the Green Line Project (Mo Chit-Saphan Mai
Section) : Passengers can be connected to the Green Line Project (Mo Chit-Saphan Mai
Section) at Wat Phra Si Maha That Station walking from the platform level of Wat Phra Si
Maha That Station of The Pink Line Project (Khae Rai-Min Buri Section)to the concourse
level of Wat Phra Si Maha That Station of the Green Line Project(Mo Chit-Saphan Mai
Section)as illustrated in Figure 3.9-6 and Figure 3.9-7.
(4) Interchange with the Orange Line Project (Bang Kapi-Min Buri
section) : Passengers can be connected to the Orange Line Project (Bang Kapi-Min Buri
section) at Min Buri station, which is the terminus of the Pink Line Project (Khae Rai-
Min Buri Section)at the concourse level as illustrated in Figure 3.9-8.
MRTA and the Consultants of the Pink Line Project (Khae Rai-Min Buri Section)
had the meeting at the Department of Highways (DOH) Meeting Room chaired by Mr.
Sarawut Songsivilai, Deputy Director General for Engineering, on August 29, 2013 at 15.00 hrs.
The Consultants presented utilization of DOH areas for the construction of stations at Lak Si
Highway Station ( Lak Si Intersection) and Thanyaburi Highway Station 2 ( the
Safeguarding the Constitutional Monument) . In this regard, DOH informed meeting
participants that they would make a discussion and keep MRTA informed the results of
discussion.
Later, Bangkok Highway District issued the official letter No. kor kor 0626.2/
Bor.1.1/3044 dated November 28,2013inviting MRTA to participate in the meeting of the
rail station design for suitability for both proposed areas under the responsibility of
Bureau of Highway 1 1 .The meeting chaired by Mr. Pramon Sathapornnanon, Director,
Bureau of Highway 11was held on Monday December 2, 2013 at 14.00 hrs. at Highway
District 1 Meeting Room ( Bangkok) , 1st floor, Vibhavadi-Rangsit Road, Don Muang
district, Bangkok.The main points of the meeting are given below.
(1) Bureau of Highway 1 1 (Bangkok) permitted MRTA to use DOH area of 9 8
square wah for the construction of Lak Si station ( PK14) . MRTA, however, shall prepare
for place management so that Lak Si Highway Station operates properly and the entry
into and exit from the place shall be possible from Vibhavadi-Rangsit Roadand Chaeng
Watthana Road. Furthermore, the traffic management plan under the stations shall be
established in order to reduce traffic congestion caused by other transportation systems.
Bangkok Highway District Director proposed that MRTA coordinate with BMTA to make
the bus stop under Lak Si Intersection Overpass for passengers from Don Muang with
special route for buses from Chaeng Watthana Roadto stop at the station area.
(2) Bureau of Highway 11 (Bangkok) permitted MRTA to use DOH area of 3 rai
7 6 square wah for the construction of Wat Phra Si Maha That station ( PK16) .Bureau of
Highway 11 (Bangkok) permitted MRTA touse the whole area. Nonetheless, MRTA shall
re-construct the office building for Thanyaburi Highway Station 2. Also, the office
building of Lak Si Highway Station will be relocated to such area. Both office buildings
will be constructed on the opposite side of existing areas, which are adjacent to Bang
Khen Police Station and Thainiyomsongkroa School. Furthermore, the traffic management
plan under the stations shall be established in order to reduce traffic congestion caused by
Figure 3.9-6 : Illustration of Connectivity to the Green Line Project at Wat Phra Si Maha That Station
Figure 3.9-7 Connectivity to the Green Line Project (Mo Chit-Saphan Mai Section)
Figure 3.9-8 : Connectivity to the Orange Line Project (Bang Kapi-Min Buri Section)
other transportation systems. Bangkok Highway District Director proposed that MRTA
allow buses to stop in the areas to reduce traffic congestion at the station and the
roundabout.
The meeting chairman assigned MRTA to coordinate with engineers of both
Highway Districts for operations after approval from the Cabinet. The meeting minutes
between MRTA and Bureau of Highway 1 1 ( Bangkok) for a discussion of rail station
design for the Pink Line Project (Khae Rai-Min Buri Section) is shown in Appendix 3A.
Land acquisition approach determined by MRTAforLak Si Highway Station
and Thanyaburi Highway Station 2is similar to the one for MRT Blue Line ( under
construction) . The land acquisition approach will be attached to TOR and bidding
documents. Contractors shall coordinate with Lak Si Highway Station and Thanyaburi
Highway Station 2 for the conclusion of building type and the locations for new office
building construction. Construction budgeting shall be prepared and proposed to MRTA
for approval prior to operation.
In addition to this, Mass Rapid Transit Authority of Thailand (MRTA) sent a
letter of request to Electricity Generating Authority of Thailand (EGAT) for preliminary
cost estimate for the construction of the structure of high voltage posts on both sides of
Chaeng Watthana Road for the Pink Line Project (Khae Rai-Min Buri Section). The
Director (Operation) of Electricity Generating Authority of Thailand ( EGAT) consented
for the request with approval letter to MRTA as shown in Appendix 3C.
The socio-economic analysis of the Pink Line Project (Khae Rai-Min Buri
Section) consists of the following steps (Figure 3.10-1):
Project cost evaluation,
project benefit evaluation,
economic viability analysis, and
project sensitivity analysis.
VOC savings= (VOCrep vehicle x VKT without project) - (VOCrep vehicle x VKT with project)
Where
VOC savings = Vehicle operating cost savings (Baht)
VOCrepresentative vehicle = Vehicle operating cost of representative vehicle
(Baht/PCU-km)
VKTwithout project = Vehicle kilometers travelled in the without-project case
(PCU-km)
VKTwith project = Vehicle kilometers travelled in the with-project case
(PCU-km)
With reference to the Feasibility Study Report for the Pink Line (Khae Rai-Min
Buri) (September 2009), VOC unit was adjusted to be the value at the base year (2011) as
presented in Table 3.10-3.
VOT unit was adjusted, in reference to the Feasibility Study Report for the
Pink Line (Khae Rai-Min Buri) (September 2009), to be the value at the base year (2011),
231.67 Baht per PCU-hr. (However, the average household income which is a factor used
to calculate VOT is not based on the minimum wage of 300 Baht.)
(3) Savings of Environmental Cost
When comparing the fuel consumption between road and rail
transportation, the latter requires less fuel than the former at the equal amount of usage.
This is because the rail transportation can accommodate more passengers and takes less
time than traveling by road. Therefore, the number of trips by rail is higher than by road
when spending the same period of travel time. The rail mass transit will help reduce air
pollution emission.
The savings of environmental costs were computed by multiplying the
pollution elimination cost by the difference of vehicle kilometers travelled of road and
rail transportation between the without-and with-project cases. With reference to the Final
Report of the Study of the Master Plan for Railway System and High Speed Train
Development (2010) and the MRT Assessment Standardization report (Public Debt
Management Office and MRT Red Line Project), the pollution elimination cost is equal to
5 Baht/PCU-km.
The project costs and benefits were compared in the form of economic values
by using the economic indicators from MRT Assessment Standardization of the Finance
Ministry. The project’s economic viability analysis was carried by taking into account the
following economic indicators.
(1) Net Present Value (NPV)
NPV is the difference between benefits and costs in different years at the
present value throughout the project life. Normally, a discount rate is applied to derive the
present value.
If NPV is positive or greater than zero, the project is worth investing. In
other words, the investment will create benefits that exceed the costs over the project
period.
However, evaluation of the project viability by considering only NPV is
not sufficient for comparing the projects with much different capital investments. This is
because the large-scale project will yield higher NPV than the one of much smaller scale.
It is necessary to take other economic indicators into account. NPV calculation is shown
below.
n
t t
t
t=1
Where NPV = Net present value
Bt = Project benefits in year t
Ct = Project costs in year t
i = Interest rate or project’s return rate
n = Project life
(2) Benefit Cost Ratio (B/C Ratio)
B/C ratio is the ratio of the total present value of benefits to the total
present value of costs of the project. Generally, a discount rate is used to obtain the
present value.
If the B/C ratio is greater than 1, the project is viable for investment. B/C
ratio calculation is as follows.
Where B/C = Benefit cost ratio
Bt = Project benefits in year t
Ct = Project costs in year t
i = Interest rate or project’s return rate
n = Project life
(3) Economic Internal Rate of Return (EIRR)
It is a discount rate which equates the present value of benefits with the
present value of costs.
The opportunity cost of the capital adopted for this project is 12% per
annum which is the rate taken from the study in Thailand by the World Bank and
NESDB. As a result, the project with EIRR greater than 12% per year is considered
viable for investment.
Where EIRR = Economic internal rate of return
Bt = Project benefits in year t
Ct = Project costs in year t
i = Interest rate or project’s return rate
n = Project life
The economic analysis results indicate economic viability of the project in all
cases as economic indicators are greater the criteria. Also, it is indicated that the monorail
with 20-baht flat rate is more economically viable than the other case.
Table 3.10-6 Economic Viability Analysis Result: Monorail with 20-Baht Flat Rate
2555) . . 2561
1,905 ! " # $ EIRR) 17.3%
#% E&M 50,730 & ! $$! NPV)
' 28,031
$! '
( ) #% * $ ! +
! , 6,755 ! %, $, B/C) 1.59
* ! , ) 57,764 ! " ## FYRR) 0.0%
-./01 : 234.546
A .B. [email protected] </42H6>. </4IJ3 K/[email protected]. G0: :;2</4F4G7GL-1MC</4 IJ3 K/4 1 :;2</4E024689 7GL-1MC :;2</4F4G2C N27GLO1J.PG0:
Table 3.10-7 Economic Viability Analysis Result: Monorail with Distance-Based Fare Rate
! " 1,905 # $ % EIRR 14.2%
E&M 50,730 &'#%%# ( NPV) 11,237